Professional Documents
Culture Documents
DA 3120
ENERGY RECOVERY
Guidelines
International Edition 1.0
March 2008
ENERGY RECOVERY
INTRODUCTION
Chapter
Contens
INTRODUCTION
WATER TEMPERATURES
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
2/27
SOMMAIRE
1
INTRODUCTION
1.1
1.2
1.3
Principles ............................................................................................................................................................8
1-stage economizer.............................................................................................................................................8
2-stage economizer.............................................................................................................................................8
GENERAL...........................................................................................................................................................4
general recommendations ...................................................................................................................................4
choice of solutions...............................................................................................................................................4
10
12
13
13
7.1
7.2
7.3
Principle ............................................................................................................................................................13
Recovery FROM the condensate tank...............................................................................................................13
Recovery FROM condensates at the exchanger output.....................................................................................13
14
Objective ...........................................................................................................................................................14
Principle ............................................................................................................................................................14
Recommendations ............................................................................................................................................14
PRINCIPLE DIAGRAMS
16
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
3/27
INTRODUCTION
1.1
GENERAL
This document expresses the intention of the Accor group to control energy. It is additional
to the technical specifications of the groups different brands concerning heating, air
conditioning, domestic hot water production installations, etc.
It is based on Accors experience in the construction and technical management of hotel
services. It gives advice and recommendations that must be interpreted and adapted as a
function of the reality of the project.
It is addressed to MEP consultants that remain responsible for the project design.
1.2
GENERAL RECOMMENDATIONS
1.3
Avoid oversizing
Select an energy that is only slightly polluting
Use the most efficient machines
Avoid technical sophistication, the operator must be capable of understanding the
installations
The choice of the solution of heating systems and cooling systems must be made as a
function of the climate
CHOICE OF SOLUTIONS
Recovery from air handling units so as to reheat fresh air using energy from the
discharged air. This principle must operate inversely in the summer
By adiabatic wheel
By heat pipe (caloduc)
By plate exchanger
By glycol water coils
Air/air heat pump
Chiller in recovery from discharged air to preheat domestic hot water
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
4/27
BASIC PRINCIPLE
2.2
2.3
HEAT PIPE
Solution applicable to AHU for guestrooms and for general services. Placement of
horizontal heat pipes can save height.
The AHU and the extractor are superposed (fresh air at the top and discharged air at the
bottom) or placed adjacent.
The efficiency of this solution is high: of the order of 65%
Operation is permanent and with no motor. A by-pass is installed to avoid using
recovery when it is not necessary (spring and autumn) and when it is required to use
outside air for cooling.
Operation is essentially for winter.
A filter protects the economizer on the fresh air inlet and on the extraction.
A manometer checks the dirtiness of filters and the coil.
2.4
PLATE EXCHANGER
Solution applicable to AHU for guestrooms and for general services.
The AHU and the extractor are superposed or placed adjacent to each other.
The efficiency of this solution is of the order of 50%
Operation is continuous with no motor. A by-pass is used to avoid using recovery when
it is not necessary
Operation is suitable for winter and for summer.
Recovery is switched off during spring and autumn.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
5/27
2.5
Caution with frost in winter, which can block up the coil on the discharged air side in
contact with fresh air at very low temperature. Fresh air needs to be heated before
entering the economizer for very cold countries, and a frost free temperature has to be
maintained at the inlet to the economizer.
A filter will protect the economizer on the fresh air inlet and on the extraction.
A manometer will check the dirtiness of filters and the coil.
2.6
2.7
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
6/27
2.7.2 RECOVERY FROM DISCHARGED AIR (EXAMPLE ON ROOMS AFTER THE GLYCOL WATER COILS)
Chiller
Circulating pump slave controls as a function of the chiller with timeouts when the chiller
is stopped.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
7/27
PRINCIPLES
3.2
1-STAGE ECONOMIZER
3.3
The recoverable energy on the smokes exhaust is close to 10% of the boiler heating
capacity.
Recovery will be made in the case in which the installation has one or several low or
very low temperature distribution networks (the water returns at a temperature less than
50C),
Several networks are usually concerned:
Hot water supplies to fan coil units
Preheating of fresh air of the AHU
Preheating of domestic hot water
The heat recovery system may be single stage or 2 stage, for example by combining a
fan coil unit return on the first stage (water 40C ) and preheating of domestic hot water
on the second stage (water at 10C).
The study must demonstrate that recovery cannot cause any overheating in the
networks used. All cases must be studied for winter, summer and for spring and
autumn.
