Professional Documents
Culture Documents
Purpose: This instruction covers the testing and commissioning of all replacements or new installations of steel standard
streetlights. The testing ensures that cables are installed correctly and that the steel standards do not become energised.
Note: The following tests must be carried out after installation and before the streetlights are put into service.
Note: Bolts and screws in all electrical connections across the Western Power network must be properly tightened.
Work Package No.:______________________
Test Site/Location:________________________
Date:_____/______/ 20___
F.
B.
G.
C.
H.
D.
I.
E.
J.
DM# 1698111
1 of 3
Yes
No
DCWI
Remove the cut-out which isolates the light from the line phase
and line neutral.
Phase to neutral
Phase to earth
Neutral to earth
If a reading is unacceptable, cease testing, investigate the problem or report this to your supervisor. Values greater than 10 M for
new cables and 1 M for existing cables are acceptable. Ensure that all persons are clear of the circuit before testing.
Note: If energisation occurs more than two weeks after these commissioning tests, conduct a final insulation resistance test to ensure
the cable is safe to energise.
Reinstate all the MEN links and N-E connections which were
disconnected as per item 3.4. (Double insulated streetlight
installations do not have a MEN connection.)
NAC #:__________________________
Ensure the cut-outs which isolate the lights from the line phase
and line neutral are removed.
For testing purposes, use an effective earthed reference point spaced more than 2 meters from any electrically conductive
object embedded in the ground.
Using a voltmeter test between the
U1 Un
216 V 253 V
U1 PE
216 V 253 V
Un PE
0V6V
Insert a fuse into the cover of the cut-out or red spot fuse (or
similar) and reinstall.
2 of 3
DCWI
7. HANDOVER OF RESPONSIBILITY
I hereby certify that all items have been completed with satisfactory results and transfer control to the project manager.
Commissioning officer:________________________________________________
Signature:______________________________________________________
1.
2.
3.
4.
NAC #:__________________________
Ensure the work area is left tidy with no hazards to the public.
Hand over responsibility to the operating authority.
Return this form to the project file as a record of the commissioning/handover certificate.
After the on-site project officer signs off on the DCWI, send a scanned copy to the relevant manager: the construction manager (for
work performed by Western Power employees); the service manager (for contractors); or the project manager (for the Future Grid).
DM# 1698111
3 of 3