You are on page 1of 8

Item

Description

Qty

Unit

BILL B - ELECTRICAL & DATA NETWORK


INSTALLATIONS BOQ
MHAS OFFICES AT BASEMENT LEVEL, EVANS
BUILDING, VALLETTA
Before materials are ordered, measurements are to be
taken on site and take-off's are to be done in
accordance with approved working drawings.
ELECTRICAL INSTALLATION
1.0

De-energize, disconnect and remove all electrical and


ELV redundant switchgear, conduit, wiring and cables
from the new MHAS Offices and from the electrical
switchroom. Existing switchgear supplying the various
departments and floors of Evans building are to remain.
Servicable items are to be handed over to the Project
Manager and unservicable items are to be carted away.
The redundant switchgear in the electrical switchroom
includes 3 distribution boards (marked Electoral Office)
and 4 switches. All services are to be removed and
shifted where the door to the switchroom is to be
opened.
The price is to include circuit tracing and all coordination and attendance with Enemalta staff when the
suspension of electrical supply is required from
Enemalta.

2.0

3.0

Lump
sum

no.

no.

24
6

m
m

Supply, install and connect a 400 Amp Main Panelboard


MPB as specified including the devices shown in the
distribution board schedules, electronic metering unit, 2
electronic sub-meters, current transformers and voltage
tap-offs with protection fuses. The panelboard has to
enter and fit in the space available.

Supply and install in the main switchroom in the


basement, one set of 4 pole, electrically and
mechanically interlocked, automatic motorized changeover switches CO1, as specified, rated minimum 160
Amps, for operation with a standby generator.

4.0

Supply and install galvanized steel cable tray for power


multicore cables complete with fittings and supports.

4.1
4.2

150mm wide
200mm wide
Page total carried forward
Page 1

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


5.0

De-energize, disconnect and remove the main switch


and cables of the Enemalta metering cubicle marked
"Evans".
The price is to include all co-ordination and attendance
with Enemalta staff when the suspension of electrical
supply is required from Enemalta to remove the main
switch and connect panelboard MPB.

6.0

7.0

7.1

8.0

8.1
8.2
8.3

Lump
sum

The single cores are not to pass through steel gland


plates in order to avoid Eddy Currents. (Aluminium
gland plates can be used).
The length shown in metres is the route lenght
consisting of 5 single cores, total length 35 metres.

Supply, install and connect on cable tray the following


copper conductor, XLPE insulated, PVC sheathed
cables including terminations, cable glands, cable ties
but excluding the cable tray:
From the Main Panelboard MPB to the existing mccb of
the first floor in the switchroom, 5 core x 70 sqmm
XLPE/PVC.

Supply, install and connect the following metalclad


distribution boards with hinged lockable door and all the
devices as specified in the distribution board
schedules:
DB1 in the switchroom, complete with the specified
surge protective device.
DB5 in the switchroom.
DB-U1 in the IT room.

1
1
1

no.
no.
no.

no.

no.

Supply, install and connect from the Enemalta metering


cubicle marked "Evans" to the Main Panelboard MPB, 5
x 1 core x 150 sqmm, copper conductor, XLPE
insulated, PVC sheathed single core cables.

9.0

Supply, install and connect the following isolators,


lockable in the OFF position:

9.1

63A, 4 pole, IP65 isolator for outdoor unit of VRF


system.
32A, 2 pole, IP65 isolator for outdoor unit of A/C split
unit of IT Room.

9.2

Page total carried forward

Page 2

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


10.0 Supply and install 180mm high x 60mm deep (minimum
dimensions), 2 compartment, CAT 6, UPVC power and
data skirting trunking and fittings as specified including
trunking covers, steel screening divider between the
power and ELV compartments, external and internal
corners, joint covers, tees, flat angles, cable retainers
and end caps.
The trunking and the fittings shall be used for 230 Volt,
50 Hz power and UTP network cables, shall be supplied
from the same manufacturer and no site fabrication of
fittings shall be accepted.
The steel EMI screening divider shall be bonded to
earth and shall be electrically continuous throughout the
whole length of trunking by means of earth straps
supplied by the manufacturer of the trunking and by
protective conductor (earth) links.
The power and data outlets shall be fixed in an upper
compartment so that 13Amp plugs with moulded cord
can fit without hitting the floor.

