Professional Documents
Culture Documents
DOC NO AATC000859
CONTENTS
Page
AIM
DEFINITIONS
3.1
Material Characteristics
4.1
4.2
4.3
Environmental Aspects
13
4.4
Standardisation
13
4.5
Belt Conveyors
14
4.6
Chutes
30
4.7
32
4.8
Fire protection
36
4.9
36
4.10
47
52
5.1
52
5.2
Conveyor Structures
53
5.3
54
5.4
Cladding of structures
55
5.5
Civil
57
5.6
Corrosion Protection
57
INTERFACES
60
6.1
Civil
60
6.2
Electrical Engineering
60
6.3
Instrumentation
61
REFERENCES
62
7.1
62
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 2 of 68
IMPLEMENTATION 11/22/2013
7.2
DOC NO AATC000859
63
REVISION HISTORY
64
APPENDICES
65
9.1
65
9.2
66
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 3 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
AIM
The purpose of this document is to provide generic design criteria and guidelines for AATC
surface infrastructure projects related to the Mechanical and Structural Steel Engineering
disciplines. Certain basic civil aspects which directly impact on the mentioned disciplines are
also covered but not from a design perspective.
Underground systems are covered under the AATC Underground Conveyor Design Guide
document number AATC000860.
The intent of the document is not to present detailed design information for each component and
system, but rather to outline guidelines and certain mandatory requirements not contained in
specifications. Any particular information not contained herein must be developed during
detailed design stage to support equipment and erection specifications.
This document shall be read in conjunction with the relevant Anglo American Specifications as
quoted, which shall be issued as part of the equipment and/or contract enquiry documents.
In project specific cases where the need arise to deviate from any item in this document a
concession must be submitted to and approved by the Engineer in writing.
Where an item is specified with a note stating or equivalent, the Engineer shall be requested in
writing to grant permission to use such an alternative.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 4 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
DEFINITIONS
Term
Definition
AATC
AFRS
APW
Approved
BMH
BS
British Standard
BS EN
CEMA
CMA
DMR
Engineer
ESS
HAZOP
ISO
MCC
OEM
PFD
P & IDs
PLC
PSD
SANS
SIB
Stay in Business
ROM
Run of mine
VSD
FEL
Phases
(Refer
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
to
APW
Page 5 of 68
IMPLEMENTATION 11/22/2013
3.1
Material Characteristics
3.1.1
DOC NO AATC000859
The table below indicates the design parameters to be used in all material handling
systems. Material flow tests should ideally be conducted during FEL 2 so that the design
data is available when FEL 3 commences.
Duty
ROM material
Contamination
Bulk density
(volumetric)
Total moisture
content
Average
12 %
Dry season 8 %
Wet season 15 %
(Guideline only, reserve specific)
Angle of repose
Bulk densities
Raw coal
Product
Discards
Guideline only - For specific project information refer to the bulk solids
flow reports or confirm with AATC metallurgy.
Table 1 General Design Parameters
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 6 of 68
IMPLEMENTATION 11/22/2013
4.1
DOC NO AATC000859
4.1.1.1 The design and construction of all works shall be carried out in accordance with all
applicable laws, regulations and standards. This document is regarded as a guideline
with certain mandatory requirements. Applicable standards which are not listed must be
included by the designer or supplier.
4.1.2
4.1.2.1 The list of Anglo American Specifications referred to in this document is provided in
Section 7 References.
4.1.3
4.1.3.1 Unless specifically stated otherwise, designs shall be based on the applicable parts of
the latest revision of the Codes, Specifications, Standards, Regulations and other
documents. The list of the codes, specifications, standards and regulations referred to
in this document provided in Section 7 References. In addition, the design must comply
with local legislation and regulations as stipulated by the DMR.
4.1.3.2 In the event of conflicting requirements, the most stringent will apply.
4.1.3.3 For conveyor designs, ISO 5048 will take preference over CEMA requirements.
4.1.3.4 The following protocol will be used where specifications are required:
1) Available Anglo American specifications must be used.
2) If no Anglo specifications are available, refer to the most relevant SANS
specification.
3) If no SANS specifications are available, international specifications recognised
within the industry may be applied.
4.2
4.2.1
General
The layout of materials handling systems must be conducted in view of an optimal
balance between operational costs and capital expenditure.
Where the implementation of new technology is considered viable, a trade off study
must be done against the conventional approach.
Designs must be carried out with consideration for the reduction of fines generation.
4.2.2
Tips General
The layout of tips must be such that free access with mobile cranes is possible from both
sides.
The topography of the location can often be used to minimise the ramp height and excavation
depth. However, free drainage is mandatory.
On certain large and more complex tip configurations, typically associated with previously
undermined reserves, an overhead crane may be required. On these installations only roof
sheeting will be required.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 7 of 68
IMPLEMENTATION 11/22/2013
4.2.3
DOC NO AATC000859
Dust hood
Passive dust suppression is mandatory on all new tip installations. The passive system
may be aided by the intermittent use of a spray system as and when required.
The volumetric design of the hood structure is somewhat specialised but essentially it
needs to provide enough volume so that the displaced air, as a consequence of the
tipping operation, can settle down such that dust pollution is minimised.
Installations must be equipped with used fire retardant conveyor belt installed in a
specific internal baffle arrangement to enable dust particles to settle out.
The ratio of the dust hood width/truck width must fall within a range of 1.8 to 2 in order to
ensure easy truck manoeuvrability and to avoid mechanical damage. Columns must
ideally be integrated with the wing walls and bin structure to eliminate structural damage.
The walls of the bin must be raised to prevent damage to the sheeting by large rolling
lumps when the bin is full or where grizzly cleaning operations are anticipated.
Safe access to the roof is required for the maintenance of lighting etc.
The orientation of the hood must ideally be such that the prevailing wind direction is
towards the tipping face i.e. into the hood.
4.2.4
Jockey Slab
The jockey slab must be equipped with cast-in rail liners to facilitate cleaning operations.
The ideal height of the wheel stopper must be 67% of the wheel diameter. Special
consideration is required where different truck types are anticipated. The steel cover
plate must be submerged well into the concrete such that it cannot be lifted during
cleaning operations by a front end loader. Avoid any ledges that can initiate material
build up.
Where a concrete bin is utilised, the jockey slab will be integrated with the wing walls
and bin structure. For a steel bins however, the jockey slab will be independent.
4.2.5
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 8 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
will be mined. The philosophy is that large lumps can be removed safer at an inspection
feeder at a lower level in the tip, which is equipped with an overhead crane.
Grizzly bars and support structures must be designed to safely withstand the impact
energy associated with the tipping operation and where applicable, the hydraulic rock
breaker.
4.2.6
4.2.7
Tip bin
The volume of the tip bin is generally taken as 2 to 3 times the capacity of the hauling
trucks but must be justified by simulation or calculation.
Steel bins should only be considered for an anticipated mining life of less than 15 years
because of corrosion considerations. All other installations must be constructed out of
concrete.
Concrete bin constructions can be integrated well with the dust hood, wing walls and
wheel stoppers.
Concrete bins must be equipped with casted in rail liners.
Discharge arrangement designs should be based on mass flow system. Appropriate
material release angles to be applied.
4.2.8
Tip feeders
The draw off pattern achievable is a function of the geometry of the interfacing plate
work. The design must be such that tipping space is continuously created at the tipping
face of the bin.
Big lumps must specifically be catered for on large operations. However, at small
operations, a trade off is required to ensure that capital cost remains at an acceptable
level.
Where previously undermined areas are included in the mining plan, the preference is to
use a conventional apron feeder. Apron feeders are generally orientated in line with the
tipping face such that dribbling is collected on the clearance conveyor.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 9 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Flight bar feeders may be used on mini-tips and larger operations where virgin areas are
mined but the bin interface requires careful consideration.
The orientation of these feeders i.e. parallel or perpendicular to the tipping face is project
specific.
A perpendicular arrangement provides good maintenance access but the tail end of the
tip clearance conveyor cannot be utilised as a spillage conveyor. A parallel configuration
is therefore preferable when using a conventional apron feeder.
A perpendicular arrangement is usually preferable when using a flight bar type feeder
but not mandatory.
4.2.9
Page 10 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 11 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
of explosion panels.
Silos and bins are generally designed for expandable flow conditions in the upper region
with mass flow conditions at the discharge hopper.
4.2.17 Silo and bunker trade-offs
Although several project specific considerations will influence the selection, Table 2
below is to be used as a guideline.
Surge / storage structure
Comment
Up to 1 000
Silo
1 000 to 6 000
up to 10 000
2 500 to 15 000
Bin, steel
Bunker, (RE C)
Bunker, longitudinal
> 6 000
RC / RC P / RE L
Where:
RC = Reinforced concrete
RC P = Reinforced concrete with pre-cast elements
RE C = Reinforced earth, circular
RE L = Reinforced earth, longitudinal
Whenever the required surge or storage capacity is close to the threshold values indicated
above, a trade-off study would be required unless an option can be ruled out because of
specific project requirements or constraints.
Table 2 Selection guideline for silos & bunkers
Page 12 of 68
IMPLEMENTATION 11/22/2013
4.3
DOC NO AATC000859
Environmental Aspects
4.3.1.1 Environmental aspects are regulated by local Legislation. Items listed below merely
highlights some important considerations directly related to designs.
4.3.1.2 All designs shall be carried out such that the impact that mining operations have on the
environment is minimised. Of particular concern are water, dust and noise pollution.
4.3.1.3 All water that arises within the conveyor area shall be contained and channelled to the
polluted water handling system.
4.3.1.4 Overland conveyors transporting material outside the boundaries of the polluted area
must be equipped with belt turnovers at the head and tail to avoid material carry back
along the conveyor. Turnovers are problematic on wide conveyors. Overland conveyors
used for AATC projects are generally less than 1500 mm wide such that turnover
designs are possible.
