You are on page 1of 51

ANALISIS DEL COSTO HORARIO DE MANO DE OBR

REGIMEN DE CONSTRUCCION CIVIL


Obra:
Cliente:

PERFORACION Y VOLADURA PARA ENSANCHAMIENTO DE CARRETERA

CATEGORIA

Supervisor

Jornal Bsico

S/.

Bonificacin especial

100.00
0.00

Jornal Bsico Total

100.00

Das Laborados
Horas Extras 60%

Horas Extras 100%

Das

30

H-H

60

H-H

0
S/.

Remuneracin Bsica

3,000.00

Horas Extras 60%

60%

1,200.00

Horas Extras 100%

100%

0.00

Da Feriado Laborado (3 jornales)

1.08

325.00

BUC (Bonificacin Unificada de Const.)

32%

960.00

Altitud (Segn zona de Obra)

0.35

10.50

Hijos

136.96

INGRESO BRUTO MENSUAL

S/.

5,632.46

13%

732.22

2%

4.50

Asignacin por Escolaridad


DESCUENTOS AL TRABAJADOR:
ONP / AFP
CONAFOVICER

INGRESO NETO MENSUAL

4,895.74

Vacaciones (30 jornales)

250.00

Gratificaciones ( 40 Jul+40 Dic)

666.67
Total de Vacaciones + Gratificaciones

INGRESO BRUTO MENSUAL(C/GRATIF. Y VAC.)

S./

916.67
6,549.13

LEYES SOCIALES:
Essalud

9.00%

577.10

IES

2.00%

114.91

SCTR

1.53%

98.11

CTS

15.00%

496.17

AFP

1.00%

64.12

Pliza de Seguro

2.50%

137.39

Sub-Total Leyes Sociales

1,487.79

IMPLEMENTOS DE SEGURIDAD

520.00

COSTO DIRECTO MENSUAL (S/.)


Tipo de cambio:

S/.
2.85

COSTO DIRECTO MENSUAL (US$)

$ 3,002.43

Porcentaje de leyes sociales

71.90

Horas efectivas programadas (25das/mes*10horas/da)


Costo Hora-Hombre

8,556.92

250.00
S/. / HH

34.23

COSTO HORA-HOMBRE

US$ / HH

IMPLEMENTOS DE SEGURIDAD
DESCRIPCION
COSTO S./
botas
50
respirador
85
filtros
45
mamelucos
65
lentes
5
tapon de oido
4
barbiquejo
3
guantes
15
casco
18
arnes y linea
190
orejeras
40
TOTAL
520

12.01

ORARIO DE MANO DE OBRA


NSTRUCCION CIVIL

DE CARRETERA
Fecha:
Operador
Hidrulico/
Mecnico

Operario Manipul.
explosivos

Ayudante
perforista

Oficial

40.80

36.10

36.10

32.50

Jornal por dia laborado

0.00

0.00

0.00

0.00

40.80

36.10

36.10

32.50

30

30

30

30

Dias del mes

60

60

60

60

2 horas por cada 2 primeras horas

1 hora por cada siguientes

S/.

S/.

S/.

S/.

1,224.00

1,083.00

1,083.00

975.00

Remuneracin basica

489.60

433.20

433.20

390.00

Horas extras de 2 primeras horas

0.00

0.00

0.00

0.00

Horas extras desde la 3ra hora

132.60

117.33

117.33

105.63

Feriados trabajados 03 jornales por dia la

391.68

346.56

346.56

312.00

BUC.

10.50

10.50

10.50

10.50

136.96

136.96

136.96

136.96

2,385.34

2,127.55

2,127.55

1,930.09

310.09

276.58

276.58

250.91

1.84

1.62

1.62

1.46

2,073.41

1,849.34

1,849.34

1,677.71

Se paga sobre 3000 m.s.n.m. S/. 0.35 di


Por cada hijo monto de S/. 68.48

102.00

90.25

90.25

81.25

272.00

240.67

240.67

216.67

374.00

330.92

330.92

297.92

2,759.34

2,458.46

2,458.46

2,228.00

236.01

208.94

208.94

188.19

47.01

41.62

41.62

37.49

No esta afecto Escolaridad, Gratifi.