Recovery shall be made from the exhaust gases flue with an energy exchanger installed
on a branch connection so that recovery is possible using any boiler.
The economizer is fitted with a fan slaved to operation of the boilers. A timeout enables
operation of the fan a few minutes after the boilers are stopped.
Exhaust gas flues and ducts will be made of stainless steel.
The power of the economizer will be chosen as a function of the recoverable power.
The water flow in the recovery system will be constant (no variable flow that could cause
overheating in the economizer).
Energy recovery device
A slope shall be provided and there shall be a drain at the low point to collect
all condensates.
Two thermometers (on the input and output sides of the economizer).
Two temperature probes connected to the BMS to monitor recovery.
The efficiency and the annual savings will be simulated taking account of the
temperature of the exhaust gases and the water.
Water connections (for example on the fan coil unit water returns)
Connection on the water return pipe before the three-way valve.
A flow controller with the fan slaved to prevent overheating.
A relief valve.
Two thermometers (on the economizer input and output sides) and two
temperature probes connected to the CTM to monitor recovery.
2-STAGE ECONOMIZER
The efficiency of the installation will be further improved if a second recovery stage is
added.
The first recovery stage is exactly as described above.
The second exchanger will operate with water at a lower temperature than the first
stage. It is suggested to use:
Preheating of domestic hot water: recovery is possible throughout the year.
Preheating of fresh air for AHU: recovery is only possible in winter.
Water connections (for example: preheating of domestic hot water)
The first tank is only used for preheating.
The capacity must be equal to 500 liters per 100 kW boiler heating capacity.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
8/27
A circulating pump slaved to operation of the boilers with timeout after stopping
to prevent overheating.
A relief valve.
Two thermometers (on the input and output sides of the economizer).
Two temperature probes connected to the CTM to monitor recovery.
Consultancy
The domestic hot water preheating tank can be used in winter on exhaust
gases from gas boilers and in summer on energy released from chillers.
The installation is thus more efficient.
The economizer on exhaust gases is not used in summer.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
9/27
4.2
4.2.1 PRINCIPLE
Storage volume
Dedicated exclusively to storage of recovered heat
20 to 30% of the hotels daily DHW needs
4.2.3 CONTROL
The chiller keeps the chilled water temperature constant for the different needs. The
adjustment is made on the chiller logic controller.
The terminal tanks provide additional heating for domestic hot water.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
10/27
4.3
4.3.1 PRINCIPLE
Total recovery can preheat domestic hot water to a maximum temperature of 50C, the
recovered energy is high.
This solution is compatible with an installation comprising a single chiller.
It is even more useful for installations with several cooling units. In this case, it is often
enough to perform recovery from a single unit.
A calculation note shall be produced, justifying needs and recoverable powers.
To optimize efficiency, the water return temperature to the condenser economizer shall
be:
As low as possible. Note that the efficiency for cooling with outside air at 30C
is the same as with water at 45C.
At least 25C. The chiller will not work with a l ower temperature.
Recovery energy
The recovery power is the total power to be evacuated from the chiller (cooling
power + electric compressor power).
Storage volume
Dedicated exclusively to storage of recovered heat
20 to 30% of the hotels daily DHW needs
The chiller keeps chilled water at a constant temperature for the different needs. The
adjustment is made on the chiller logic controller.
An independent logic controller manages the recovery
The tank 1 electric heater is used only as a standby and if there is a legionella
contamination to increase the tank temperature to 60C.
The tank 2 electric heater is authorized to operate in off-peak hours. The logic controller
determines the start time such that the tank reaches a temperature 60C at 6:00 in the
morning at the beginning of the drawing-off period. (peak hours are depending the local
electricity board )
The last tank is always in operation at 60C so as maintain the temperature loop.
Operation from 6:00 to 15:00: the temperature of tanks 1 and 2 is left to drift.
Operation from 15:00 until forced restart at night:
When the chiller is in operation, recovery is authorized. Pump P1 is in
operation, pump P2 is in operation, the three-way valve V1 regulates to
maintain a minimum return temperature of 25C on th e cooling unit
economizer, the three-way valve V2 is open to tank 1. When the temperature
of sensor S3 is greater than the temperature of sensor S2, water is transferred
to tank 2, and if the temperature of sensor S3 is less than sensor S2, water is
transferred to tank 1.
If the cooling unit stops, recovery stops with all pumps stopping and the valves
closing. Recovery is started again if necessary when the unit starts again.
Recovery stops when all sensors in the recovery tanks are at 50C. The
cooling unit releases its calories to the outside.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
11/27
Control in winter
The cooling unit is stopped. There is no possible recovery.
