Professional Documents
Culture Documents
: RMC/JnNURM/DRN/01-06/0508
Estimated Cost
Period
05-06 TO 07-08
Date of Preparation
Date of Submission
No.: RMC/JnNURM/DRN/01-06/0508
Contents
C
Co
on
ntteen
nttss
Forward
Executive Summary
1.0 INTRODUCTION....
1.1 Background
1.2 Need of the Project
1.3 Objectives
1.4 Scope & Limitation
1.5 Methodology
2.0 BACKGROUND
...
2.1 Sectoral Policies outlined in CDP
2.2 Linkage of the projects to the CDP
22
28
Detail Project Report for Drainage Phase-II &II (Part-I) for Rajkot city
Contents
8.0 RECOMMANDATIONS...............................................
8.1 Issues and Performance Assessment
8.2 SWOT Analysis
8.3 Recommendation
92
97
10.0
170
11.0
174
Detail Project Report for Drainage Phase-II &II (Part-I) for Rajkot city
ii
Contents
Table Details
Table 1 :
Table 2 :
Quality of Air
Table 3 :
Table 4 :
Table 5 :
Table 6 :
Table 7 :
Table 8 :
Phasing of Sewage
Table 9 :
Table 10 :
Table 11 :
Table 12 :
Table 13 :
Sources of water
Table 14 :
Table 15 :
Table 16 :
No of Complaints
Table 17 :
Table 18 :
Table 19 :
Table 20 :
Table 21 :
Table 22 :
Table 23 :
The Detials Of Designed Capacity Of Pumping Stations For Rajkot Sewerage Project
Phase-
III
Table 24 :
The Details Of Designed Pumps And Motors For Pumping Stations For Rajkot Sewerage
Project Phase-III
Table 25 :
Table 26 :
Table 27 :
Bill Of Quantities For Collective System of T.P. scheme no. 1 part 1, T.P. 1
Table 28 :
Bill Of Quantities For Collective System of T.P. scheme no. 1 part 2, T.P. 4
Table 29 :
Table 30 :
Table 31 :
Table 32 :
Table 33 :
Table 34 :
Table 35 :
Table 36 :
Table 37 :
Bill Of Quantities For House Connection of T.P. scheme no. 1 Part 2 & T.P. 4
Table 38 :
Table 39 :
Detail Project Report for Drainage Phase-II &II (Part-I) for Rajkot city
iii
Contents
Table 40 :
Table 41 :
Table 42 :
Table 43 :
Table 44 :
Table 45 :
Table 46 :
Bill Of Quantities For House Connection of T.P. scheme no. 1 Part 2 & T.P. 4
Table 47 :
Table 48 :
Level of subsidies
LLiisstt ooff M
Maappss
No.
Map:
Location Map
Details
Map:
Map:
Drainage Status
Detail Project Report for Drainage Phase-II &II (Part-I) for Rajkot city
iv
Contents
A
Abbbbrreevviiaattiioonnss
ALV
APMC
ARV
BOD
BPMC
CA
CBO
CCP
CDS
CEPT
COD
CPHEEO
CUR
DA
FOP
GIDC
GMFB
GOG
GOI
GPCB
GSRTC
GUD & HD
GWSSB
HUDCO
IMR
JnNURM
NGO
NIOH
OR
PF
RCC
REA
RMC
RTO
RUDA
SC
SPM
ST
SWOT
TDS
UDPFI
WPR
Detail Project Report for Drainage Phase-II &II (Part-I) for Rajkot city
Introduction
Introduction
1.1 Background
Rajkot City with a population of one million (as per census 2001) and with an area of 104.86
Sq. Kms. is situated on the bank of river Aji. This fortified town on the West bank of Aji river was
founded by the then ruler of Sardhar in the year 1608. The city is having good road, Rail and Air links
with other important centers of the Country. Rajkot city has taken rapid strides in industrial and
commercial development and is growing in to an important urban center in the State. Further, very
fast industrial development also took place in the vicinity of Rajkot city. Area, like Sapar-Veraval and
Lodhika Industrial Estate have also affected in the growth of population of Rajkot city and urban area
of Rajkot remarkably.
The metropolitan areas, cities and towns have attracted a large numbers of rural migrants for
employment, higher education, purchases, medical treatment etc. Due to heavy rush on cities,
Government of Gujarat formed independent autonomous urban development authority for six cities in
the year 1978. Rajkot Urban Development Authority (RUDA) was formed on 30th January 1978. The
authority has to plan, implement and follow up the development of 483 sq.km. This area includes
Municipal Corporation and 39 villages in the immediate periphery of the city. Till June 1998 the
authority had prepared eight town planning schemes in the immediate periphery of the city boundary
towards west side of the city and covered land of three villages namely Raiya, Nanamava and Mavdi.
Because of the development took place in the town planning scheme area, basic infrastructure
facilities were sought out by the residents and ultimately in the year 1998, city limits of Municipal
Corporation on western area (Mavdi, Nanamava and Raiya) was extended for 35.86 Sq.Km and total
area of city limits became 69 sq.kms. to 104.86 sq.km. This resulted total population of the city about
one million ( as per Census 2001). With the rapid growth of the city, the need arise to augment the
existing basic infrastructures services of the city. Since the extended area was without any kind of
infrastructure facilities these basic service needs to be implemented on priority basis.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Introduction
Govt of India recently launched urban Infrastructure development mission for selected 63 cities of
India as Jawaharlal Nehru National Urban Renewal Mission (JnNURM) which also encourages
preparing Detail Project Report for under ground drainage project Phase-II ( Part-I) and PhaseIII(Part-I).
1.3 Objectives
The broad objectives of the Detail Project Report (DPR) are to determine a technically and
economically viable Sewerage & Sewage Treatment project for a phased implementation to meet the
requirements of the year 2030. Following are the specific objectives:
1. Assessment of the existing supply situation
2. Population and generation of sewage projections
3. Planning for Projects identified for JnNURM
4. Project scheduling & cost estimates
5. Projects phasing
6. To prepare operational plan
7. Organizational and financial studies
8. To set recommendation with respect to JnNURM reforms & sustainability
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Introduction
1.5 Methodology
Aim/Objectives
Situation analysis
Waste water characteristics
System analysis
Institutional and
financial analysis
Staff structure for the
drainage department
Total capital
investment for the
sewerage system
O & M expenses for
sewerage system
Existing Tariff
Structure
Level of Subsidy
Proposed Tariff
structure
Identification of problems
and issues
Requirement
Assessment
Civil Design
Mech/Elect Design
Future requirement
Population forecast
Future Land use
Water supply
Selection of best
alternatives for cost
Costing
Implementation
Drainage DPR
(Phase II & III (part-I)
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
B
Baacckkggrroouunndd ooff tthhee ssttuuddyy
: New Sewer Program & Sewage Planning_ This program is aimed at improving
the coverage of city waste water and also to cater population of newly merged area. It is proposed to
augment existing drainage net work of old city limit by adding more 20 sq.kms. area and to
implement an underground drainage system to the present developed area of 15 sq.kms (Out of 35
sq.kms newly merged area)> Similarly newly area the capacity of the plant will be 51 MLD.
DS2:
: Coverage of Low Income Settlements_ There is 84 slum notified slum area within
the old city limit of Rajkot. Existing drainage net work passes near to at least 55 slum areas. Therefore
it is proposed to cover this locality by using Pay & Use type toilet facility under GOI & GOG scheme
of Valmik Swatchhata Abhiyan. The same has been implemented by the Corporation. This will serve
as part of slum networking program. It is proposed to use budgetary head of 63\2 as matching fund
requirements
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
: Sewage Operation & maintenance _ Presently RMC privatized the O& M works.
DS4
It is found more effective, & economical. Therefore it is proposed to widen the scope of present
contract system.
No.
Details
20052006200706
07
08
Rajkot Under ground drainage project Phase -II old city area
1
Work of collective system &
300
300
300
house connections for inner city
area
Year
200809
Rs. In Lakhs
20092010201110
11
12
Total
300
245
50
50
1545
15
135
0
0
Additional pumping machinery
in various pumping station
3
Work of Rising main from
50
455
0
0
poptpara pumping station to
sewage treatment plant
4
Extension of existing treatment
0
400
200
200
plant by 44.5 MLD at Madhapar
Rajkot Under ground drainage project Phase -III for newly merged area
5
700
700
700
700
Const of main line , collective
50
50
50
300
505
800
500
500
500
4300
200
200
268
200
200
100
1168
400
570
600
500
2070
200
500
300
1000
20
20
1285
10.98
2790
23.83
2538
21.68
1200
10.25
995
8.50
1400
11.96
1500
12.81
11708
100
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
C
Chhaarraacctteerriissttiicc ooff tthhee ssttuuddyy aarreeaa
between
Jetulsar-Veraval-
3.3 Geography
Rajkot forms central part of
plateau, hills, linear ridges and alluvial plains. The southern and western parts of the city are
primarily covered by Deccan Traps, characterized by undulating topography with the presence of
plateaus at some locations. In the northern part, topography is plain with gentle slope towards north and
west. The average elevation attained in the district is 130 meters above mean sea level. The general
topography of RMC area is almost undulating with level difference from 125 m to 158 m from south east
to north west. The city of Rajkot is situated along the Aji River, which is seasonal in nature. The main
tributary of Aji in the area is khokhadadi located on southwest side of Rajkot city. Two nos at natural
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
water reservoirs (lakes) are located near Rajkot city viz. Lalpari and Randerda, at the distance of 4 kms
and 6 kms respectively from the city. Across the river Aji , Aji reservoir is built up at a distance of 9 kms
from Rajkot city and Aji II at a distance of 15 kms. In the RUDA area Nyari I and Nyari II reservoirs are
constructed which are located within of 15 Kms to 30 Kms from the city. In addition to this, for draining
storm water, Nos. of Natural courses exist, in RMC and RUDA areas which are ultimately meting to
river Aji to drain storm water.
Soil Type: Soil of the entire Rajkot area can be broadly classified as medium black to shallow
black. The black soil, being rich in minerals and organic matter is more fertile. These soils have been
formed even from granite and gneiss parent materials. The depth of the top soil is generally 25 cm to 50
cm deep. The color of soil surface varies from light gray to dark gray and is clayey in texture. The soil
reaction is neutral to alkaline with Calcium Carbonate. Beyond 50 cm depth the under ground strata are
soft rock & hard rock. The vegetative cover is minimal in the open area due to lack of adequate topsoil.
The topsoil is underlain with hard rock formations thereby limiting the growth of vegetation in the
region. .
Ground Water Table The fluviomarine alluvium of Upper Tertiary to Quaternary age forms
poor aquifer because of the predominance of argillaceous nature of formations and poor quality of
ground water. The ground water occurs under water table and confined conditions. Depth of tube wells
ranges from 30 to 120 meters below ground level, whereas depth to water level ranges from 20 to 100
meter below ground level. The seasonal fluctuations in the water table ranges from 1.8 to 12.0 meters.
The yield from the tube wells ranges from 2.50 to 10.00 cubic meters/day. In hard rock areas the
availability of ground water in a particular year is the direct response to intensity of monsoon and quick
response is seen in such aquifers. In the years of normal and above normal rainfalls the water level
decline. The seasonal availability of ground water also varies widely.
Rajkot district forms central part of Saurashtra Peninsula and has a diverse landscape made up of
plateau, hills, linear ridges and alluvial plains. The southern and western parts of the district are primarily
covered by Deccan Traps, characterized by undulating topography with the presence of plateaus at some
locations. In the northern part, topography is plain with gentle slope towards north and west. The east
west trending linear ridge forming upland south of Rajkot forms water divide for south & southwesterly
flowing drainage basin of Bhadar and north & northeasterly flowing drainage basins of Aji, Machhu etc.
Air Pollution : The principal sources of Air pollution in Rajkot are from vehicular emissions,
industrial emissions, construction related activities. Uses of Kerosene as fuel by Auto- rickshaw,
pollution
from
Chhakada
and
emission
relatively
of
more
Month
of
vehicular
While
sources
emissions.
of
industrial
air
quality
Aug-2003
Octo-03
Dece-03
Feb-04
Apr-04
July-04
Aug-04
Sep-04
Resi.
Area
NA
17
14
7
15
23
10
11
Indu.
Area
18
10
24
21
21
14
12
18
Resi.
Area
NA
14
19
7
14
8
13
10
SPM in
g/cu.mt.
Indu. Resi.
Area
Area
550
NA
230
120
310
210
190
210
320
130
180
180
230
210
240
160
monitoring is carried out at three locations by Gujarat Pollution Control Board (GPCB) since 2000. The
Monthly average of SO2 , NOX, and SPM of last year as collected from two station viz., Aji GIDC
Industrial area and GPCB Office- residential area are as shown in the table below: O2 and NOX levels in
Rajkot are within the NAAQS (Monthly Average) during both the years. However, the SPM levels in
Rajkot are found exceeding NASQS(Monthly Average) during both the years, particularly in Industrial
Area and 50% time in a year in residential area.
Water Pollution: The city lies within the watershed expansion of Aji river basin and it is
network of 19 natural drainage courses, locally known as Voklas. Unfortunately, these voklas are being
used for sewage disposals resulted the pollution of water Aji- river in down stream of Aji dam. Nyari-2
dam which collects water from Aji river and Nyari river is fully polluted water dam. An analysis of
different water bodies in down stream of Aji dam indicates the most of water bodies within city limit are
contaminated. Pollution of under ground water due to electro-plating industries and sari-printing
industries is also observed.
Pollution due to SW : The main causes for pollution include increasing household and
commercial waste, commercial waste as well as bio-medical waste. Though, Rajkot Municipal
Corporation is making efforts to ensure minimize the solid waste at source, but the result is not being
seen up to the mark.
Both these areas were separated by North-South Railway track then existed but
subsequently railway track was removed. Both these areas merged with each other resulting in
coordinated development of the town. Hence the city developed from a village, civic development was
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
in the process and in the course of time some of the major works came to be permanently visible. To
name some of them, we can mention Raj Kumar College, Alfred High School which was subsequently
named Mahatma Gandhi High School, Jubilee Garden, Railway line, Railway Junction, Lakhajiraj
Railway Station which geared up the development of whole town of Rajkot. By the end of 19th century,
Rajkot emerged as a premier town having a population of 36,000.
Rajkot was capital of Ex-Saurashtra State and has a central location in the region being a part of
Gujarat State. Its importance as a capital is attributed to geographical location, its cultural heritage and
the development potential possessed by the city.
outcome of the process of progressive development going on since decades. It will be useful to recall the
historical background of the city enjoying a position of importance in the field of Trade, Industry,
Education, Transportation, Communication, Entertainment and urbanization.
Rajkot is also affected by the wave of rapid urbanization and industrialization in the country over
the last few decades. The development of trade and industry has gradually reshaped the life of the people.
In the earlier period, the establishment of cloth mills in the city led to the development of new residential
areas like Millpara, Harishchandra Plot, Gundawadi, Kevdawadi etc. The new Railway Station known as
Bhaktinagar station also came into being.
Further, around the year 1940, new industrial estates, residential areas, schools, colleges, cinema
houses came into being. Thereafter, Rajkot eventually became a vibrant trading city with a wide network
of transport facilities by air, railway and road. A number of transport companies established their head
offices at Rajkot. The Industrial Estates known as Bhaktinagar Industrial Estate and Aji Industrial Estate
were established. Trade and Industry fast developing in the city also attracted foreign investment during
these periods. This trend of city development generated rising demand for creating new civic amenities in
the city.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
state, creating large number of employment opportunities. However, since then the decadal growth rate is
fluctuating between 41% to 54%. The city has grown up in area from 150 hectare in 1901 to 10404
hectare in 1998. i.e. it has growth approximately 70 times of its initial size.
The city is growing rapidly in western direction. However, city is also simultaneously growing in
all direction. The city can be divided in to three parts due to Aji River and railway tracks, which are
passed through the city. The city has greater and prosperous development on the western side, Industrial
development on Southern side and low-income housing towards northeastern side.
At present, Rajkot Municipal Corporation covers an area of 104. 86 sq.kms. including merged
three area viz., Raiya, Nana-Mava and Mavdi area.
The city is divided in to 23 administrative wards.
Year
Population
Growth rate
1901
36151
---
large
1911
34191
-5.42
1921
45845
+34.08
1931
59122
+28.96
1941
66353
+12.23
Corporation
1951
132069
+99.04
1961
194145
+47.00
1971
300112
+54.58
1981
445076
+48.30
1991
559407
+25.69
2001
1002000
+79.12
1941
to
limit
1951
by
because
merging
of
the
three
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
10
Population
800000
700000
600000
500000
400000
300000
200000
2001
1991
1981
1971
1961
1951
1941
1931
1921
1911
1901
100000
Year
Population Projections: The trend of population growth is an important indicator and base for the
assessment of future requirements of basic in the area for the future. In 1963, the RMC area was
extended from 38 Sq Kms to 69 Kms. Again in June 1998 the RMC area was extended by another
34.865 Sq Kms. This is credited to the immense growth in trade, commerce and industry, in and around
Rajkot.
Population projections for the RMC area have been carried out on the basis of the past growth
trends. It is required to estimate separately for RMC old area and Newly merged area as on June 1998.
The population growth rate of RMC area has been given in table. It has been observed that since last 100
years, the population of Rajkot City has increased at different growth rates. The growth rate of Rajkot
City from 1901 to 1941 has been calculated as very nominal i.e. 0.15 on average annually. After
Independence i.e. after 1951, the rate of population growth of Rajkot City has increased tremendously.
Based on the above population figure for the past decades, the RMC population ( excluding
newly merged area)has been projected utilizing ratio methods, the geometric growth method as well as
incremental increase method and graphical method. The growth rate in higher side found as 3.11% raise
per annum, medium as 3.05% and lower growth rate as 2.67%. However, Population growth rate of
newly merged area found population growth rate as 11.79%. Therefore, combine population growth rate
for RMC old area and the merged area calculated. The combined growth rate found as 4.59% for higher
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
11
side, 4.05 Medium side and 4.00% for lower side estimation. Table 1.1.3 shows population projections
for the years 2011and 2021.
Table: RMC Population projection
Sr.
Year
Population Projection
No
High
Medium
Adopted Population
Projection estimate
Low
2011
1,570,000
1,484,500
1,490,000
1,484,500
2021
2,215,000
2,207,000
2,232,000
2,207,000
Thus total population of the RMC area in the year 2011 is expected to 14.85 millions while for
the year 2021 reach to 22 million persons.
Population
2000000
1500000
1000000
500000
0
1971
1981
1991
2001
2011
2021
Year
Density : The population of Rajkot city is spread over an area of 104.86 sq.kms., with density of 9556
persons /sq.kms. The density in the older part of the city wards like ward no.1 to ward 8 ranges from
14952 to 35653 persons per sq.kms. the lowest density 3131 person per sq.kms. is registered in ward no.7
having the largest area. Ward no.2 has highest density of 35653 per sq.kms.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
12
Table 1.1.5: Ward wise Population, Area and Density of Rajkot city
Ward
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Total
Newly Merged
Area ( 21-23)
TOTAL
Area
( sq.kms.)
0.8227
0.7012
1.0900
1.0822
5.0741
1.7588
3.4360
0.9108
1.4714
1.5277
1.8571
2.875
2.9419
4.0682
1.2919
7.1330
18.8416
4.7052
5.7221
1.3905
69.6836
35.1764
104.86
As per 1991Census
Population
Density
29766
36181
26738
38132
28104
26289
30411
28101
29505
5815
27097
15406
29677
8637
27547
30245
26943
18311
25669
16802
25322
13635
25499
8869
25222
8573
25602
6293
26761
20663
25316
3549
30999
1645
31146
6619
30848
5391
31235
22463
559407
8028
81971
22330
641378
6116
Rise/
Fall
-ve
-ve
+ve
-ve
+ve
+ve
+ve
-ve
-ve
+ve
+ve
+ve
+ve
+ve
-ve
+ve
+ve
+ve
+ve
+ve
9556
Literacy Rate: Literacy level of Rajkot has always been higher than state literacy levels. With a
total literacy rate of 73.86% in the year 2001, the
city has comparatively higher literacy rate than 69.96% of State literacy rate as well as 54.16% of
National literacy rate.