40.12

35.52

35.52

31.99

No esta afecto Escolaridad

229.77

208.62

208.62

192.42

26.22

23.22

23.22

20.91

No esta afecto Escolaridad

56.21

49.76

49.76

44.83

No esta afecto Escolaridad

635.35

567.67

567.67

515.83

520.00

520.00

520.00

520.00

3,914.69

3,546.13

3,546.13

3,263.83

$ 1,373.57

$ 1,244.26

$ 1,244.26

$ 1,145.21

74.22

74.66

74.66

75.07

250.00

250.00

250.00

250.00

15.66

14.18

14.18

13.06

Record de 260 das


Ene-Dic (80 jornales)

No esta afecto Escolaridad

Es el 15% de R.Basica + HE (considerar

5.49

4.98

4.98

4.58

983702271

por dia laborado

s por cada 2 primeras horas

por cada siguientes

neracin basica

extras de 2 primeras horas

extras desde la 3ra hora

os trabajados 03 jornales por dia laborado

a sobre 3000 m.s.n.m. S/. 0.35 dia laborado

da hijo monto de S/. 68.48

d de 260 das

c (80 jornales)

a afecto Escolaridad

a afecto Escolaridad, Gratifi.

a afecto Escolaridad

5% de R.Basica + HE (considerar como HN.)

a afecto Escolaridad

a afecto Escolaridad

S/.

CALCULO DE PERFORACIN Y VOLADURA CON


TRACK DRILL (POR TURNO)
FRAGMENTACIN MAXIMA
Tipo de Roca

35.00

cm

SEMIDURA

Resistencia a la Compresin

> 200

Mpa

N Perforadoras Hidrulicas

1.00

und

Horas Programadas por Turno

9.00

Velocidad de Perforacin

17.00

m/h

Tiempo de Utilizacion

45.00

min/h

Horas Netas 1 Perforadoras / Turno

6.75

h/dia

Produccin de Metros Perforados

114.75

m.p/dia

Diametro de Perforacin

2.50

Pulg

Burden

1.80

Espaciamiento

2.00

Altura de Banco

2.80

Sobre perforacion

0.40

Longitud del taladro

3.20

m
m
Tal

Nmero de Taladros por Turno

Rendimiento real del disparo (avance)


Volumen por metro lineal
Volumen efectivo por metro
Produccin por Turno
Produccin por Hora
Turnos por Da
Produccin por Da

35

87.50%
3.60
3.15
352.80
52.27
1.00
352.80

m3/m
m3/m
m/Turno
m/h
Turnos
m/Turno

EXPLOSIVO A POR DISPARO


Diametro de perforacion

2.50

pulg

Tipo de explosivo

anfo

kg

Densiad del explosivo

0.80

g/cc

Longitud de taladro

3.20

Taco

1.71

Longitud de carga

1.49

Concentracion de carga por metro

2.53

kg/m

Carga por taladro

3.77

kg/tal

Carga por disparo

132.12

kg/dis

5.28

Und.

105.00

Und.

Mecha de seguridad

3.00

Und.

Perforacion especifica

0.32

m/m3

Densidad de carga

0.37

Kg/m3

Sacos de anfo
Cartuchos por disparo

75.00% Eficiencia

=
Disponibilidad mecanica =
Disponibilidad operativa =

0.75
0.80
1.07

CALCULO DE PERFORACIN Y VOLADURA CON


rock DRILL (POR TURNO)
FRAGMENTACIN MAXIMA
Tipo de Roca

35.00

cm

SEMIDURA

Resistencia a la Compresin

> 200

Mpa

N Perforadoras Hidrulicas

1.00

und

Horas Programadas por Turno

9.00

Velocidad de Perforacin

25.00

m/h

Tiempo de Utilizacion

50.00

min/h

Horas Netas 1 Perforadoras / Turno

7.50

h/dia

Produccin de Metros Perforados

187.50

m.p/dia

Diametro de Perforacin

2.50

Pulg

Burden

1.80

Espaciamiento

2.00

Altura de Banco

2.80

Sobre perforacion

0.40

Longitud del taladro

3.20

m
m
Tal

Nmero de Taladros por Turno

Rendimiento real del disparo (avance)