357

11.0 Supply and install 50 mm diameter PVC pipe and


fittings to link the DATA (UTP) trunking compartment
across doors including the floor chasing. Long sweep
bends in the pipework shall be done to avoid sharp
bends.(One pipe cross per door)

60

12.0 Supply and install 25 mm diameter galvanized steel


conduit and fittings to link the POWER trunking
compartment across doors including the chasing and
conduit gland terminations. (One conduit cross per
door)
The earth continuity of the steel screen divider of the
trunking is to be maintained by protective conductor
(earth) cable links.

60

13.0 Supply and install 75mm x 75mm galvanized steel


trunking for 400/230 Volt wiring including fittings and
supports.

125

52
25

m
m

14.0 Supply and install galvanized steel cable tray for power
multicore cables complete with fittings and supports.
14.1 100mm wide
14.2 150mm wide

Page total carried forward

Page 3

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


15.0 Supply and install 100mm x 50mm white UPVC trunking
and fittings.

12

52

46

17.0 Supply and install hand dryer as specified.

no.

18.0 Supply and install 1 core x 16 sqmm protective (earth)


conductor from the main earth terminal to the earth
terminals of MHAS IT cabinets 1 and 2.

16

6
26

no.
no.

141

no.

no.

no.

no.

no.

no.

16.0 Supply, install and connect on cable tray the following


copper conductor, XLPE insulated, PVC sheathed
cables including terminations, cable glands, cable ties
but excluding the cable tray:
16.1 From the Main Panelboard to DB5, 5 core x 95 sqmm.
16.2 From DB5 to change-over switches CO1, 5 core x 50
sq mm.
16.3 From change-over switches CO1 to DB1, 5 core x 50
sq mm.
16.4 From DB5 to isolator of VRF system no.1, 5 core x 10
sq mm.
16.5 From DB5 to isolator of VRF system no.2, 5 core x 10
sq mm.

19.0 Supply, install and connect the following power points


including the conduit, wiring accessories and the wiring
specified in the distribution board schedules but
excluding the trunking.
Wiring shall be installed in surface electrical trunking
above false ceiling and in skirting trunking (for power
points on trunking) where this is shown on drawings
and in conduit elsewhere. Conduit shall be installed
surface above false ceiling and buried below.
19.1 Single 13A socket outlet on wall.
19.2 Twin 13A socket outlet on wall.
19.3 Twin 13A socket outlet on an upper compartment of the
skirting trunking including trunking clip on box.
19.4 13A switched fused spur outlet on the wall for hand
dryer.
19.5 13A switched fused spur outlet on the wall for electric
water storage heater.
19.6 13A switched fused spur outlet on the wall for
ventilation fan.
19.7 13A unswitched fused spur outlet on the wall for fire
alarm panel at GF reception.
19.8 13A unswitched fused spur outlet on the wall for
intrusion alarm panel in the IT room.
Page total carried forward
Page 4

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


19.9 13A switched fused spur outlet on the wall for electric
door at main entrance.
19.10 13A switched fused spur outlet for access controller.
19.11 13A unswitched fused spur outlet for power supply unit
of CCTV camera.
19.12 40 Amp, 2 pole isolator of a/c close control unit in the
printing room.
19.13 32 Amp, 2 pole isolator of a/c close control unit in the
strong room.
19.14 13A switched fused spur outlet A/C indoor unit of VRF1.

no.

no.

20

no.

no.

no.

10

no.

no.