4.3.1.5 Generation of dust shall be strictly controlled by avoiding degradation of the coal and
the dust that is generated shall be controlled by both passive and active means.
4.3.1.6 The noise generated by the plant shall be minimised by selecting inherently quiet
equipment and processes and, where unavoidable, acoustic enclosures.
4.3.1.7 Special note shall be taken for electrical drives that are electronically controlled which
have an inherent noise generation through the motor drive shaft. This shall be taken
into account with respect to noise abatement. Noise abatement technical information
shall be obtained from the drive manufacturer. Resonance points, if applicable, shall be
provided in the ramp-up to full speed.
4.4
Standardisation
4.4.1
General
The selection of major equipment must not be done in isolation. Equipment already used
within AATC must be considered.
When selecting conveyor belting for purposes of an FEL 3 Study or Detail Design,
belting already used at AATC operations must be considered.
For SIB type project designs, it is essential to stick to standard equipment and supplier
brands which are already used at the specific Operation unless the deviation can be
motivated.
A preferred vendors list is provided in Appendix A: Preferred Vendor List. Vendors not
listed are not necessarily excluded nor are vendors tabulated in order of preference.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 13 of 68
IMPLEMENTATION 11/22/2013
4.5
Belt Conveyors
4.5.1
DOC NO AATC000859
Conveyor designs are to be in accordance with the latest ISO 5048 Standard,
Continuous mechanical handling equipment and guidelines prepared by Conveyor
Equipment Manufacturers Association (CEMA).
Conveyors must be designed for continuous operation and starting under full design
load.
4.5.2
Standardisation
4.5.2.1 The conveyor designer is to give consideration to economical design while rationalising
mechanical components for optimum spares holding and interchangeability. The
process shall be based on component priority selection as follows:
Priority 1 belting
Priority 2 - drives
Priority 3 - pulleys
Priority 4 other
In view of power savings, right-sizing must be traded off against standardisation.
4.5.3
Vertical inclination
4.5.3.1 The maximum permissible angle of inclination shall be dictated by the material, particle
size distribution, type of loading, belt speed etc. of the particular design.
4.5.3.2 The maximum inclination angle shall however not exceed 13.
4.5.3.3 Where material run-back on the conveyor is expected e.g. conveyors exclusively
handling screened oversize or spherical type lumps, conveyor inclinations will be kept
below 10.
4.5.3.4 For stacker boom belts, the inclination angle, and subsequently the angle at which
material is loaded, will be limited to 14.
4.5.3.5 For normal loading conditions, with the tail pulley positioned for full trough, the conveyor
incline should be 0.5 to provide effective drainage.
4.5.3.6 The maximum incline at loading shall not exceed 5
4.5.4
Vertical curves
Dynamic calculations must be performed for all vertical curves to ensure safe and
reliable conveyor operation. Calculations must be based on the worst case combination
of conveyor loading and geometry.
A suitable factor, taking cognisance of the start-up device, must be applied to the
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 14 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
calculated dynamic start-up tensions when calculating the required concave radius.
4.5.4.1 For concave curves, the following criteria should be met:
On all conveyors featuring trippers (eg. stacker feed conveyors), the belt shall not lift off
the radius during start-up or normal running when loaded to 15 % of the conveyors
maximum design capacity in the curve only, with the rest of the belt fully loaded for the
load-case causing highest tension in the curve. The belt mass used for these
calculations shall be based on 50 % top cover wear. Belt-lift control must be considered
where it is not possible to satisfy these criteria.
For cases where the rear tangent point is close to the feed chute, the above calculation
shall be repeated with load up to the rear tangent point and no load on the belt in the
curved section to ensure that the belt will never lift into the chute or skirt sections.
On all other conveyors, the belt shall not lift off the radius during start-up or normal
running when empty. The belt mass used for these calculations shall be based on 50 %
top cover wear.
Centre tension in the curve area shall be limited to 115 % of the maximum rated tension
for the particular conveyor.
The edges of the belt shall not buckle in the curve area.
4.5.4.2 For convex curves, the following criteria should be met:
The additional stress imposed on the idlers as a result of the convex curve shall not
lead to idler shaft deflections and idler bearing lives that do not comply with Anglo
specifications.
Edge tension in the curve area shall be limited to 115 % of the maximum rated tension
for the particular belt.
The centre of the belt shall not buckle in the curve area.
4.5.5
4.5.6
Conveyor Dynamics
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 15 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.6.1 All conveyors shall be analysed for behaviour during starting (for vertical curves),
coasting and where applicable, braking.
4.5.6.2 For conveyors >1 km, or where special profiles are encountered, dynamic transients
and the application of torque prior to starting must be considered.
4.5.7
4.5.7.1 Conveyor design capacities shall be calculated from the Life of Mine plan and recorded
on a flow sheet. Only the approved flow sheet capacities shall be used for detail
conveyor designs.
4.5.7.2 The width of belt shall be selected as follows:
For a maximum lump size up to 180 mm: Flow sheet peak capacity and the standard
recommended edge distance shall be used according to the latest ISO 5048 Standard,
Continuous mechanical handling equipment and CEMA.
The designer shall optimise belt speed and installed power by achieving as close as
possible a belt loading of 80 % full at the installed power. Where designs incorporate
trippers and multiple feed points, the belt loading must be reduced.
For maximum lump size over 180 mm: As a minimum requirement, the belt width shall
be maximum lump size x 4 and then selecting the closest standard belt width above this
value. Thereafter, the criteria above for a maximum lump size below 180 mm shall
apply.
4.5.8
Feed factors
4.5.8.1 In order to cater for fluctuations in feed to the conveyors, the following feed factors shall
be used as a guideline:
Application
Feed factor
1.1
1.15 - 1.25
Reciprocating feeders
1.7
2.0
* The above factors will be incorporated in the conveyor designs but will not be reflected in
the flow sheet capacity.
Table 3 Feed Factors
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 16 of 68
IMPLEMENTATION 11/22/2013
4.5.9
DOC NO AATC000859
4.5.9.1 The general philosophy of wide and slow belts shall be adopted with the following
recommended speeds:
Incline conveyors
< 4 m/s
2 to 3 m/s
Overland conveyors
4.5.9.2 For typical transfer heights in the chutes, a nominal 250 mm lump will produce up to
900 Joules on impact with the receiving belt, which is the upper limit of the allowable
impact energy. It therefore follows that the initial kinetic energy of the lumps entering the
transfer chutes be minimised by way of conservatively slow belt speeds.
4.5.9.3 Where multiple feed points are required, lower speeds must be considered to reduce
spillage.
:fc = .019
fr = .017
:fc = .0195
fr = .018
In-plant conveyors
:fc = .02
fr = .022
:fc = .022
fr = .022
4.5.10.2 A friction factor of 0.022 should be used for both underground and surface conveyors
with an adjusted length factor Lo of 60m for all conveyors longer than 100 m.
4.5.10.3 In extremely cold conditions during winter mornings a load factor of between 1.1 and
1.2 should be applied when selecting the sizes of the drives.
4.5.10.4 The above factors serve only for static analysis. Visco-elastic friction, indentation
resistance and idler resistance calculations shall be included in the design of long
overland conveyors.
Page 17 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 18 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
VSD
Fluid
Coupling
Electronic
Soft Start
U/G Section
No
1st
No
1st
2nd
No
1st
2nd
No
Overland > 2 km
1st
2nd
No
Plant < 2 km
2nd
1st
No
No
1st
No
No
1st
2nd
Type conveyor
Remark
4.5.12 Couplings
4.5.12.1 Fluid couplings will be fitted on the high speed side of all drives exceeding 22 kW where
VSD or Electronic starters are not provided.
4.5.12.2 All couplings shall be complete with guards.
4.5.12.3 All low speed couplings shall be of the rigid flange type, accurately aligned and fitted to
shafts via locking elements (no keyways allowed on shafts). The drive supplier shall fit
the rigid couplings to the pulley at the pulley suppliers premises.
4.5.12.4 Drives with an installed power exceeding 22 kW shall be fitted with a soft starter i.e.
fluid coupling or electronic.
4.5.12.5 For long overland conveyors with high inertia where the start-up times would be in
excess of 50 seconds (which is the limit of the capability of fluid couplings), Variable
Speed Drives (electrical VSDs) are selected.
4.5.12.6 The overhung on motor output shafts must be checked when using large fluid coupling
sizes. Jack shafts may be required to support the fluid coupling.
4.5.13 Belting
4.5.13.1 Steel cord conveyor belting shall comply with the latest AA Specifications, Steel cord
reinforced conveyor belting (AA_SPEC_377022) and Steel cord reinforced conveyor
belting (SANS 1366).
4.5.13.2 All fabric conveyor belting shall comply with the latest SANS Specification, General
purpose textile reinforced conveyor belting (SANS 1173).
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 19 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.13.3 PVC impregnated solid woven conveyor belting shall comply with the latest SANS
Specification, Fire retardant textile reinforced conveyor belting (Solid woven PVC,
SANS 948 and SANS 971).
4.5.13.4 All conveyor belting shall be selected with consideration of the standardised list of
belting already in use at Anglo Coal plants.
4.5.13.5 Ply belting to be natural rubber, minimum 3 ply with suitable top and bottom covers,
minimum 3 mm and 2 mm respectively. The top to bottom cover ratio is not to exceed
3:1.
4.5.13.6 Conveyor belt final selection shall be based on the calculated tension taking
standardisation into consideration.