Slum Population: Rajkot city has 84 notified slum area having population of about 202371. It
is spread in almost all wards. There are total 106574 males & 95769 female including total
children of 88865 (30516 children age below 5 yrs.& 58349 children age 6-17 yrs.). It shows sex
ratio as 899:1000. The caste structure is found as 33.29% SC, 2.47 % ST, 45.22 OBC (Other
Backward Class) & 10.02% general. The literacy rate is observed 63.70%. Out of 44914
household of slum and urban poor, it is found in total survey of all household that (survey carried
out by united research organization survey,2002), 32701 HH are living below Poverty line i.e.
about 72%. The total population below Poverty line is about 147342 people. Comparing to total
population of Rajkot city, which is 1002000 as per census 2001, the BPL population is about
14.7% of city population.
13
Rajkot city is characterized by a pattern of multiple land uses. The total area developed for
urban activities constitute 77% of the Rajkot Municipal Area. Residential use occupies about half of this
area, while industries occupy a fifth and commercial zones occupy less than 2%. Although a
Land Use
Residential
Commercial
Industrial
Traffic &
Transportation
Public & Semipublic
Recreational
Space
Agriculture
Water bodies
Vacant Land
Other
TOTAL
development
plan
has
been
result
in
quite
1400
13.35
1650
15.74
149
1.42
249
2.38
123
995
236
1510
988
10484
1.17
9.49
2.25
14.40
9.42
100 %
523
800
236
-508
10486
4.99
7.63
2.25
-4.84
100 %
for
total
urban
area
activities
area and balances constitute activities enmarked for vacant land, water bodies and other purposes.
Residential Uses: The residential development is spread over 54 sq.kms. high density of
residential development is found in older parts of city especially Kotak street, Raghuvir para, Ramnath
para, Kumbhar wada, Soni bazaar etc., The densities are low in the newly merged area especially in and
around kalwad road, Raiya road, 150 feet ring road, university road and in some parts of junction area,
popat para area etc. It is obvious that newly developed area where TP schemes were developed is
planned. However, old city areas like Prahlad plot, Jayraj plot area are developed with a regular street
pattern, well shaped plots but these area lack open space. Percentage of residential area to total area is
found 51.34% while residential area to developed area is 60.23% .
Commercial Use: Main commercial areas are Soni bazaar, Dharmendra road, Lakhajiraj road,
area around jubilee vegetable market.etc., of old city, which is also described as city area A in GDCR;
Yagnik road, Dhebar road, gondal road, Jagnath area etc., which is known as city area B etc.; and
Kalwad road, amin road, university road, Raiya road, st.kabir road, pedak road etc, called Other area_ as
described in GDCR. Traditionally, dana pith area was for grains & grocery whole sale and retail
marketing; lakhaji raj road, kapad market and dharmendra road for clothing sale; soni bazaar for jewellry
market; sadar for retail provisions stores etc., are established since long. These commercial activities
demand substantial space in prime areas. The percentage of commercial area to total area is found about
1.89%, while same is to develop area seems to about 2.11%.
Industrial Use: Two Industrial estates were developed by Gujarat Industrial Development
Corporation. They are Bhaktinagar Industrial Estate and Aji Industrial Estate. Above which ,sorathiawadi
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
14
plot area had been developed by private developers as another industrial area. Besides, National Textile
mill, which is closed, occupies very prime land and is spread in huge area. Rajkot city is developed as an
industrial city hence, growth of industries and residences of industrial employees developed
simultaneously which resulted in mixed land use pattern. The percentage of Industrial area to that of total
area and developed area are found 20 % & 22.28% respectively.
Public Purposed Use:Main components of Pubic purpose use can be described as open space,
parks & play ground, recreational space, hospital space, schools, govt. office buildings etc., The major
contribution to the component is by race course complex, which has facility of international cricket
stadium, indoor stadium, hockey ground, foot ball ground etc.; garden and fun world & open ground.
Other such space is Shastri Maidan. The total public purposed space to total area is 9% while it is 10%
against developed area.
3.9 Housing
Housing reflects the economy & quality of life of any urban area. Poor planning mechanism
leads to slum & illegal growth. Though, there exists an elaborate Regulatory Mechanism to promote,
guide & control the building activities, it is often claimed that its procedure are very restrictive and
difficult to comply. Such rigidity in regulation mechanism has minimized its scope. Almost 25 to 28
percent addition to the housing stock are estimated to be made informally without obtaining necessary
permissions and sanctions. On one side lot of financial agencies and Govt incentives, encourages the
development of housing sector where as on other side the regulation mechanism creates complex hurdle
to the development. Therefore it is necessary to form housing strategy for better city and reducing slum
& illegal development.
As described above there are 51.34% land is reserved for Residential purpose. Out of which
80% is being developed. The average house holds size as per census 2001 is 5.64, and the total number
of residential property as per RMC tax branch report is 1,65,000 which describes about 40000 yet to be
required.
It is observed that nearly about 5000 dwelling units are added annually to the housing stock
of the city. In contrary to this, the number of applications for development permission received by RMC
is as low as sixteen hundred. However, many of these applications are taken for multi-storied building
having more than one dwelling unit. On these ground, it is estimated that nearly half of the dwelling
units are constructed beyond the framework of regulation framework. The development permission in
the Rajkot city is accorded as per the provisions given in General Development Control Regulation
(GDCR)- revised May-2000.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
15
Year
constructed
for
MIG
2001/02
2002/03
2003/04
2004/05
multi-purpose
room,
kitchen
and
71.18 per cent of the hutments in the slums in Rajkot are built of semi-permanent or temporary (kutcha)
material.
38
Women councilors
23
Scheduled caste
4*
Backward classes
7*
16
** Out of 7 backward class councilors, two are included in the women's group.
The ward-wise population and break up of the elected representatives in terms of female
councilors, councilors from reserved category as well as from general category is shown in statement
kept at Annexure-A. The elected body is responsible for governing the affairs of the municipal
corporation. The City Corporation has a mayor whose term is for a period of two and half years and for
the first time in the history of Gujarat State by an amendment in law, the mayor has been brought into the
main stream of municipal administration. Unlike many other states in india, the Mayor of Rajkot enjoys
certain powers to effectively carry forward the activities of city government.
The Municipal Corporation's administration is under the control of Municipal Commissioner.
His appointment is made by the State Govt. from time to time. He is assisted by Deputy Municipal
Commissioners and a large work force of Municipal officers and servants to discharge the functions of
the Corporation. The main functions of the corporation are as under:
Water supply
Sanitation
City cleaning and waste disposal
Health
Roads
Streetlights
Fire brigades
Parks and gardens
Library, etc.
Separate department of Drainage is under the administrative control of the City Engineer.
17
Besides there are number of laws, like Food Adulteration Act, Animal cruelty law, the different
legislation enacted in India exclusively for environmental protection and conservation are:
a. The Air (Prevention and Control of Pollution) Act 1987
b. The Water (Prevention and Control of Pollution) Act 1974
c. The Environment Protection Act 1980
d. The Forest Conservation Act 1980
e. The Wildlife Protection Act 1972 and
f.
It may be interesting to note that there are about two hundred laws dealing with environmental protection
both before and after Independence India. The 42nd amendment to the constitution enacted in 1974 has
two Articles (Art 48-A) and (Art 5-IA (g) - throwing the responsibility on the State government and on
every citizen to protect and improve the environment. A study of these laws reveals that a number of
provisions are suggestive and advisory. The Indian Penel Code (IPC Section 270) provides a fine of
Rupees 200/- for creating public nuisance and health hazard and Rupees 500/- for making atmosphere
noxious. Thus adequate Legislations are there but they require proper review for making it more
effective.
74th Constitutional Amendment Act
74th Amendment Bill was passed in December 1992. The Bill was ratified by almost all the
states with few exceptions. It received the assent of the President in April 1993, and came into force on
June 1,1993. However, the Constitution 74th Amendment Act 1992, provides for a period of one year
by way of transition during which time amendments to the existing State Acts have to be carried out so
as to bring provisions of the said Amendments Act.
Salient Features of 74th Constitution Amendment Act 1992
a. The provisions of the 74th Constitution Amendment Act 1992, being pad of the constitution are
applicable to all the States. They are applicable to the union territories also (243-ZB).
b. This Act has conferred powers on the President of India to direct, by a public notification, the
application of this Act to a part of a union territory also with such exceptions and modifications
as he may specify in such notification (243.78 Proviso). The provisions of this 74th Constitution
Amendment Act are not applicable to the scheduled areas specified in Art. 244(1) and the tribal
areas specified in Art. 244(7)
c. Definition of urban areas (243-q (1))
d. Division of municipal area (urban local body) into wards (243-r (1))
e. Composition of each municipal body (243.r (2)
f.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
18
a. The State Legislature is competent to authorize a Municipal Council to levy, collect and
appropriate such taxes, duties, tolls and fees in accordance with such procedure and subject to
such limits, (243-X (a))
b. The State Legislature is also empowered to assign to Municipal Council such purposes and
subject to such conditions and limits. (243X(b))
c. The State Legislature is competent to make provisions to allotment of such grants-in-aid to the
Municipality as it may consider necessary, from the Consolidated Fund of the State (243 X(c)).
d. Constitution of funds in the municipal financial administration (243-x(d))
e. Functions & Responsibilities of ULB_ Extract of Twelfth Schedule (Article 243 W) of
Constitution of India
Schedule XII gives the list of functions & responsibilities to Urban Local Bodies as describe below:
1. Urban Planning including town planning
2. Regulation of land-use and construction of buildings
3. Planning for economic and social development
4. Roads and bridges
5. Water Supply for domestic, industrial and commercial purposes
6. Public Health, Sanitation conservancy and solid waste management
7. Fire services
8. Urban forestry, protection of the environment and promotion of ecological aspects.
9. Safeguarding the interests of weaker sections of society, including the handicapped and mentally
retarded
10. Slum improvement and upgradation
11. Urban poverty alleviation
12. Provision of urban amenities and facilities such as forests, gardens, playgrounds
13. Promotion of cultural educational and aesthetic aspects.
14. Burials and burial grounds; cremations, cremation grounds and electric crematoriums.
15. Cattle ponds: prevention of cruelty to animals.
16. Vital statistics including registration of births and deaths,
17. Public amenities including street lighting, parking lots, bus stops and public conveniences
Bombay Provincial Municipal Corporation Act, 1949
In Gujarat, Bombay Provincial Municipal Corporation Act, 1949 was enacted for Municipal
Corporation of Gujarat. The act was amended as Gujarat Act No.21 of 1989 on 05.09.1989, thereafter,
for Municipal Corporations in Gujarat have to function as per the Bombay Provincial Municipal
Corporation Act (Gujarat Amendment) Act, 1989. However, till to day the amendment act is popularly
described as BPMC Act.The Act contents 33 main Chapters, Four Appendixes, and Four schedules.
Chapter IV about administrative set-up while Chapter-V to VIII, largely describes the powers &
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
19
functions including obligatory & discretionary duties of the Corporation as well powers and mode of
contractor and Acquisition of property & disposal of properties.
Relevant sections of BPMC:
Important section of BPMC Act, 1949 in respect to urban infrastructures facilities, taxes etc., are as given
below:
Sr.
No.
1
Relevant Sec.
BPMC Act
Sewerage
Sec.63 (3)
Chapter-VI
Sec.153-155
& Sect.161
Chapter-XII
Sect.161-XII
Sect.157-XII
Sec.176-177
Chapter-XII
Sec.157(2)
Chapter-XII
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
20
3. Constitution of the Board of Appeal to hear and decide appeals (Section 55/1)
4. Board of Appeal's decision communicated to TPO (Section 62/2).
5. Sanction of the Final Scheme with or without the modifications (Section 65/lb)
6. Final scheme comes into force (Section 65/2)
Relevant Section of GTP & UD Act-1976 for Infrastructure Development
Table: GTP & UD Act, 1976 relevancy for MC Infrastructure Development
Sr.
No
1
Relevant Sec.
GTP&UD Act,1976 Main contents of the section
Sewerage & Storm Water
12(2)(e)
Proposals for water supply, drainage, sewage disposal, other public
utility amenities and services including supply of electricity and gas
12(2)(n)
23(1)(vi)
40(3)(f)
40(3)(jj)(a)
2.
Finance
23(1)(vi-a)
23(1)(viii)
24(1)
77(1)(b)
77(1)(g)
92
********
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
21
Existing Situation
E
Syysstteem
mO
Ovveerrvviieew
Exxiissttiinngg S
w
4
4.1 General
Prior to implementation of underground sewerage project, the city waste was being collected
through surface drainage and was being disposed off in the river Aji which ultimately was meeting at
Aji-II reservoir constructed in down stream of Rajkot city on river Aji . However, as per the guidelines
of Water Pollution Control Board, it is not permissible to dispose off the untreated sewage in natural
courses. Under the circumstances, Rajkot Municipal Corporation started under ground drainage work
phase wise programmes is as under_
Sr
Phase
No
1
Phase-I
Phase-II
(Part-1)
Phase-II
(Part-2)
Phase-III
(Part-1)
Phase-III
(Part-2)
Status of work
Old city area which is admeasuring 69 sq.kms. out of Works are already
completed
between
which 40 sq.kms. had been covered in this phase
1981 to 1994
Old city area which is admeasuring 69 sq.kms. out of Works are proposed to
which 20 sq.kms., which is planned
carry out during 2006
to 2008 period
Old city area which is admeasuring 69 sq.kms. out of Works will be carried
which remaining 9 sq.kms., which is yet to be planned
out during 2008 to
2010 period
Newly merged which is admeasuring 35.86 sq.kms., out Works are proposed to
of which 15 sq.kms., which is planned
be carried out during
2006 to 2008 period
Newly merged which is admeasuring 35.86 sq.kms., out Works will be planned
of which 20.86 sq.kms., which is yet to be planned
and carried out during
2008 to 2010 period
Detail Project Report for Drainage Phase-II & III ( Part-I ) for Rajkot city
22
Existing Situation
In 1980-81, the project was conceived for whole city approximately 60 Sq. Kms. area.
However, at that time the development of the city was only in 35 to 40 Sq. kms. & remaining 20 sq.
kms. was Greenfield under the circumstances the project was specified in two parts as under :
Table : 4.2 Phase-I & Phase-II
Zone under Phase-I
( 40 sq. kms. area )
350 kms
450 kms
7 nos.
22 Sets
44.5 mld capacity
2.
3.
4.
5.
The project was conceived with base year 1980-81 with covering area of old city 69
sq.km. but at that time the city was not fully developed and as such in stage-I the only
developed area covering 40 sq.km was considered splitting the work of pumping machinery,
sewage treatment plant and collective system. The project was prepared by Consultant
M/s.Paramount Pollution Control Pvt.Ltd., Baroda.
Phase-I & II drainage network is divided into 12 nos. of drainage zones and spread over to 20
wards out of 23 wards. However, in certain wards some pockets will yet remain vacant which will be
connected later on.
Sr.No.
1
450 km
58 km
Main manholes
10,000 Nos
2,500 Nos
1,10,000 Nos
9,518 Nos
Drainage connections
1,60,000 Nos
Pumping stations
Detail Project Report for Drainage Phase-II & III ( Part-I ) for Rajkot city
15,000
23
Existing Situation
Rajkot Municipal Corporation drainage collective system consisting of 1800 mm dia RCC NP4
Class to as small as 150 mm diameter stoneware. The pipe materials are RCC / prestressed. For house
connections, normally stoneware pipes are used with 100 mm diameter chambers. Some parts of house
connections are given by using PVC pipes. However, PVC pipes are largely discouraged. House
connections are laid about 45 cms to 90 cm below ground level while collective system are laid up to as
much as 2 to 6 mt below ground level.
Pumping Stations: There are seven pumping station which pumps sewage water of city area to
Madhapur Sewage Treatment Plant. The details of pumping stations are as under_
Table:4.4 Details of Pumping Station
Name of pumping station
Pedak road
Capacity in
cum/h
Nos. Of
motor
Stand
by
Power requirement in
HP.
35
30
Bedipara
315
120
Bedinaka
950
200
100
40
215
60
Popatpara small
20
15
Popatpara main
1200
600
Total
22
1065
1
2
3
4
5
Detail Project Report for Drainage Phase-II & III ( Part-I ) for Rajkot city
24
Existing Situation
The Phase-I scheme was conceived with base year population 80-81 and was implemented
during 1984 to 1994. Because of severe water crisis during 1985 to 1988 and excavation in hard rock
the progress was slow.
Subsequently, the city is developed fast and as on 1999-2000 all most all left out area were
developed fully and RMC started the work of Phase-II (Part-I) for approximate in area of 20 sq.km. At
first instant, work of collective system and house connection are taken up on hand in 2000-01 and since
then most of the city area has been covered under underground sewage system. The total quantity of
sewage being generated daily is around 57 to 58 MLD. Under the circumstances, at present, the existing
plant is being over loaded and because of which during the current year Rajkot Municipal Corporation
has decided to augment the capacity of existing plant by 44.5 mld and capacity of pumping machinery
and additional rising main i.e to take up works under Phase-II(Part-I).
25
Existing Situation
is for 4.5 mgd i.e. 20.43 MLD. Similarly, Rajkot Municipal Corporation is getting about 1.5 mgd i.e.
6.81 MLD from twin lakes of Lalpari and Randarda. Thus, total quantity available at Aji-I head work in
normal year 20.43 + 6.81 = 27.24 MLD.
Nyari-I Water supply Scheme: Due to strategy and geographic location, Rajkot has attracted
so many people from outside, which resulted in higher demand for water supply. Same demand cannot
be
Sr.
No
1
2
5 kms.
8 kms.
1007
Mcft.
21 Mcft
1028
945
Mcft.
20 Mcft.
965
NyariII
22 Km
Bhadar
65 kms.
fulfilled
by
reservoir.
Aji
Hence
In
450
45
500
7030
Mcft.
45 Mcft.
7075
Rajkot
city
for
water
demand
of
dam owned by Rajkot Municipal Corporation. This scheme commenced in 1975 and the population of
the western part of the city is being served through the said scheme. The present availability of water
from the reservoir is 4.7 mgd, about 1.0 mgd from seepage. Total 5.7 mgd i.e. 25.90 MLD,
Bhadar Water supply Scheme : To provide better sanitary facilities to the public of Rajkot by
means of underground drainage Rajkot Municipal Corporation has implemented water supply scheme
based on Bhadar reservoir located at 60 kms. away from Rajkot.. This scheme is major scheme for the
supply of water to Rajkot city. The scheme was completed within 135 days during the year 1988. The
Bhadar reservoir is for irrigation purpose, however, Government of Gujarat has reserved 10 mgd of
supply in reservoir for drinking purpose to Rajkot and accordingly every year water is being made
available from the said reservoir depending upon the storage available in the reservoir. After
implementation of the said scheme the existing Aji and Nyari system was interconnected with Bhadar so
that water from one zone to another zone could be transferred. At present, the total availability is 45
MLD.
Nyari-II Water Supply Scheme: In 1998 the city limit was extended by the government and
because of which water supply demand of newly merged area had increased by 2.5 mgd. And
accordingly, the State Government had given the reservation of 1.5 mgd in Nyari-2 reservoir and 1.0
mgd from seepage of Nyari-2 and accordingly to cater the demand of newly merged area namely; Nana
Mava, Raiya, and Mavdi, a water supply scheme costing Rs.15 crores was implemented by Rajkot
Municipal Corporation based on Nyari-II reservoir.
Drinking Water from the Narmada Canal : The Government of Gujarat has planned to
implement a water supply scheme based on Narmada reservoir wherein 0.86 MAF quantity has been
reserved for drinking purpose for 12 Districts of State Government. The water supply project based on
Narmada costing Rs.7000 Crore is under implementation with the State Government. In the above water
Detail Project Report for Drainage Phase-II & III ( Part-I ) for Rajkot city
26
Existing Situation
supply project, the allocation of water for Rajkot city is 160 MLD which is to be obtained from the
Table : 4.7 Zones & Storage Capacity & supply
Zone
ESR/ GSR Capacity Total water Supply
(MLD)
from each headwork
( MLD)
Aji
38
37
Nyari
30
30
Gurukul
20
21
Jubillee
20
19
150 ring road
35
33
TOTAL
143
140
section-A
i.e.
Dhodhidhaja
Dwarka
pipeline
project.
of quantity to Rajkot from the section- Maliya Jamnagar. Water from Bhadar , after treating water at
Ribda is transmitted to the underground sumps at Gurukul and Jubillee water distribution Stations.