Lump
sum

15

18

32

no.

no.

no.

no.

19.15 13A switched fused spur outlet A/C indoor unit of VRF2.

20.0 Supply, install and connect 3 core PVC/PVC cables:


20.1 3 core x 4 sq mm from DB1 to a 2 pole, 16Amp mcb in
MHAS IT cabinet no.1 and from the mcb to the rack
mounted UPS, including the mcb and its enclosure.
20.2 3 core x 4 sq mm from the rack mounted UPS no.1 to
DB-U1.
20.3 3 core x 4 sq mm from DB1 to a 2 pole, 16Amp mcb in
MHAS IT cabinet no.2 and from the mcb to the rack
mounted UPS, including the mcb and its enclosure.
20.4 3 core x 2.5 sq mm from DB2 to 2 isolators of outdoor
units of a/c split units of the IT Room, on 100 mm cable
tray but excluding the tray.
21.0 Supply and install conduit, wiring, cables, switches and
microwave presence detectors with light sensors, all as
specified, for the following light points.

21.1
21.2
21.3
21.4

Wiring shall be installed in surface electrical trunking


above false ceiling where this is shown on drawings
and in conduit elsewhere. Conduit shall be surface
fixed above the false ceiling and buried below.
Where there is no false ceiling (IT room, main
circulation area near reception and archives room) the
prices shall include also the supply and installation of
white UPVC trunking fixed to the ceiling.
1 light point on 1 microwave presence detector & light
sensor and 1 switch.
2 light points on 1 microwave presence detector & light
sensor and 1 switch.
3 light points on 1 microwave presence detector & light
sensor and 1 switch.
3 light points on 2 microwave presence detector & light
sensor and 1 switch.
Page total carried forward
Page 5

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


21.5 4 light points on 1 microwave presence detector & light
sensor and 1 switch.
21.6 4 light points on 2 microwave presence detector & light
sensor and 2 switches.
21.7 5 light points on 1 microwave presence detector & light
sensor and 1 switch.
21.8 5 light points on 2 microwave presence detector & light
sensor and 1 switch.
21.9 6 light points on 2 microwave presence detector & light
sensor and 2 switches.
21.10 8 light points on 2 microwave presence detector & light
sensor and 1 switch.
21.11 9 light points on 2 microwave presence detector & light
sensor and 1 switch.
21.12 9 light points on 4 microwave presence detector & light
sensor and 2 switches.
22.0 Supply and install conduit, wiring, cables, and switches
for the following light points.
Wiring shall be installed in surface electrical trunking
above false ceiling where this is shown on drawings
and in conduit elsewhere. Conduit shall be surface
fixed above the false ceiling and buried below.
22.1 1 light point on 1 switch.
22.2 2 light points on 1 switch.
22.3 6 light points on 1 switch.
22.4 8 light points on 2 switches.
22.5 Stand-alone emergency light point.

no.

no.

no.

no.

no.

no.

no.

no.

6
1
1
1
1

no.
no.
no.
no.
no.

33
16
5
5
3
2
10
8
1

no.
no.
no.
no.
no.
no.
no.
no.
no.

12

no.

23.0 Supply, install and connect the following light fittings as


specified including lamps, cut-outs in the false ceiling
where applicable, connection cable and accessories:
23.1
23.2
23.3
23.4
23.5
23.6
23.7
23.8
23.9
23.10

Type A1 (4x14W, recessed)


Type A1 with emergency pack
Type A2 (3x14W, recessed)
Type A2 with emergency pack
Type B1 (18W, recessed)
Type B1 with emergency pack
Type B2 (26W, recessed)
Type B2 with emergency pack
Type B3 with emergency pack(2x26W, recessed)
Type C,(2x54W, fluorescent tube, diffuser)
The luminaire shall be supplied with end kits, power
supply and incoming cable connectors, links, wire
suspension kits and all other accessories which shall be
supplied from the same luminaire supplier as part of the
lumianire kit.
Page total carried forward

Page 6

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


23.11 Long in-fill (1.5 m long) in between 2 type C luminaires
to create a continuos row complete with power
connectors and all accessories.
23.12 Type C with emergency pack
23.13 Type D,(2x35W, fluorescent tube, louvre)
23.14 Type D with emergency pack
23.15 Type E1 (standalone emergency luminaire)
23.16 Connect only type G light fitting in partition supplied by
the Client, supplied from the false ceiling.