Volumen por metro lineal
Volumen efectivo por metro
Produccin por Turno
Produccin por Hora
Turnos por Da
Produccin por Da

58

87.50%
3.60
3.15
584.64
77.95
1.00
584.64

m3/m
m3/m
m/Turno
m/h
Turnos
m/Turno

EXPLOSIVO A POR DISPARO


Diametro de perforacion

2.50

pulg

Tipo de explosivo

anfo

kg

Densiad del explosivo

0.80

g/cc

Longitud de taladro

3.20

Taco

1.71

Longitud de carga

1.49

Concentracion de carga por metro

2.53

kg/m

Carga por taladro

3.77

kg/tal

Carga por disparo

218.95

kg/dis

8.76

Und.

174.00

Und.

Sacos de anfo
Cartuchos por disparo
Mecha de seguridad

3.00

Perforacion especifica

0.32

m/m3

Densidad de carga

0.37

Kg/m3

83.33% Eficiencia

=
Disponibilidad mecanica =
Disponibilidad operativa =

0.83
0.80
0.96

CALCULO DE PERFORACIN Y VOLADURA CON


TRACK DRILL (POR TURNO)
FRAGMENTACIN MAXIMA
Tipo de Roca

35.00

cm

SEMIDURA

Resistencia a la Compresin

> 200

Mpa

N Perforadoras Hidrulicas

1.00

und

Horas Programadas por Turno

9.00

Velocidad de Perforacin

30.00

m/h

Tiempo de Utilizacion

50.00

min/h

Horas Netas 1 Perforadoras / Turno

7.50

h/dia

Produccin de Metros Perforados

225.00

m.p/dia

Diametro de Perforacin

2.50

Pulg

Burden

1.80

Espaciamiento

2.00

Altura de Banco

2.80

Sobre perforacion

0.40

Longitud del taladro

3.20

m
m
Tal

Nmero de Taladros por Turno

Rendimiento real del disparo (avance)


Volumen por metro lineal
Volumen efectivo por metro
Produccin por Turno
Produccin por Hora
Turnos por Da
Produccin por Da

70

87.50%
3.60
3.15
705.60
94.08
1.00
705.60

m3/m
m3/m
m/Turno
m/h
Turnos
m/Turno

EXPLOSIVO A POR DISPARO


Diametro de perforacion

2.50

pulg

Tipo de explosivo

anfo

kg

Densiad del explosivo

0.80

g/cc

Longitud de taladro

3.20

Taco

1.71

Longitud de carga

1.49

Concentracion de carga por metro

2.53

kg/m

Carga por taladro

3.77

kg/tal

Carga por disparo

264.25

kg/dis

Sacos de anfo

10.57

Und.

Cartuchos por disparo

210.00

Und.

Mecha de seguridad

3.00

Perforacion especifica

0.32

m/m3

Densidad de carga

0.37

Kg/m3

83.33% Eficiencia

=
Disponibilidad mecanica =
Disponibilidad operativa =

0.83
0.80
0.96

CALCULO DE PERFORACIN Y VOLADURA CON


MARTILLO PARA ACCESOS (POR TURNO)
FRAGMENTACIN MAXIMA
Tipo de Roca
Resistencia a la Compresin