At Aji head works, water from available Aji dam, Lalpari & Randarda lake and Narmada pipe
line is being filtered at Aji and same is being stored and transmitted to Dudhsagar sub head works,
150ring road., Mavdi headworks and Jubillee water distribution stations .
Water from Nyari-1 dam is being supplied, after treatment at Nyari filter plant to Nyari zone
which includes sub zones like sojitranagar ESR etc.,
Water collected from Nyari-2 dam is treated at Ghanteshwar filter plant and supplied through
sub-zones Bajrangwadi. Water. Main pipe lines are of Mild Steel, PS , and AC Pressure line ranges
from 900 mm to 450 mm as main. Distribution networks is of AC pressure pipe line with diameter 450
mm to 80 mm. Total length of Transmission line is about 250 kms. The total distribution network length
excluding the transmission lines is 1375 kms.
Table : 4.8 Water supply Distribution Net works
Details
Unit
Number of Zones
5
Number of Sub zones
11
Mains line length
105 kms.
Distribution line length
1350 kms.
202
adequacy of all the water distribution stations to the total water supply is 144 percent.
Detail Project Report for Drainage Phase-II & III ( Part-I ) for Rajkot city
27
Extent of Privatization
E
Exxtteenntt ooff P
Prriivvaattiissaattiioonn
The tax structure in Rajkot Municipal Corporation has also remained static over the
years coupled with the political problems attached with raising the taxes.
This
Detail Project Report for Drainage Phase- II & III (Part-I) for Rajkot city
28
Extent of Privatization
Total cost incurred in operating and maintaining the six pumping station is fixed on shift
basis. It is estimated that Rs 17.75 lacs per year for the running maintenance and operation cost of 7
pumping station, which means per pumping station per year the average cost comes to 2.54 lacs. We
assume that pumping station is operated on an average for two shifts per day. So total average cost per
shift per pumping station is comes to Rs. 350 only.
29
Extent of Privatization
It is observed that total no. of complaint received in ward no. two to eight was 58441 for eight
months.
Sr.
No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11.
12.
13
Table:5.1 No of Complaints
Month
No. of Complaints
April 05
5320
May 05
4030
June 05
6549
July 05
5141
August 05
4243
September 05
4746
October 05
4268
November 05
4190
December 05
4871
January 06
5038
February 06
4769
March 06
5276
Total
58441
Note:
10% of complaint is of Main line
90% of complaint is of House connection chamber.
The cost for Main line complaint is Rs 250 per complain,
while for house connection is Rs 25 per complain.
Total expenditure incurred to redressal of the complains was Rs 27.76 lacs for financial year
2005-06. The contractors works remain satisfactory. Previously, response and redressing of complain
was took four to five days and some time complain never attended. But after the task is assigned to
the private contractor, the response and redressing of complain becomes fast. So by privatizing, RMC
achieves efficiency in managing complains as well as cost savings.
Detail Project Report for Drainage Phase- II & III (Part-I) for Rajkot city
30
Extent of Privatization
The contractor has to develop billing and collection system which includes issuing of bills,
collection of payments, necessary supervision and development and updating of database.
The minimum collection target must be designed based on the past experience.
The contractor has to deposit the all collected amount whether cash, cheques or in other form
on the same day of receipt.
Incentive fee should be given to the contractor for the over and above minimum collection
target.
Penalty clause also designed for the not achieving the minimum target.
To evaluate the performance of the contractor, contractor has to submit performance report
every month.
At the end of contract duration all the updated database must be submitted to RMC.
Contract can be terminated at any time if RMC fills that the performance of contractor is not
up to the mark.
As the operation and maintenance of sanitation service requires skill personnel as well as
special equipment, the contractor has to employ qualified personnel and must have required
equipment.
The contractor shall not make any capital expenditure on the sanitation service.
The contractor must pay in timely manner to his employees as per minimum labour wages.
The contractor has to carry out the necessary repairs within the predefined time as soon as he
receives complaints.
Detail Project Report for Drainage Phase- II & III (Part-I) for Rajkot city
31
Extent of Privatization
In case of emergency, the contractor has to carry out the necessary repairing work as directed
by the RMC.
If RMC fills the working of contractor is unsatisfactory, the contract can be terminated.
C) Construction of collection network and treatment plant for newly merged area:
The construction of collection network and waste water treatment plant for newly merged
area should be given to the private sector either on concession basis or forming joint venture
Company with private sector. If the contract is given on concessionary base, then the total capital
investment as well as expenditure for operation and maintenance for the service will be born by the
private sector. At the end of contractual period (usually 25 to 30 years) the whole system should be
handed over to the RMC. During the contract period all necessary charges should be levied by the
contractor.
********
Detail Project Report for Drainage Phase- II & III (Part-I) for Rajkot city
32
Civil Designs
D
Deettaaiilleedd E
Ennggiinneeeerriinngg D
Deessiiggnn-- C
Ciivviill
providing and erecting pumping machinery suitable for stage-I requirement Total 22 sets
900 mm dia PSC rising main from main pumping station to STP through field.
44.5 MLD capacity sewerage treatment plant with disposal arrangement with 50% capacity
As on date, the said scheme is in working condition and same is under maintenance with
Rajkot Municipal Corporation. So far, Rajkot Municipal Corporation has given about 1,60,000 house
connections sewage is being treated in the existing plant at Madhapar. The part of the work of zone-311 was carried out by Rajkot Municipal Corporation from its own fund with the cost of rs.4 crores.
Thus, the total expenditure incurred on Phase-I work is around Rs.40 crores and Rajkot Municipal
Corporation is making repayment of the loan regularly.
As stated above, the original project was framed with the development of the city up to 1980
but subsequent to 1980, all the peripheral areas have been developed fully and are now required to be
connected with the existing drainage system, as the system has been designed to cater the whole area
of the city. And accordingly, Rajkot Municipal Corporation has taken up the Phase-II (Part-I) work in
a phase manner onward 2000 from support of the budget allocation. So far, approximately, works to
the tune of Rs.400 lacs has been completed and commissioned. In Phase-II (Phase-I), the following
works are yet to be carried out:
1. The work of collective system with house connection in approximately 20 sq.km area
2. Installation of pumping machinery for additional load 11 sets
3. Extension of existing sewerage treatment plant by 44.5 mld
4. Power connection
5. Compound wall and area development
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
33
Civil Designs
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
34
Civil Designs
pH value
Unit
6.8-9.1
SS
525 mg/l
COD
630 mg/l
BOD
200 mg/l
Alkalinity
185 mg/l
Sulphates
110 mg/l
Phosphates
10 mg/l
16.8 mg/l
Ammonical Nitrogen
15 mg/l
4 mg/l
O&G
15 mg/l
Parameter
Unit
pH value
6-9
SS
< 100
mg/l
COD
< 100
mg/l
BOD
< 30
mg/l
O&G
< 10
mg/l
* Pre-1995 discharge norms prescribed 30 mg/l SS and 20 mg/l BOD value, which was duly
revised as above.
35
Civil Designs
From the analysis, it is observed that the concentration of Suspended Solids (SS) is very high
during morning hours. Data recorded for morning session 0830 to 0930 indicates SS concentration as
high as 2000 mg/l. This is peculiar situation in semi-urban area experiencing scarcity of water,
wherein major water intensive activities are at halt during evening and late night hours leading to
deposition of solids in to sewers. These get re-suspended during peak flow, which takes place in
morning session. Volume of solids to be handled would be enormously high and special attention
must be given to this aspect, particularly sludge storage/sump and handling equipment like pump sets
and/or classifier mechanism. However, this is not accompanied by steep rise in BOD values. Hence,
shock load will not have significant effect on aerator (oxygenation equipment). But sludge production
would vary on hourly basis and hence retention time of the sludge sump would be decided
accordingly.
Analysis of various treatment processes
Numbers of processes are in vogue for treatment of domestic sewage (municipal wastewater).
This ranges from physico-chemical process to direct oxidation process (zimpro process) for treatment
of wastewater. However, physico-chemical processes are generally used for small capacity plants, in
particular, industrial plants. Physical process followed by biological process and purely biological
processes are more popularly used world over. Each system has its own cutting edge features for
selection of particular process for some region and respective time context. Physical process followed
by biological process and purely biological process are predominantly used in India and Gujarat
region.
Best examples for STPs based on physical process followed by biological process are
conventional activated sludge process (suspended growth), trickling filter (attached growth), and
anaerobic lagoons followed by facultative lagoons etc.. Best examples for biological processes are
facultative lagoons followed by extended aeration lagoons, Upflow Anaerobic Sludge Blanket
(UASB) followed by polishing lagoons etc.
Selection of best process suitable for sewage generated in Rajkot would be governed by
number of factors. However, attributes for selecting suitable treatment process will decide the
treatment steps. Major attributes are enlisted hereunder.
1.
Ease of construction
2.
3.
4.
5.
Reliability of process:
i.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
36
Civil Designs
7.
8.
9.
Apart from above factors, raw sewage characteristics also play an important role. Availability
of skilled personnel and spare parts will play major role while selecting the process. Amongst selected
processes, its Capex and Opex, capitalized cost and financial sensitivity will govern the finally
selected process.
2)
Facultative Lagoons followed by Extended Aeration (with & without power generation)
3)
4)
Each alternative is analysed with its capital cost (Capex), operation & maintenance cost (Opex),
energy charges, resource recovery (power generation), financial sensitivity (capitalized cost with
different IRR). Subsequent chapters address the design of each unit of the STP and above factors.
Operation of STP depends upon so many factors. But introduction of advanced tools like PLC/ microcontroller/ micro-processor based process control systems would enhance control over process and
also achieve the energy saving. Developed countries have fully automated plants and unit operations,
which has got very high O & M cost. Hence, emphasis has been made to introduce modern tools
suitable for Indian condition. Few of the areas of automation suggested are:
Aerator operation: DO levels in the tank shall be maintained at 2 mg/l. during lean flow
period, if it exceeds, number of aerators to be stopped on rotation basis could be introduced. Also
diminished level of DO would give alarm for attention of the aeration unit.
Pumping operation: Level based sensor to start/off the pumps on rotation basis.
Flow measurement: Flow entering into each battery depends upon the sizing of the gates, as
built levels etc. Even though, the gate opening is proper, flow distribution is likely to vary. Hence, to
measure the flow entering to each unit is crucial information to decide the performance of the same
and rectification thereof for process control.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
37
Civil Designs
1)
Inlet Chamber
2)
Screen Chamber
3)
Detritor
4)
Parshall Flume
5)
6)
Aeration Tank
7)
8)
9)
10)
11)
Sludge digester
12)
Gas holder
13)
14)
First three units are considered to be Preliminary Treatment Units. 4th, 5th and 6th are
secondary treatment units and remaining are supporting units for MWwTPs. Though all the units are
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
38
Civil Designs
designed to handle peak flows and other loadings, sludge digesters need to be designed for sufficient
solids loading for effective functioning in the view of the high concentration of SS.
1.
INLET CHAMBER : An Inlet Chamber is provided as receiving unit to STP with special
arrangements. In case of normal operations, the sewage will be diverted to STP and in case of
eventuality/ repair/ maintenance, a bypass arrangement is provided for discharge of sewage into
receiving body.
2.
removal of large size floating materials like rags, plastics, tobacco pouches, wooden pieces etc. which
otherwise would damage pumps and interfere with the performance of the subsequent units. This
consists of bars placed parallel in vertical or inclined system across the flow to trap the floating
material. Generally 20 mm spacing is considered to be adequate for STPs. However, considering the
problem of pouches of tobacco passing thru it parallel to flow, finere screens with spacing of 12 mm
followed in mesh pattern are in vogue. 50 mm x 10 mm thick flats are considered to be standard
practice in India. Timer based racking mechanism cleans the screen periodically and put the
screenings to belt conveyor system. Material is conveyed to collection van provided beneath the end
of the belt conveyor for final disposal. CI Gates upstream and downstream to the screen are provided
to control flow.
3.
DETRITOR :Detritus Tank popularly known as detritor is provided after screen to remove
heavy inorganic fraction of the sewage prior to physical and biological process. Difference in settling
velocities between organic and organic content due to specific gravity is the basic principle followed
to design the unit. Grit consists coarse sand particles, ash, clinker, egg shells and silt coated by
organic matter (generally marginalized group use silt/ash for washing of utensils) etc. Grit is
considered to be non-putrescible possessing higher hydraulic subsidence value than organic matter.
Grit removal, if not done, causes abnormal wear and tear to mechanical parts, scrappers/ pumps/
aerators etc. With proper hydraulic design, grit can be effectively removed from the sewage. To
prevent loss of useful organic content and to prevent emanation of highly malodorous emissions from
the removed grit, grit classifier based on reciprocating mechanism is provided.
4.
matter (SS), scum and reduce BOD in quiescent condition. Brownian motion and settling
characteristics of solids supported by proper overflow rate and weir loading rate enhances
settlement of solids. It also settles BOD (integral part of SS) and hence reduces BOD load on
subsequent units. Reduction in BOD load will have great effect on power consumption.
Plastics escaped from the screen and grit chamber would float on surface and can be removed
by scum arm provided at top. Various functional parts like inlet, baffle, scrapper, outlet weir,
sludge removal, telescopic valve, scum box are major components of the PST.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
39
5.
Civil Designs
organic matter) if favorable pH value and oxygen is available for faster consumption of organic
matter. This unit is heart of the process. Various parameters are controlled to maximize efficiency.
Food to microbe ratio, power level, MLSS, means cell residence time, decay rate, volumetric loading,
organic loading etc. Washout of microbes must be avoided. It is desirable to maintain DO level at 2
mg/l, which may diminish to 0.5 mg/l as an alarming level. Growth of filamentous bacteria and
Nocardia must be avoided and controlled. Sufficient HRT shall be maintained to prevent washout.
Entire biomass gets activated in this system by means of suspended growth. Microbes can move to
any place within reactor to get food and balance struck between microbes and substrate facilitates
conversion of organic matter into active biomass.
6.
biomass to settle in form of sludge and sludge settled is pumped back to aeration tank to maintain
MLSS. Due to highly active biomass, lumps of biomass are formed and higher ratio of volume to
surface area enhances the settlement. Now, major portion of organic content is converted into
biomass, which is settled as sludge. Supernatant comprise very low BOD and SS and other
parameters. In case the treated sewage is to be discharged into natural water body, the parameters
comply with the norms prescribed by pollution control board.
However, in case treated sewage is to be reused for some purpose like gardening, recreational
activities, tertiary treatment shall be given.
7.
RAW SLUDGE PUMP HOUSE :Raw sludge accumulated in PST is generally put to SDB or
sludge digester. Considering low volumes, this is very small units and used as control room for PTU.
8.
RETURN SLUDGE PUMP HOUSE :Performance of aeration tank depends upon effective
function of this pump house. Generally return flow varies from 25 % to 50 % depending upon
concentration of sludge. Considering its functional importance, 100% standby pump sets are
provided in this unit.
9.
FILTRATE PUMP HOUSE : Filtrate from sludge drying bed/filter press/centrifuge contains
high BOD and SS and hence prior to disposal into natural water body, it shall be treated. Filtrate
pump house pumps back filtrate to the inlet chamber of PST and hence only treated sewage is
discharged from the STP. Though quantity of filtrate is very low in terms of percentage, overall
quantum is in terms of few thousand liters and hence it must be treated prior to discharge.
10.
SLUDGE DRYING BEDS/ FILTER PRESS/ CENTRIFUGE : Digested or raw sludge is dewatered
and converted to utilizable form of sludge cake for manure. Sludge drying bed is most common form
of concentrating the sludge and it is most common practice in India.
11.
SLUDGE DIGESTER : Digestion of sludge is achieved in this unit to break the long chains and
convert it to simple form ready to use as manure for improved absorbance as nutrient and reduce the
harmful effects on environment. Initially, design of digester with mechanical mixing of sludge posed
serious problems of civil structure and blasting. This has been overcome with help of gas mixing
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
40
Civil Designs
system, being used in India for more than 10 years with satisfactory performance. Sludge volume also
reduces in this system and area required for sludge reduces to a great extent.
12.
GAS HOLDER :Gas produced in digester is collected here for further utilization like power
DUAL-FUEL GAS ENGINES/ GAS FLARING SYSTEM : Gas produced in the digester is
enriched with methane and high calorific value. Dual fuel engines capable of using gas (80-90%) and
diesel (20-10%) can yield power sufficient to run more than half of the operations of the STP. Though
it is very attractive, STPs initially set up with an objective to have captive power generation either in
CASP or UASB has not been successful on large scale.
Above steps briefly describes preliminary aspects of various process units. Sufficient details
are discussed about basic principles and area of attention for successful performance of the STP based
on CASP. There are many more forms of the CASP like continuous flow (as described above), plug
flow, Sequential Batch Reactor etc., but this is most common form easy to maintain and operable and
adopted in India.
This process is having following advantages
1)
2)
Availability of spare parts is also not a problem since all the equipments like
scrapper, aerator are already installed in existing STP and RMC officials are familiar
with the equipment and are easily available
3)
4)
5)
6)
7)
Since the process is proven world wide, construction techniques are known and
hence easy to construct (the word conventional itself suggests its large scale
acceptability)
8)
9)
Area requirement is very low amongst all 4 processes under consideration. Hence,
future expansion is possible, particularly in urban area like Rajkot where land is
scarce.
Sludge digesters pose operational problems due to moving mechanical parts- some of the
municipal authorities had overcome this problem by using non-moving mechanical
mixers. E.g. Vadodara, Delhi
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
41
2)
Civil Designs
Skilled personnel (biologist) are required to maintain process parameters like MLSS, BOD,
COD, SS etc.
Unit Sizing: Conventional Activated Sludge Process
All dimensions are in m unless otherwise specified
Sr.
Power
rqnt
(W+SB) HP
1
Screen Chamber
6+6
Grit Chamber
3 Nos., 8 x 8 x 1.1
6+3
Parshall Flume
Primary Clarifier
6+0
Aeration Tank
2 Nos., 36 x 72 x 4.15
400+0
Secondary Clarifier
3+3
15+15
60+(30+30)
5+5
10
Nos.
with
digester
9
Sludge Digester
2 No., 24 dia, 11 ht
50+50
10
Gas Holder
6+0
11
Power Generator
18 x 12 x 6
-405
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
42
Civil Designs
is maintained apart from aeration. After extended aeration, biomass attains saturation level of activity
and then admitted to settling lagoon for settling of biomass and accumulation of sufficient quantity of
return sludge to help activation of biomass in extended aeration tank. Sludge produced is returned to
extended aeration tank or put through sludge digester and/or directly to sludge drying beds/filter
press/centrifuge, wherein biomass is dried and sludge concentration is increased. Filtrate from drying
beds/filter press/centrifuge would be returned to facultative lagoon for further treatment.
Description of functional requirement of each unit for FLEA is discussed in brief.
1)
Inlet Chamber
2)
Screen Chamber
3)
Detritor
4)
Parshall Flume
5)
6)
7)
8)
9)
10)
Sludge digester
11)
Gas holder
12)
13)
First three units are considered to be Preliminary Treatment Units. 4th, 5th and 6th are secondary
treatment units and remaining are supporting units for MWwTPs.
1.
INLET CHAMBER : An Inlet Chamber is provided as receiving unit to STP with special
arrangements. In case of normal operations, the sewage will be diverted to STP and in case of
eventuality/ repair/ maintenance, a bypass arrangement is provided for discharge of sewage into
receiving body.
2.
removal of large size floating materials like rags, plastics, tobacco pouches, wooden pieces etc. which
otherwise would damage pumps and interfere with the performance of the subsequent units. This
consists of bars placed parallel in vertical or inclined system across the flow to trap the floating
material. Generally 20 mm spacing is considered to be adequate for STPs. However, considering the
problem of pouches of tobacco passing thru it parallel to flow, finere screens with spacing of 12 mm
followed in mesh pattern are in vogue. 50 mm x 10 mm thick flats are considered to be standard
practice in India. Timer based racking mechanism cleans the screen periodically and put the
screenings to belt conveyor system. Material is conveyed to collection van provided beneath the end
of the belt conveyor for final disposal. CI Gates upstream and downstream to the screen are provided
to control flow.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
43
3.
