Title to such imported materials and equipment (including spare


parts and toOls) shall pass on to COMPANY upon delivery at the
WORK SITE. Any materials and equipment in excess of the
reqUirements of the PROJECT shall remain COMPANY property,
unless otherwise directed by COMPANY.

6.12.3

NotWithstanding the transfer of title to COMPANY of such imported


materials and equipment (including spare parts and tools), the
responsibility for care and custody thereof together with the risk of
loss or damage thereto shall remain with CONTRACTOR in
accordance with Paragraph 20, Risk and Responsibility, of this
Schedule "A" until Preliminary Acceptance of the PROJECT and
thereafter until completion of corrective WORK on warranty defects
during the warranty period.

Marshalling of CONTRACTOR Tools and Eguipment

On completion of the WORK, CONTRACTOR shall be responsible for the


marshalling of all tools and equipment imported for the execution of the
WORK and for the obtaining of re-export permits, transportation and
freighting of such tools and equipment. COMPANY shall not provide land for
CONTRACTOR's USe for such marshalling.
6.14

Care, Control and Custody of Materials

CONTRACTOR shall be responsible for the care, control, and maintenance of


all materials, tools and equipment obtained for the execution of the WORK up
to Preliminary Acceptance of all the PROJECT PORTIONS and failure, loss, or
damage to such material or equipment prior thereto shall be for account of
CONTRACTOR.
6.15

Special Tools Required to Operate and Maintain the PROJECT

CONTRACTOR shall provide any special tools to install, adjust, operate and
maintain the PROJECT during start-up. In case further special tools are
discovered necessary for subsequent standard maintenance activities, then
the supply of them by CONTRACTOR shall be mutually. agreed upon. All
special tools for subsequent maintenance, as agreed upon, shall be checked
and cleaned and damaged tools will be replaced by CONTRACTOR and
provided and turned oVer to COMPANY in an as-new condition on Preliminary
Acceptance of the last Power Plant Unit.
For purposes of this paragraph, the follOWing categories are considered as
special tools:
6.15.1

All commercially available tools which are not readiiy available in


the Kingdom of Saudi Arabia.

6.15.2

All tools and fixtures which are needed for operation and
maintenance of the Plant which are modified commercially available
tools.

6.15.3

Tools and fixtures needed for operation and maintenance of the


plant which are commercially unavailable.

A-ll
Conversion of Open Cycle Gas Turbines to Combined Cycle at Qurayyah Power Plant
Schedule" A"

,f

CONTRACT NO.

SCHEDULE "A"
7.

30621127/00

Technical Documentation

CONTRACTOR shall supply to COMPANY all the technical documentation as specified


in the Scope of Work and Technical Specifications, PTS No. 07EG908.
7.1

Language to be Used

All correspondence and documentation provided by CONTRACTOR shall be in


the English language. The metric system of measurement shall be used;
however, suppliers using American system of measurement shall furnish the
drawings/documents with equivalent metric units as well.
7.2

Submission of "As-Built" Drawings

Upon completion of warranty period of the PROJECT PORTIONS as indicated


in Paragraph 17.8 of this Schedule "A", CONTRACTOR shall submit to
COMPANY the final "as-built" drawings and documents the COMPANY deems
necessary to maintain for its own records, and in accordance with the
requirements of the Scope of Work and Technical Specifications, PTS No.
07EG908.
7.3

Dimensions and Locations of Existing Installation

Dimensions and locations of eXisting and proposed installations and


appurtenances shown on drawings and data sheets supplied by COMPANY are
apprOXimate only. All dimensions and locations relating to existing and
proposed installations shall be checked and verified by CONTRACTOR at the
WORK SITE before starting the WORK.
7.4

Interpretation of the Technical Specifications

Whenever disagreement between CONTRACTOR and COMPANY arises


concerning the meaning of a part of or the whole Technical Specifications,
then COMPANY REPRESENTATIVE's interpretation of the applicable part, or
the whole, shall govern and CONTRACTOR shall and will perform the WORK in
accordance with such interpretation. However, CONTRACTOR acceptance to
perform the WORK under the COMPANY representative's interpretation shall
not preclude him from exercising his rights under Paragraph 28, Settlement
of Claims and Disputes, of this Schedule "A".
8.

Ouality Assurance and Ouality Control fOA IOC)


8.1

Ouality Assurance Activities

CONTRACTOR shall provide quality assurance to ensure that all specifications


and standards of the CONTRACT are met. CONTRACTOR's quality assurance
activities shall include quality control functions including but not limited to
inspection, testing and examination.
8.2

OA/OC Plan

Prior to the commencement of WORK under the CONTRACT, CONTRACTOR


shall submit to COMPANY, CONTRACTOR's quality assurance and quality
control plan in accordance with the Scope of Work and Technical
Specifications, PTS No. 07EG908, for engineering, materials procurement,
fabrication, testing and inspection.

A-12