25.00

cm

SEMIDURA
> 200

Mpa

N Perforadoras

3.00

und

Horas Programadas por Turno

9.00

Velocidad de Perforacin

7.00

m/h

Tiempo de Utilizacion

45.00

min/h

Horas Netas 3 Perforadoras / Turno

20.25

h/dia

Produccin de Metros Perforados

141.75

m.p/dia

Diametro de Perforacin

1.50

Pulg

Burden

0.80

Espaciamiento

0.80

Altura de Banco

2.80

Sobre perforacion

0.30

Longitud del taladro

3.10

m
m
Tal

Nmero de Taladros por Turno

Rendimiento real del disparo (avance)


Volumen por metro lineal
Volumen efectivo por metro
Produccin por Turno
Produccin por Hora

45

90.32%
0.64
0.58
80.64
3.98

m3/m
m3/m
m/Turno
m/h

Turnos por Da

1.00

Turnos

Produccin por Da

80.64

m/Turno

Diametro de perforacion

1.50

pulg

Tipo de explosivo

anfo

kg

Densiad del explosivo

0.80

g/cc

Longitud de taladro

3.10

Taco

1.04

Longitud de carga

2.06

Concentracion de carga por metro

0.91

kg/m

Carga por taladro

1.88

kg/tal

Carga por disparo

84.55

kg/dis

Sacos de anfo

3.38

Und.

Cartuchos por disparo

45.00

Und.

Mecha de seguridad

3.00

Perforacion especifica

1.73

m/m3

Densidad de carga

1.05

Kg/m3

EXPLOSIVO POR DISPARO

75.00%

Eficiencia =
Disponibilidad mecanica =
Disponibilidad operativa =

2.25
0.80
0.355555556

IMPLEMENTOS DE VIVIENDA
CAMAROTES
COLCHONES
FRAZADAS
SABANAS
ALMOHADAS
SUB TOTAL
LAVADO
TOTAL

HERRAMIENTAS

UNIDAD

CANTIDAD

UND.
UND.
UND.
UND.
UND.

6
12
24
12
12

UND.

36

UNIDAD

Atacador de madera
Barretilla de 6'
Combo de 8 lb
Lampa Minera
Llave francesa de 14"
Llave Stilson de 14"
Pico Minero
Afilador de brocas
Botones de Afilador de broca
Wincha 50 mts
Flexometro 5 mts
Cordel de 50 mts
Martillo
Arco de cierra
Cierra
Mochila
Alambre
Manga de cristal

pza
pza
pza
pza
pza
pza
pza
pza
pza
und
und
und
und
und
und
und
kg
kg

SUB TOTAL
OTROS
TOTAL

5%

CANTIDAD

5
3
2
4
1
1
3
1
5
1
0
2
2
1
3
3
5
5

HERRAMIENTAS PARA CARGUIO Y VOLA


HERRAMIENTAS

Atacador de madera
Barretilla de 6'

UNIDAD
pza
pza

CANTIDAD
5
3

Lampa Minera
Pico Minero
Flexometro 5 mts
Cordel de 50 mts
Balanza chica
Mochila
Manga de cristal

pza
pza
und
und
und
und
kg

SUB TOTAL
OTROS
TOTAL

5%

4
3
2
2
3
3
5

Cambio US$
P.U.(S/.)

V. UTIL (MESES) P.PARCIAL (MES)

180
40
30
15
10

60
60
36
24
48

P.U.($)
3.00
15.00
30.00
10.00
14.00
20.00
8.00
500.00
150.00
26.66
7.00
16.66
6.00
10.00
3.00
28.00
3.00
3.20

V. UTIL (dias)
30
120
120
90
180
180
90
365
90
60
30
60
180
240
5
90
5
10

Flete

18.00
8.00
20.00
7.50
2.50
56.00
48.00

5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%

P.PARCIAL S/. (MES)

Flete

42.90
32.18
42.90
38.13
6.67
9.53
22.88
117.53
715.00
38.12
0.00
47.65
5.72
3.58
154.44
80.08
257.40
137.28

5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%

P.PARCIAL S/. (MES)