Civil Designs
DETRITOR : Detritus Tank popularly known as detritor is provided after screen to remove
heavy inorganic fraction of the sewage prior to physical and biological process. Difference in settling
velocities between organic and organic content due to specific gravity is the basic principle followed
to design the unit. Grit consists coarse sand particles, ash, clinker, egg shells and silt coated by
organic matter (generally marginalized group use silt/ash for washing of utensils) etc. Grit is
considered to be non-putrescible possessing higher hydraulic subsidence value than organic matter.
Grit removal, if not done, causes abnormal wear and tear to mechanical parts, scrappers/
pumps/ aerators etc. With proper hydraulic design, grit can be effectively removed from the sewage.
To prevent loss of useful organic content and to prevent emanation of highly malodorous emissions
from the removed grit, grit classifier based on reciprocating mechanism is provided.
4.
FACULTATIVE LAGOON : Sewage traveling long distances generally turns septic while
entering into STP and presence of anaerobic and facultative bacteria dominates the system.
Conversion of this condition to aerobic condition is power intensive and hence concept of developing
facultative culture for biological process of sewage was conceived. Here low level of DO is
maintained and thus odor emanation is eliminated. Generally HRT ranges from 1 to 3 days and STPs
in Mumbai are set up on this principle. Then sewage undergoes further treatment in aerobic lagoons.
5.
AEROBIC LAGOON : After facultative process, microbes can survive aerobic condition and
are activated to consume maximum substrate. Aerobic bacteria dominate the system. Power level is
almost double as compared to facultative one. Sludge from settling tank is returned to this lagoon to
maintain MLSS. Generally mixing requirement governs the design rather than oxygen demand as in
case of CASP since HRT is comparatively very high. Here the biomass enters into phase of
endogenous respiration minimizing sludge production. Maintaining of MLSS and MLVSS is
important for better performance.
6.
SETTLING TANK/ LAGOON : SST/SL permits activated biomass to settle in form of sludge
and sludge settled is pumped back to aeration tank to maintain MLSS. Due to highly active biomass,
lumps of biomass are formed and higher ratio of volume to surface area enhances the settlement.
Now, major portion of organic content is converted into biomass, which is settled as sludge.
Supernatant comprise very low BOD and SS and other parameters. In case the treated sewage is to be
discharged into natural water body, the parameters comply with the norms prescribed by pollution
control board.
However, in case treated sewage is to be reused for some purpose like gardening, recreational
activities, tertiary treatment shall be given.
7.
RETURN SLUDGE PUMP HOUSE : Performance of aeration tank depends upon effective
function of this pump house. Generally return flow varies from 25 % to 50 % depending upon
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
44
Civil Designs
concentration of sludge. Considering its functional importance, 100% standby pump sets are
provided in this unit.
8.
SLUDGE DRYING BEDS/ FILTER PRESS/ CENTRIFUGE : Digested or raw sludge is dewatered
and converted to utilizable form of sludge cake for manure. Sludge drying bed is most common form
of concentrating the sludge and it is most common practice in India.
9.
FILTRATE PUMP HOUSE : Filtrate from sludge drying bed/filter press/centrifuge contains
high BOD and SS and hence prior to disposal into natural water body, it shall be treated. Filtrate
pump house pumps back filtrate to the inlet chamber of PST and hence only treated sewage is
discharged from the STP. Though quantity of filtrate is very low in terms of percentage, overall
quantum is in terms of few thousand liters and hence it must be treated prior to discharge.
10.
SLUDGE DIGESTER : Digestion of sludge is achieved in this unit to break the long chains and
convert it to simple form ready to use as manure for improved absorbance as nutrient and reduce the
harmful effects on environment. Initially, design of digester with mechanical mixing of sludge posed
serious problems of civil structure and blasting. This has been overcome with help of gas mixing
system, being used in India for more than 10 years with satisfactory performance. Sludge volume also
reduces in this system and area required for sludge reduces to a great extent.
11.
GAS HOLDER :Gas produced in digester is collected here for further utilization like power
DUAL-FUEL GAS ENGINES/ GAS FLARING SYSTEM :Gas produced in the digester is
enriched with methane and high calorific value. Dual fuel engines capable of using gas (80-90%) and
diesel (20-10%) can yield power sufficient to run more than half of the operations of the STP. Though
it is very attractive, STPs initially set up with an objective to have captive power generation either in
CASP or UASB has not been successful on large scale.
Above steps briefly describes preliminary aspects of various process units. Sufficient details
are discussed about basic principles and area of attention for successful performance of the STP based
on FLEA. There are many more forms of the FLEA like without return sludge, only facultative
lagoons followed by maturation pond etc., but this is most common form easy to maintain and
operable and adopted in India. STP at Madhapar, Rajkot is also based on this process.
This process is having following advantages
1)
Availability of spare parts is not a problem since all the equipments like scrapper, aerator are
already installed in existing STP and RMC officials are familiar with the equipment and are
easily available
2)
Process is having high level of reliability, well established reaction kinetics, amenability to
control, can absorb shock loads.
3)
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
45
4)
Civil Designs
Since the process is proven world wide, construction techniques are known and hence easy to
construct (STPs based on this process are established at cities like Ahmedabad, Mumbai etc.
indicating its large scale acceptability)
5)
Sludge removal pose operational problems due to lower level and large area to be covered for
de-silting. Chances to damage to membrane are more during operation of sludge removal.
2)
3)
Skilled personnel (biologist) are required to maintain process parameters like MLSS, BOD,
COD, SS etc.
4)
Less safety of operating/ maintenance personnel in case defects in aerators are to be rectified
5)
Area requirement is very large as compared to CASP and restricts future expansion
6)
Power rqnt
(W+SB) HP
Screen Chamber
6+6
Grit Chamber
3 Nos., 8 x 8 x 1.1
6+3
Parshall Flume
Facultative Lagoons
240+0,
54 x 140 at both, 6 m
Nos., 15 HP
2 Nos., 78 x 50 at top
300+0, 6 Nos.,
Aerated Lagoon
58 x 50 at bot, 5 m
4
Settling Lagoon
2 Nos., 78 x 31 at top
16
50 HP
-
52 x 18 at bot, 6.5 m
5
50+50+(50 SB)
7.5+7.5
10
Nos.
with
digester
8
Sludge Digester
2 No., 24 dia, 11 ht
50+50
Gas Holder
6+0
10
Power Generator
18 x 12 x 6
-175
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
46
Civil Designs
Inlet Chamber
2)
Screen Chamber
3)
Detritor
4)
Parshall Flume
5)
6)
7)
Settling Lagoon
First three units are considered to be Preliminary Treatment Units. 4th, 5th and 6th are secondary
treatment units and remaining are supporting units for MWwTPs.
1.
INLET CHAMBER : An Inlet Chamber is provided as receiving unit to STP with special
arrangements. In case of normal operations, the sewage will be diverted to STP and in case of
eventuality/ repair/ maintenance, a bypass arrangement is provided for discharge of sewage into
receiving body.
2.
removal of large size floating materials like rags, plastics, tobacco pouches, wooden pieces etc. which
otherwise would damage pumps and interfere with the performance of the subsequent units. This
consists of bars placed parallel in vertical or inclined system across the flow to trap the floating
material. Generally 20 mm spacing is considered to be adequate for STPs. However, considering the
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
47
Civil Designs
problem of pouches of tobacco passing thru it parallel to flow, finere screens with spacing of 12 mm
followed in mesh pattern are in vogue. 50 mm x 10 mm thick flats are considered to be standard
practice in India. Timer based racking mechanism cleans the screen periodically and put the
screenings to belt conveyor system. Material is conveyed to collection van provided beneath the end
of the belt conveyor for final disposal. CI Gates upstream and downstream to the screen are provided
to control flow.
3.
DETRITOR : Detritus Tank popularly known as detritor is provided after screen to remove
heavy inorganic fraction of the sewage prior to physical and biological process. Difference in settling
velocities between organic and organic content due to specific gravity is the basic principle followed
to design the unit. Grit consists coarse sand particles, ash, clinker, egg shells and silt coated by
organic matter (generally marginalized group use silt/ash for washing of utensils) etc. Grit is
considered to be non-putrescible possessing higher hydraulic subsidence value than organic matter.
Grit removal, if not done, causes abnormal wear and tear to mechanical parts, scrappers/ pumps/
aerators etc. With proper hydraulic design, grit can be effectively removed from the sewage. To
prevent loss of useful organic content and to prevent emanation of highly malodorous emissions from
the removed grit, grit classifier based on reciprocating mechanism is provided.
4.
ANAEROBIC LAGOON : Sewage traveling long distances generally turns septic while entering
into STP and presence of anaerobic and facultative bacteria dominates the system. Conversion of this
condition to aerobic condition is power intensive and hence concept of utilizing anaerobic culture for
biological process of sewage was conceived. Here absence of DO is maintained by deep lagoons.
Odor emanation could be eliminated since uppermost layer acts as a solvent to gases escaping from
the system. Generally HRT ranges from 1 to 1.5 days and STPs in Ahmedabad are set up on this
principle. Then sewage undergoes further treatment in aerobic lagoons.
5.
AEROBIC LAGOON : After anaerobic process, microbes can survive facultative and aerobic
condition and are activated to consume maximum substrate. Aerobic bacteria dominates the system.
Generally mixing requirement governs the design rather than oxygen demand as in case of CASP
since HRT is very high comparatively.
6.
SETTLING TANK/ LAGOON : SST/SL permits activated biomass to settle in form of sludge.
Due to highly active biomass, lumps of biomass are formed and higher ratio of volume to surface area
enhances the settlement. Now, major portion of organic content is converted into biomass, which is
settled as sludge. Here the biomass enters into phase of endogenous respiration minimizing sludge
production. Supernatant comprise very low BOD and SS and other parameters.
In case the treated sewage is to be discharged into natural water body, the parameters comply
with the norms prescribed by pollution control board. However, in case treated sewage is to be reused
for some purpose like gardening, recreational activities, tertiary treatment shall be given.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
48
Civil Designs
Above steps briefly describes preliminary aspects of various process units. Sufficient details
are discussed about basic principles and area of attention for successful performance of the STP based
on ANAL. There are many more forms of the ANAL like return sludge from settling lagoon, microaerofoil based system etc., but this is most common form easy to maintain and operable and adopted
in India.
This process is having following advantages
1)
Availability of spare parts is not a problem since all the equipments like scrapper, aerator
are already installed in existing STP and RMC officials are familiar with the equipment and
are easily available
2)
Process is having high level of reliability, well established reaction kinetics, amenability to
control, can absorb shock loads.
3)
4)
Since the process is proven world wide, construction techniques are known and hence easy
to construct (STPs based on this process are established at Ahmedabad indicating its large
scale acceptability)
5)
6)
Sludge removal pose operational problems due to lower level and large area to be covered
for de-silting. Chances to damage to membrane are more during operation of sludge
removal.
2)
3)
4)
Area requirement is very large as compared to CASP and restricts future expansion
5)
Aerated Lagoon
Settling Lagoon
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
Power rqnt
(W+SB) HP
6+6
6+3
400+0,
16
Nos., 25 HP
-
49
Civil Designs
Inlet Chamber
2)
Screen Chamber
3)
Detritor
4)
Parshall Flume
5)
6)
7)
8)
Settling Lagoon
9)
10)
11)
Gas holder
12)
13)
First three units are considered to be Preliminary Treatment Units. 4th, 5th and 6th are secondary
treatment units and remaining are supporting units for MWwTPs.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
50
1.
Civil Designs
INLET CHAMBER : An Inlet Chamber is provided as receiving unit to STP with special
arrangements. In case of normal operations, the sewage will be diverted to STP and in case of
eventuality/ repair/ maintenance, a bypass arrangement is provided for discharge of sewage into
receiving body.
2.
removal of large size floating materials like rags, plastics, tobacco pouches, wooden pieces etc. which
otherwise would damage pumps and interfere with the performance of the subsequent units. This
consists of bars placed parallel in vertical or inclined system across the flow to trap the floating
material. Generally 20 mm spacing is considered to be adequate for STPs. However, considering the
problem of pouches of tobacco passing thru it parallel to flow, finere screens with spacing of 12 mm
followed in mesh pattern are in vogue. 50 mm x 10 mm thick flats are considered to be standard
practice in India. Timer based racking mechanism cleans the screen periodically and put the
screenings to belt conveyor system. Material is conveyed to collection van provided beneath the end
of the belt conveyor for final disposal. CI Gates upstream and downstream to the screen are provided
to control flow.
3.
DETRITOR : Detritus Tank popularly known as detritor is provided after screen to remove
heavy inorganic fraction of the sewage prior to physical and biological process. Difference in settling
velocities between organic and organic content due to specific gravity is the basic principle followed
to design the unit. Grit consists coarse sand particles, ash, clinker, egg shells and silt coated by
organic matter (generally marginalized group use silt/ash for washing of utensils) etc. Grit is
considered to be non-putrescible possessing higher hydraulic subsidence value than organic matter.
Grit removal, if not done, causes abnormal wear and tear to mechanical parts, scrappers/ pumps/
aerators etc. With proper hydraulic design, grit can be effectively removed from the sewage. To
prevent loss of useful organic content and to prevent emanation of highly malodorous emissions from
the removed grit, grit classifier based on reciprocating mechanism is provided.
4.
Blanket (UASB), was developed to treat industrial waste possessing high COD and BOD, posing
power intensive treatment-if one opts for aerobic treatment. Hence anaerobic treatment was found to
be techno-economical. Deficiencies of Septic Tank/s Imhoff Tanks/ Upflow Anaerobic Filters were
attended and researchers have tried to ensure uniform distribution of flow, restricted upward velocities
etc. To maintain sludge blanket at mid-level, upward velocity shall be applied to flow at moderate
range. Wastewater enters the reactor from bottom at uniform flow rate and travels upward direction.
This eliminated necessity of separate sedimentation tank. Anaerobic bacteria are developed in the
reactor for sufficient time. In order to ensure sufficient contact between the incoming sewage and the
sludge blanket (mass of anaerobic bacteria), the velocity of upward flow is restricted and uniform
feeding rate of wastewater is ensured all over the bottom of the reactor. Organic compound present in
the sewage are absorbed/ adsorbed on the sludge particles in the reaction zone. Further mixing is
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
51
Civil Designs
achieved by movement of biogas in upward direction, the density currents and settling of solids in
downward direction. Organic compound are converted to biogas consisting of methane-enriched gas
and new bacterial biomass. The gas is collected in the gas collector and used as energy source. A gas,
liquid and solid separator (GLSS) is provided below the gas collector in order to maximize collection
of gas (gas bubbles attached to sludge particles could lose contact and can be trapped into gas
collector).
5.
PRE AERATION TANK : After UASBR, anaerobic microbes dominates the system since
sewage has undergone anaerobic treatment. Gases like methane and hydrogen sulfide are at saturation
level and nature of the bio-culture is anaerobic. To change the anaerobic nature of the sewage and to
make it amenable for aerobic treatment, pre-aeration shall be provided. Basic objective of this unit is
to remove dissolved gases of anaerobic process and prepare culture suitable for aerobic treatment.
6.
AEROBIC LAGOON : After pre-aeration, sewage would undergo aerobic treatment in lagoons
SETTLING TANK/ LAGOON : SST/SL permits activated biomass to settle in form of sludge.
Due to highly active biomass, lumps of biomass are formed and higher ratio of volume to surface area
enhances the settlement. Now, major portion of organic content is converted into biomass, which is
settled as sludge. Supernatant comprise very low BOD and SS and other parameters. In case the
treated sewage is to be discharged into natural water body, the parameters comply with the norms
prescribed by pollution control board.
8.
SLUDGE PUMP HOUSE : Sludge produced in the UASB is collected in the sump and pumped
to the sludge drying beds/ centrifuge/ filter press to reduce water content and amenable to use as
manure. Concentration of sludge varies from 2% to 6% depending upon the status of biological
process within reactor. Generally higher concentration prevails in the reactor, if performance is good.
Considering its functional importance, 100% standby pumpsets are provided in this unit.
9.
SLUDGE DRYING BEDS/ FILTER PRESS/ CENTRIFUGE : Digested or raw sludge is dewatered
and converted to utilizable form of sludge cake for manure. Sludge drying bed is most common form
of concentrating the sludge and it is most common practice in India.
10.
FILTRATE PUMP HOUSE : Filtrate from sludge drying bed/filter press/centrifuge contains
high BOD and SS and hence prior to disposal into natural water body, it shall be treated. Filtrate
pump house pumps back filtrate to the inlet chamber of PST and hence only treated sewage is
discharged from the STP. Though quantity of filtrate is very low in terms of percentage, overall
quantum is in terms of few thousand litres and hence it must be treated prior to discharge.
11.
GAS HOLDER : Gas produced in digester is collected here for further utilization like power
DUAL-FUEL GAS ENGINES/ GAS FLARING SYSTEM : Gas produced in the digester is
enriched with methane and high calorific value. Dual fuel engines capable of using gas (up to 8090%, generally 60%) and diesel (20-10%, generally 40%) can yield power sufficient to run more than
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
52
Civil Designs
half of the operations of the STP. Though it is very attractive, STPs initially set up with an objective
to have captive power generation either in CASP or UASB has not been successful on large scale.
This process is having following advantages
1)
2)
Power generation is considered to be only attractive aspect and advantage due to emerging
power scenario world wide.
Process is having very low level of reliability, reaction kinetics are yet to well-established,
not easy amenability to control and absorb shock loads.
2)
Sludge removal pose operational problems due to higher depth and accessibility.
3)
4)
5)
Less safety of operating/ maintenance personnel in case defects in hood/ baffle, gutter,
GLSS are to be rectified
6)
Area requirement is very large as compared to CASP and restricts future expansion
7)
Power generation is main slogan to promote the process. However, operationalisation of dual
fuel engines for purely domestic waste has not become successful.
8)
Process is not proven world-wide, construction techniques are known to limited agencies
restricting competition and rectangular reactors with higher depths becomes more costly.
9)
10)
Lifecycle of upper hood and dome is not assured leading to uncertainty of the recurring
cost.
Unit Sizing: Upflow Anaerobic Sludge Blanket Reactor
Sr.
Power
rqnt
(W+SB) HP
6+6
6+3
2
3
Aerated Lagoon
Settling Lagoon
6
7
8
9
10
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
53
Civil Designs
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
54
Civil Designs
Background: During the period about last 10 years further development occurred in RUDA
area mostly on the west side of the old city and along South North direction also. The specific
planning of development in these areas was not sought out during that time, however, on the occupied
plots at various pockets in the said area, the construction of buildings were going on without having
any permission basic facilities like roads, electricity and water supply network as well as waste water
disposal system. This area came under rule of RMC in the year 1998. Therefore now, it is a duty of
the authority to provide all the basic facilities as stated above, to the people of those areas. To provide
drinking water facilities to the people of those areas a water supply project based on Nyari-II reservoir
and its seepage was carried out, but due to scarce of water in the reservoir, the water supply system
could not be put in to commission during this year. Similarly, subsequent problem of waste water
disposal shall have to be faced immediately after commissioning of drinking water supply. To solve
this problem a Sewerage Project Phase-III was thought out by Rajkot Municipal Corporation
Field Survey : For the proposed project area, where town planning schemes was prepared,
the road alignment survey was carried out. This includes taking of levels at 30 mt. Interval along the
roads, all the crossings and turning points etc have been covered with additional levels at 30 mt
interval on center line of the road. For areas outside the town planning schemes, i.e. pockets
developed like near Mavdi village, layout of such areas have been prepared and incorporated with the
levels at 30 mt interval. Total length of roads are shown in the below mentioned table.
Details of T.P.Roads in Town Planning Schemes
Sr
No
01
02
03
04
05
06
07
Name &
Nos.of
scheme
T.P.S. 1
Raiya
T.P.S. 2
Nana
Mava
T.P.S. 3
Nana
Mava
T.P.S. 4
Raiya
T.P.S. 5
T.P.S. 6
Raiya
T.P.S.
7&8
Mavdi
Total
Sub
Road
Tot. of
Roads
45m
30m
24m
28m
18m
15m
12m
9m
1420
--
1400
1000
80
--
7385
3090
24375
24840
39215
240
2180
1180
1340
--
1340
4380
1240
11900
21140
33040
1260
--
1260
--
--
280
5710
5370
13880
8200
22080
--
--
1120
--
2800
--
4320
6150
14390
8280
22670
-1600
600
--
1060
1460
---
---
-820
4840
5500
2120
3160
8620
12540
8040
17040
16660
29580
--
--
--
--
--
--
--
--
21755
25000
46755
Total
210000
Ground levels have been recorded in the level books and same have been submitted as
Survey And Investigation Report( For Population Projection Kindly Refer Annexure). The TBM
list with location and RL in meters for TP scheme 1 to 8 and pocket areas have been identified ,
Sketches of locations also have been shown in the drawing No.01 to 08. Field Book record i.e. level
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
55
Civil Designs
Book No.01 to 21 have been also incorporated in the survey report for permanent record for Rajkot
Municipal Corporation.
