Past Questions
Up to November 1999
If you have to accelerate the works for Employer or Contractor delay, what are the
costs to be considered?
What Clause governs determination by the contractor and what actions warrant a
determination?
What Clause governs determination by the employer and what actions warrant a
determination?
What Clause governs joint determination and what actions warrant a determination?
Are there any time restrictions on the Architect to issue an Extension of Time?
Do you know any formulae for calculating head office overheads and profit?
You mentioned immediate costs, are there any restrictions imposed on the
contractor?
Why cant I get any Liquidated and Ascertained Damages if I give an Extension of
Time?
If by the nature of the Works the Employer requires third party insurance to be taken
out, how is that incorporated into the contract?
Claims. When they make clams they label various Heads of Claims. Are
overheads a fair head of claim?
How do you question the build up process (eg. Plant for so many number of hours)?
An AI to carry out work has disrupted another activity. Is this a Head of Claim?
What does prolongation mean and how would you value it?
We hear that the Works have been suspended. Why would the works be
suspended?
If the Architect instructed a suspension, what would the contractor be entitled to?
If the contractor was negligent and damages an adjoining building, where would the
employer be covered?
Explain what clause 21.2 will cover the client for in JCT 80
What is adjudication
What are the differences in arbitration before and after the act
What is prolongation
What is disruption
What happens in MW 80
Under clause 26 of the JCT the contractor is required to prove what 2 issues?
If you were a contractor what is the order for making a claim under the JCT?
10
11
If damage is caused to a project through a design fault, how does the employer
recover losses?
A fire-damaged building that you worked on was only six years old. Assume that the
cause of the fire was through an original design fault. Does the client have any
recourse against the original design team for the fault?
How do you prepare an estimate for the reinstatement of the building without any
design information?
You have a client who is a Local Authority for which you have an appointment but
have not yet carried out the service. The client asks you if he can pay you in
advance for that service before the end of the financial year because otherwise he
will lose that money. What is your response to the client?
12
On a project with a contract duration of 8 weeks the contractor has been on site for
6 weeks of which he has done 2 weeks worth of productive work, but he is in delay
by 4 weeks, due 2 weeks of Contractor delay and 2 weeks Employer delay. In a
valuation how would you value the prelims?
13
Can you explain the circumstances under which you would request a Parent
Company Guarantee?
14
If a variation incurs cost and programme implications, what would you expect to
receive in the Contractors Notice of Delay?
When a delay occurs what actions are required to be taken by the Contractor?
A client asks your advice on L.A.D.s, what questions would you ask and how would
you determine the figure?
The client says he wants some teeth in the damages figure as an incentive to make
the Contractor perform and suggests that a penalty figure of 20,000 per week
should do the trick, if this is stated in the documents and the contractor signs on that
basis, is it valid?
Please advise us of the basic insurance provisions of the JCT `98 contracts if it is
easier
15
What if the delay falls over a statutory holiday period like Christmas where a couple
of days delay before the break for Christmas effectively means that the contractor
loses a further two weeks overheads which he says where not covered by this
contract?
In determining claims for loss and expense can you employ formulas?
16
Ditto a contractor?
Can you under JCT contracts go to law to settle disputes (ie. Opt out of adjudication,
arbitration?
A contract is running considerably over the date for completion and no extensions of
time are justified. Damages are very small and the contractor is still working but
nothing is being completed. The employer requests you advice on what to do.
17
If I wanted to start a project I needed to pre- order long lead in time of materials,
how would you suggest I prove it?
How long after PC has been given does the Architect have to confirm Extensions of
Time?
18
An Extension of Time has bee given, does this entitle the contractor to loss and
expense?
What can a contractor claim for if the delay means plant stands idle?
Why is it required?
19
20
21
If the project, say a school with a critical end date, what LADs would you require?
22