42.90
32.18

Flete
5.00%
5.00%

P.P+flete

18.90
8.40
21.00
7.88
2.63
58.80
50.40
109.20
P.P+flete

45.05
33.78
45.05
40.04
7.01
10.01
24.02
123.41
750.75
40.03
0.00
50.03
6.01
3.75
162.16
84.08
270.27
144.14
1839.60
91.98
1931.58

TAS PARA CARGUIO Y VOLADURA


P.U.($)
3.00
15.00

V. UTIL (dias)
30
120

P.P+flete
45.05
33.78

10.00
8.00
7.00
16.66
5.00
28.00
3.20

90
90
30
60
60
90
10

38.13
22.88
40.04
47.65
21.45
80.08
137.28

5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%

40.04
24.02
42.04
50.03
22.52
84.08
144.14
485.72
24.29
510.00

2.50
US$/Mes

7.5600
3.3600
8.4000
3.1500
1.0500
23.5200
20.1600
43.6800
US$/Mes

18.0180
13.5135
18.0180
16.0160
2.8028
4.0040
9.6096
49.3644
300.3000
16.0120
0.0000
20.0120
2.4024
1.5015
64.8648
33.6336
108.1080
57.6576
735.8382
36.7919
772.6301
1200

US$/Mes
18.0180
13.5135

US$/DIA
25.7543

16.0160
9.6096
16.8168
20.0120
9.0090
33.6336
57.6576
194.2861
9.7143
204.0004

US$/DIA
6.8000

COSTOS DE EXPLOSIVOS Y ACCESORIOS

DESCRIPCION
SEMEXA 65% 7/8 x 7
EXAMON
Cordon detonante
Fulminante simple
Retardos de 17 ms
Retardos de 42 ms
Retardos de 100 ms
Mecha de seguridad

UND

US$/UND
Trujillo

% FLETE

Kg
Kg
m
UND
UND
UND
UND
m

3.4
1.16
0.19
0.19
3.58
3.58
3.58
0.19

5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%
5.00%

TOTAL

DISTRIBUCIN DE CARGA EXPLOSIVA POR DISPARO

Filas

de Tal.

Long. Tal

(m)

N de Tal.

Metros Perfor.
(m)

TRACK DRILL

3.20

35.00

114.75

ROCK DRIL

35.00

58.00

187.50

MARTILLO

3.10

45.00

141.75

138.00

444.00

Cantidad/Disp
Precio unitario

US$

Precio total

US$

Costo por Disparo

US$/DISP

US$/UND
Proyecto
3.57
1.218
0.1995
0.1995
3.759
3.759
3.759
0.1995
16.6635

DISPARO
Dinamita 65% de
7/8x7" (Kg)

ANFO (Kg)

Cordn detonante
Fulminante (Pza)
5P (m)

Guia de seg. (m)

Retardo de 17 MS
(Pza)

8.61

132.12

230.00

2.00

3.00

1.00

174.00

218.95

380.00

2.00

3.00

1.00

3.74

84.55

330.00

2.00

3.00

1.00

186.35

435.62

940.00

6.00

9.00

3.00

3.57

1.22

0.20

0.20

0.20

3.76

665.25

530.59

187.53

1.20

1.80

11.28

Retardo de 25 MS Retardo de 42 MS
(Pza)
(Pza)
1.00

1.00

1.00

1.00

1.00

1.00

3.00

3.00

3.76

3.76

11.28

11.28
1,420.19

ANALISIS GASTOS GENERALES


PROYECTO :
Perforacion y Voladura Carretera
UBICACION: Arequipa
:
CLIENTE: COSAPI S.A. INGENIERIA Y CONSTRUCCION
PLAZO OBRA
:
12.00
Meses

Descripcin

FECHA PRESUPUESTO : 17-jun-2013


TIPO CAMBIO (1 US$) :
Precio
Unitario
(US$)