For preparation of estimation of sewer lines, trial pits in the project area have been taken.
data of population and sample studies of two TP areas partly developed and / or under developing,
considering the number of persons 5 per house / flat for the occupation of 65% of total houses. Thus
the projected population in the year 2030 is forecasted to 3,97,000 including the prospective
population of three villages also as drainage collective system is generally designed for 30 years of
period.
Water supply: Saurashtra region is the semi arid zone and Rajkot city is falling in this area
where water is scares. Other cities of Gujarat State like Vadodara, Surat and Ahmedabad, total
quantity of water per capita is supplied (considering all other sources) 250 liters and these figures are
always taken into account by the consultants for calculation of generation of waste water for the
design of collective system of sewer lines. Whereas to run the underground drainage, Central Public
Health and Environmental Engineering Organization. (Ministry of Urban Development) has fixed
criteria per capita bases and it is 140 to 150 liters / capita water requires to run the underground
drainage system smoothly. Therefore, Rajkot Municipal Corporation has followed minimum
requirement of water supply as per the criteria fixed by the CPHEEO New Delhi 140 to 150 LPCD to
function the underground drainage of city area as well as proposed project area. The proposed project
area is only of residential zone and hence no other demand like industry etc has been taken into
account. The Rajkot Municipal Corporation has also planned to provide sufficient supply the water
required for efficient functioning an commissioning of this sewerage project of extended area of the
city simultaneously.
Waste water generation: Normally 80 to 85% of the quantity of water reaching the
consumer's end is considered as waste water for the sewerage disposal system. Per capita waste water
flow for the design of sewerage system is considered as 128 liters in this design. The estimation of
ground water infiltration shall be practically zero as the ground water table in this region are very
much below the designed depth of sewer lines. However, the provision of ground water infiltration
has been estimated as per the criteria shown in Manual on sewerage & sewage treatment (Page 40) i.e.
minimum 500 liters / km day for approximately 200 kms length is equal to 0.10 MLD which is
negligible quantity against the total flow of the project.
Design of sewers : The system design parameters for sewers are as per CPHEEO manual
which is the requirement of financing institutions. The design criteria for sewers are as follows:
Design Year: The design year considered for the sewerage system for this project area is
2030.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
56
Civil Designs
Design Flow : The design is based on the waste water generated duly considering the water
demand of 150 LPCD as stated above in the year 2030. The design flow is therefore considered as 128
LPCD after considering losses and considering that 85% of water supply is converted to sewage.
Peak Factor : Peak factors, depend upon the density of population, topography of the project
area and hours of water supply etc for design of sewerage system of project area, peak factor 2.25 is to
be considered for the design based on contributory population recommended by CPHEEO in the
manual. However, looking to the individual TP scheme population 2.50 peak factor is taken in the
sewer design. The peak factor is applied to the projected population for the design year.
Average Dry weather flow :This would comprise average domestic sewage flow and
infiltration.
Peak Dry weather flow : This is the design flow. It comprises peak domestic sewage flow
and infiltration.
Design formula :For design of new sewerage system, Manning's formula is adopted which is;
0.003968(D)0.67 x (S)0.50
N
Q=
Q=
Discharge in lps
V=
Velocity in mps
N=
D=
S=
Coefficient of Roughness : For sewerage system, NP2/NP3/NP4 class RCC pipes for higher
diameter as well as stoneware glazed pipes for smaller diameter sewer line are generally provided.
The roughness coefficient, N, is assumed same for all diameters of RCC pipes with collar joints and is
considered 0.015. For stoneware pipes for all diameters, N, is assumed 0.013. As pipes deteriorate
with age, a roughness co-efficient is considered corresponding to fair condition of the interior surface
of sewers.
Minimum size of Sewer: A minimum diameter of 150 mm has been considered to identify
the proposed sewer under study. Three factors are influencing for deciding the diameter of sewer
pipeline.
Proposed gradient in sewer line : Rajkot city is under semi arid zone and availability of
water quantity here is scarce resource. Hence, minimum criteria of water supply 140 LPCD to 150
LPCD is adopted by the Corporation for smooth functioning of sewer lines. Rajkot city Sewerage
project phase-I was started in the year 1979 and completed and commissioned after 23 years of
period. The main reason of delay of this project was a severe hard rock excavation and steep slope of
initial pipelines in the design. Initial slopes of 150 mm dia pipelines were taken 1 in 80 to get very
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
57
Civil Designs
easy initial self cleansing velocity. Due to such design, depth of pipeline had gone very deep and due
to hard rock it was found more difficult in the excavation. Ultimately, a decision was taken to adopt
grade of 150 mm dia pipeline 1 in 130 which is found sufficient for 750 population of initial stage to
achieve self cleansing velocity during peak hours. Hence based on the past experience of Rajkot city
sewerage project phase-I and its present results of well functioning in the water scares period. It is
proposed to provide 150 mm diameter as minimum for initial sewer lines. Major lengths of sewers in
any project area are always with smaller diameters and these initial pipeline sections are not getting
enough flow in the commissioning stage. Hence, as per the recommendations of World Bank in the
previous sewerage project Phase-I, Stoneware pipes of minimum diameter 150 mm size is proposed in
this project for initial sewer lines and same will be more convenient in cleaning in the initial stage of
commissioning. More care is required for frequent cleaning during initial period. Stoneware pipes of
ISI quality are now easily available in the market and hence it is recommended to use 150 mm to 250
mm dia pipes in this project as stoneware salt glazed ISI marked quality for initial sections of sewer
lines.
Minimum Depth of Cover : The minimum depth of cover to be provided over the top of pipe
Self Cleansing Velocities :A minimum velocity of 0.75 to 0.80 mps at design peak flow (in
the year 2030) in the sanitary sewer is considered subject to a minimum velocity of 0.6 mps for
present peak flows (in the year 2001) as per the recommendations of CPHEEO manual.
Limiting velocities for particles varying in specific gravity from 1.01 to 2.65 were studied.
The specific gravity of grit is usually in the range of 2.4 to 2.65. For minimum velocity of 0.6 m/sec
all particles of specific gravity 2.65 and size less than 1.0 mm will remain in suspension. Hence, the
velocity of 0.6 m/s should be adequate to prevent situation in sewers. However, the problem of silting
may occur in early years, particularly for smaller sewers with velocities of flow less than 0.6 m/s but
the assumption is made that the deposited silt would be flushed out during the peak flows. Where such
velocities are not obtained periodical flushing would be required.
Design capacity of sewers : Sewers designed to carry estimated peak flows generated in the
year 2030 will run partially full for all variations in the flow. The maximum permissible depth of flow
in sewers for established velocity criteria are tabulated in the following table.
Depth of Flow : From considerations of ventilation in waste water flow, sewers should not be
designed to run full. All sewers are be designed to flow 0.8 full at ultimate peak flow. However, as per
Hydraulic design the depth of flow at Ultimate Peak is between 0.45 to 0.8.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
58
Civil Designs
Following table shows the hydraulic properties of circular sections for Manning's Formula.
Area Ratio
Velocity Ratio
Discharge Ratio
d/D
a/A
r/R
v/V
q/Q
0.100
0.052
0.254
0.401
0.021
0.200
0.143
0.482
0.615
0.088
0.300
0.252
0.684
0.776
0.196
0.400
0.373
0.857
0.902
0.337
0.500
0.500
1.000
1.000
0.500
0.600
0.626
1.110
1.072
0.671
0.700
0.748
1.185
1.120
0.838
0.800
0.858
1.217
1.140
0.988
0.900
0.949
1.192
1.124
1.066
1.000
1.000
1.000
1.000
1.000
where d, a, r, v and q denote depth of flow, area, hydraulic radius, velocity of flow and
discharge respectively for partial flow condition and D, A, R, V and Q are the corresponding
characteristics for full flow condition.
Topography of the proposed project area : Detailed survey investigations have been
completed and based on the detailed survey the actual topographical conditions, sewerage network
have been prepared to have minimum excavation of pipelines. A natural drain (Vonkala) coming from
South direction of the project area flows towards North i.e. from near by Mavdi village to passing
through out skirt of the extended area of the city to the west of the villages of Munjaka and Raiya
meeting to the tributary of river Nyari on up stream of Nyari II reservoir. Therefore in general the
natural slopes of the ground have been taken into account for planning the sewerage network.
been carried out on present and projected density and same have been distributed per manhole in the
TP scheme layout. Special consideration is given to the areas where high rise buildings exists and
areas where such type of high rise buildings are expected in future. Per manwhole increase of flow
has been calculated and for each sewer section, present average flow, present peak flow, projected
average flow, projected peak flow and full flow have been calculated and applied as basic data of
hydraulic design of sewer sections of entire network. Network have been prepared as per Town
Planning Scheme Numbers 01 to 08 considering each Town Planning Scheme as individual drainage
zone for convenience of execution, maintenance and supervision.
The hydraulic analysis of all sewer sections as collective system have been carried out using
Excel Computer Software Programming for all the four conditions of all sewer sections of network. It
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
59
Civil Designs
has been cross checked with the computer software recommended by the UNDP Sewer Software
Version 3.0. Statements of design of sewer sections and designed Invert Levels have been attached
herewith as an annexure.
Sewer appurtenances: Manholes are to be provided at all junctions, change of sewer size,
gradient and direction. As per the RMC practice the spacing of manhole is kept between 25 to 40 mt
for all diameters.
However, additional manholes are to be provided on junctions of the street avoiding standard
distance. For sewers of 600 mm diameter and above, scraper manholes are proposed to be provided at
major junctions and at about 200 m c/c. The typical details of proposed house connection chamber,
conical type manhole, A, B, C, D1, D2 and scraper manhole S1, S2, S3 are shown in Annexure.
Bedding for sewers: The type of bedding (First class bedding, concrete cradle, full encasement)
shall depend on the depth at which the sewer is laid. Thus the load due to backfill and superimposed
load (live load), and the three edge bearing strength of pipe will be the governing criteria for selection
of appropriate bedding factors.
60
Civil Designs
Gujarat Pollution Control Board (GPCPB) has already approved the site and RMC has already
finalized DTPs
Process design options
The number of approaches and advanced techniques are prevailing at present to treat the
domestic waste water as well as industrial waste water. Normally biological treatments are used world
wide and they are suitable for sewage treatment plant,. Following are the options of biological
treatment for treatment of domestic sewage.
Following review is made.
Looking to the techno-economical aspect- Conventional Activated Sludge Process with Sludge
digester is recommended to be adopted for Sewage Treatment Plant
Location of the Works
The Works are to be constructed at Raiya located approximately 3 km west of the city limits
of Rajkot in the State of Gujarat, India. The detailed location is shown on the Drawings.
Inlet chamber;
Screen Chamber;
Grit Chamber;
Parshall Flume;
Primary Clarifier;
Aeration Tank;
Secondary Clarifier;
Sewage sampling;
Service water;
MCC Room.
Raw Sewage
Raw Sewage Quality
Generally, the raw sewage has a low suspended solids, but during morning hours, its concentration
rises from less than 200 mg/l to 800-1000 mg/l. At the same time other parameters does not change
substantially.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
61
Civil Designs
The treatment works shall be designed to treat sewage of the following quality:
Units of measurement
pH units
Value
6.5 - 9.2
Suspended Solids
mg/l
525
mg/l
200
mg/l
630
Alkalinity
mg/l
185
Sulphates
mg/l
110
mg/l
10
Ammonical Nitrogen
mg/l
16.8
mg/l
15
The quality of the raw sewage entering into existing Sewage Treatment Plant at Madhapar
over the period January 2005 to December 2005 is summarized in Appendix ___.
Compliance Requirement
Effluent
from PST
BOD<150 mg/l
SS<250 mg/l
Effluent
from SST
BOD<20 mg/l
SS<30 mg/l
pH 6 to 9
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
62
Civil Designs
35oC
30oC
75%
Altitude
125 m
site conditions
semi-arid
The plant shall be designed for an ambient temperature of 40 C with the Contractor
making due allowance in his designs for the increased temperatures experienced by Plant
exposed to direct sunlight.
Works Life Expectancy
The Contractor shall design the Works for a life expectancy as follows:
concrete structures
60 years;
mechanical plant
25 years;
electrical plant
25 years;
50 years;
control panels
25 years;
15 years;
computer systems
The major units comprises
a) Elevated inlet chamber
12 years.
b) Main plant by-pass pipeline from Inlet chamber to effluent disposal point
c) Elevated screen chamber
d) Elevated grit chamber
e) Flow measuring channel Parshall flume
f) Distribution chamber for Primary Settling Tank (PST)
g) By pass pipeline from Distribution chamber to main plant bypass pipeline
h) Primary Settling Tank (PST)
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
63
Civil Designs
2. Design criteria
Elevated Inlet chamber and plant by-pass
Inlet chamber shall be adequately sized to receive sewage from pumping main and to
provide plant bye pass having peak hydraulic carrying capacity of 114.75 Mld plant by- pass
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
64
Civil Designs
shall be designed to attain 0.9 m/sec to 1.5 m/sec velocity at peak flow duly considering the
available hydraulic head at the plant from inlet chamber to discharge point. Hydraulic
Detention Time shall be 60 seconds minimum at peak flow.
Elevated screen chamber
a)
114.75
Mld
b)
Average flow
51
Mld
c)
Number of Screens
d)
Number of channels
e)
Velocity
in
approach 0.4
channel during average
flow (minimum)
m/ sec
f)
Max
velocity through 1.2
screen at peak flow
m/sec
g)
h)
i)
0.5 m
Peak flow
114.75
mld
b)
Average flow
51
mld
c)
d)
2.45
e)
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
mm
65
Civil Designs
m3/m1
f)
0.1
g)
m/sec
h)
Temperature of sewage
(design)
18
i)
0.80
j)
60
sec
k)
0.9
l)
m)
0.5
Peak flow
114.75
mld
b)
Average flow
51
mld
c)
d)
e)
35
m3/day/m2
f)
80
m3/day/m2
g)
2.25
hours
h)
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
66
Civil Designs
i)
I V to 12 H
j)
150
m3/day/m
k)
370
m3/day/m
l)
40
m)
60
n)
Note:
a)
b)
c)
0.5
d)
50
mm
Aeration Tank
a)
Peak flow
114.75
mld
b)
Average flow
51
mld
c)
Number of tanks
d)
f)
0.3 0.6
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
67
Civil Designs
2000 mg/1
h)
80% of MLSS
i)
0.2-0.4
10 days
k)
1.0 m
l)
Oxygen requirement
1 kg O2 /kg of BOD 3 @
27 c removed
m)
2.0
n)
mg/1
o)
kg O2/KWhr
p)
Mixing requirement of KW
KW/m3
0.015-0.026
All other flow reaching the tank as per layout plan shall be considered in the design.
Secondary Settling tank
a)
Peak flow
114.75
mld
b)
Average flow
51
mld
c)
d)
28
m3/day/m2
e)
Hours
f)
3.5
g)
1 V to 12 H
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
68
h)
Civil Designs
185-370
m3/day/m
m3/hour/m
i)
Solids concentration in
secondary sludge
1%
j)
70-140
kg/day/m2
k)
210
kg/day/m2
a)
b)
c)
0.50 m
d)
0.05 m
Digesters
a)
b)
Volatile solids
50%
c)
1.07
d)
60
e)
Temperature of digestion
30
f)
30
days
15
days
g)
h)
nos.
i)
Solids loading
0.75
kg VSS/day/m3
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
69
Civil Designs
j)
1 V to 4 H
k)
Mixing system
Gas
mixing
unconfined
l)
0.005
m)
Velocity gradient
50-80
Sec-1
n)
0.05-0.10
m/sec
o)
Watts/m3 (min.)
p)
15-35
Sq. mt / No.
m3/m3.min(min)
m3/hr.m2 (min)
Gas Holder
m3/kg of VSS
destroyed
a)
0.9
b)
Gas is to be utilized in
plant.
Future (not in
present contract)
c)
d)
Gas to be burnt
100%
e)
day
nos
20 m x 20m
b)
0.3
c)
12
days
d)
e)
Moisture concentration of
dried sludge amenable for
spading and carting away.
40
% at 40 C
f)
nos.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
70
Civil Designs
Sludge concentration
b)
1.07
c)
As required
d)
mm
e)
hour
f)
hrs/day
b)
Concentration of solids in
return sludge
c)
hour
d)
1.02
e)
Minimum diameter of
pumping main to avoid
chock age.
200
mm
f)
200-300
mg/1
b)
Minimum diameter of
pumping main
150
mm
c)
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
71
Civil Designs
Pipeline
a)
Pipeline for Main plant by pass from inlet chamber to final disposal point
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
Washout for aeration tank shall be provided and connected to bypass line
for emptying the unit by gravity with a minimum size of 450 mm dia DI,
K-9 class pipeline with valve of same size
All above channels/ pipeline shall be designed for peak flow including all other flow as per layout
plan. Maximum velocity shall be limited to 1.5 m/sec for bypass. Velocity at average flow shall not be
less than 0.6 m/sec for interconnecting units/chambers and shall not exceed 1.35 m/sec at peak flows.
Minimum velocity of 1.5 m/sec shall be maintained to prevent solids deposition and clogging of
pipeline for sludge carrying/conveying pumping mains.
3. Process description
3.1
General :
Average flow. . .
Peak flow..
51.00 MLD.
114.75 MLD.
3.2 Inlet chamber: Inlet chamber of suitable size shall be constructed at the location, shown in the
layout plan. Sewage into inlet chamber shall be received through 1 no. 1100 mm Rising main from the
pumping station located outside the plant about 1 km. toward town, which is under construction.
Tentative sizing and RLs of inlet chambers are given below.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
72
Civil Designs
Size of opening for inlet pipe.. suitable for 1300 mm dia. PS pipe
Size of opening for plant bypass. suitable for 1300 mm dia. RCC NP-4 pipe
Size of plant bypass gate. as required (C.I. SLUICE GATE with
penstock)
Size of opening at outlet side.. as required.
Nos. of openings.. 2 nos.
Size of gate on this opening
as required (C.I. SLUICE GATE with
penstock)
The inlet chamber shall be provided with required number of DI puddle collars both ends
flanged with creeping flange at middle of wall. This is to be fixed while concreting of inlet chamber
under progress. Necessary precaution shall be taken to avoid leakage. Necessary C.I. GATES shall be
provided to plant bypass exit, at inlet chamber. Necessary platform / passage at upper level (R.C.C.
construction) shall be made to locate the penstock for gate operation and inspection purpose.
Plant bypass shall be designed for peak flow carrying the sewage and ultimately disposed into
the existing culvert on natural drain outside the plant premises. Primary treatment units Bypass after
the preliminary treatment units and Secondary treatment units, a bypass after the primary settling
tank, i.e. before the aeration, shall be provided as shown in the layout plan and as directed by engineer
in charge. All bypass lines and pipe carrying treated sewage (excluding sludge & interconnecting
treatment units) shall be of R.C.C. NP4 class pipe. Pipe carrying raw sewage for treatment, i.e. inlet
and outlet of PST & SST, shall be of R.C.C. NP4 class.
Pipe from SUDGE DIGESTER to each SLUDGE DRYING BEDS shall be of 300 mm. Dia.
minimum D.I. K-9 class. Filtrate collected beneath sludge drying beds shall be conveyed from each
SLUDGE DRYING BED to FILTRATE PUMP HOUSE (FPH) through 300 mm. Dia. R.C.C. NP4
class pipe. From FPH, filtered sludge shall be carried to DISTRIBUTION CHAMBER after Parshall
Flume to recycle the sewage and assure zero discharge of raw sewage. No sewage shall be let out
without treatment. Supernatant from sludge digester shall be conveyed to distribution chamber of PST
by gravity only.
2.2
constructed in R.C.C. M-25 grade. An upstream channel of minimum 6.0 m. length and downstream
channel of minimum 3.0 m. length. Shall be provided before and after the screen chamber. The peak
flow velocity in the channel shall be around 0.80 m/sec and velocity at average flow shall not be less
than 0.60 m/sec. The channel shall be adequately widened to accommodate the screens. Indicative
sizing of the channel and bar screen is tabulated below.