4.5.13.7 In determining the length required allowance shall be made for hot vulcanized splicing.
4.5.13.8 Mechanical clips may be used in emergency situations only.
4.5.13.9 During belt and cover selection, consideration must be given to minimise the risk of
igniting flammable gas during installation and operation. Belt selection must also be
done considering the possibility of burning coal to minimise the risk of fire and noxious
gasses.
4.5.13.10
In selecting the belt type, the following table must be used as a guideline:
Area application
Belt type
Ply belts where impact permits.
Solid woven to be considered on tip clearance
belts and where significant steel contamination
is anticipated.
Plant
Ply belts
Stock yards
Ply belts
Interconnecting
overland
conveyors
shorter than 1 km
Ply belt
Overland conveyors
but
but
Shaft
&
conveyors
high
lift
Page 20 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 21 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.17 Holdbacks
4.5.17.1 A full risk assessment per conveyor belt shall be carried out prior to selection of the
holdback considering:
4.5.17.2 Where the design dictates the need for a holdback, external or reducer integrated units
may be considered.
4.5.17.3 Slow speed backstops, mounted directly onto the drive pulley shaft or the intermediate
reducer shaft, are preferred.
4.5.17.4 High speed holdbacks, fitted between the motor and the reducer, may be considered for
conveyors equipped with single drives.
4.5.17.5 Where it is desired to have a high speed holdback installation on a multiple drive
configuration, torque limiting type devices are required to ensure load sharing.
4.5.17.6 For external holdbacks, a horizontal mounting configuration will reduce bearing loading
and is therefore preferred.
4.5.17.7 Although stiff support steel is required to transfer the holdback reaction forces, the
torque arm end of an external unit must not be rigidly attached. This will prevent
damage to the bearings of the device.
4.5.17.8 The mounting of the torque arm must not permit any slack between the device and the
support steel. Cushioning between load contact surfaces is precluded.
4.5.17.9 Holdback selection must be based on the calculated runback load of the belt in
conjunction with a dynamic impact factor. The holdback rating shall not be less than the
maximum torque capacity of the gearbox.
4.5.17.10
Where required, turn down of the shafts may be considered to accommodate
maximum bore for selected backstop, provided that permissible shaft stresses, as
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 22 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.17.11
For standardization purposes, the selection of the internal holdbacks shall be
based on the highest torque requirement across the range of affected conveyors.
Standardised reducer units must be interchangeable, hence internal holdbacks must be
fitted for all these units unless economical considerations dictates otherwise in which
case clear visual identification must be provided.
Page 23 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.19.4 The lagging philosophy of the operation shall be considered when conducting SIB
designs and projects.
4.5.19.5 Plummerblocks should be the split type.
4.5.19.6 Spherical roller bearings with an adapter sleeve should be used.
4.5.19.7 Plummer blocks with its bearings to be fitted with an easily accessible grease nipple.
Inaccessible grease point must be equipped with a hydraulic hose and grease block to
facilitate safe remote manual lubrication.
4.5.19.13
Plummer block orientation shall be such that the bearing force acts through the
base of the plummer block. Cap bolts shall never be under tension.
4.5.19.14
Bearing temperatures on critical belts will be monitored at the head, tail, drive and
take-up pulleys using resistance temperature detector. (RTD)
4.5.19.15
4.5.19.16
The number of pulleys must be kept to a minimum when designing new
conveyors.
4.5.20 Idlers
4.5.20.1 Idlers shall be in accordance with the latest AA Specification, belt conveyor idlers and
rolls (AA_SPEC_373001) and shall bear the SANS certification mark to the latest SANS
Specification, conveyor belt idlers.
4.5.20.2 Idler spacing selection must be done by balancing the capital expenditure with
operational costs.
4.5.20.3 The maximum allowable idler shaft deflection is limited to 8 minutes at the designed
throughputs.
4.5.20.4 For the average operating throughputs, the minimum idler life is 40 000 hours.
Page 24 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.21.5 The preferred troughing angle is 35 although 45 and higher may also be used when
justified.
4.5.21.6 The head frame or the stringers leading up to the head frame shall include a transition
section to flatten the belt in accordance with the CEMA recommendations, precautions
shall be taken to prevent spillage at this point.
4.5.21.7 Head and tail transitions are to be designed to run out to 0 by installing the appropriate
transition idlers. 3 idler sets are generally required.
4.5.21.8 When required, the tail pulley may be positioned at half or third trough to reduce the
transition distance. This is however not preferred.
4.5.21.9 Standardization across designs remains to be an important consideration.
4.5.21.10
High angle troughing idlers should be considered to eliminate long and high
maintenance skirting on conveyors with multiple loading points typical for coal plant
product and discard belts.
Page 25 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 26 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.24.15
For vertical gravity take-up, over 6m in height, belting flap to be restrained with
flat return idler guides. This configuration should however be avoided.
4.5.24.16
Vertical gravity take-up should have a clearance between frame and guides of
approximately 10 mm per side.
4.5.24.17
Gravity take-up towers shall be of sufficient height to accommodate the change in
the length of the conveyor belting under all operating conditions with a minimum of
500mm travel distance before any object will be encountered.
4.5.24.18
4.5.24.19
Gravity take-up towers shall have a buffer at the bottom. This buffer shall be able
to absorb the impact of the free falling take-up weight to prevent damage to the
structural components. The preference is to use a sand box with screed closure.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 27 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.5.26.2 Care must be taken to position tail scrapers such that material is not scraped into the
tail guard area.
4.5.26.3 Where V-return idlers are used, the positioning of the plough must be such that proper
contact between the belt and plough is maintained. Flat return idlers must be provided.
4.5.26.4 Where access to one side of the belt for cleaning purposes is not available, bias
ploughs shall be installed so that material is scraped off to the side where access is
readily available.
4.5.26.5 Where ploughs are installed on elevated conveyors, safety precautions due to falling
material shall be taken. Easily cleanable catchment boxes should be installed.
4.5.27 Skirting
4.5.27.1 Continuous skirting is to be used for multiple load points onto a single belt. Flared
skirting or spaced skirting shall only be incorporated into the design with the prior
approval of the Engineer.
4.5.27.2 Skirting rubber shall be 40 shore hardness or below. Used conveyor belting in skirt seal
locations is prohibited.
4.5.27.3 AATC standard skirts will be installed at all single loading points.
4.5.27.4 All conveyor feed chutes shall be equipped with steel skirting to contain material at the
feed point. Skirts shall extend a minimum distance of 1 m past the stabilized material on
the belt. Chute skirt covers to be easily removable.
4.5.27.5 All discharges below crushers, centrifuges etc. shall be fully enclosed to eliminate
spillage completely.
4.5.27.6 High angle troughing idlers may be considered to eliminate long and high maintenance
skirting on conveyors with multiple loading points typical for coal plant product and
discard belts.
Page 28 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 29 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Frame construction
Guard mesh
Fixed
50x50x6L
50
Swivel
50x50x6L
50
None
25
Under-belt
50x50x6L**
Not restricted
4.6
Chutes
4.6.1.1 The minimum width of the conveyor feed chutes (measured inside of liners) shall be 2,5
x the particle size. The width of such feed chutes shall not exceed 2/3 of the conveyor
belt width.
4.6.1.2 Chutes shall be designed to pass the peak load continuously, without spillage or buildup, and to transfer it to the receiving equipment smoothly and equally distributed across
the receiving equipment. The chute shall also pass the maximum lump size without
blocking, hanging-up or spilling or excessive wear, and shall transfer it to the receiving
equipment such that the possibility of damage is minimized.
4.6.1.3 Chute design shall accommodate dust extraction and suppression requirements where
applicable (on transfers within buildings, chutes carrying dry coal). The velocity of dust
shall be kept to a minimum regardless of whether dust extraction or suppression is
applied. Connection flanges shall be supplied for dust suppression or extraction
equipment where such systems are required.
4.6.1.4 The impact pressure on the chute and on the receiving equipment shall be kept to a
minimum and shall not exceed 8 kPa.
4.6.1.5 The angle of impact, i.e. the angle between the material stream and the impacting
surface, shall be minimised and shall preferably be less than 20.
4.6.1.6 Suitable support for the chute shall be provided. In designing the chutes, the forces
likely to be encountered as a result of large lumps passing through the chute shall be
taken into account.
4.6.1.7 Where appropriate, deflector chutes must be provided at ploughs, take-up and drives.
4.6.1.8 When chute plates have to be stiffened, care must be taken in positioning stiffeners so
that no water traps occur.
4.6.1.9 Although chutes need to be suitably stiffened in line with the liner selection, over
stiffening must be avoided.
4.6.1.10 New ceramic tiles have a high co-efficient of friction, which must be considered when
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 30 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
conveying fines.
4.6.1.11 Light weight chute inspection doors must be provided with welded hinges. To prevent
finger injuries, these doors shall always open sideways, never to the top or bottom.
4.6.1.12 Where possible, the head snub pulley must be located within the main chute so that the
fines can be carried away with the main flow of material. The chute back plate must be
positioned such that there will be no build-up of the fine material.
4.6.1.13 The guideline for the required clearance between the belt and chute is obtained by the
ratio of the selected belt width divided by 12.
4.6.1.14 In order that degradation of material and belt wear may be minimised, all transfer
chutes shall be designed in accordance with the following principles:
All chute designs shall be based on friction characteristics obtained from bulk solids
flow test for material on material and material on liner surfaces,
In determining chute angles, the co-efficient of friction between the wear material and
the coal shall be taken into account.
The functional design of transfer chute arrangements shall prevail over mechanical and
structural considerations,
Material velocity throughout the entire chute shall be designed in accordance with
measured friction characteristics for direct sliding and sliding under impact conditions,
Material transferred to chutes shall impinge on the chute at the least practical angle of
impact,
Where unavoidable and to eliminate impact wear in the top section of the chute, in-line
dead boxes will be permitted.
