ANNEXURE - VI-PRICE BID (BIDDER'S CONFIRMATION SHEET)-1


PRICE SCHEDULE (LUMP SUM)
TENDER No: UP14C15018
NAME OF WORK:"HIRING THE SERVICES FOR REPAIR OF REGENERATION COLUMNS
C-1202 & C-1302 in GSU-12 & 13 AT ONGC URAN PLANT"
BIDDER'S NAME :
DESCRIPTION
TOTAL LUMP SUM PRICE (Rs.)
Lump sum price for job of "HIRING THE SERVICES
FOR REPAIR OF REGNERATION COLUMNS C-1202
& C-1302 in GSU-12 & 13 AT ONGC URAN PLANT"
as per enclosed scope of work and Technical
Specifications. The lump sum price is inclusive of all
taxes, duties, levies, insurance, Octroi, Cess,
transportation charges etc. including but not limited to
applicable customs duty, excise duty, Value Added Tax,
Corporate Tax, Works Contract Tax, Service Tax as
applicable to complete job.
RATES OF TAXES & DUTIES CONSIDERED AND INCLUDED IN THE ABOVE LUMP SUM
PRICE ARE TO BE INDICATED FOR THE PURPOSE OF CLAIM IN ACCORDANCE WITH
CHANGE IN LAW
Laws, Acts, Rules, Regulations etc. and the tariffs thereof considered by the bidder while
estimating the incidence of taxes, duties, fees, levies etc. considered and included in the
bidders Lump sum price quoted above, as per relevant provisions of General Conditions of
Contract to be used for the purpose of adjustment to the contract price in the event of
change in law in terms of relevant clause of General Conditions of Contract are as under:
ITEM

TENDER
DOCUMENT
CLAUSE
REFERENCE

LAW/ ACTS/
RULES/
REGULATIONS,
ETC.
REFERENCE

EXCISE DUTY
SERVICE TAX &
CESS
Value Added Tax
WORK CONTRACT
TAX

UP14C15018

TARIFF
INDICATING
RATE OF TAX/
DUTY/ FEE/
LEVY ETC.

Note : 1. Bidder may suitably add other heads in terms of Change in Law clause
of General Conditions of Contract. 2. The bidders not indicating the rates as
desired above shall not be entitled for any claim due to change in law.

3. The successful
bidder has to give an undertaking that they will submit invoices in a way that
ONGC will be able to get CENVAT benefit on EXCISE duty as well as Service Tax
based on tax invoice as per respective rules under the act.

UP14C15018

ATION

SHEET)-1

EGENERATION COLUMNS
"

L LUMP SUM PRICE (Rs.)

IN THE ABOVE LUMP SUM


IM IN ACCORDANCE WITH

nsidered by the bidder while


nsidered and included in the
sions of General Conditions of
ontract price in the event of
s of Contract are as under:
AMOUNT INCLUDED
IN THE LUMP SUM
PRICE

UP14C15018

of Change in Law clause


dicating the rates as
change in law.

3. The successful
invoices in a way that
as well as Service Tax
ct.

UP14C15018

Page 160
ANNEXURE - VI-PRICE BID (BIDDER'S CONFIRMATION SHEET)-2

BREAK-UP OF LUMP SUM PRICE


TENDER No.-.-UP14C15018
NAME OF WORK: "HIRING THE SERVICES FOR THE JOB OF REPAIR OF REGENERATION
COLUMNS C-1202 & C-1302 in GSU-12 & 13 AT ONGC URAN PLANT"
BIDDER'S NAME :

Note : 1. Rates shall be inclusive of all taxes, duties, levies, insurance , octroi, cess
handling & Transportation charges etc.
2. No discount shall be seperately given, discount if any shall be included in t
itself.
A. SCHEDULE OF RATE for C-1202 of GSU-12:
Sl
Description
Quantity Unit rate
Unit rate of
No.
for repair
taxes

Fillet weld patches area


(MXM) (Including material+
Service like welding etc.)

Weld overlay area (MXM)


(Including material+ Service
like welding etc.)

Lump sum charges for


Erection/dismantling & rent
of material for scaffolding
(Nos)

Lump sum charges for


painting of railings,
platform, grating & column
as per the procedure with
supply of all painting
material

A' Total Rs.

UP14C15018

Page 161

B. SCHEDULE OF RATE for C-1302 of GSU-13


Sl.No

Description
Area of Lap bands (MXM)
OD of shell-2.74 m
(including material +service
like welding etc.)

Quantity

Unit rate
for repair

Unit rate of
taxes

38.7

Fillet weld patches area ( M


x M) (including material
+service like welding etc.)

Weld overlay area (M x M)

Replacement of SS cladding
(3.0mm thick) inside the
column( M x M)

6.75

Lump-sum charges for


Erection/dismantling/transp
ortation to & fro & rent of
material for
scaffolding(nos.)

Lump-sum charges for


painting of railing, platform,
grating & column as per
procedure with supply of all
painting materials(no.)

B' Total Rs.


Total 'A' + 'B'

UP14C15018

MATION SHEET)-2

CE

EPAIR OF REGENERATION
PLANT"

insurance , octroi, cess,

ny shall be included in the offer

of GSU-12:
Total unit
rate with
taxes

Total
amount Rs.

UP14C15018

2 of GSU-13
Total unit
rate with
taxes

Total
amount Rs.

Total 'A' + 'B'

UP14C15018