Channels
Size (u/s channel) 1.50 m width x 1.20 m. depth
Size (d/s channel) 1.50 m width x 1.20 m. depth
Nos. 2
Floor level RL. 129.55 m.
Top water level (u/s channel) RL. 130.75 m.
Top water level (d/s channel) RL.depending up on the headloss
Free board 0.30 m. minimum
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
73
Civil Designs
Nos...
74
Civil Designs
As required
3
As required
As required
Three grit chambers each having capacity of 57.375 MLD flow shall be designed to remove
100 % percent grit particles of 0.15 mm diameter having specific gravity of 2.45. The container wall
depth at outlet side shall not be less than 1.20 M. (diff. Between wall top and floor level). The bottom
300 mm. depth of the grit chamber shall be made circular by casting P.C.C at all corners. Outer
corners of the square grit chamber shall be sloped towards center. One no. C.I. penstock gates at the
inlet side of each grit chamber shall be provided for isolation purpose. Necessary platform at all levels
for operation of GATES, resting GRIT REMOVAL MECHANISM, with suitable R.C.C. stair for
access shall be provided. All platforms/passages shall be provided with GI. PIPE & POST RAILING
to both sides.
The flow from the screen chamber shall be allowed into the grit chamber for removal of grit
matter. The flow into the grit channel will be received through the main channel coming out from the
screen chamber. Individual flow distribution inlet channel to the grit chamber shall be tapered. The
grit chamber shall be square detritus type with central scrapping mechanism for removal of grit. The
out flow from the grit chamber shall be from an over flow weir into the outlet channel, which shall be
tapered. Grit shall be collected through one pocket at suitable location of the chamber and by means
of rake type classifier mechanism in mild steel, epoxy painted; grit shall be washed & discharged into
hopper, which shall be received in a trolley. The organic return pump with suitable motor shall return
the organic matter, at inlet side of the grit chamber.
The central drive shall be made up of worm gears of suitable torque and driven by 1440 rpm
motor of required hp. Suitable drive shaft (pipe shaft) shall be connected with the drive at the top and
shall have guide arrangement at the bottom end. Three nos. of scrappers shall be connected with the
drive shaft at the lower end. Each scrapper shall span the radius of the tank and shall be spaced at 120
degree intervals. Scrapper/raking plate with scooping arrangement at the outer end of the scrapper
shall push the grit towards the openings on the classifier sidewalls at the bottom. The grit shall thus be
pushed to the classifier bottom through the openings in sidewalls. The drive shall be provided with
mechanical shear pin arrangement for overload protection.
The grit chamber works on velocity principle and shall be so designed that only the grit settles
down and organic materials overflows out for further treatment. The velocity in the chamber thus has
to be uniformed and the uniform flow shall have to be maintained at the inlet side of the grit chamber
(detritor). Diffusers at inlet side shall be adequately provided at equidistant, vertically aligned with
central bar embedded and extending from floor up to the chamber top. Necessary arrangement shall
be provided to rotate the diffuser in horizontal plane and thereby shall permit required angle settings.
Diffusers shall be of uniform shape and factory made precast R.C.C. construction covered with steel
sleeve all around. Necessary R.C.C. beam/platform shall be provided to regulate the diffuser from
chamber top.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
75
Civil Designs
The classifier mechanism shall comprise of reciprocating rake driven by a gear drive fitted
with 1440 rpm and of required HP motor. The gear motor shall provide rotating motion to link
mechanisms that will convert the rotating mechanism to reciprocating raking action. The reciprocating
travel and continuous scooping washes the grit in the classifier and in the process the grit is delivered
from the top of the classifier through a chute for further disposal. Organic Return Pump returns the
washed organic liquor lying in the classifier back to the detritor collection chamber. The classifier
drive shall be provided with mechanical shear pin arrangement for overload protection. There shall
not be moving parts or bearings under the water so that maintenance required becomes minimal.
Flow measuring channel
The outlet channel emerging from the grit chamber shall have necessary arrangement to
observe the discharge ranging from 3.0 MLD to 166.20 MLD with help of parshall flume. The flume
shall be designed for peak flow capacity of 114.75 MLD. A straight uniform channel of minimum 6.0
m. length u/s to flume and minimum 3.0 m. length d/s to flume shall be provided. The throat width of
the flume shall be 1200 mm with required convergent and divergent cone sections. Necessary
platform at suitable levels with M. S. post and G.I. PIPE railing in three rows shall be provided for
inspection purposes with necessary staircases. Dimension of the parshall flume are given below.
Parshall Flume
Length of u/s channel 6.00 m. minimum
Length of d/s channel 3.00 m. minimum
Throat width of flume 1.20 m. minimum
Convergent & divergent cone as required.
Distribution Chamber
Size as required
Top water level . 129.30 m. maximum
Floor level as required
Throat width of flume1.20 m. minimum
Convergent & divergent coneas required.
Bypass line RCC NP41100 mm dia.
Pipe to PST RCC NP4800 mm dia.
Nos of CI sluice gates.3 nos of required size
Distribution chamber for primary settling tank
There shall be a distribution chamber after parshall flume from which bypass pipe with C.I.
penstock gate, having peak flow capacity of 114.75 MLD and connected to plant bypass TRUNK
SEWER at the location shown in the layout plan shall be provided.
Distribution Chamber
Size as required
Top water level . 129.30 m. maximum
Floor level as required
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
76
Civil Designs
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
77
Civil Designs
Peripheral launder of each settling tank shall be designed for peak flow of 114.75 MLD while
designing the peripheral launder half the peak flow shall flow in clockwise direction and half shall
flow in anticlockwise direction, meeting at a point on periphery and flow shall be from upstream to
downstream of the 0.75 m. velocity in the launder shall be minimum of 1.0 m/sec at peak flow. Free
fall from the launder shall not be less than 50 mm with respect to launder crest. Effluent from the
peripheral launder shall be collected at outlet of the settling tank from where through chamber it shall
be conveyed to distribution chamber of the aeration tank.
A series of 90 FRP V Notch shall be provided all along around the periphery of the weir for
uniform distribution of flow. Thickness of FRP plate shall be minimum of 6 mm. The height of the V
notch shall not be lass then 75 mm. Clearance between two V notch at top shall not be less then 50
mm. Bottom of the V notch shall be minimum 25 mm. Above the crest of the trough. It should be
possible to adjust the V notches within the range of 50 mm. V notches shall be fitted on weir by
providing rag bolts made of stain less steel.
Scum skimming arm shall be provided to remove the scum. Scum shall be collected and
discharged into a hopper, provided at the periphery of the settling tank. The scum shall be collected by
means of 300-mm. dia. D.I. pipe provided with a sluice valve into a sump constructed outside the
primary settling tank. Peripheral FRP scum baffle, which shall extend 150 mm. above TWL & 450
mm. below TWL, shall extend 450 mm. ahead of launder. Thickness of FRP baffle shall be 6 mm.
Appropriate disposal arrangement shall be made.
A C.I. telescopic sludge draw-off valve of 300 mm dia. shall be provided. The sludge
deposited at the bottom of the settling tank shall be collected in the sump provided near the
mechanism by scrapper mechanism. The scrapers shall be hung from the bridge and shall have
neoprene squeezes at the lower end for matching the slope. Slip ring collector shall be provided over
central bearing at central point for current distribution to traction drive. All parts of the mechanism
shall be sand blasted and epoxy painted. Peripheral driven PST mechanism suitable for the
designed/approved tank size, comprising half bridge of 1.0 m. width with chequered plates and
handrails, supported on central pier top at central end on center pivot bearing and driven by traction
drive fitted with mild steel wheels at peripheral end shall be provided. Groove for the traction on the
periphery of the PST wall for the moving of the nylon tyred wheels shall also be provided. Traction
drive shall be driven by 1440 rpm and of required HP MOTOR. The sludge from the sump shall be
hydrostatically withdrawn by means of D.I. pipeline of diameter not less than 300mm. This pipeline
shall be provided in the chamber constructed near PST. Tee shall extend 0.6 m above TWL. The
sludge shall be withdrawn and carried to sludge sump of raw sludge pump house. A bridge shall be
provided to have access to the central rotating mechanism. All necessary arrangement for resting the
MOTOR for driving the scraper bridge, M.S. sections for running the cables etc. shall be provided.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
78
Civil Designs
79
Civil Designs
adequate size shall be provided to dampen the waves in tank due to aerators. From the outlet weir
which shall be adjustable type the mixed liquor shall flow into a common channel from where main
channel shall be taken to distribution chamber of secondary settling tanks. Some portion of activated
sludge shall be returned to the inlets of each of two compartments of the aeration tank through D.I.
pumping main of suitable diameter. This shall run parallel to the wall of the aeration tank & shall be
provided with necessary cross connections, bends & sluice valve to control the return of activated
sludge into each section of aeration tank. For washout/ scour purpose 450 mm dia pipe with valve of
same size with necessary valves and chamber for each compartment up to plant bypass line by gravity
flow shall be provided.
Distribution chamber for secondary settling tank:
The mixed liquor from outlet of the aeration tank shall be distributed into secondary settling
tank through distribution chamber. The distribution chamber shall be provided with two nos. C.I.
penstock gets of suitable size for dividing & isolating the flow to the secondary settling tank.
Secondary Settling Tank:
Two numbers, circular secondary settling tank with shall be designed for a total average flow
of 51 mld plus return sludge of 25% of the average flow, flow of filtrate from sludge of drying beds,
supernatant from sludge digester and excess sludge. In calculating detention period, the volume of
hopper bottom shall not be considered. The hopper bottom slope shall be 1 vertical to 12 horizontal
towards center. Indicative sizing with RLs is given below.
Hydraulic retention time
2.00 Hours minimum at average flow plus other
returned flows
Size 35.00 m. dia. x 3.50 m.depth of side water
Nos 2 nos.
Inner dia of RCC central inlet pier..
2.50 m.
Inner dia of central feed well. 5.00 m. to 5.50 m.
(i.e. FRP deflector box)
Floor level at side wall base. RL. 124.45 m.
Floor slope toward center. 1 : 12
Free board 0.50 m. minimum
Top water level of tank. RL. 127.95 m.
Top water level of launder RL. 127.80 m. maximum
Top of wall RL. 128.45 m.
Type of launder.. Double weir type
Central pier bottom levelRL. 121.53 m.
RCC Central pier top level As required (minimum RL 128.75 m.)
In calculating detention period, the volume of hopper bottom shall not be considered. The
hopper bottom slope shall be 1 vertical to 12 horizontal towards center. The RCC NP4 feeder pipe
from distribution chamber shall enter in bottom of settling tank and terminate into central feed well.
Required openings of suitable size in the inner face of the central pier shall be provided the central
pier shall extend above TWL so that the scrapper bridge mechanism can easily be installed. Entry port
shall be submerged 0.3 m to 0.6 m below TWL. A platform all around the central pier shall be
provide. The diameter of central feed well shall be 15 % of the diameter of PST, this shall extend 25
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
80
Civil Designs
mm below maximum TWL and 1.5 m below maximum TWL. Deflector box shall be hung from the
central pier.
Peripheral launder of each settling tank shall be designed for peak flow of 114.75 MLD while
designing the peripheral launder half the peak flow shall flow in clockwise direction and half shall
flow in anticlockwise direction, meeting at a point on periphery and flow shall be from upstream to
downstream of the 0.75 m. velocity in the launder shall be minimum of 1.0 m/sec at peak flow. Free
fall from the launder shall not be less than 50 mm with respect to launder crest. Effluent from the
peripheral launder shall be collected at outlet of the settling tank from where through chamber it shall
be conveyed to distribution chamber of the aeration tank.
A series of 90 FRP V Notch shall be provided all along around the periphery of the weir for
uniform distribution of flow. Thickness of FRP plate shall be minimum of 6 mm. The height of the V
notch shall not be lass then 75 mm. Clearance between two V notch at top shall not be less then 50
mm. Bottom of the V notch shall be minimum 25 mm. Above the crest of the trough. It should be
possible to adjust the V notches within the range of 50 mm. V notches shall be fitted on weir by
providing rag bolts made of stain less steel. A C.I. telescopic sludge draw-off valve of 300 mm dia.
shall be provided.
The sludge deposited at the bottom of the settling tank shall be collected in the sump provided
near the mechanism by scrapper mechanism. The scrapers shall be hung from the bridge and shall
have neoprene squeezes at the lower end for matching the slope. Slip ring collector shall be provided
over central bearing at central point for current distribution to traction drive. All parts of the
mechanism shall be sand blasted and epoxy painted. Peripheral driven SST mechanism suitable for
the designed/approved tank size, comprising half bridge of 1.0 m. width with chequered plates and
handrails, supported on central pier top at central end on center pivot bearing and driven by traction
drive fitted with mild steel wheels at peripheral end shall be provided. Groove for the traction on the
periphery of the PST wall for the moving of the nylon tyred wheels shall also be provided. Traction
drive shall be driven by 1440 rpm and of required HP MOTOR. The sludge from the sump shall be
hydrostatically withdrawn by means of D.I. pipeline of diameter not less than 300mm. This pipeline
shall be provided in the chamber constructed near PST. Tee shall extend 0.6 m above TWL. The
sludge shall be withdrawn and carried to sludge sump of raw sludge pump house.
A bridge shall be provided to have access to the central rotating mechanism. All necessary
arrangement for resting the MOTOR for driving the scraper bridge, M.S. sections for running the
cables etc. shall be provided.
Treated sewage from the secondary settling tank shall be discharged into chamber and a
pipeline leading to final disposal point.
Sludge digester:
Two digester each of requisite effective capacity (below the TWL) shall be provided with
steel dome. TWL shall be at the bottom of the ring beam. Bottom hopper shall have slope of 1 vertical
to 4 horizontal.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
81
Size
Civil Designs
Nos 2 nos.
Floor slope toward center. 1 : 4
Each digester tank shall be provided with DI/ C.I piping, specials, equipment etc. as per
requirement of design. Minimum of the 200-mm. dia. D.I. sludge feeder main from top with sluice
valves to individual digesters.
Sludge withdrawal D.I pipeline shall be of minimum 300 mm diameter. The pipeline shall be
provided with necessary valves and fitting as required. The pipeline shall start from the center of the
hopper portion. It shall be connected with the RCC overflow chamber provided below ring beam
level. Down take pipe of min 300-mm. diameter from this chamber to sludge drying beds shall be
provided. One sluice valve with Y shape tee connection having blank flanges shall also be provided
in the sludge withdrawal pipeline for each digester for back pressure application/rodding for opening
of chockages etc. The RCC overflow chamber as stated above shall be used for sludge withdrawal and
second portion for supernatant withdrawal. Necessary bends, valve, fitting etc. shall be provided.
Supernatant withdrawal D.I. pipeline 200 mm (min.) diameter with ring for adjusting the levels shall
terminate into the overflow chamber below the ring beam of the digesters and from this chamber
another down take pipe of min 300 mm diameter shall be connected to a common header which leads
to the distribution chamber of primary settling tank. Necessary bends/specials valves shall be
provided.
C.I. gas line of minimum 150 mm diameter with a pressure gauge on the top of digester shall
be provided with gas tight/gas leak proof valves of standard make (as per details of E&M
specifications). It shall be connected to a common header of minimum 150 mm leading to the
gasholders. The C.I. pipelines shall be provided with drip traps at suitable elevations. The grip traps
shall be provided with suitable disposal arrangements.
Each digester shall be provided with inspection manhole suitably located on the dome and
having removable covers and shall be leak proof.
Two-manhole opening of 1.2 m dia each shall be provided in the vertical wall just above
formation level. The mixing of digester contents shall be done by injection compressed gas drawn
from the gasholder. The digester shall work as constant level tanks. Whenever fresh sludge is added,
equal quantity of supernatant & sludge shall overflow.
The
digester
shall
be
tested
both
hydraulically as well as pneumatically with compressed air to withstand a pressure of 250 mm water
gauge to ensure no leakage of gas.
Gas holder (single stage bell) :
There shall be two wet seal gas holder of suitable effective gas holding capacity. Volume is
calculated from TWL in RCC tank during raised position to the springing level of bell. In calculating
the effective capacity the volume of dome portion of bell shall not be considered. The volume location
shall consist of the following.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
82
Size
Nos
Civil Designs
A circular RCC tank of adequate diameter and height to accommodate ladder between steel
bell and RCC wall shall be provided with RCC floor, partly below ground level. In raised position of
steel bell the top water level in RCC tank shall be 500 mm above the bottom of the bell. A free board
of 500 mm above TWL in RCC tank shall be provided the RCC tank shall have a walkway all around
the tank. A balcony of 1.5 m x 1.5 m with a staircase shall be provided.
A steel bell of circular cylindrical shape for gas storage shall be provided. The gasholder shall
be having gas inlet & outlet pigpens. Control valves, vacuum and pressure relief valve with flume
arrestors.
There shall be a C.I. gas header coming from digester to feed the gasholder tank. Provision
shall be made for burning the gas by connecting gasholder outlet pipeline to the burner. Connection
from outlet shall also be made to compressor to compress gas. The compressed gas shall be supplied
to different digester through main/branch pipelines for mixing of digester content. Adequate number
of valves shall be provided as required for control. The outlet pipe from gasholder shall also supply
sewage gas to compressors to run the burner/ dual-fuel engine. Outlet from gasholder shall have
adequate diameter to serve the above requirement.
The entire control valve provided for gas holder shall be housed inside chamber at suitable
elevation from formation level. Drip traps shall be provided on gas lines entering into and coming out
from gasholder with suitable draining arrangements at suitable elevation.
The gasholder shall be provided with RCC open stepped staircase to have access from the
formation level up to the top RCC tank of the gasholder. At the top of the RCC wall of the tank,
platform and a balcony with G.I. vertical pasts one meter high suitably spaced along the periphery of
the tank. Necessary water connection for filling RCC tank of gasholder shall be provided by the
department near the tank. The contractor shall provide necessary arrangement for filling the tank. The
gasholder shall also be provided with PVC sheet fixed on one of the guide girder of the gasholder.
The PVC sheet shall have graduations marked, to indicate the level. An alarm system shall also be
provided.
Necessary opening of size 1.2 m dia in the vertical wall at the formation level for clear access
to gasholder.
An overflow pipe at suitable elevation having adequate diameter shall be provided and
connected to nearest natural drain.
Gas meter : The gas flow meter having adequate capacity of reputed make as approved by the
department for measuring gas shall be provided and installed in the digester control room.
Gas burner: Adequate number of gas burners (minimum 2 nos.) Shall be provided to burn all the gas
generated in one day.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
83
Civil Designs
Sludge drying beds : Suitable no. of drying beds shall be provided for the open drying. The size of
each bed shall be 20m x 20m. The filter media shall consist of the following:
First layer from top
Second layer
Third layer
Fourth layer
Bottom layer
Size
Nos
The under drainage system shall consist of brick masonry lateral drain at 6 m c/c of suitable
size and slope. the filtrate
chamber outside the bed. This chamber shall and lead eventually to the sump of he filtrate pump
house. All the brick chamber in front of each draying bed shall be provided with precast RCC
removable covers with lifting hooks. The brick masonry chambers on the filtrate pipelines shall be
provided at interval of 30 m for inspection and cleaning. The top of the chamber shall be 0.6 m above
formation ground level or road level. Manhole cover with lifting hooks and manhole with necessary
C.I. rungs for access inside the chamber shall be provided.
The sludge feed channel/ pipelines shall be 300 mm dia of cast iron and shall run over the
partition or common walls. Necessary C.I. crosses/tees with valves shall be provided for feeding
sludge in each drying bed. Provision shall be made for walkway to operate the sluice valves. The
brickwork shall be widened at top to provide walking space to operate the sluice valves. The sludge
shall be discharged at the center of each bed over a 75 mm thick precast concrete splash tray of size
1.0 x 1.0m laid on the sand bed. Necessary brick wall enclosure may be provided arums the platform.
The bottom of the sludge drying bed shall be above the ground water table.
Treated sewage line
Common Chamber for collection of treated sewage
Size as required.
Top Water Level. RL. 127.50 m.
Nos 1 no.
Treated Sewage Out Let pipe 1100 mm dia. RCC NP-4 CLASS
CI Sluice gate on Out Let pipe.. 1 no. of required size.