Where a chute transfers material onto a belt conveyor, the difference in the velocities of
the material in the direction of the conveyor, and the belt shall be within 10% of the belt
velocity for average friction characteristics of the material on the chute liner surface,
The kinetic energy of the largest particle reasonably anticipated on a receiving conveyor
belt shall not exceed 500 joules,
Where the stopping time of a conveyor is such that it may deliver more material to the
receiving equipment than the receiving equipment can absorb without the possibility of
spillage or blockage overloading, provision shall be made for the conveyor head chute
to accommodate the overrun material. The amount of overrun material to be
accommodated shall be based on the peak capacity of the conveyor,
The chute angle at the bottom of the chute shall be minimum 5 steeper than the friction
angle for direct sliding.
4.6.1.15 Transfer point arrangements must be designed to minimise the fragmentation of coal.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 31 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.6.1.16 Blocked chute detection will be installed at all conveyor discharge ends in accordance
with the latest AA Specification, Conveyor belt protection systems (AA_SPEC_673018).
4.6.1.17 Also refer to general plate work and lining requirements under section 4.10 Platework
and Lining.
4.7
4.7.1
Design
4.7.2
Design factors
4.7.2.1 Service factor shall be in accordance with the latest AA Specification, Mechanical
Standards (AA_SPEC_999022).
4.7.2.2 Where specific manufacturer or other requirements exist, these will be stated in the
relevant equipment specification.
4.7.3
Transmissions
Page 32 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.7.4
Bearings
the latest
4.7.4.2 All bearings must be SKF with the exception for conveyors pulleys (only) where FAG
may be used as an alternative where SKF bearings are not available.
4.7.4.3 The L10 life shall be calculated at the maximum speed and radial and axial loads
resulting from rated motor power.
Mechanical Equipment
60,000
Pumps
60,000
Agitators
80,000
100,000
Conveyor idlers
40,000
Screens
80,000
100,000
4.7.4.4 Plummer blocks shall be designed and installed such that the belt load acts through the
mounting base. Stored energy within the conveyor belt must not result in an unsafe
condition when the bearing cap is removed.
4.7.4.5 Greasing points shall be provided for all plummer blocks.
4.7.4.6 All electric motors used on VSD installation above 90 kW, must be equipped with
insulated bearings at either the drive or non drive end to mitigate the effect of stray
currents.
4.7.4.7 Bearing sole plates must be supplied loose for site welding to ensure that bearing
housings can be aligned. Galvanising must be grinded off locally prior to site welding
and repaired according to CPS41 A after installation.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 33 of 68
IMPLEMENTATION 11/22/2013
4.7.5
DOC NO AATC000859
Brakes
4.7.6
Lubrication
4.7.6.1 Lubricants and lubrication shall be in accordance with the latest AA Specification,
Mechanical Standards (AA_SPEC_999022).
4.7.6.2 All equipment which normally contains lubricant and is despatched without such
lubricant shall have their interior sprayed with a suitable moisture inhibitor, to prevent
corrosion during transport and storage. Such equipment shall carry clear legible tagging
indicating that it does not contain lubricant. All machinery and equipment shall be
checked for cleanliness and lubrication prior to testing or start-up.
4.7.6.3 As far as possible a centralised lubrication system shall be considered for multiple items
of equipment supplied. Where a centralised lubrication system is not justified, multiple
lubrication points in close proximity shall be plumbed to a central manifold block
accessible without removing safe guards. Lubrication plumbing shall be neatly run and
supported as required. Lubrication points shall be labelled to indicate the point supplied.
4.7.6.4 All oil lubricated equipment shall be provided with a valve at the outlet (where practical)
so that samples for oil analysis may be easily taken.
4.7.6.5 First fill of lubricants shall be agreed by project team and included in the Capex or SIB
costs.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 34 of 68
IMPLEMENTATION 11/22/2013
4.7.7
DOC NO AATC000859
4.7.7.1 In designing or selecting the equipment, attention shall be given to the ease of
operation and maintainability of the plant as well as operational costs.
4.7.7.2 The design and selection of equipment shall be directed towards minimizing
maintenance and maintenance durations.
4.7.7.3 Steelwork, walkways, stairs, platforms, etc. must allow safe and adequate operational
and maintenance access shall be provided.
4.7.7.4 Crawl beams, equipped with crawls but not lifting tackle, strategically placed so that all
heavy lifts required to maintain the plant and equipment may be safely and easily
carried out shall be provided.
4.7.7.5 Equipment must be arranged so that overhead crawl or lifting beams provide simple
and adequate suspension for in situ stripping and/or removal to an external workshop.
4.7.7.6 Electrical overhead travelling cranes will be provided in the main plant and plant
workshop. Cranes shall be in accordance with the latest BS 466 standard.
4.7.7.7
The plant crane will be sized to lift the heaviest piece of equipment within the cranes
reach.
4.7.7.8 Crawl beams will be fitted over equipment that is not accessible by the overhead crane
including all transfer towers, bins and the discard silo.
4.7.7.9 Crawl beams will be fitted with manual trolleys.
4.7.7.10 Stop blocks will be fitted to both ends of the crawl beams.
4.7.7.11 The safe working load, SWL, must be stencilled onto both sides of crawl beam web
after passing load test certification.
4.7.7.12 No lifts, including construction activities, shall take place on a new crawl beam prior to
passing load test certification.
4.7.8
Cleaning operations
4.7.8.1 All floors in wet areas should be concrete and easily accessible for skid steer loaders
(bobcat) without obstacles.
4.7.8.2
Skid steer loaders (bobcat) access is required around conveyor tail end areas and
inside tunnels.
4.7.9
4.7.9.1 All materials handling facilities will be designed to minimise, and where possible, to
prevent the generation and liberation of dust.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 35 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.7.9.2 Methodologies will vary from passive e.g. tip dust hood and active systems e.g. water
spray systems.
4.7.9.3 Ducted dust extraction systems and filters are not preferred. These may be used in
limited quantities where required by an analysis of an experienced dust control
specialist.
4.7.9.4 Water sprays will be used to suppress dust escaping from enclosures. Each water
spray system will be designed for the optimised droplet size and velocity. The objective
will be to balance the system requirements in terms of water consumption,
maintainability, dust suppression efficiency, water quality requirements and simplicity.
4.7.9.5 Where fine droplet sizes are preferred, the spray systems will make use of suitable
atomizing nozzles (using either by pneumatic or high pressure hydraulic
methodologies). Water supply systems to atomising dust spray systems will include fine
filtration and possibly reverse-osmosis treatment, as required by an analysis of the
quality of the water supply system.
4.7.9.6 Water sprays, where used will be specified in a manner which avoids caking and buildup on materials handling equipment. Sprays must ideally be directed towards the
conveyed material.
4.8
Fire protection
4.8.1.1 Fire suppression and detection to be provided in accordance with the latest
Specifications:
AATC000168
AATC000169
4.9
4.9.1
General
4.9.1.1 Piping covered in this document specifically addresses plant related environments. Bulk
supply and services to the plant are covered by civil engineering.
4.9.1.2 All piping systems, equipment and design shall comply with the latest relevant
standards, regulations, codes and statutory requirements. (Refer to Reference
Documents)
4.9.1.3 Piping systems shall be designed to facilitate reliable and continuous operation, as well
as easy accessibility for operation, maintenance, equipment replacement, handling,
cleaning and inspection.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 36 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.1.4 All pipe work, equipment and apparatus supplied and installed shall be designed to
ensure satisfactory operation under the atmospheric, ambient and other conditions
prevailing at the plant/site.
4.9.1.5 The Contractor shall ensure that all piping and components stored on site are placed on
sleepers or pallets. All open ends of piping, valves and fittings shall be provided with
plastic or wooden end caps to prevent ingress of dirt and other foreign matter.
4.9.2
Piping Categories
4.9.3
Alternate of
aggressive
slurries
Correct medium
distribution
4.9.3.1 All pipe and fittings supplied shall be new and unused.
4.9.3.2 Pipe routes shall be as short and straight as possible using 45 and 90 bends.
4.9.3.3 Consideration shall be given to the overall piping system behaviour under dynamic
conditions. 90 bends do not lend itself to being self-draining; 85 are preferred.
4.9.3.4 Relevant pipe routes shall be self-draining. Drain valves shall be fitted on any pipelines
which do not self drain, however this should be avoided. No dead legs are
acceptable.
4.9.3.5 Pipe deliveries into sumps and tanks shall be directed away from the suction inlet to
avoid air entrainment, instrumentation and towards the centre of the sump or tank to
minimise wear and vortex generation.
4.9.3.6 Flushing points shall be provided to assist drainage and cleaning where necessary.
4.9.3.7 The number of connectors shall be minimised wherever possible.
However the
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 37 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Page 38 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.3.21 Axial bellows units shall comply with the requirements of the Expansion Joint
Manufacturers Association (USA). Further guidance on the design and specification of
bellows and bellows installation is detailed the latest British Standard, Code of practice
for the selection and application of bellows expansion joints for use in pressure
systems.