Unidad

Cantidad

CAMPAMENTOS
Oficinas
Implementacin deVivienda

mes
Glb

12.00
12.00

0.00
43.68
Sub-Total

POLVORINES DE EXPLOSIVOS
Custodia en Puesto Policial de la zona
Custodia Policial Diario (Explosivos a Obra)
Transporte de expolsivos y accesorios
Tramite de permiso de Explosivo

mes
mes
mes
mes

12.00
12.00
12.00
12.00

0
0
0
200
Sub-Total

MOVILIZACION Y DESMOVILIZACION
Personal Administracin Lima / Mecnico
Maquinaria, equipos y materiales

Pje.
Glb

12.00
1.00

0
0
Sub-Total

1. GASTOS EN OBRA
a)

b)

c)

d)

e)

f)

ADMINISTRACION DE OBRA
Ingeniero Residente
Administrador
Chofer camioneta
Chofer de combi
Vigilantes

Total
0.75
1
1
1
2

mes-h
mes-h
mes-h
mes-h
mes-h

12.00
12.00
12.00
12.00
12.00

2,629
1,256
764
764
614
Sub-Total

EQUIPOS Y VEHICULOS
Camioneta de supervisin
Camin de transporte de servicios
Combi para transportar personal
Radio walkie talkie
Iluminaria

Total
1
1
1
3
1

mes
mes
mes
mes
mes

12.00
12.00
12.00
12.00
12.00

3,662
3,694
2,145
295
850
Sub-Total

GASTOS VARIOS
Avisos de seguridad (voladura) en obra
Trmites diversos personal y equipos

Glb
mes

1.00
12.00

60
50

Economato para la oficina

mes

12.00

0
Sub-Total

TOTAL GASTOS EN OBRA

2. GASTOS OFICINA
Gastos de Oficina Central

TOTAL GASTOS GENERALES

mes

12.00

2,000.00

US$
17,211.11
2.62
1,723.68
30
51,710.40
135,303.60
12.720

S/. 2.50
Precio
Parcial (US$)

0
524
1,724
0
0
0
2,400
2,400
0
0
0
23,791
15,070
150
150
14,745
53,906
32,962
44,323
25,739
10,620
10,200
123,843

Produccin / Turno (m/10 h)


Produccin / Da (m/12 h)
Das trabajados / mes
Produccin / mes
Produccin Total

1,724
2,068
25
51,710

Tiempo total obra (meses)

0.00

S/. 250.00
S/. 109.20

800
600
4000
400

Custodia en Zona
S/. 10,000 por mes
S/. 80

Sueldo Mensual
US$
1,614
720
400
400
400
Vehculo
US$/mes
3,000
2,700
1,350

25

BB. SS.

Costo Parcial US$

53.59%
865
386
214
214
214

Viticos Mensual
US$

2,479
1,106
614
614
614

150
150
150
150
0

km/da

km/gln

Petrleo
100
150
120

60
600
0
660
182,533

PERFORACION

CARGUIO Y
VOLADURA

180,133

98,195

24,000

24,000

204,133

122,195

24,000

206,533
$/mes
$/m3
m3/turno
DIAS
m3/mes
$/MES
% GG

4,000
571

2,000

17011.1087017544 10182.9407017544
2.62

2.62

1,723.68

1,723.68

30
51710.4
135303.60

30
51710.4
135303.60

12.57254708 7.525993964

S/gln
25
25
25

13.80
13.80
13.80

Costo Mensual US$


2,629
1,256
764
764
614
US$/mes
662
994
795

COSTO UNITARIO
Obra

PERFORACION Y VOLADURA
LUGAR : Arequipa

Partida

Rendimiento

Fecha

PERFORACION Y VOLADURA DE ROCA


1,723.68 m/Turno

Horas / Turno
Tipo de Cambio US$
N de Turno

Concepto

Und

Cantidad

Incidencia

1.0 MANO DE OBRA


Supervisor

H-H

1.00

0.0052

Operario de Perforacion

H-H

5.00

0.0261

Ayudante Perforacion

H-H

6.00

0.0313

Manipulador de explosivos

H-H

2.00

0.0104

14.00
2.0 EQUIPOS
Compresora I.R. 750CFM

H-M

1.00

0.0052

Rock Drill SD 1000II

H-M

2.00

0.0104

Track Drill ECM 350 I.R.