17
7
7
3
1

no.
no.
no.
no.
no.

no.

24.0 Supply and install rigid plastic photoluminiscent signs


emergency exit / route sign, to EC Directive (running
man), approx. 200mm x 100mm. Full details of
directions will be given at installation stage.

no.

25.0 Supply, assemble and connect 2 compartment power


and CAT 6 data pole for the island desk including
installation kit and anchoring to the floor and structure
ceiling.The price shall include the mounting boxes for
the power and data outlets and all installation
accessories such as earth strips and hardware.

no.

26.0 Supply and install above false ceiling a heavy duty


electrozinc cable basket complete with fittings and
supports to be used for the ICT cables (UTP, fibre optic
and telephone cables).
26.1 200mm wide and 50mm high

92

27.0 Supply and install 50mm diameter PVC pipe and fittings
(chased in the wall or in partition, as applicable in
accordance with the drawings) for the UTP cables from
the cable basket to the skirting trunking, including wall
chases.
Long sweep bends are to be used instead of 90 degree
bends. The branch-offs from the cable basket are
shown on the cable management drawings.

23

no.

28.0 Supply and install 25 mm pvc conduit and fittings from


the skirting trunking to the flush-mounted RJ 45 outlet
installed on the wall including 75mm x 75mm conduit
box (for network cameras, WiFi points, TV points,
access controllers, etc) .

31

no.

DATA NETWORK INSTALLATION (To MITA


Standards)

Page total carried forward

Page 7

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

Item

Description

Qty

Unit

Page total of previous page brought forward


29.0 Supply and install CAT 6 UTP cable on cable basket
and in the data compartment of the skirting trunking
from the patch panel in the IT cabinet to the CAT 6
RJ45 outlets, excluding the trunking.

160

cables

30.0 Supply and install CAT 6 twin RJ 45 outlet on the


skirting trunking including mounting frame.

no.

31.0 Supply and install CAT 6 triple RJ 45 outlet on the


skirting trunking including mounting frame.

33

no.

32.0 Supply and install CAT 6 quadruple RJ 45 outlet on the


skirting trunking including mounting frame.

no.

33.0 Supply and install CAT 6 single RJ 45 outlet on buried


conduit box (for network cameras, WiFi points, TV
points, access controllers, etc) .

21

no.

34.0 Supply and install CAT 6 twin RJ 45 outlet on buried


conduit box (for network cameras, etc).

no.

35.0 Terminate and label CAT 6 UTP cable end on RJ 45


outlet and on Patch Panel.

160

no.

lump
sum

37.0 Carry out all civil works and fire sealing measures
required for the electrical and data installations.

Lump
sum

38.0 Supply 3 sets of Working Drawings in accordance with


the latest architectural layouts, finishes and
requirements for approval before the installation is
started. Amend and correct the drawings in accordance
with the comments of the Engineer for issue of the
drawings for construction.

lump
sum

lump
sum

lump
sum

36.0 Test and certify all CAT 6 UTP cables and terminations
as specified and supply test reports.

GENERAL ITEMS

39.0 Supply 3 sets of As Fitted Drawings of the electrical and


data network installations on print and one copy on disk.

40.0 Inspect, set, programme, test, label, commission and


certify all the electrical works.
Total for electrical and data network installations

Page 8

Rate
(incl. of
VAT)
Euro

Amount
(incl. of VAT)
Euro

You might also like