4.9.4
Line Sizing
4.9.4.1 Line sizing shall be calculated considering the effects of friction drop, erosion, solids
settling, product degradation, water hammer, NPSHr, process flow variations, provision
for future capacity increases. The following velocity ranges are a guide:
Fluid Type
DN450
DN750
Min
Max
Pump Suction
0,6
0,9
1,2
1,6
1,3
1,7
1,8
2,3
Pump
Discharge
1,2
2,1
2,4
2,5
3,1
3,2
4,6
to
Liquids
Pump
Discharge
flocculent
1,2
1,5
1,8
1,0
1,0
1,0
1,0
Pump
discharge
fuel/lube oil
0,5
1,0
0,5
1,0
0,5
1,0
0,5
1,0
Gravity
1,0
1,0
1,0
1,0
Slurries
Pump Suction
1,2
1,4
1,2
1,5
1,3
1,7
1,8
2,3
Pump
Discharge
1,5
1,6
1,8
2,4
2,0
2,6
3,8
Gravity-non
settling
Gravity-settling
slurry
1,0
1,0
1,0
1,0
4.9.4.2 The above guide is not applicable for two phase flow or pressure relief lines.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 39 of 68
IMPLEMENTATION 11/22/2013
4.9.5
DOC NO AATC000859
4.9.5.1 For all slurry applications HDPE pipes to comply with the latest SANS Specification,
Polyethylene (PE) pipes for water supply (SANS 4427). The nominal pressure rating
shall be PN 6 or higher if pressure dictates.
4.9.5.2 HDPE slurry piping shall be flanged throughout or a combination of fusion welds and
flanges, depending on the system length and duty.
4.9.5.3 All fittings are to be fabricated from HDPE pipe.
4.9.5.4 All fittings to be provided with weld on stub-ends and backing rings on both sides.
Backing rings to latest SANS Specification, Pipe flanges (SANS 1123), table 1000/ 3
and hot dip galvanized.
4.9.5.5 Maximum pipe lengths to be 9 meters. Shorter lengths shall be used as necessary
inside buildings for installation purposes.
4.9.5.6 Correct Medium feed box and HM cyclone feed piping will be Basalt lined.
4.9.5.7 HDPE pipe bends to be seamless and pulled to have a radius of minimum 3D for all
slurry lines.
4.9.5.8 Bends to be standardized with regard to bend degrees and centre to face dimensions.
4.9.5.9 Fittings and pipes which have misalignment on welded joints due to ovality will not be
accepted.
4.9.5.10 Welding of HDPE joints shall conform to the Manufacturers procedures.
4.9.6
Steel Pipes
4.9.6.1 150NB and below to be mild steel to the latest SANS Specification, Steel pipes: Part 1,
Pipes suitable for threading and of nominal size not exceeding 150mm. Pipes shall be
heavy wall hot dip galvanized.
4.9.6.2 Pipe 200NB and above to be mild steel to the latest SANS Specification, Electric
welded low carbon steel pipes for aqueous fluids (large bore). Pipes shall be grade "A",
6mm thick wall hot dip galvanized.
4.9.6.3 Steel pipe bends shall have a radius equal to 1 x nominal bore (i.e. long radius) and
constructed to steel pipes material specification.
4.9.6.4 Lined pipes are painted on the outside as per specifications.
4.9.6.5 Pump suctions to be mild steel as per the above relevant SANS Specifications and
coated as per the latest Anglo American corrosion prevention specification.
4.9.6.6 Maximum working pressures:
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 40 of 68
IMPLEMENTATION 11/22/2013
Slurry
Raw, process or gland service water
Compressed air
Tails lines
Spray water pipes
Wedged blank flanges
DOC NO AATC000859
650 kPa
1000 kPa
1000 kPa
As per Engineers design
Rated to run @ 450 kPa
Knock-off flanges to be installed on
selected
tanks,
sumps
and
platework to provide instant
emergency drainage
4.9.7
4.9.7.1 Compressed air piping and distribution headers will be galvanised and provided with
suitable filter/lubricator sets, air pressure gauge, isolating valve and water drainage
valve. Headers will be installed at approximately 5 to the horizontal for water collection
and drainage.
4.9.7.2 Compressed air and instrument airlines shall be sized so the pressure at the end of the
most resistant branch line does not drop below minimum requirements with full flow in
that line
4.9.7.3 Compressed air and instrument air branches shall be taken off the top of the respective
header.
4.9.7.4 Compressed air systems shall have a moisture trap at the low point in the air system for
each major plant area.
4.9.8
4.9.8.1 Schedule pipe to ASTM A106 Gr.B and pipe fittings to BS 3799 screwed to BS 21 ISO
R7 and EN10226-1, are to be used for spray bars below 50 NB. All items are to be hot
dip galvanised to ISO 1461 Heavy duty.
4.9.8.2 In the event of GSW pipework having an operating pressure in excess of 600kPa (two
stage pumping) then schedule pipe and fittings to BS EN 10241 shall be used.
4.9.8.3 Single stage pumps will have GSW fabricated to General Purpose Pipework
specification.
4.9.9
Slurry pipes
4.9.9.1 Slurry pipes are to be routed as directly as possible, with the minimum, least angled
bends possible. Head box nozzle orientations shall where possible aid in the elimination
of pipe bends.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 41 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.9.2 Slurry pipes shall be routed in such a way that self drainage will occur. Dead legs may
only be installed when there is no alternative. In such cases a drain valve must be
installed at the lowest point.
4.9.9.3 Slurry piping shall be arranged and supported to facilitate dismantling, flushing and
descaling. Straight lines shall be flanged to permit rotation and bends should be
flanged to permit replacement. Pipes shall be self-draining, preferably back to a tank or
vessel. Where this is not practical, provision shall be made for dumping the slurry at
low points.
4.9.9.4 The process engineer shall advise the minimum allowable angle for slurry, which will
normally be between ten and twenty degrees fall from the horizontal.
4.9.9.5 Selection of pipe sizes for slurry service shall ensure that line velocities are kept above
solids settling velocities.
4.9.9.6 Steel slurry pipelines (including rubber-lined) shall be flanged at every fitting and
branch.
4.9.9.7 Slurry lines shall have a maximum flanged length of 6 m within the process plant and a
maximum length of 9 m outside of process plant areas. Rubber lined slurry lines shall
have a maximum flange length of 6 m for all process applications.
4.9.9.8 The first pipe spool immediately after the pump discharge reducer shall be a minimum
of three meters long to reduce wear created by the pump discharge velocity and
turbulence.
4.9.9.9 Sacrificial spools, approximately 1000 mm long shall be installed on the downstream
side of bends.
4.9.9.10 Long radius swept bends shall be utilised for all slurry piping. No lobster back bends
shall be permitted.
4.9.9.11 Flushing water and drain connections will be provided at pump boxes and sumps and at
vertical piping as required.
4.9.9.12 Pipes shall be either rubber lined, materials handling hose or high-density polyethylene
or similar as per the piping specification and P&IDs.
4.9.9.13 Slurry pump suction lines shall reduce according to the requirements of the P&IDs.
Reductions shall be made with eccentric reducers with the bottom flat.
4.9.9.14 Slurry pump suction lines will be kept as short as practically possible.
Page 42 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
with the flat on top; except for slurry lines where the flat shall be on the bottom.
4.9.10.3 Elbows or bends shall not be placed within 4 pipe diameters of the pump suction
nozzle.
4.9.10.4 Isolating valves are to be accessible and in the case of Knife Gate Valves, are to be
orientated with the hand wheel or actuator as vertical as possible.
4.9.10.5 Drain valves must drain the suction completely.
4.9.10.6 Pump suctions smaller than 300 NB shall be installed with a bellows.
4.9.10.7 Pumps shall be mounted on an integral pump support frame designed to enable pump
alignment and pump drawback to facilitate removal of suction piping and pump internals
replacement.
4.9.10.8 Pump suctions will be designed to allow for ease of maintenance of the pump
4.9.10.9 Steel Pipes Bends (Water & Air Lines) to have radius equal to 1 x nominal bore (i.e.
long radius) and constructed to steel pipes material specification.
4.9.10.10
4.9.10.11
The ratio of the mean bend radius to the outer diameter of the pipe shall be not
less than 2. Bends in unlined steel pumped lines > 80 NB and in gravity lines where the
vertical fall before the bend is greater than 3 metre shall be white cast iron complying
with the latest British Standard, Founding. Abrasion resistant cast irons.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 43 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.15 Closures
4.9.15.1 To be supplied 150 mm longer than installed length.
4.9.15.2 Flanges on stubs to be left loose and welded during erection.
4.9.16 Marking
4.9.16.1 All items to be clearly marked on pipes approximately 300 mm from fixed flange with
line number and item number. Rubber hoses to be securely tagged with item and line
number.
Page 44 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.18 Fasteners
4.9.18.1 All pipe bolts, nuts and washers to be SANS 1700 Class 4.8 hot dip galvanised and
suitably bagged, labelled and dispatched to site together with pipes.
4.9.18.2 High pressure piping with flanges table 25/3 or higher to be bolted with Class 8.8 hot dip
galvanized fasteners.
4.9.20 Nozzles
4.9.20.1 To conform to pipework fabrication and platework lining requirements.
4.9.21 Supports
4.9.21.1 Pipe support to the requirements of BS 3974
4.9.21.2 This will generally take the form of U-bolts and angle or channel-iron brackets and
supports welded to the adjacent building steelwork during and after completion of pipe
installation. HDPE piping of 75 O.D. or smaller shall be provided with continuous
supports.
4.9.21.3 All pipe supports and U-bolts to be hot dip galvanized.
4.9.21.4 Galvanized steel structure surfaces damaged due to welding of the supports shall be
repaired as per the Anglo American procedure CPS 41A.
4.9.21.5 Pipelines shall be adequately anchored to withstand the reactions caused by changes
in pipe direction, temperatures, pressure, etc. Pipes connected to a fixed item of
equipment shall be anchored in such a way that no thrust forces are imposed on the
item to be connected.
4.9.22 Valves
4.9.22.1 Valves shall comply with the latest Anglo American Specification (General purpose
valves).
4.9.22.2 Valves shall be selected for the specific duty, rating and operation required.
4.9.22.3 In order to ensure a fit for purpose the expertise of the valve supplier must be sought
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 45 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.9.22.5 Valves and instrumentation shall be located in readily accessible positions for operation
and maintenance. Access platforms shall be provided where necessary.