H-M

1.00

0.0052

Compresora Sullair 375

H-M

1.00

0.0052

Perforadoras manueles RH 658

H-M

3.00

0.0157

Combustible

Gln

540.00

0.3133

Aceite motor

Gln

4.32

0.0025

Aceite hidrulico

Gln

3.24

0.0019

Aceite de transmisin

Gln

3.60

0.0021

Grasa

Kg

2.16

0.0013

Filtros 20%(Combustible)

20.00

Dinamita 65%7/8"x7"

Kg

186.35

0.1081

Anfo

Kg

435.62

0.2527

Fulminante

Pza

6.00

0.0035

3.0 MATERIALES

Mecha Lenta

9.00

0.0052

Cordon detonante 5g/m

940.00

0.5453

Retardo de 17 MS

Pza

3.00

0.0017

Retardo de 42 MS

Pza

3.00

0.0017

Retardo de 100 MS

Pza

3.00

0.0017

Shank T38 de 04 aletas

mp

120.00

0.0696

Barras

mp

130.00

0.0754

Brocas de 2.5" diam.

mp

140.00

0.0812

Afiladora de Brocas

mp

140.00

0.0812

Accesorios de perforacion

mp

140.00

0.0812

Barrenos integrales 10'

mp

180.00

0.1044

Barrenos integrales 8'

mp

170.00

0.0986

Barrenos integrales 5'

mp

160.00

0.0928

Barrenos integrales 3'

mp

150.00

0.0870

4.0 HERRAMIENTAS
5.0 ALIMENTACION
TOTAL COSTO DIRECTO
GASTOS GENERALES

12.72

UTILIDAD

10.00

TOTAL COSTO UNITARIO (SIN IGV)


TOTAL COSTO UNITARIO (SIN IGV)

h
de Cambio US$

9.00
2.75

1
P.Unitario

P.Parcial

12.0097

0.0627

4.9770

0.1299

4.5808

0.1435

4.9770

0.0520

Sub-Total

0.3881

40.0000

0.2089

150.0000

1.5664

50.0000

0.2611

35.0000

0.1827

10.0000

0.1566

Sub-Total

2.3757

7%

1.4938
44%

28%

72%

Horas

Consumo

Consumo

Turno

Turno

Horario

3.8600

1.2093

9.00

540.00

60.00 Gl/h

4.7380

0.0119

9.00

4.32

0.48 Gl/h

7.6015

0.0143

9.00

3.24

0.36 Gl/h

6.3365

0.0132

9.00

3.60

0.4 Gl/h

2.5990

0.0033

9.00

2.16

0.24 Gl/h

0.2419
3.5700

0.3859

1.2180

0.3078

0.1995

0.0007

0.1995

0.0010

0.1995

0.1088

3.7590

0.0065

3.7590

0.0065

3.7590

0.0065

0.8239
$

$/mp

P.unit

$/m.p.

CUARCITA
Vida util

0.3750

0.0261

450

0.375

1200 mp

0.3917

0.0295

470

0.392

1200 mp

0.4980

0.0404

249

0.498

500 mp

0.2000

0.0162

150

0.200

750 mp

0.3000

0.0244

120

0.300

400 mp

0.2143

0.0224

150

0.214

700 mp

0.2000

0.0197

140

0.200

700 mp

0.2400

0.0223

120

0.240

500 mp

0.2500

0.0218

100

0.250

400 mp

25.7543

0.0149

105.2632

0.0611

Sub-Total

2.6166

US$/m

5.3804

US$/m

0.6844

US$/m

0.5380

US$/m

6.6029

S/m

18.16

49%

S/. 69,555.93

DESCRIPCION

Vida util (mp)

P.unit. (US$)

US$/m.p.

