You are on page 1of 6

01

00

15 JAN 2014
22 OCT 2013
DATE

AKM
AKM

REV. NO.
CLIENT:

ISSUED BY

MINISTRY OF ELECTRICITY &


WATER

FOR APPROVAL
FOR APPROVAL

REVISION DETAILS

STATE OF KUWAIT

POWER STATION AND


DISTILLATION PLANT
PROJECT SECTOR
PROJECT:

SUPPLY, ERECTION, OPERATION AND MAINTENANCE OF GAS


TURBINES TO UPGRADE POWER CAPACITY AT SABIYA
POWER AND DISTILLATION PLANT SITE

CONTRACT NO.

MEW/C/4608-2013/2014

MEW DOC. NO.

A/SE/DCSY-CAL/101219 Rev. 01

CONTRACTOR:

ALGHANIM INTERNATIONAL

CONTRACTORS CONSULTANT:

GENERAL TRADING & CONTRACTING Co. W.L.L.


L&T-SARGENT & LUNDY LIMITED

PROJECT:
DRAWN
DESIGNED
CHECKED
APPROVED
DEPT.

ORIG. PC : KWU3025
DATE
15 JAN
2014
15 JAN
2014
15 JAN
2014

NAME
SG
SH

SCALE:
TITLE:

SIZE:

CALCULATION FOR
UPS SYSTEM SIZING

TYPE: YT10
CONTENT CODE
BRU

AKM

ELEC
DEPT. ELEC

DOCUMENT NO.

KWU3025-YT10-BRU-6330337

UNID 081148337

REV.

01

PAGE NO. C 01

ALGHANIM INTERNATIONAL GENERAL


TRADING AND CONTRACTING COMPANY

MINISTRY OF ELECTRICITY AND WATER


Contract No. : MEW/C/4608-2013/2014

Project : Supply, Erection, Operation & Maintenance


of Gas Turbines to Upgrade Power Capacity at Sabiya
Power & Distillation Plant Site.

Document Title : UPS SYSTEM SIZING CALCULATION


Document No. : A/SE/DCSY-CAL/101219 Rev. 01

UPS SYSTEM SIZING CALCULATION

Rev.:- 01

Date :- 15 JAN 2014

Issued for Approval


Project Code :- KWU3025

1 of 5
Approved By :- AKM

ALGHANIM INTERNATIONAL GENERAL


TRADING AND CONTRACTING COMPANY

MINISTRY OF ELECTRICITY AND WATER

Project : Supply, Erection, Operation & Maintenance


of Gas Turbines to Upgrade Power Capacity at Sabiya
Power & Distillation Plant Site.

Contract No. : MEW/C/4608-2013/2014

Document Title : UPS SYSTEM SIZING CALCULATION


Document No. : A/SE/DCSY-CAL/101219 Rev. 01

PREPARED
REVISION
NO.

NAME

00

SG

01

SG

DATE
22 OCT
2013
15 JAN
2014

MECH
SYSTEM

REVISION CERTIFICATION
REVIEWED
NAME
MECH
ELECT
CIVIL
PIPING

APPROVED
C&I

SH

ARU

SH

ARU

DATE
22 OCT
2013
15 JAN
2014

NAME

DATE
22 OCT
2013
15 JAN
2014

AKM
AKM

REVISION SUMMARY SHEET

REV.

Rev.:- 01

DETAILS / DESCRIPTION

DATE

00

FOR APPROVAL

22 OCT 2013

01

FOR APPROVAL

15 JAN 2014

Date :- 15 JAN 2014

Issued for Approval


Project Code :- KWU3025

2 of 5
Approved By :- AKM

ALGHANIM INTERNATIONAL GENERAL


TRADING AND CONTRACTING COMPANY

MINISTRY OF ELECTRICITY AND WATER


Contract No. : MEW/C/4608-2013/2014

Project : Supply, Erection, Operation & Maintenance


of Gas Turbines to Upgrade Power Capacity at Sabiya
Power & Distillation Plant Site.

