Professional Documents
Culture Documents
can betackled in verydifferentways, dependingonthe marketsystem characteristic (nodal orsingle-bus), the dispatching method
(sequential vs.joint) orthe ancillaryservices considered (typically
frequency and loadregulation divided into primary,secondary and
tertiary reserves). In additionto these factors, newpossible market
designs might arise, as,for instance, the existence of a uniquemarket in which the whole group of services is cleared bymeansof a
uniqueoffer.
It has beenpointed out that reserve modelingrequires the consideration of short-term constraints such asthe rampinglimits of
the generationunits orthe responding times of reserves. In addition,reserves are related to uncertain contingencies, reinforcing the
stochastic/probabilisticdimensionof the problem.It also requires
the formulation of interaction factors betweencommoditiesas,for
instance, lost opportunity costs betweenservices,orthe dependencyof reserve requirements onenergydemand.
Centralized dispatcheshave been thoroughly studied and a
widevariety of modelshavebeenelaboratedleading to interesting
results. A challenging via for future workwill bethe study of the
couplingbetweenmedium-term decisions (hydrothermalcoordination,fuel and maintenanceplanning, etc.)withthese short-term
centralized energyand reserve marketmodels.
Onthe contrary, oligopolistic models, havenot yet reached the
same level of maturityfor the combined energy and reserve dispatch than for the onlyenergy dispatch. Asshown in this paper,
the degreeof mathematicalcomplexity turns out to beconsiderablyhigher.Furthermore, the inclusion of additional variablesand
constraints criticallyincreases the size of the problem,and consequently, the expected computational times. These drawbackswill
surely besome of the challengesthat future works will haveto cope
with.
The effect of uncertainty is limited to the growth rate of
demand, to which a Markov Chain Monte Carlo approach is
applied. One hundred sequences of thirty years of demand
growth rates were generated. The performance of each of
the different market designs was tested against each of these
demand growth rate scenarios. With such a large number of
scenarios, statistical analysis of the results yields statistically
significant results. The differences between the average outage
rates are an indicator for the relative reliability of the different
market designs. We should not expect large differences in
long-run average prices, as investment is programmed to
take place up to the point that it is just expected to be profitable. Therefore, in every market design, long-run average
prices should approximate long-run average cost. However,
the differences between the standard deviations in de the different models are an indicator for price volatility. In an earlier
version of the model, historic data and a fixed growth rate were
used ( De Vries and Heijnen, 2006 ). However, we could not
generalize from the historic data while the fixed growth rate
provided little indication of the stability of the different market
designs in the presence of random variations in the growth rate
of demand. The Monte Carlo approach makes it possible to
evaluate the impact of demand growth rate uncertainty upon
various market designs in a statistically significant way.
The basic structure of the model is as follows. For each
year, the model calculates the supply function and the loade
duration curve for an imaginary electricity market (loosely
2004) and, at 10% of installed capacity, appear to be reasonably large. Of course, choosing different parameters will
lead to different performances. However, because investment
is modeled to always tend towards an equilibrium where price
equals long-run marginal cost, the models will provide
sufficient indication whether an alternative constitutes an
improvement or not. Therefore this comparison provides the
necessary insight into the dynamic behavior of the different
capacity mechanisms, but the results should be interpreted in
a qualitative manner.
outages and schedule maintenance. The outages in generation
units are modeled using a two-state probabilistic generation
model. A forced outage rate (FOR) is assumed for each technology
j . Interruptible contracts are seen as a generation technology
which has a variable cost and no fixed cost.
The demand in each local market is characterized by a load
duration curve and modeled on an hourly basis. The growth rate
of demand is represented by a discrete random variable following
a triangular distribution function similar toDe Vries and Heijnen
(2008).
3
In order to consider the influence of electricity trading
between local-markets on spot prices, demand is modified
according to the power flow between systems.
To calculate the electricity price, we assume a perfect competition framework and it is generally settled by the marginal cost of
generation which in turn corresponds to the variable cost of the
marginal generation technology. However, if demand exceeds the
available generation capacity, the electricity price is equal to the
cost of interruptible load contracts.
3.3. Modeling interaction between local markets in relation to their
interconnection capacity
Within regional electricity markets, local markets continuously interact. These interactions not only allow the most efficient
generation resources to be used, but also it increases the security
of supply. In order to consider these interactions, we rely on a
simplified version of an optimal power flow (OPF) algorithm,
which dispatches generation assets according to the regional
merit order (least-cost) subject to the physical constraints of the
interconnector. Here, the power flow through the transmission
line is the result of the free interaction of generation and demand
in both markets until the constraint of transmission capacity are
reached. It is assumed that system operators will not interrupt
exports to adjacent markets in case of a domestic emergency of
supply. This seems to be the purpose stated in Article 24 of
Directive 2003/54/EC: In taking the measures to be adopted in
emergency situations, Member States shall not discriminate
between cross-border contracts and national contracts .
We consider that the interconnector capacity is constant and
perfectly reliable throughout the simulation period. Although the
relationship between the dynamics of generation and transmission investments is strongly linked, we isolate the dynamic nature
of generation investment in order to focus on the impact of
market design on generation investment.
3.4. Investor s behavior
3.4.1. Investor s anticipation in an imperfect information context
The key economic agents in the model are the power producing companies. Their decisions cover investment in and decom-
y for that. A
national perspective on security of supply leads to higher costs due to national
excess capacities.
These capacities would be seldomly used, since imports usually substitute their
production. These
definitions should be politically answered, though it would be advisable to take
the consequences of
these definitions thoroughly into consideration.
Assumptions on the supply side play a crucial role for the short to medium-term
perspective on the
need for action. Many electricity market models need to be based on
assumptions regarding the
technical lifetime of the different types of power stations in order to draw con
clusions on the future
need for investment. The BET (2011) and EWI (2012) models have been b
ased on these fixed
lifetimes and have thus determined the future need for new power stat
ions. Consentec (2012)
considers the assumption of typical
lifetimes generally only suited to a limited ext
or a more
detailed assessment of the development of the power plant fleet . The argum
ents of r2b (2012)
likewise refer to potential incentives for extensions or reductions of the lifet
ime of conventional power
plants.
The assumption of fixed technical lifetimes of power stations helps to assess th
e order of magnitude
of future investment needs. This assumption however represents only an aid. In r
eality, it is mainly
the electricity price that plays a decisive role when retrofitting measures and
consequently extended