INTRODUCTION
The Taj Trapezium Zone, which is in the form of trapezoid is between 27 030’N &
77030’E to 27045’N & 77015’E and 26045’N & 77015’E to 27000’N & 78030’E, was
notified by the Government of India for intensifying efforts prevention and control of
pollution. In 1999, , the Ministry of Environment and Forest, Government of India has
notified the Taj Trapezium Zone (Pollution Prevention and Control) Authority for
protection and improvement of the environment in the Trapezium.
(c) DG Sets
Due to power breaks daily, a number of DG sets are used in the city. The fuel consumed
by the DG Sets by different sectors and the average consumption of diesel varies as per
the capacity of the generators.
350
300
3
g/m )
250
SOURCES FROM www.cpcb.nic.in and www.google.co.in 3
Action Plan for the Control of Air Pollution for the city of Agra ( As
on October 2003)
The salient features of actions taken to control industrial pollution are as follows:
In zone I,II & III 114 industries are drawing natural gas for use in production
processes.
Strict vigil on compliance of 292 industries that were directed by the Supreme Court
not to use coal or coke. Out of 292 industries 87 has been connection for CNG by
GAIL.
All the brick kilns within the radius of 20 kms of significant monuments of Agra
city have been closed.
New Industries using coal and coke are not being allowed to set up in Agra
Trapezium zone in Uttar Pradesh.
Regular monitoring of ambient air quality in the Agra city. Currently four monitoring
stations are there in the Agra city.
The salient features of actions plan to control industrial pollution are as follows:
It is proposed to supply CNG as fuel for processing /production & it is also proposed
to replace DG sets with Gas generators. It is proposed to implement the same in
different zone in the following manner:
Zone-I : Already started.
Zone-II & III : By Sept’02 laying of pipe lines expected & by supply expected by
Oct 2002.
Zone-IV: If gas is available then one year from the date of approval
Restriction on supply and usage of coal. Coke, wood, rice husk, baggase to the
industries situated in the city limit of Agra.
D.G sets installed by Industries/ commercial establishments in no gas zones shall be
fitted with wet scrubber 7 acoustic enclosures.
Only small scale Service & Business related Enterprises (SSSBE) that are essentially
required within the city, should be allowed in the designated commercial areas/
authorized markets/ authorized shopping plaza.
Strict vigil on compliance of 292 industries that were directed by the Supreme Court
not to use coal or coke.
Petha Industries operating in the city shall be shifted to Kalindi Vihar site identified
for this industry and shall operate by CNG/LPG only
Setting up of CNG/LPG retail outlets within Agra City for supplying CNG/LPG
to the vehicles in a phased manner. For the establishment of CNG station for
vehicles and piped natural gas at Agra the total project cost will be around Rs.
102 crores The detailed engineering work are in progress fro project
implementation. One Auto LPG dispensing station is already stationed and is
expected to be operational by October 2003.
Phasing out grossly polluting vehicles plying within the city in a phased manner.
Commercial vehicles including 3 wheelers, Tempo, Auto Rickshaws, Taxis,
Buses etc being used for public transport are proposed to be converted to clean
fuel like CNG/ LPG etc in a phased manner. Till; such time these vehicles shall be
fitted with wet scrubber /filter and a notification for compulsory wet scrubber /
dry filter shall be made.
Stop plying diesel driven tempo-taxis and auto rickshaws on MG road and
prohibition of all type of commercial vehicles within the radius of 500 mts of Taj
Mahal.
Notification and compliance for fitting of filter/wet scrubber in tempo, Taxi, 3
wheeler, city buses diesel ambassador taxi, commercial jeeps, light / medium
goods vehicles heavy goods vehicles registered in Agra.
Supply of ultra low sulphur diesel (0.05%) and premixed petrol in Agra.
Ban on supply of loose 2T oil at petrol pumps and supply of only premixed 2T oil
gasoline in all petrol pumps
Checking for adulteration.
Strict checking of vehicular emissions &PUC.
Better traffic management.
Introduction of clean fuels like CNG/LPG
For CNG two online stations and 5 daughter stations are proposed to be
commissioned by GAIL within 15 months after approval .In zone –I CNG is
already being supplied, Zone-II & III it is proposed to supply CNG by Oct’02
while in Zone-IV supply will be ensured within one year after approval. While
zone-V is no gas zone.
For LPG work has been initiated for establishment of one Auto LPG stations by
IOC. One workstation has been established by IOC and supply is expected within
one month.
Findings
SO2 levels are with the prescribed National Ambient Air Quality Standards for sensitive
areas. The reason for low levels of SO2 may be various measures taken such as reduction
of sulphur in diesel, implementation of stricter emission norms and commensurate fuel
quality. NO2, RSPM and SPM levels exceed the prescribed National Ambient Air Quality
Standards for sensitive areas. The reason for high particulate matter levels may be