4.9.23.3 For fabricated lifting lugs all welds shall be examined by NDT. Acceptance criteria shall
be in accordance with the registered Engineers approved design requirements.
4.9.23.4 The maximum allowable sling angle from the vertical shall be determined and marked at
all lifting points.
4.9.23.5 Removable lugs shall be bolted to each component in the shop prior to shipment and
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 46 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.10
All new platework shall be painted on the outside in accordance with CPS 132.
Internal surfaces shall be prime painted after drilling and before liners are fitted.
The outside finish colour shall be Aircraft Grey Green (SABS 1091 D18).
4.10.1.12 Impact onto any platework shall be avoided (and high impact is unacceptable), but
where it cannot be entirely eliminated a suitable design shall be submitted to the
Engineer for an approval.
4.10.1.13 Internal surfaces below steel liners will be prime painted only.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 47 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.10.3 Welding
4.10.3.1 Plate joints to be 6 mm (leg length) continuous fillets on both sides, unless otherwise
specified by the design engineer.
4.10.3.2 External stiffeners shall have a full 2 mm seal weld to prevent ingress of moisture. Stitch
welding to achieve the required structural strength is permitted.
4.10.5 Joints
4.10.5.1 To be sealed with compri band strips on the full flange width where faces are not rubber
lined.
4.10.6 Fasteners
4.10.6.1 For platework, bolts, nuts and flat washers to conform to SANS 1700 Class 4.8 and to
be hot dipped galvanised.
4.10.6.2 Bolts on chutes where high impact is anticipated to be secured with Nylock, Cleveloc or
Huck fasteners. Electro plated galvanised bolts are permitted on these applications.
4.10.6.3 Taper washers to be fitted to steel sections with taper flanges.
4.10.6.4 Site bolts to be suitably bagged, labelled and wired to platework item for delivery.
4.10.6.5 Nylock nuts shall not to be used where burning coal is anticipated.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 48 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
4.10.7 Marking
4.10.7.1 All items to be hand stamped (min. size 12 mm) with drawing and item number. Hand
stamps shall be clearly visible after hot dip galvanising.
4.10.8 Painting
4.10.8.1 External and Internal: Refer to Corrosion Protection under section 5.6.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 49 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Plant Applications:
4.10.9.11
Very high wear wet abrasive areas such as HM cyclones under flow boxes
(impact face) to be lined with 50 mm hi-aluminium tiles.
4.10.9.12
High wear wet abrasive areas containing raw materials (coals and discards) and
magnetite will be lined with 25 mm thick hi-alumina tiles, e.g. cyclone mixing boxes,
floats and sinks boxes as indicated on the drawings.
4.10.9.13
Wet abrasive areas containing coal water slurries or magnetite/coal suspensions
will be lined with 13 mm thick hi-alumina tiles, e.g. screen underpans, head boxes,
magnetic separator underpans and the conical portions of all process tanks (including
outlet nozzles). Split tiles.
4.10.9.14
Wet areas of relatively low abrasion will be lined with 6 mm thick hi-alumina
epoxy, e.g. vertical tank sides, tailings launders, etc.
4.10.9.15
Areas above hi-alumina tiles or epoxy will be lined with 1 mm thick brushable
wearing compound. Edge smoothing must be done.
4.10.9.16
Platework for wet and sticky fine material will be lined with minimum 8 mm thick
solidur or equivalent, e.g. fine coal centrifuge feed and discharge chutes, dewatering
screen discharge and conveyor dribbling chutes where material hang-ups could occur.
4.10.9.17
Drop boxes shall be used on certain platework items such as cyclone overflow
and underflow collection, distribution or feed boxes to prevent direct flow of the slurry
against the ceramic lined surfaces if practical. At the same time, the possibility of
blockages shall be considered.
b) Laying of tiles:
Lay the tiles that joints are offset in direction of flow wherever practical.
Tile length shall be perpendicular to the main stream flow.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 50 of 68
IMPLEMENTATION 11/22/2013
4.10.10.2
DOC NO AATC000859
Steel Lining
4.10.10.3
All steel liners to be 400 Brinell (minimum tensile strength 1340 MPa) or
equivalent. Also refer to 4.10.9.5 and 4.10.9.6
4.10.10.4
4.10.10.5
4.10.10.6
4.10.10.7
For all steel liners, bolts are to be accessible from the outside of the chute or bin.
4.10.10.8
4.10.10.9
Fastening holes in liners must be drilled such that only 3 mm of liner thickness
below the counter sunk bolt head remains to ensure the maximum liner life.
4.10.10.10
UHMWPE Lining
4.10.10.11
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 51 of 68
IMPLEMENTATION 11/22/2013
5.1
5.1.1
General
DOC NO AATC000859
5.1.1.1 Design of structural steelwork shall comply with the latest Anglo American
Specifications AA_SPEC_114/01 (Design of steel structures) and AA_SPEC_114/02
(Construction of structural steelwork)
5.1.1.2 AA_SPEC_114/01 requires that the latest versions of normative reference documents
are used. AATC nevertheless has a conditional concession to continue using the SABS
0160-1989, (amended 1993) loading code until the end of 2017.
5.1.1.3 When designing support structures for major equipment such as jaw crushers, rotary
breakers, screens, hydraulic rock breaker, apron feeder etc. the structural designer shall
initiate a clarification meeting with the OEM to ensure that certified equipment loads,
and the operation of the equipment is fully understood.
5.1.1.4 When designing crawl beams, it is acceptable to use BS2853:1957 for flange cross
bending calculations.
5.1.1.5 All steelwork shall comply with the following general requirements:All welds shall be in accordance with AWS D1.1 and shall be 6 mm continuous fillet
welds, unless otherwise specified by the design engineer.
All holes in structural members shall be 22 mm diameter for M20, Class 8.8 hot dipped
galvanised bolts unless otherwise specified by the design engineer.
Holes in lightly loaded components, e.g. purlins, girts, handrail fixings, ladders, etc.,
shall be 18 mm diameter for M16 grade 4.6 hot dipped galvanised bolts.
Care must be taken to orientate structural members toe down to avoid dead boxes
where water and material can be trapped.
Stiffeners on column bases must be positioned to avoid dead boxes. Where pockets do
occur, it needs to be filled with concrete and a non-shrink epoxy grout.
The use of high strength galvanized fasteners i.e. Class 10.9 and above, should be
avoided as far as possible.
The use of electroplated bolts is not permitted.
All bracing end connections must have a minimum of two bolts per connection.
Before fabrication of steelwork may commence the designs and drawings shall be
submitted to the Engineer for comment. This requirement shall in no way relieve the
Contractor of nor diminish his responsibility for the correctness and functionality of the
steelwork.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 52 of 68
IMPLEMENTATION 11/22/2013
5.2
Conveyor Structures
5.2.1
General
DOC NO AATC000859
5.2.1.1 All structures shall be designed for 100 % belt loading. The ultimate strength of the
structure must be validated for flooded belt conditions which will be treated as an
emergency load case. Serviceability requirements may be disregarded for this
condition.
5.2.1.2 The conveyor head frame shall be designed to withstand the forces imposed on it by
the conveyor under all operational conditions. The head frame shall be free standing
and shall not transmit any forces into the conveyor gantries. The head frame support
steelwork shall be designed to withstand the maximum head frame load.
5.2.1.3 The drive and take-up sections may be incorporated into elevated gantries provided the
gantry is designed to withstand the forces imposed on it.
5.2.1.4 Wherever a conveyor is elevated to the extent that maintenance or inspection will be
difficult or impossible from ground level, elevated or gantry sections with inspection and
maintenance walkways shall be provided. The elevated section shall adequately
support both the carrying and return strands of the conveyor belt. Idlers and idler
spacing on the elevated section shall be as for the run of conveyors section.
5.2.1.5 The elevated sections at the head end of conveyors shall be designed to tie-in with the
head frame, without transmitting or receiving any forces from the head frame.
5.2.1.6 Holes for pig tails to support a pull wire cable shall be provided on both sides of the
conveyor.
5.2.1.7 No deck plates to be used at any section of the conveyors, spilt material may burn
spontaneously.
5.2.1.8 Approximately 150 mm clearance between belt and structures are required.
5.2.1.9 Heavy duty conveyor modules and civil foundations must be considered at chute
discharge or material impact regions.
5.2.2
Gantries
For walkway requirements, refer to Section 5.3 Walkways, access, platforms and
flooring.
For sheeting requirements, refer to Section 5.4 Cladding of structures
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 53 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
5.2.2.2 Open gantries is generally used on all conveyor structures unless a specific need exist
to use a box type gantry.
5.2.2.3 Box gantries must be considered on conveyors significantly elevated above ground
level or where the use can be motivated.
5.2.2.4 Vehicle underpasses Gantries inclined below 5 may be equipped with vastrap
flooring. Solid concrete decks must be provided above underpasses where the
conveyor inclination exceeds 5. Provision must be made for wash down.
5.2.2.5 General gantry requirements
Gantries are to have welded side panels and bolted top and bottom lacing
to suit transport limitations.
Where substantial additional loads e.g. piping, cabling etc must be carried
by a gantry, the design must specifically cater for these. Minor loads such
as a 50 mm diameter pipe or small cabling may be disregarded subject to
the discretion of the designer.
5.3
5.3.1
General
5.3.1.1 All landings, stair treads, walkways and handrails shall be in accordance to the latest
Anglo American Specification: Design, Fabrication, Installation and Maintenance of
open grid grating for floors, stairways and hand railing (ACSA_SPEC_114012).
5.3.1.2 Conveyors 900 mm wide or smaller shall have a single walkway 900 mm wide where
the belt line is elevated more than 1.5 m above ground level.