The tanks operate directly with the electrical heaters.
The chiller maintains a constant chilled water temperature for the different needs. The
adjustment is done on the chiller logic controller.
A logic controller manages recovery.
Heating of tank 3 is maintained permanently at 60C using the exchanger.
Operation from 6:00 to 15:00: The temperature of tanks 1 and 2 is left to drift.
Operation from 15:00 to forced operation at night:
When the chiller is in operation, recovery is authorized. Pump P1 is in
operation, pump P2 is in operation, the three-way valve V1 regulates to
maintain a minimum return temperature of 25C on th e cooling unit
economizer, the three-way valve V2 is open to tank 1. When the temperature
of sensor S3 is greater than the temperature of sensor S2, water is transferred
to tank 2, and if the temperature of sensor S3 is less than sensor S2, water is
transferred to tank 1.
If the cooling unit stops, recovery stops with all pumps stopping and the valves
closing. Recovery is started again if necessary when the unit starts again.
Recovery stops when all sensors in the recovery tanks are at 50C. The
cooling unit releases its calories to the outside.
A new recovery cycle is authorized when the temperature S1 of tank 1 drops
below 25C.
Control in winter
The cooling unit is stopped. There is no possible recovery.
Tanks are heated using the exchanger, by modifying manual valves.
Installations fitted with water / water cooling units located in a service room use a cooling
circuit at a temperature of 45/50C and outdoor coo ling towers.
Cooling units operate at full power in summer and partially in winter.
Energy released by the cooling units must be recovered.
The heating recovery can be used for:
Preheating of domestic hot water (needs are constant throughout the year).
Recovery is done using a preheating tank dedicated to recovery.
A
temperature comparison will prevent recovery if the temperature of the hot
water is higher than the cooling network.
Hot water distribution to fan coil units. If the fan coil units operate at
temperatures of 45/40C, part of the heating in spr ing and autumn can be
performed and possibly the temperature loop in summer can be maintained.
In all cases, take care to maintain a minimum water return temperature of 25C on the
cooling unit condensers.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
12/27
PRINCIPLE
7.2
7.3
This solution is applicable for Cities that have a heat distribution network in the form of
steam.
Heat is supplied in the form of steam and the return to central production is hot water at
a temperature of about 70C. Heat is metered by me asuring the consumed water flow.
Recovery is made to preheat domestic hot water.
The quantity of heat is variable and takes account of building needs:
In winter, consumption is high.
In summer, heating needs are low. They usually apply only to production of
domestic hot water.
In summer, it would be possible to use the recovery tank on recovery from cooling units.
This would make it possible to amortize the two installations more quickly.
All condensates that exit from the heating exchanger pass through a hot water buffer
tank
The volume of the recovery tank is depending on the size of the installation.
All cold water intended for domestic hot water production goes into the tank.
Recovery is important at times when DHW is being drawn off.
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
13/27
OBJECTIVE
8.2
8.3
PRINCIPLE
Production
Flat panels or solar tubes on flat roof or on exposed walls.
Possible isolation of each panel.
Pipes to resist high temperatures, preferably in copper.
Use of a frost-resistant heat transporting fluid.
Hi performance thermal insulation of pipes.
Heat exchanger between the primary and domestic hot water.
Safety device to avoid exceeding 80C in the tanks
Expansion vessel to enable large expansions of the heat transporting fluid.
Storage
At least 1 tank reserved exclusively for solar recovery
Resistance of the inside coating to temperature (100C)
Possibility of increasing the tank temperature to 70C using energy in the case
of legionella.
Access manhole for maintenance.
RECOMMENDATIONS
Increase collector height to enable renovation of the waterproofing on the flat roof.
Remember that hot water consumptions may be reduced on some days.
Use reliable tested processes
The various elements must resist high temperatures. Even if they are accidental or
occasional.
Take account of different climates (strong winds, rain, hail, etc.).
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
14/27
WATER TEMPERATURE
The inlet/outlet chilled water temperatures, the inlet/outlet water temperatures from the
heating recovery system are important for the efficiency. Here under results on test done on
factory. They are valid just for one type of chiller, but it is a good example and can be
extrapolate on other equipment.