Document Title : UPS SYSTEM SIZING CALCULATION


Document No. : A/SE/DCSY-CAL/101219 Rev. 01

TABLE OF CONTENTS
1.0

PURPOSE AND SCOPE....................................................................................................................... 4

2.0

DESIGN INPUTS .................................................................................................................................. 4

3.0

ASSUMPTIONS .................................................................................................................................... 4

4.0

METHODOLOGY .................................................................................................................................. 4

5.0

ACCEPTANCE CRITERIA .................................................................................................................... 4

6.0

CALCULATIONS ................................................................................................................................... 5

7.0

RESULTS .............................................................................................................................................. 5

8.0

REFERENCES ...................................................................................................................................... 5

9.0

ATTACHMENTS ................................................................................................................................... 5

Rev.:- 01

Date :- 15 JAN 2014

Issued for Approval


Project Code :- KWU3025

3 of 5
Approved By :- AKM

ALGHANIM INTERNATIONAL GENERAL


TRADING AND CONTRACTING COMPANY

MINISTRY OF ELECTRICITY AND WATER


Contract No. : MEW/C/4608-2013/2014

Project : Supply, Erection, Operation & Maintenance


of Gas Turbines to Upgrade Power Capacity at Sabiya
Power & Distillation Plant Site.

Document Title : UPS SYSTEM SIZING CALCULATION


Document No. : A/SE/DCSY-CAL/101219 Rev. 01
1.0
PURPOSE AND SCOPE
The purpose of this calculation is to select rating of Station Uninterrupted Power Supply (UPS) for the
proposed Sabiya 500 MW Open Cycle Gas Turbine Project. It will cater to the load of Main Plant
DCS, PLCs of various packages, Instruments and any other AC load of the plant that needs
uninterrupted power supply.
Scope
The scope of this calculation includes sizing of Station Uninterrupted Power Supply (UPS) for the
proposed Sabiya 500 MW Open Cycle Gas Turbine Project.

2.0

DESIGN INPUTS

2.1

Owners specification / Tender document, Doc. No.: MEW/8-2012/2013.

2.2

UPS load list from C&I.

3.0

ASSUMPTIONS/CONSIDERATIONS [U-UNVERIFIED INPUT, EJ-ENGINEERING


JUDGEMENT]

3.1

Loads are obtained in KVA only. However, wherever loads are obtained in KW, a power factor of 0.85
is considered to derive into equivalent KVA. [EJ]

3.2

Load factor for Continuous loads (C) is considered as 1 whereas for Intermittent (I) loads, it is
considered as 0.3. [EJ]

3.3

Rating of various Loads considered shall be verified after receipt of vendor inputs [U].

3.4

For Data Centre, ADCS, Siemens GTG and IPBX separate UPS shall be procured & sizing for the
same is out of scope of this calculation.

4.0

METHODOLOGY

4.1

Total loads are calculated in KVA from the design inputs.

4.2

25% design margin is considered in UPS sizing as per clause no 5E.8.2 of Volume 4 of 8, Section 5E.

4.3

Final UPS rating is arrived at 50 deg C.

4.4

Calculations have been done using following software:


Microsoft Excel - 2010 (MS-Office 2010, Windows XP Professional)

5.0

Rev.:- 01

ACCEPTANCE CRITERIA

Date :- 15 JAN 2014

Issued for Approval


Project Code :- KWU3025

4 of 5
Approved By :- AKM

ALGHANIM INTERNATIONAL GENERAL


TRADING AND CONTRACTING COMPANY

MINISTRY OF ELECTRICITY AND WATER


Contract No. : MEW/C/4608-2013/2014

Project : Supply, Erection, Operation & Maintenance


of Gas Turbines to Upgrade Power Capacity at Sabiya
Power & Distillation Plant Site.

Document Title : UPS SYSTEM SIZING CALCULATION


Document No. : A/SE/DCSY-CAL/101219 Rev. 01
5.1

The selected UPS will be able to supply the required power for continuous operation of the connected
load.

6.0

CALCULATIONS

6.1

The calculation is as per attached Attachment I for UPS sizing.

7.0

RESULTS

7.1

The selected rating of UPS is 135 kVA (Output kVA) at 50deg.C design ambient.

8.0

REFERENCES

8.1

Owners specification / Tender document, Doc. No.: MEW/8-2012/2013

9.0

ATTACHMENTS

9.1

Attachment I : UPS Sizing

Rev.:- 01

Date :- 15 JAN 2014

Issued for Approval


Project Code :- KWU3025

5 of 5
Approved By :- AKM