5.3.1.3 Conveyors wider than 900 mm shall have double-sided walkway access, 750 mm and
900 mm wide at main access side where the belt line is elevated more than 1.5 m
above ground level.
5.3.1.4 A sufficient clearance (400 mm minimum on wide walkway side) must be provided in
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 54 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
area of take-up pulleys where the pulley guards restrict the walkway width.
5.3.1.5 Maintenance access must be provided to crawls, take-up towers etc. A 600 mm wide
stair case and 750 mm wide platform will suffice unless the risk assessment dictates
otherwise.
5.3.1.6 No cat ladders are permitted whatsoever.
5.3.1.7 Refer to 4.5.28 and 4.5.29 for guarding and conveyor underbelt guard requirements.
5.4
Cladding of structures
5.4.1
General
Page 55 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
5.4.1.12 Sheeting colour for new projects must be confirmed by environmental impact studies.
The following colour schemes are nevertheless standard within AATC:
Outside
Inside
Option 1
Sandstone Beige,
C59
Option 2
Gemsbok Sand
0.8
0.6
0.8
0.6
0.6
0.8
5.4.2
5.4.2.1 Roof and side sheeting must be reversed lapped. A full length gap must be provided
between the roof and the side sheeting to ensure a natural draft.
5.4.2.2 Ridge ventilators and louvers must be provided in line with the recommendations of a
sheeting specialist.
5.4.2.3 Plant structures housing large screens must specifically designed taking cognisance of
pressure pulsation phenomenon associated with big screens.
5.4.3
Conveyor gantries
5.4.3.1 To eliminate a natural draft and propagation of fire, approximately 30 % of the sides
must be left un-sheeted. Translucent sheeting is therefore generally not required on
environmental and boxed gantries.
5.4.3.2 Open gantries must be equipped with doghouse type roof sheeting which allows access
to idlers. Walkways must be side sheeted on the outside. Where wide cable racks are
affixed to the outside of handrails, side sheeting must be omitted on that specific side
only.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 56 of 68
IMPLEMENTATION 11/22/2013
5.4.4
DOC NO AATC000859
Conveyors
5.4.4.1 Doghouse type sheeting must be installed on all conveyors such that the conveyed
material is shielded from the prevailing wind direction. Doghouse sheeting must allow
access from the enclosed side such that the sheeting line is terminated approximately in
the middle of the wing roll.
5.4.4.2 In close proximity of dwellings, it may be required to enclose the entire conveyor.
5.4.5
Pedestrians crossings
5.4.5.1 0.8 mm IBR sheeting protection will be installed at all areas where fall of material
could occur.
5.4.5.2 Dedicated pedestrian underpasses, integrated with the civil infrastructures designs, are
required beneath conveyors.
5.5
Civil
5.5.1
General
5.5.1.1 Design of civil works shall comply with the latest Anglo American Specifications
AA114/10 (Design of concrete structures) and AA114/11 (Construction of concrete
work)
5.5.1.2 Kerbs around buildings must be a minimum of 450 mm away from the sheeting
perimeter.
5.5.1.3 Column bases in processing buildings must be 1000 to 2000 mm above floor level.
5.5.1.4 The floor level must be elevated no less than 200 mm above the normal ground level.
5.5.1.5 The minimum kerb height around buildings and structures should be 200 mm above the
floor level and no less than 150 mm thick.
5.5.1.6 Drainage slopes of 1:75 are required within buildings.
5.5.1.7 Drainage soil slopes of at least 1:50 are required.
5.5.1.8 Trestle plinths must be elevated by 1000 mm above the natural ground level.
5.5.1.9 Where vehicle access bays or pass through are provided in plants or next to trestles,
plinths must be raised to 2000 mm.
5.5.1.10 Stockpile tunnels, tip areas etc. must be free draining.
5.6
Corrosion Protection
5.6.1
General
5.6.1.1 All corrosion protection systems to be in accordance with the latest Anglo American
Specifications, AA_SPEC_164000, Users guide for corrosion prevention and
AA_SPEC_164050, System selection and Corrosion Protection of Steelwork with
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 57 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
Coatings.
5.6.1.2 Colour coding shall comply with the
AA_SPEC_164051, Plant colour coding.
latest
Anglo
American
Specification,
Coating system
Specification
Hot dipped
galvanised unless
painting is specified
Hot dipped
galvanised
AA_CPS_41A
CPS 132
Hot dipped
galvanised
AA_CPS_41A
Cast in
plates/frames
Hot dipped
galvanised
foundation bolts,
fastening)
AA_CPS_41A
Stockyard
Equipment
Consult specialist
AA_SPEC_164000
and 164050
TBA
Mechanical,
electrical
equipment
OEM specification,
approval / review
on request of
Engineer
AA_SPEC_164000
and 164050
OEM
Structural steel*
Vastra
floor
plates, all floors
horizontal and
inclined 5
Handrailing,
flooring &
stairtreads
Typical DMS
plant tanks,
cells,
distribution
boxes and
launders
Water & Air
piping
Piping
Paint, Consult
specialist
AA_SPEC_164000
and 164050
Hot dipped
galvanised
Paint, Consult
specialist
TBA
* All new steelwork shall be hot dipped galvanised in accordance with SANS ISO 1461 to
comply with SANS ISO 14713 Table 2 e, long (10 to < 20) maintenance years i.e.
minimum mean coating thickness of 85 micron (for steel > 6 mm thick). This requirement
must be reviewed where the design life of the operation exceeds 30 years.
Where exceptionally low acidity levels are anticipated, particularly at DMS washing plant
operations, a corrosion specialist must be consulted. Hot dipped galvanizing on its own is
not suitable for these conditions and a duplex system or paint system may be required.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 58 of 68
IMPLEMENTATION 11/22/2013
DOC NO AATC000859
5.6.1.4 The Contractor shall be responsible for ensuring that he is fully conversant with the
specification requirements as detailed under the utilization of each system.
5.6.1.5 A qualified applicator shall be defined as a workman regularly engaged in the
application of protective coatings. Unqualified workmen shall be engaged in the
preparation and cleaning only, prior to coating.
5.6.1.6 The Contractor shall provide all the facilities necessary in order to ensure satisfactory
preparation and number and thickness of coats. All workmen shall at all times be under
the constant supervision of a qualified supervisor.
5.6.1.7 The Engineer or his duly authorised representative shall be provided access to inspect
the surface preparation and the application of any or all of the coats, to ensure that
these have been applied in accordance with the specifications. No steelwork, pipework
or items of plant and equipment shall be delivered to site until inspection has been
carried out and a release issued.
5.6.1.8 It shall be the contractor's responsibility to ensure that inspection is called for and the
necessary clearance certificates obtained prior to delivery of goods to site.
5.6.1.9 All equipment, motors, main plant, light fittings, etc. shall be suitably protected by
means of wrapping or covering before grit blasting or spray painting any steelwork after
the installation of the aforesaid equipment.
5.6.1.10 The Contractor must ensure that the correct materials are provided as designated in the
specifications.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 59 of 68
IMPLEMENTATION 11/22/2013
INTERFACES
6.1
Civil
DOC NO AATC000859
6.1.1.1 AATC design and construction contracts are structured such that civil works which are
required to support materials handling systems are included under the mechanical
design and construction scope which also includes structural steel.
6.1.1.2 Battery limits are not always identical on all projects but defined during the early stages
of the project. Shown below are examples of typical battery limits:
Overland conveyor:
Route preparation
Civil contract
Mechanical contract
Overland sleepers
Mechanical contract
Tip:
Tip ramp and retaining wall
Civil contract
Mechanical contract
Silo:
Concrete works, all inclusive
Civil contract
Mechanical contract
6.2
Electrical Engineering
6.2.1.1 AATC design and construction contracts are structured in such a manner that electrical
equipment and associated infrastructure required for Bulk Materials Handling Systems
are designed according to an Electrical Load List provided by the Mechanical Designer
which details the required motor ratings and speed. Motor specifications shall be
according to AATC Specifications and shall be approved by the Electrical Discipline
Engineer.
6.2.1.2 Electrical design for Motor Control and associated infrastructure is normally contracted
in terms of a separate contract due to the nature of electrical bulk power supply. The
battery limit in terms of Bulk Materials Handling Systems is the terminals of the drive
motor/s associated with the BMH System. BMH Contractor responsible through AATC
Supply Chain for supply of motors.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 60 of 68
IMPLEMENTATION 11/22/2013
6.3
DOC NO AATC000859
Instrumentation
6.3.1.1 The requirements for instrumentation and controls supplied as part of packaged
equipment is specified within document AA_REQ_673035, Packaged equipment and
plants discipline requirement.
6.3.1.2 The integration option and associated instrumentation to be approved by the AATC
Instrumentation engineer.
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 61 of 68
IMPLEMENTATION 11/22/2013
REFERENCES
7.1
Document No.
AA_SPEC_114001
AA_SPEC_114002
ACSA_114012
AA_SPEC_114005
AA_SPEC_114010
AA_SPEC_114011
AA_SPEC_164000
AA_SPEC_164050
AA_SPEC_164051
AA_SPEC_166005
AA_SPEC_166014
AA_SPEC_248002
AA_SPEC_254001
AA_SPEC_255004
AA_SPEC_371001
AA_SPEC_373001
AA_SPEC_373005
AA_BPG_375001
AA_SPEC_377002
AA_SPEC_377003
AA_SPEC_377005
AA_SPEC_377006
AA_SPEC_377008
AA_SPEC_377010
AA_SPEC_415003
AA_SPEC_421017
AA_SPEC_673018
AA_SPEC_999022
AATC000168
AATC000169
DOC NO AATC000859
Description / Title
Design of Steel Structures
Construction of structural steelwork
Design Fabrication, Installation and Maintenance of
Open Grid Grating for Floors, Stairways and Hand
railing
Steel and FRP Flooring, Stairs, Ladders and
Guardrails
Design of Concrete Structures
Construction of concrete work
Users guide for corrosion prevention: System
selection
Corrosion Protection of Steelwork with Coatings
Plant colour coding
Lubricants specific requirements for industrial gear
oils
Lubricants specific requirements for greases
Materials handling Machines Structural Components
Specification.