9.1
7/12C
Chiller
load
100%
75%
50%
20%
100%
75%
50%
20%
Outside T = 28C
Outside T = 36 C
Outside T = 44C
CL
Pe
EER
CL
Pe
EER
CL
Pe
EER
CL
Pe
EER
294
78
3.8
271
89
3.0
230
56
4.1
214
65
3.3
246
195
103
75
2.4
2.6
222
174
119
86
1.9
2.0
167
35
4.7
155
41
3.8
142
47
3.0
127
55
2.3
74
17
4.3
69
20
3.4
63
23
2.7
56
27
2.1
265
72
3.7
243
86
2.8
208
54
3.9
193
63
3.1
222
176
99
72
2.2
2.4
200
158
115
84
1.8
1.9
139
61
40
20
3.5
3.1
149
35
4.3
66
17
3.9
126
46
2.7
113
54
1.8
55
23
2.4
49
26
1.9
DESUPERHEATER
Here under test done on factory on one chiller (same machine as here above). The letters in
bolt are more realistic points, for ex at 20C the chiller is 25% loaded only. The water
temperature at the desuperheater = 55/60C (inlet/o utlet):
Chilled
water
10/15C
Chiller
load
100%
75%
50%
20%
Outside T = 20C
Outside T = 28C
Outside T = 36 C
Outside T = 44C
CL
Rec
EER
CL
Rec
EER
CL
Rec
EER
CL
Rec
EER
265
28
3.8
243
46
2.9
208
18
3.9
193
31
3.1
222
176
68
47
2.3
2.4
200
148
89
64
1.8
1.9
149
4.3
139
16
3.5
126
26
2.7
113
38
2.1
74
4.3
69
3.4
63
13
2.7
56
19
2.1
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
15/27
Higher is loaded the chiller, better is the recovery. Cf here under a summary:
Outside T
20C
28C
36C
Chiller load
in %
20
50
75
75
100
Heating recovery
in % of the
cooling load
4%
11%
16%
26%
30%
Chiller
Load
100%
75%
50%
20%
20
4.4
4.4
4.1
4.0
The recovery is efficient, the energy transferred is the total of cooling load and the electric
consumption of the machine, whatever is the chiller load.
According the needs, the chiller runs under 2 various modes:
normal, the cooling used the outside air. This mode is done when there is no more
needs to produce DHW.
recovery, the cooling is done by energy transfer to a plate exchanger where the DHW
is pre-heated.
Analysis of the here above data:
EER is deteriorate when the recovery water temperature is too high,
Conversely EER is improved when the water temperature is not too high.
Between that, the balance points are around:
EER on air at 30C = EER on water at 45C
EER on air at 35C = EER on water at 50C
For exemple if we keep only this last line, when the outside temperature is 35C the
production of water at 50C is absolutely free. The global efficiency of the system is greatly
improve.
Conclusion
: A total heating recovery system is generally a good solution
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.doc
16/27
10 PRINCIPLE DIAGRAMS
ADIABATIC WHEEL
Extracted air
Cf 2.2
Return air
Fresh air
Supply air
Fresh air
Supply air
Extracted air
Return air
PLATE EXCHANGER
Cf 2.4
Extracted air
Supply air
Return air
Fresh air
17/27
Extracted air
Extracted air
Supply air
Fresh air
Supply air
Fresh air
Return air
Extracted air
18/27
Valves opened in
winter
11C
55C
Tank dedicated to
energy recovery
To DHW users
DHW return
25C mini
Cold water
19/27
Cf 3.2
Exhaust gas flues
Heat recovery
equipment
1st stage
recovery
To DHW users
DHW return
50C mini
Cold water
20/27
Cf 3.3
Exhaust gas flues
Heat recovery
equipment
1st stage
recovery
2nd stage
recovery
Hotel FCU
network
Tank dedicated to
energy recovery
To DHW users
DHW return
Cold
water
21/27
CHILLERS DESUPERHEATERS
Cf 4.2
Tank dedicated to
energy recovery
To DHW users
DHW return
> 50C
Cold water
22/27
Tank dedicated to
energy recovery
To DHW users
DHW return
To/from heat
production (boilers)
25C mini
Cold water
23/27
Dry cooler
Dry cooler
To/from boilers
40C
Heating recovery to FCU
hot water return
45C
Heating recovery to
DHW production
Cold water
25C mini
55C
50C
Chilled water
network
24/27
Opened in winter
Closed in summer
Heating network
Chilled water
network
25 / 27
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.do
From hotel
steam network
Tank dedicated to
energy recovery
Classical DHW production
To DHW users
DHW return
Condensates tank
Condensates
return
Cold water
26 / 27
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.do
Expansion tank
Classical DHW production
Automatic control
system
Tank
dedicated to
solar energy
To DHW users
DHW return
Cold water
27 / 27
ACC_WE_DA3120_ENERGY_RECOVERY_Guidelines_1.0_Mar_08.do