Shank T38 de 04 aletas

1200

330.4

0.275

Barras

1200

403.2

0.336

Brocas de 2.5" diam.

500

173.6

0.347

Afiladora de Brocas

750

112

0.149

Accesorios de perforacion

400

134.4

0.336

Barrenos integrales 10'

700

131.04

0.187

Barrenos integrales 8'

700

118.72

0.170

Barrenos integrales 5'

500

101.92

0.204

Barrenos integrales 3'

400

89.6

0.224

" Especialistas en Perforacin y Voladura en Carreteras, Canteras y Ca

PROPUESTA TCNICA ECON


Cliente: COSAPI

AVANCE EN M3 DE ROCA VOLADA

Resumen:
1
2

PROCEDIMIENTO

EQUIPOS

PRECIOS UNITARIO PERFORACION Y VO


FIJA

Trujillo, Mayo del 2013

arreteras, Canteras y Canales "

NICA ECONMICA

e: COSAPI

DE ROCA VOLADA

FORACION Y VOLADURA DE ROCA

ayo del 2013

CORTE EN ROCA FIJA


OBJETIVO
Perforacin y Voladura de roca compacta mediante la utilizacin de explosivos, Asimismo el desqu
.calificado
PROCEDIMIENTO
Colocar seales de seguridad
Previamente se efectuara el trazo antes de iniciar con la perforacin, a fin de obtener mayor volum
.los planos
.Perforacin de roca fija utilizando compresora, martillos neumticos y barrenos de 3,5,8 y 10
.Colocacin de material explosivo y fulminantes en los hoyos perforados en cantidades especificad
.Efectuar disparos controlados por personal especializado
.Realizar el desquinche y peinado de talud por personal calificado con sus implementos de segurid
.El material triturado se proceder a eliminar a los depsitos de material excedente empleando el
.Todo las actividades estaran supervisadas por el Ing. de Seguridad
.Retirar seales de seguridad y liberar el area
METODO DE MEDICION
El trabajo ejecutado se medir en metros cbicos de material excavado en su lugar de origen, seg
.excavados usando levatamiento topografico y el mtodo de reas extremas en estaciones de 20 m
BASES DE PAGO
El pago se efectuara al precio unitario del contrato por metro cbico medido en su posicin origina
.total por toda mano de obra, equipo, herramientas, materiales e imprevistos necesarios para su e
tem de Pago
Unidad de Pago
.Corte en roca fija
Metro cbico (m3)

explosivos, Asimismo el desquinche y peinado de taludes con el uso de equipo mecnico y personal

n, a fin de obtener mayor volumen de voladura y se pueda cortar acorde a las secciones transversales de

os y barrenos de 3,5,8 y 10
ados en cantidades especificadas por metro cbico (0.30 kg/m3)

on sus implementos de seguridad requeridos para este procedimiento


terial excedente empleando el Tractor Oruga, Cargador Frontal y Camiones Volquetes

vado en su lugar de origen, segn indicaciones de los planos. Para tal efecto se calcularan los volmenes
extremas en estaciones de 20 m. o las que se requieran segn la configuracin del terreno

o medido en su posicin original, entendindose que dicho precio y pago constituir la compensacin
mprevistos necesarios para su ejecucin

mecnico y personal

cciones transversales de

uetes

alcularan los volmenes


el terreno

uir la compensacin

EQUIPOS

Equipo o Maquina

Marca

Trackdrill
Rock drill
Compresor
Compresor
Martillo Neumtico
Camioneta 4x4
Camioncito

Ingersoll Rand
Jun Jin
Sullair
Sullair
Atlas Copco
Toyota
Mitsubishi

Modelo

Cantidad

ECM-351 VL 130
SD 1000II
750 cfm
375 cfm

1
1
1
1
3
1
1