Stacking and Reclaiming Equipment Mechanical
and Structural
Apron Feeders
Conveyor pulleys and shafts
Belt conveyor idlers and rolls
Installation tolerances for belt conveyors and
structures
Conveyor guarding best practise guideline
Steel cord reinforced conveyor belting
Splicing of steel cord reinforced conveyor belting
Splicing of textile reinforced conveyor belting
Solid woven conveyor belting
Splicing of PVC and nitrile covered Solid Woven
Conveyor Belting
Cold Splicing of Plied (Textile) Conveyor Belting
High Pressure Mine Water Reticulation Systems
General Purpose Valves
Conveyor Belt Protection Systems
Mechanical Standards
Fire protection for buildings and structures
Fire protection for conveyors and coal transfer
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
Page 62 of 68
company.
IMPLEMENTATION 11/22/2013
7.2
DOC NO AATC000859
Document No.
SANS 14
SANS 62-1
SANS 121
SANS 719
SANS 971
SANS 1123
SANS 1173
SANS 1313
SANS 1669
SANS 1366
SANS 1431
SANS 4427
SANS 10083
SANS 10103
SANS 10400
ISO 1461
ISO 5048
AWS D1.1
DD CEN/TS
13001-3-2
PD 5403
BS 21
BS 436-5
BS466
BS 545
BS 1640
BS 3381
BS 3974
Description / Title
Malleable cast iron fittings threaded to IS0 7-1
Steel Pipes Part 1: Pipes suitable for threading and of
nominal size not exceeding 150 mm
Hot dip galvanized coatings on fabricated iron and steel
articles - Specifications and test methods
Electric welded low carbon steel pipes for aqueous fluids
(large bore)
Fire retardant textile reinforced conveyor belting (Solid
Woven PVC)
Pipe Flanges
General purpose textile reinforced conveyor belting
Conveyor idlers
Conveyor belt pulleys
Steel cord reinforced conveyor belting
Weldable structural steels
Polyethylene (PE) pipes for water supply
The measurement and assessment of occupational noise for
hearing conservation purposes
The measurement and rating of environmental noise with
respect to land use, health, annoyance and speech
communication
The application of the National Building Regulations
Hot dip galvanized coatings on fabricated iron and steel
articles -- Specifications and test methods
Continuous Mechanical handling Equipment Belt
conveyors with carrying idlers calculation of operating
power and tensile forces
American Welding Society - Structural Welding Code
Cranes General design - Part 3-2: Limit states and proof of
competence of wire ropes in reeving systems
Guidance on safe use of machinery
Pipe threads for tubes and fittings where pressure-tight
joints
are made on the threads (metric dimensions)
Spur and helical gears. Definitions and allowable values of
deviations relevant to radial composite deviations and
runout information
Specification for power driven overhead travelling cranes,
semi-goliath and goliath cranes for general use
Specification for bevel gears (machine cut)
Steel butt-welding pipe fittings
Specification for spiral wound gaskets for steel flanges to BS
1560
Specification for pipe supports. Large bore, high
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 63 of 68
IMPLEMENTATION 11/22/2013
BS 3799
BS 6129:
Part 1
BS EN
10226-1
BS EN 10241
BS EN
10253-2
BS EN 12513
BS2853
DOC NO AATC000859
REVISION HISTORY
Version No.
Date
Draft:
May 2013
Final Draft:
August 2013
Published:
October 2013
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 64 of 68
IMPLEMENTATION 11/22/2013
APPENDICES
9.1
DOC NO AATC000859
Assizing
SKF
Belt Arrestors
ICO
Belt Ploughs
Belt Scrapers Primary and
Secondary
Hosch
Brelko
Scorpio
Hosch
Brelko
Scorpio/Mar
tin Eng
Process
Automation
Goodyear/V
eyance
Dymot
Thermo
Fisher
Schenck
Process
Dunlop
Fenner
Voith
Svendborg
Binder
Centrifuges
Malvern
Ludowici
Couplings - Fluid
Voith
Multotec
Seprotech
Transfluid
(BMG)
Belting (Existing
AATC contracts)
Brakes - Capstan
Brakes - High
Speed and Low
Speed
Cranes
Transmissio
n
Component
s
Morris
Cyclone
Multotec
Couplings - High
Speed and Low
Speed
Dust Suppression
and Extraction
Systems
Electro-hydraulic
actuators
Elemental Moisture
Density Analysers
Feeders - Apron
Feeders Observation
Feeders - Vibrating
Feeders - Grizzleys
Dustaway
Dabeb
Elram
Thermo
Fisher
Metso
Vendor 6
Vendor 5
Thermo
Fisher
FAG
(pulleys
only)
Bearings
Belt Weighers
Vendor 4
Atlas Copco
Process
Automation
Vendor 3
Air Compressor
Vendor 2
Equipment Type
Vendor 1
Phoenix
Andritz
Voith
Kone
Krebs FL
Smidth
Mikropul
Condra
Demag
Malvern
Air Cleaning
Equipment
Hytec
MMD
Bateman
Osborn
Osborn
Metso
Vibramech
Joest
Schenck
Vibramech
Joest
Schenck
Osborn
Magquip
Osborn
Vibramech
Joest
Schenck
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Vipro
Page 65 of 68
IMPLEMENTATION 11/22/2013
Fire Protection
Systems
Fire Control
Systems
Gearboxes
Hansen
Paramax
Hoists
Holdbacks External
Hydraulic Power
Packs
Idlers (Existing
AATC contracts)
Jaw Crushers
Morris
Kone
Falk
Marland
Denquip
Hytec
Hyflo
Melco
Lorbrand
Osborn
Osborn
FFE
Sandvik
Lubrication
Magnetic
Separators
Lincoln
Multotec/
Magquip
Overband Magnets
Eriez
Mineral Sizers
Motors
Siemens
TH (Tecnicas
Hydraulicas)
CPM
Weir
Warman
Pumps
Ring Roll
Granulators
Rock Breakers
Rotary Breakers
Sampling Plant
Packages
Screens
Stock
yard
Equipment
Stackers/
Reclaimers
Thickener
Winches,
Sheave
Wheels and Ropes
9.2
Bateman
SEW
Yale
David
Brown
Demag
Elco/ Ernest
Lowe
Malvern
Mechani
Mag
Process
Automation
MMD
Metal Detectors
Flender /
Siemens
Condra
DOC NO AATC000859
ABB
Sandvik
W.E.G /
ZEST
EET
Malvern
Multotec/Ma
gquip
Thermo
Fisher
FFE (Abon)
Alstom
CMG
Ishigaki
Bosworth
Krebs
MillMAX
MS Pulleys
Metso
Osborn
Atlas Copco
Rammer
CRM
Osborn
Metso
Osborn
Vibramech
Bateman
Thermo
Fisher
Schenck
Ludowici
ConnWeld
Linatex
Joest
Krupp
Metso
Tenova/
Takraf
Sandvik
Schade
FLSmidth
GKD Delkor
MIP
Outotec
FLSmidth
Dymot
Atlanta
Multotec
Drawing Number
0000-0000-MED-0001
0000-0000-MED-0002
0000-0000-MED-0003
0000-0000-MED-0004
0000-0000-MED-0005
0000-0000-MED-0006
0000-0000-MED-0007
Drawing Title
STANDARD HANDRAILING
*HOLD* GENERAL NOTES
ACSA - STANDARD A1 DRAWING SHEET
TEMPLATE
SCREW TAKE-UP DETAIL
EQUIPMENT SCHEDULE , PULLEY SCHEDULE
AND SOLE PLATE SCHEDULE
SLIDING JOINT DETAIL - 1500 WIDE BELT
BELT TURN-OVERS - 1200 WIDE BELT
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 66 of 68
IMPLEMENTATION 11/22/2013
0000-0000-MED-0008
0000-0000-MED-0009
0000-0000-MED-0010
0000-0000-MED-0011
0000-0000-MED-0015
0000-0000-MED-0016
0000-0000-MED-0017
0000-0000-MED-0018
0000-0000-MED-0019
0000-0000-MED-0020
0000-0000-MED-0021
0000-0000-MED-0022
0000-0000-MED-0023
0000-0000-MED-0024
0000-0000-MED-0025
0000-0000-MED-0026
0000-0000-MED-0027
0000-0000-MED-0028
0000-0000-MED-0029
0000-0000-MED-0030
0000-0000-MED-0031
0000-0000-MED-0032
0000-0000-MED-0033
0000-0000-MED-0034
0000-0000-MED-0035
0000-0000-MED-0036
0000-0000-MED-0037
0000-0000-MED-0038
0000-0000-MED-0039
0000-0000-MED-0040
0000-0000-MED-0041
0000-0000-MED-0042
0000-0000-MED-0043
0000-0000-MED-0044
0000-0000-MED-0045
0000-0000-MED-0046
0000-0000-MED-0047
0000-0000-MED-0048
0000-0000-MED-0049
0000-0000-MED-0050
DOC NO AATC000859
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 67 of 68
IMPLEMENTATION 11/22/2013
0000-0000-MED-0052
0000-0000-MED-0053
0000-0000-MED-0054
0000-0000-MED-0065
0000-0000-MED-0066
0000-0000-MED-0067
DOC NO AATC000859
Refer to the AATC Document Management System for the latest version of the document. Copyright resides with the
company.
Page 68 of 68