Raw sludge pump house and control room : A raw sludge pumping station and control room for
primary treatment unit shall be provided as shown in layout plan. The pumping station shall have
wet sump and control room. All electrical and mechanical equipment shall be housed in pump house
and control room.
Size of dry well cum wet well
(with central partition wall)
live storage depth
Height of dry well portion above GL
Capacity of HOT crane..
Nos...
14.00 m. diameter
2.00 m.
4.50 m.
3.00 MT
1 no.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
84
Civil Designs
Sludge from primary settling tank shall be withdrawn hydrostatically from the DI pipeline and
will be collected in the wet sump of pump house. The sludge will be pumped into the digesters
through D.I. pumping main of 200 mm diameter minimum into digester.
Return sludge pump house and control room: Return sludge pump house with control room for
final settling tank shall be provided as show in layout plan. The pumping station shall have wet sump
and dry sump of required size and control room. All electrical, mechanical equipment shall be housed
in pump house & control room.
Size of wet well .
(with central dry well)
Size of dry well .
Height of dry well portion above GL..
Capacity of HOT crane..
live storage depth
Nos...
20.00 m. diameter
8.00 m. diameter
4.50 m.
3.00 MT
2.00 m.
1 no.
Sludge from secondary settling tank shall be withdrawn hydrostatically into the wet sump of
pump house, from where the sludge will be discharged directly into aeration tank through pumping
main. The excess sludge shall be discharged into raw sludge pump house. The return sludge admitted
into aeration tank shall vary from 25% to 75% of the average flow.
Control Room for Aeration Tank :A Control room of 12 m x 8 m as shown in layout plan shall be
provided. All the necessary control required for operation of aeration shall be housed in the control
rooms.
Control Room for Digester, Gasholder and Gas Mixing arrangements: A control room as shown
in layout plan shall be provided. All controls required for operation of digester, gasholder and gas
mixing equipment shall be housed in this control room.
Filtrate Pump house: A filtrate pump for filtrate from sludge drying bed shall be provided as show in
layout plan. The pumping station shall have wet sump. All mechanical and electrical equipment shall
be housed in this pump house. The filtrate shall be pumped through C.I. pumping main to distribution
chamber ahead of primary settling tank.
Substation Building: A substation building shall be provided as show in
appearance, creating an environment conducive for plant operators to work efficiently and attend the
filth with minimum odour problem, plants emitting fragrance, and also ease of visitor to inspect all
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
85
Civil Designs
units. Landscaping shall include planting of suitable trees and development of grassed areas.
Landscaping in general shall meet ecological and environmental conditions of the site. Plants
selected near sludge drying beds shall have shade and fragrance to facilitate the manure removal
personnel. Such fragrant trees ad shrubs include Saptaparni, Kadam, Parijat, Ixora, Champo and
Borsalli. Shrubs like Bougainvillea and Kadvi mehndi shall be selected for fencing around PTU.
Straight trees like Asopalav shall be planted around aeration tank. Boundary of the STP shall be
covered with tall trees like Gulmohar, Neem, Ashoka, Peltophorum, Keshudo, Shirish, Eucalyptus,
Garmalo, Arjun etc. Depending upon the availability of space, trees shall be planted in single, double
to multiple rows in bunch of 5-10 trees. Trees flowering during the same season shall be planted
together, alternating with each other depending upon the flower color.
E.g. Combinations of
1) Peltophorum (Copper pods) and Gulmohar (Begins to flower in May/June)
2) Garmalo and Gulmohar (Both flower in May/June)
3) Keshudo and Garmalo (Both flower in April)
4) Keshudo and Peltophorum (Both flower in May/June)
Road widths shall determine the size of the tree height and spread to be selected for planting.
Trees suitable for local conditions shall be selected. Medicinal and fruit trees shall be
avoided. To enhance aesthetic beauty, herbaceous flowering plants like Cosmos, Coreopsis,
Tagetes (Galgota), Gaillardia etc. shall also be laid. Berm of the PST/SST shall be provided
with grass turfing.
Security Fencing and Gates for Transformer yard :
Security fencing for the STP plot complex and associated works shall be of 2000mm high
with 230/350 mm thick brick masonry, in cement mortar (1:6), with recessed pointing in cement
mortar (1:3), on both the faces. There shall be concrete coping over brick/random rubble masonry
wall and 750 mm high barbed wire fencing above it. Substation shall have internal fencing as per
Gujarat Electricity Board (GEB) guidelines.
4.5m wide x 2.2m high main steel gates and 1m wide x 2.2 m high steel wicket gate made out
of tubular sections/square bars/flats of welded construction along with the locking arrangement and
posts to match with security fencing shall be provided at appropriate places. Gates shall be painted
with similar synthetic enamel paint.
*********
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
86
D
Deettaaiilleedd E
Ennggiinneeeerriinngg D
Deessiiggnn-- M
Meecchhaanniiccaall &
&E
Elleeccttrriiccaall
Detail Project Report for Drainage Phase II & III (Part-I) for Rajkot City
87
STATEMENT SHOWING THE DETIALS OF DESIGNED CAPACITY OF PUMPING STATIONS FOR RAJKOT SEWERAGE PROJECT PHASE-III
Sr
No
Pumping
station
APS-1
Mavdi
2
3
Average
flow
inlet
59
Incoming
sewer
I.L.
131.6
Retention time
Volume
30
107
APS-2
Klv.rd
APS-3
TP-6
326
119.3
30
595
49
121.4
30
90
Main
pumping
station
588
116.75
30
1058
Wet
well
size
suction
pit level
6
mt
dia 3.80
mt H
21x8.1
x 3.5
6
mt
dia 3.20
mt H
37 x 13
x 2.20
127.2
115.8
Detail Project Report for Drainage Phase II & III (Part-I) for Rajkot City
117.2
114.55
Length
mt
TP-6
/600
138.67
136.29
400 CI
TP-4
/1238
TP6/729
130.09
127.5
131.81
129.81
STP
basin
122.75
126
FRL
MH No
Designed head
Peak
factor
Designed discharge
840
15
2.25
133
900
PSC
400 CI
1566
16.6
2.25
734
650
17
2.25
110
900
PSC 2
Nos.
1000
15
2.25
1323
88
STATEMENT SHOWING THE DETAILS OF DESIGNED PUMPS AND MOTORS FOR PUMPING STATIONS FOR RAJKOT SEWERAGE PROJECT PHASE-III
Sr
No
Pumping station
1
2
APS-1 Mavdi
APS-2
Kalavad Road
aPS-3 TP-6
Main
pumping
station Raiya.
3
4
Head mt
Operative
Nos
HP
2
4
Pumps
No.pumps
Q
per
standby
pump
in
LPS
1
67
2
183.50
15
16.6
2
4
30
65
2
4
1
2
17
15
2
4
17
105
No.pumps
operative
55
331
Detail Project Report for Drainage Phase II & III (Part-I) for Rajkot City
Motors
standby
Nos.
HP
Design
load HP
Demand
load KV
1
2
30
65
60
260
45.45
196.96
1
2
25
105
50
420
37.88
318.18
89
For large size pumping station, having peak flows more than 1 m3/sec, while provision will
be made for automatic start and stop, system would be capable of being operated manually.
b)
Not more than tow starts and stops per hours will be considered for manual operation of
pumps
c)
the need for one or more pumping mains will be decided from consideration of minimum
velocity requirement and variation of head on the pumps.
d)
Mechanically operated screens for large APS and manually operated screens for small APS
shall be provided before the wet well to prevent clogging of pumps
e)
Forced ventilation system shall be provided for terminal sewage pumping stations.
f)
Sewage level indicator for the wet well (Mechanical type) shall be provided for APS
g)
Depending upon capacity, depth, site conditions and ease in operation and maintenance either
rectangular or circular configuration shall be provided.
h)
Depending upon configuration, either horizontal type or vertical type pumps will be selected.
Consideration is given for submersible pumps for APS No.01 and APS No.03.
Power Distribution
The distribution scheme will be based on the group of estimated loads for each sewage
pumping station. This will comprise HT switch gear, transformer and LT switch gear.
b)
Motors:
Induction motors suitable for 415 V, 50 Hz supply will be provided. They will either be of
squirrel cage, or slip rig type with screen protected drip proof IP 23 construction depending
upon the supply authority's conditions of power supply. Motors will be corrosion protected to
meet environment likely to be encountered at sewage pumping station / treatment plant.
c)
Cabling
HT cables will be XLPE or PILC insulated aluminum conductors with steel armour and
overall PVC sheathing. cables used for power distribution at 415/240 v will be of aluminum
conductor with PVC insulation, steel armour and overall pvc sheathing. xlpe insulated cables
will be used where found beneficial in terms of current carrying capacity vis--vis termination
requirement.
d)
Lighting
The lighting system provided will comprise fluorescent lighting fittings in dry well and other
indoor areas and post top lantern or swan neck type fluorecent fittings for outdoor areas.
Detail Project Report for Drainage Phase II & III (Part-I) for Rajkot City
90
Indoor as well as outdoor lighting when beneficial will be using energy efficient discharge
lamp fittings.
e)
Control
Push button starter will be provided for manual start and stop of motors with specific
concurrence from RMC automatic operation would be considered.
f)
Safety Earthing
Earthing grid comprising mild steel conductors with adequate corrosion factor and suitably
located GI pipes electrodes for safety earthing system will be provided. Conductors exposed
to atmosphere will be galvanized to take care of atmospheric corrosion. whole installation
shall be carried out as per IS:3043.
Pumping Station
A.P.S.01
MAVDI
A.P.S.01
KALAVAD RD.
A.PS.01
GANDHIGRAM
MAIN
PUMPING STN.
RAIYA
Diameter
pipeline
400 MM
of Category
& Length of pipe Flow receiving
class of pipe
in m.
MH
PSC class
840
No.600/TP-8
900 MM
PSC. 10 kg/cm2
1566
No.1238/TP-4
400 MM
PSC class
650
No.729/TP-6
900 MM
P.S.C.
twin LINE or kg/cm2
1300 dia single
line
10 1000
FRL OF STP
STILLING
CHAMBER
********
Detail Project Report for Drainage Phase II & III (Part-I) for Rajkot City
91
Recommendations
R
mm
meennddaattiioonn
Reeccoom
8
8.1 Issues and Performance Assessment
Followings issues are identified for drainage & storm water components
a. Polluted Aji river
b. Low Population coverage
c. Use of natural water drainage for sewerage
d. Use of open gutter and septic tanks due to inadequate drainage net work in merged
area
Performance Assessment of the Drainage System are identified as follow:
Attributes
Component
Treatment
% of Wastewater Treated
Service Coverage % of Pop Covered by
Underground Drainage
% HH area covered by
Sewerage Under ground
drainage
Service Cost and Connection Cost per
Efficiency
Sewerage Connection
Cost Recovery
Indicator Unit
55
%
60
%
55
500
Rs./
Conn.
%
40
Rationale Planning
Availability of Competent Expertise and Technical know-how
Profound experience in the Operations of Systems in the Region
Public support and cooperation
Adequate availability of distribution networks and sewerage systems
Efficient Capital Improvement Planning
WEAKENESS
Lack of public awareness with respect to operations of RMC
Topography of the city results in high capital investments
Recovery of taxes and charges insufficient to support operation & maintenance
Low tax rates/ water charges and Irregular revision of tax rates.
No perennial water sources
Lack of awareness with regards to recycling and reuse of wastewater
OPPORTUN ITY
Private Sector Participation in the delivery of basic services
Capital Market /JnNURM fund is available to undertake urban infrastructure schemes
TRE ATS
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
92
Recommendations
8.3 Recommendation
Following recommendations are recommended as follows:
Technical recommendations
Relying on current practice to deal with domestic wastewater treatment and its related
problems in Rajkot is very complicated and difficult. Several changes have to be made immediately to
provide satisfactory service and to stop further environmental deterioration.
The domestic wastewater problems that require changes are:
Community awareness
Community Awareness
The success of any sanitation project is critically depends upon the effective advocacy of the
project to the people and public awareness. Public awareness plays a very important role in success of
sanitation project and especially where they have to pay for sanitation service. Many sanitation
projects which are well designed but failed due to lack of public awareness and two way
communication between the project designer and community and community events.
Community awareness is still poor and the government is still too dominant to deal with the
problems. Reliance on either the community or the government for solutions to the problem cannot
achieve a desirable environment. Information and campaigns are needed to generate society
consciousness to provide better environments. Transferring the information to people from diverse
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
93
Recommendations
background of the domestic wastewater problem is crucial. Visualizing the damage that will occur
from wastewater problems has to be easy to understand by the entire community. Preventing pollution
is better than solving the problems once it has occurred. Public awareness can be built through
effective two way communication, advocacy of the projects through mass media, advertising and
using people participatory approach in planning and implementation of the project.
First identify the top most stake holders such as political leader, community leader and NGOs
who are working at grass root level.
Before designing a detailed sanitation project a meeting should be held with the top most
stake holders and brief of the sanitation projects should be discussed. And suggestions are
invited.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
94
Recommendations
According to discussion and suggestion made by the top most stake holders, necessary
changes should be made and detail design of the project planning should be carried out.
After designing the project, the aim, goals to be achieved through the sanitation services
should be display for the public.
Also ward wise meeting with the people should be held with the help of the community as
well as political leaders and NGOs. In the meeting general brief of the project including
financial aspects are discussed and suggestions are invited.
After receiving the suggestions, a general meeting should be held to discuss the suggestions
made by the people and necessary changes should be made. Also in general meeting financial
aspects are discussed in detail. Because for any project cost recovery is more important and
also it is very sensitive issue for community as well as politicians if people have to pay for the
service that they will receive.
In this context, alternatives regarding following issue should be given to the community
members
Technology and service level option based on willingness to pay and affordability,
After making appropriate selection implementation of the project should be carried out.
Community events:
Community events are also helpful in creating public awareness. Community events like
environmental day/ sanitation day should be celebrated with involving the community as active
participant. If possible environment and living condition improvement through sanitation
improvement should be coupled with the community festivals. To motivate and increase the
awareness of people regarding environmental and sanitation improvement, competitive situation
should be developed among the different part of the city.
Seminars regarding the environment improvement should be arranged periodically and people
are allow to take participation freely.
Waste water minimization and Water conservation:
Rajkot city always face water scarcity so it is necessary for Rajkot Municipal Corporation to
formulate the strategy that promotes water conservation. Water conservation reduces the volume of
sewage requiring collection and treatment. The benefits of water conservation include reduced cost of
facilities for water supply and wastewater treatment, and reduced impacts in the region from which
surface or ground water supplies are abstracted.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
95
Recommendations
*******
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
96
Cost Estimate
C
Coosstt E
Essttiim
maattee
9
9.1 General
Preliminary cost estimates for various components of proposed Drainage projects are presented
here. The proposed works are divided in phase wise manner and it is scheduled to complete within
seven years. The proposed works are categorized as follows:
Work under Phase-II (Part-I)
1. The work of collective system with house connection in remaining area Phase-II part-I
2. Installation of pumping machinery for additional load
3. Extension of existing sewerage treatment plant by 44.5 MLD
4. Power connection
5. Compound wall & area development at STP
Work under Phase-III (Part-I)
6. Collective system and house connection
7. Construction of STP of capacity 51 MLD disposal work
8. Pumping station with pumping machinery and pumping main
9. Purchase of equipment and Misc work
Rates (SOR) - 2005 the rates are adopted to get abstract sheet. The measurement sheets for each
idea are prepared as per the standard civil engineering practice. The specifications for the works
shall generally conform to the stipulations made in Specifications for Road and Bridge
Works (Itch Edition August 2000) of MORT&H.
For the purpose of analysis the rates of materials, labour and machineries has been
determined as:
1.
The Hire Charges of Plant and Machineries as approved by the MOST&H are given in the
updated data book and the same has been adopted. For the plant & machineries used in the
analysis but not covered in the data book, prevailing market rates have been adopted
wherever considered appropriate.
2.
Updated rates of material, labour and machineries has been further verified with the market
rates and was found to be at par with the market rates.
3.
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
97
Sundries
Financing Expenditure
Cost Estimate
Work Insurance/compensation
Contractors profit has been taken uniformly as 10 %, over the cost of items
2. Development of new STP:
Based on the actual market rate a unit cost of Rs.22 Lakhs /MLD has been adopted for
treatment plants on actual (recently contracted other similar work by Rajkot Municipal
Corporation Electrical & mechanical works at pumping stations, an average cost rate of
Rs.25000/KW has been adopted on basis of experience on similar jobs.
3. SW/RCC/PS pipes :
It has been finalized to use Stoneware Pipes / RCC pipe or PS pipes. The present prevailing
rates of all these pipes are adopted from the rate contract of GWSSB. And the rest of labour
work Rajkot Municipal Corporation current SOR is being followed.
3
4
5
______________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
98
Cost Estimate
Name of Work :Providing, lowering, laying, jointing and testing work for collective system along with house
connection system under Phase-II Part-I work of underground sewerage project of Rajkot in for
remaining areas of old city.
Item
Qty
Item
Rate
Per
Amount
No.
1.0
Excavation for sewer line trenches,
manholes incl. All safety provisions using
site rails etc. including refilling the
trenches & stacking the excavated stuff up
to a lead of 90mt as directed.
1.1
UP TO 1.50mt depth
1.1.1
118993
In all sorts of soil and soft murrum, hard
39.50
M3
47,00,223/murrum, boulders, and macadam road.
1.1.2
11855
In hard rock and soft rock
135.00
M3
16,00,425/1.2
1.50mt to 3.00mt
1.2.1
6156
In all sorts of soil and soft murrum, hard
47.50
M3
2,92,410/murrum, boulders, and macadam road.
1.2.2
8032
In hard rock and soft rock
166.50
M3
13,37,328/1.3
3.00mt to 4.50mt
1.3.1
205
In hard rock and soft rock
199.50
M3
40,897/1.4
4.50mt to 6.00mt
1.4.1
In hard rock and soft rock
252.50
M3
2.0
7274.00 Providing C.C. bedding in 1:3:6 (M 100)
M3
85,10,580/1170.00
using 12 to 20mm machine crushed metal
incl. Consolidation curing etc. complete.
(C-type bedding as per type design)
3.0
Providing, supplying, lowering, laying and
jointing Stoneware pipes in C.M. 1:1 of
following diameters in proper position
grade and alignment as directed by
Engineer-in-charge including labour,
giving necessary testing etc., complete
including cost of jointing materials
including all the taxes, duties, freight,
insurance etc. complete.
3.1
57490
For 100mm dia Stoneware pipes
85.00 RMT
48,86,650/3.2
51300
For 150mm dia Stoneware pipes
130.00 RMT
66,69,000/3.3
2360
For 200mm dia Stoneware pipes
190.00 RMT
4,484400/3.4
1026
For 250mm dia Stoneware pipes
280.00 RMT
2,87,280/3.5
500
For 300mm dia Stoneware pipes
390.00
1,95,000/Providing and constructing house
4.0
connection chambers as per type design in
brick masonry in C.M. 1:4 and inside
plastering in C.M. 1:3 necessary coping in
C.C. M-200 and fixing of RCC frame and
cover (But excluding supply of frame and
covers) over house connection chambers
etc., complete (excluding excavation) as
per stipulation in the type design
complete.
4.1
1126.00 House connection chamber as per type
770.00
Nos.
8.67.020/design (Depth upto 0.60 mt.)
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
99
Item
No.
4.2
Qty
Item
8390.00
5.0
5.1
5.1.1
256
5.2
5.2.1.
1026
5.2.2
103
5.3
5.3.1.
646.00
5.3.2
462.00
5.4
5.4.1
5.00
5.4.2
6.0
6.1
Cost Estimate
102
Rate
Per
Amount
1000.00
Nos.
83,90,000/-
1550.00
No.s
3,96,800/-
2640.00
Nos.
27,08,640/-
1632.00
RMT
1,68,096/-
4960.00
Nos.
32,04,160/-
2604.00
RMT
12,03,048/-
15456.00
Nos.
77,280/-
4068.00
RMT
20,340/-
708.00
Nos.
72,216/-
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
100
Item
No.
6.2
102
7.0
47311
8.0
9515
9.0
1282
10.0
556
11.0
11.1
Qty
11.2
49248.0
0
5130.00
12.0
7797.00
Cost Estimate
Item
Rate
Per
Amount
552.00
RMT
56,304/-
33.00
M3
15,61,263/-
600.00
1 Pair
57,09,000/-
690.00
One
pair
8,84,580/-
900.00
One
pair
5,00,400/-
18.00
Sq. Mt
8,86,464/-
26.00
Sq. Mt
1,33,380/-
20.00
Nos.
1,55,940/-
Total
Rs.5,99,99,124/Say Rs.6,00,00,000/(Rupees Six crores only)
______________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
101
Cost Estimate
______________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
102
Cost Estimate
Name of work:-Construction of pre-cast RCC compound wall around Sewage Treatment Plant at
Madhapar.
:: A B S T R A C T FOR ESTIMATE :: Stage-II Part-I
Item
Qty.
Short Description of
Rate
Unit
Amount
S.O.R.
No.
work.
In Figure
Rs.
Ps.
Number
1
2500.00
Rmt
145.00
Cu. Mt
145.00
Cu. Mt
2500.00
Rmt
150.00
Cu. Mt
456.00
Rmt
11,40,000/- MR
39.50
Cu mt
1450.00
Cu mt
2,10,250/- 62
74.00
Rmt
1,85,000/- MR
55.00
Cu mt
Total
Say
5727-50 23+28
2
8250/- 702
14,99,227-50
15,00,000-00
(Rupees Fifteen lacs only)
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
103
Cost Estimate
Qty
Description
Rate
Unit
2500000/- 1 MLD
125/- sq mt
Amount
11,12,50,000/-
7,50,000/11,20,00,000/-
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
104
Cost Estimate
3.
Description
Rs. in Lakhs
1860.76
Collective System
a. TP scheme 1 (Part I)
158.87
504.00
scheme- 4
c. TP scheme 6
227.40
d. TP scheme 2
118.61
e. TP scheme 3
185.72
f. TP scheme 5
179.14
g. TP scheme 7
97.42
h. TP scheme 8
258.00
i. Slums (Mavdi)
131.60
1404.59
House Connections
a. TP scheme 1 (Part I)
163.16
303.45
scheme- 4
c. TP scheme 6
162.65
d. TP scheme 2
131.65
e. TP scheme 3
137.76
f. TP scheme 5
111.57
g. TP scheme 7
61.89
h. TP scheme 8
233.65
i. Slums (Mavdi)
98.81
293.06
18.32
142.51
c. APS 3 (Gandhigram)
21.09
d. MPS (Raiya )
4.
111.14
139.60
11.77
61.38
c. APS 3 (Gandhigram)
9.32
d. MPS (Raiya )
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
57.13
105
Sr. No.
5.
Description
Cost Estimate
Rs. in Lakhs
245.25
22.50
78.00
c. APS 3 (Gandhigram)
18.75
126.00
d. MPS (Raiya )
6.
1328.81
1275.00
b. Outfall pipelines
Total
Add 5% Contingency charge
TOTAL
Say Rs.
53.81
5272.07
263.60
5535.67
5536
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
106
Cost Estimate
Qty
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
2
22970
9850
5420
5420
1820
70
1160
3
3.1.1
3.1.2
3.1.3
3.1.4
18900
930
290
390
3.1.5
70
3.1.6
210
3.1.7
260
3.1.8
290
Item
Excavation for sewer line trenches,
manholes including all safety provisions
using side rails etc. including refilling
the trenches & stacking the excavated
stuff up to a lead of 90 mt. as directed.
Up to 1.50 mt. depth
In all sorts of soil & soft murrum, hard
murrum, boulders, & macadam roads.
in hard rock & soft rock
1.50 to 3.00 mt. depth
in soft soil & hard murrum
in hard rock & soft rock
3.00 to 4.50 mt. depth
in hard rock & soft rock
4.50 to 6.00 mt. depth
in hard rock & soft rock
Providing c.c. bedding in 1:3:6 (M100)
using 12 to 25 mm machine crushed
metal incl. consolidation, curing, etc
complete. ( c type bedding as per type
design)
lowering, laying and jointing stone ware
pipes & RCC pipes in CM 1:1 of
following dia. In proper position grade
& alignment as directed by engineer in
charge incl. conveyance from stores to
site of work, labour, giving hydraulic
testing as per IS code, etc. complete
incl. cost of jointing materials.
for 150 mm dia SWG pipes
for 200 mm dia SWG pipes
for 250 mm dia SWG pipes
for 300 mm dia RCC & NP-3 class
pipes
for 350 mm dia RCC & NP-3 class
pipes
for 400 mm dia RCC & NP-3 class
pipes
for 450 mm dia RCC & NP-3 class
pipes
for 500 mm dia RCC & NP-3 class
pipes
Rate
Per
Amount
SOR
No.
39.5
135
M3
M3
907315
1329750
23+28/2
33+38/2
47.5
166.5
M3
M3
257450
902430
24+29/2
34+39/2
199.5
M3
363090
35+40/2
252.5
M3
17675
36+41/2
1170
M3
1357200
616/2
130
190
280
RMT
RMT
RMT
2457000
176700
81200
855/3
855/4
855/6
256
RMT
99840
906
602
RMT
42140
918
638
RMT
133980
919
707
RMT
183820
920
853
RMT
247370
921
1133
RMT
135960
921-A
3.1.9
for 600 mm dia RCC & NP-3 class
120 pipes
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
107
No.
Qty
Cost Estimate
Item
4.1
4.1.1
411
4.1.2
60
4.2
4.2.1
302
4.2.2
260
4.3
4.3.1
4
4.3.2
1
4.4
4.4.1
3
4.4.2
6
Rate
Per
Amount
SOR
No.
2640
NOS.
1085040
608/1
1632
RMT
97920
608/2
4960
NOS.
1497920
608/3
2604
RMT
677040
608/4
15456
NOS.
61824
608/5
4068
RMT
4068
608/6
15240
NOS.
45720
610/1
4596
RMT
27576
610/2
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
108
No.
Qty
5530
6
543
7
180
9
9.1
9.2
10
10.1
10.2
7822
7822
23702
15643
Cost Estimate
Item
Removing the surplus earth after
refilling the trenches as directed with in
the Municipal Corporation limits incl.
spreading etc. complete
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 10 T,MD
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 20 T,MD
Breaking of pavement surface
Conventional Asphalt surface
Paver Asphalt surface
Re- instating the road surface
WBM
Asphalt
Rate
Per
Amount
182490
SOR
No.
33
M3
712
690
1
PAIR
374670 659+660
900
1
PAIR
162000 666+668
18
26
M2
M2
140796
203372
43
44
55
85
M2
M2
1303610
1329655
15886621
MR
MR
Say. Rs15887000
Only Rupees One Cores fifty eight lakhs eighty seven thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
109
Cost Estimate
BILL OF QUANTITIES FOR COLLECTIVE SYSTEM OF T.P. SCHEME NO. 1 part 2 T P No.4
No.
Qty
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
51520
22080
15540
15540
9840
1180
2
3880
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
3.1.9
3.1.10
Item
Excavation for sewer line trenches,
manholes including all safety
provisions using side rails etc.
including refilling the trenches &
stacking the excavated stuff up to a
lead of 90 mt. as directed.
Up to 1.50 mt. depth
In all sorts of soil & soft murrum,
hard murrum, boulders, & macadam
roads.
in hard rock & soft rock
1.50 to 3.00 mt. depth
in soft soil & hard murrum
in hard rock & soft rock
3.00 to 4.50 mt. depth
in hard rock & soft rock
4.50 to 6.00 mt. depth
in hard rock & soft rock
Providing c.c. bedding in 1:3:6
(M100) using 12 to 25 mm machine
crushed metal incl. consolidation,
curing, etc complete. ( c type
bedding as per type design)
lowering, laying and jointing stone
ware pipes & RCC pipes in CM 1:1
of following dia. In proper position
grade & alignment as directed by
engineer in charge incl. conveyance
from stores to site of work, labour,
giving hydraulic testing as per IS
code, etc. complete incl. cost of
jointing materials.
Rate
Per
39.5
135
M3
M3
2035040
2980800
23+28/2
33+38/2
47.5
166.5
M3
M3
738150
2587410
24+29/2
34+39/2
199.5
M3
1963080
35+40/2
252.5
M3
297950
36+41/2
1170
M3
4539600
616/2
130
190
280
RMT
RMT
RMT
4374500
355300
198800
855/3
855/4
855/6
256
RMT
194560
906
602
RMT
860860
918
638
RMT
325380
919
707
RMT
49490
920
1133
RMT
736450
921-A
1654
RMT
1438980
923
2495
RMT
3318350
925
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Amount
SOR
110
No.
3.8
3.8
Qty
1920
360
4.1
4.1.1
728
4.1.2
90
4.2
4.2.1
579
4.2.2
480
4.3
4.3.1
45
4.3.2
20
4.4
Item
Rate
for 1200 mm dia RCC & NP-3 class
pipes
3082
for 1600 mm dia RCC & NP-3 class
pipes
4740
providing & constructing sewer
manholes, scraper manholes & unit
house connection chamber, as per
the type design in brick masonry in
CM 1:3 & out side plastering CM
1:3 necessary coping in RCC M200,
fixing CI steps & fixing manhole
frame & covers. (but excluding
supply of manhole frame &
covers)over manholes & house
connections, chambers & fixing
manhole covers (but excluding
supply of manhole covers) over
scraper manholes etc. complete,
providing & fixing safety chain
wherever necessary as per the
stipulation in the type design
Manhole type "A" circular type
having inside dia. of 1200 mm for
depth upto 1.50 mt. for 150 mm to
500 mm dia sewer.
Manhole type "A" as above but
upto 1.00 mt. depth.
2640
Extra depth beyond 1.00 mt. but
upto 1.50 mt. depth for "A" type
manhole above.
1632
manhole type "B" circular type
having inside dia of minimum 1500
mm & for depth from 1.5 mt to 4.00
mt. (for 150 mm to 600 mm dia
sewer)
Manhole type "B" as above but upto
1.50 mt. depth.
4960
Extra depth beyond 1.50 mt. but
upto 4.00 mt. depth for "B" type
manhole above.
2604
manhole type "C" circular type
having inside dia of minimum 1500
mm & for depth from 4.0 mt to 6.00
mt. (for 150 mm to 1800 mm dia)
Manhole type "C" as above but upto
4.0 mt. depth.
15456
Extra depth beyond 4.00 mt. but
upto 6.00 mt. depth for "C" type
manhole above.
4068
Scraper manhole pipe "SI"
rectangular type for 600 mm dia to
1200 mm dia sewer pipes & for
depth 2.5mt. To 9.0 mt.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Cost Estimate
Per
Amount
SOR
RMT
5917440
927
RMT
1706400
929
NOS.
1921920
608/1
RMT
146880
608/2
NOS.
2871840
608/3
RMT
1249920
608/4
NOS.
695520
608/5
RMT
81360
608/6
111
No.
4.4.1
4.4.2
7
9
9.1
9.2
10
10.1
10.2
Qty
Cost Estimate
Item
Rate
Per
Amount
15240
NOS.
335280
610/1
4596
RMT
137880
610/2
33
M3
640860
712
690
1 PAIR
652740 659+660
900
1 PAIR
365400 666+668
18
26
M2
M2
55
85
M2
M2
315454
455656
SOR
No.
43
44
2920871
MR
2979288
MR
50389408.63
Rs. 50400000
Only Rupees Five Crore four lakhs
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
112
No.
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
1.5
1.5.1
3.1.1
3.1.2
3.1.4
3.1.5
3.1.6
3.1.8
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
113
No.
Qty
Item
4.1
4.1.1
492
4.1.2
70
4.2
4.2.1
299
4.2.2
250
4.3
4.3.1
Cost Estimate
56
4.3.2
40
6
10
7
Rate
Per
2640
NOS.
1298880
608/1
1632
RMT
114240
608/2
4960
NOS.
1483040
608/3
2604
RMT
651000
608/4
15456
NOS.
865536
608/5
4068
RMT
162720
608/6
22764
NOS.
136584
608/7
2592
RMT
25920
608/8
15240
NOS.
106680
610/1
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Amount
SOR
No.
114
No.
Qty
20
5
7550
6
645
7
215
9
9.1
9.2
10
10.1
10.2
10335
10335
31318
20670
Cost Estimate
Item
Extra depth beyond 4.00 mt. but upto
6.00 mt. depth for "S1" type manhole
above.
Removing the surplus earth after
refilling the trenches as directed with in
the Municipal Corporation limits incl.
spreading etc. complete
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 10 T,MD
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 20 T,MD
Breaking of pavement surface
Conventional Asphalt surface
Paver Asphalt surface
Re- instating the road surface
WBM
Asphalt
Rate
Per
Amount
SOR
No.
4596
RMT
91920
610/2
33
M3
249150
712
690
1 PAIR
445050 659+660
900
1 PAIR
193500 666+668
18
26
M2
M2
186030
268710
55
85
M2
M2
1722505
1756955
43
44
MR
MR
22739670
Rs. 22740000
Only Rupees Two Crore Twenty Seven Lakhs Forty Thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
115
No.
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
18630
7990
3930
3930
1140
10
2
900
3.1.1
3.1.2
3.1.3
3.1.4
3.1.6
Cost Estimate
16510
470
320
450
40
39.5
135
M3
M3
735885
1078650
23+28/2
33+38/2
47.5
166.5
M3
M3
186675
654345
24+29/2
34+39/2
199.5
M3
227430
35+40/2
252.5
M3
2525
36+41/2
1170
M3
1053000
616/2
130
190
280
RMT
RMT
RMT
2146300
89300
89600
855/3
855/4
855/6
256
RMT
115200
906
638
RMT
25520
919
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
116
No.
Qty
Item
4.1
4.1.1
345
4.1.2
50
4.2
4.2.1
4.2.2
231
91
4.3
4.3.1
4.3.2
1
4.4
5
3710
6
437
7
145
9
9.1
9.2
10
10.1
10.2
Cost Estimate
6382
6382
19340
12764
Rate
Per
Amount
SOR
2640
NOS.
910800
608/1
1632
RMT
81600
608/2
4960
NOS.
1145760
608/3
2604
RMT
236964
608/4
15456
NOS.
92736
608/5
4068
RMT
4068
608/6
122430
712
33
M3
690
1 PAIR
301530 659+660
900
1 PAIR
130500 666+668
18
26
M2
M2
114876
165932
55
85
M2
M2
1063700
1084940
43
44
MR
MR
11860266
Say Rs..11861000
Only Rupees One Crore Eighteen Lakhs Sixty One Thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
117
Cost Estimate
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
21200
9080
6460
6460
6160
1540
2
1490
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.9
3.1.10
16200
560
280
190
890
39.5
135
M3
M3
837400
1225800
23+28/2
33+38/2
47.5
166.5
M3
M3
306850
1075590
24+29/2
34+39/2
199.5
M3
1228920
35+40/2
252.5
M3
388850
36+41/2
1170
M3
1743300
616/2
130
190
280
RMT
RMT
RMT
2106000
106400
78400
855/3
855/4
855/6
256
RMT
48640
906
602
RMT
535780
918
1654
RMT
760840
923
1945
RMT
875250
923
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
118
No.
Qty
Item
4.1
4.1.1
326
4.1.2
50
4.2
4.2.1
213
4.2.2
190
4.3
4.3.1
65
4.3.2
50
4.4
Cost Estimate
Rate
Per
Amount
SOR
2640
NOS.
860640
608/1
1632
RMT
81600
608/2
4960
NOS.
1056480
608/3
2604
RMT
494760
608/4
15456
NOS.
1004640
608/5
4068
RMT
203400
608/6
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
119
No.
4.4.1
4.4.2
7
9
9.1
9.2
10
10.1
10.2
Qty
Cost Estimate
Item
Rate
Per
Amount
SOR
15240
NOS.
76200
610/1
4596
RMT
68940
610/2
33
M3
222750
712
690
1 PAIR
315330 659+660
900
1 PAIR
136800 666+668
18
26
M2
M2
129159
186562
55
85
M2
M2
1195920
1220345
43
44
MR
MR
18571546
Rs.. 18572000
Only Rupees One Crore Eighty Five Lakhs Seventy Two Thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
120
Cost Estimate
No.
Qty
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
19220
8240
6670
6670
4300
140
2
1630
3.1.1
3.1.2
3.1.3
3.1.4
3.1.6
3.1.7
11920
420
450
1750
330
400
3.1.9
160
3.1.120
3.1.13
1160
40
Item
Excavation for sewer line trenches,
manholes including all safety
provisions using side rails etc.
including refilling the trenches &
stacking the excavated stuff up to a
lead of 90 mt. as directed.
Up to 1.50 mt. depth
In all sorts of soil & soft murrum,
hard murrum, boulders, & macadam
roads.
in hard rock & soft rock
1.50 to 3.00 mt. depth
in soft soil & hard murrum
in hard rock & soft rock
3.00 to 4.50 mt. depth
in hard rock & soft rock
4.50 to 6.00 mt. depth
in hard rock & soft rock
Providing c.c. bedding in 1:3:6
(M100) using 12 to 25 mm machine
crushed metal incl. consolidation,
curing, etc complete. ( c type
bedding as per type design)
lowering, laying and jointing stone
ware pipes & RCC pipes in CM 1:1
of following dia. In proper position
grade & alignment as directed by
engineer in charge incl. conveyance
from stores to site of work, labour,
giving hydraulic testing as per IS
code, etc. complete incl. cost of
jointing materials.
for 150 mm dia SWG pipes
for 200 mm dia SWG pipes
for 250 mm dia SWG pipes
for 300 mm dia RCC & NP-3 class
pipes
for 400 mm dia RCC & NP-3 class
pipes
for 450 mm dia RCC & NP-3 class
pipes
for 600 mm dia RCC & NP-3 class
pipes
for 1000 mm dia RCC & NP-3 class
pipes
for 1100 mm dia RCC & NP-3 class
pipes
Rate
Per
Amount
SOR
39.5
135
M3
M3
759190
1112400
23+28/2
33+38/2
47.5
166.5
M3
M3
316825
1110555
24+29/2
34+39/2
199.5
M3
857850
35+40/2
252.5
M3
35350
36+41/2
1170
M3
1907100
616/2
130
190
280
RMT
RMT
RMT
1549600
79800
126000
855/3
855/4
855/6
256
RMT
448000
906
638
RMT
210540
919
707
RMT
282800
920
1133
RMT
181280
921-A
2495
RMT
2894200
925
2718
RMT
108720
927
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
121
No.
Qty
Item
4.1
4.1.1
240
4.1.2
30
4.2
4.2.1
220
4.2.2
220
4.3
4.3.1
22
4.3.2
10
4.4
4.4.1
Cost Estimate
10
4.4.2
2
Rate
Per
Amount
SOR
2640
NOS.
633600
608/1
1632
RMT
48960
608/2
4960
NOS.
1091200
608/3
2604
RMT
572880
608/4
15456
NOS.
340032
608/5
4068
RMT
40680
608/6
15240
NOS.
152400
610/1
4596
RMT
9192
610/2
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
122
No.
Qty
Item
Rate
Per
Amount
SOR
6920
33
M3
228360
712
369
690
1 PAIR
254610
659+66
0
900
1 PAIR
110700
666+66
8
18
26
M2
M2
115884
167388
43
44
55
85
M2
M2
1072940
1094375
7
123
9
9.1
9.2
10
10.1
10.2
Cost Estimate
6438
6438
19508
12875
MR
MR
17913411
Rs..17914000
Rupees One Crore Seventy Nine Lakhs Fourteen Thousand Only.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
123
No.
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
1.5
3.1.1
3.1.2
3.1.4
3.1.8
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
124
No.
Qty
Item
4.1
4.1.1
131
4.1.2
21
4.2
4.2.1
99
4.2.2
100
4.3
4.3.1
Cost Estimate
40
4.3.2
20
6
10
Rate
Per
Amount
SOR
2640
NOS.
345840 608/1
1632
RMT
34272 608/2
4960 NOS.
491040 608/3
2604
RMT
260400 608/4
15456 NOS.
618240 608/5
4068
RMT
81360 608/6
15240
NOS.
91440 610/1
4596
RMT
45960 610/2
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
125
No.
Qty
Item
5
3550
6
206
7
70
9
9.1
9.2
10
10.1
10.2
Cost Estimate
3421
3421
10366
6841
Rate
33
Per
Amount
SOR
M3
117150
712
142140
659+
660
63000
666+
668
61572
88938
43
44
1
690 PAIR
1
900 PAIR
18
26
M2
M2
55
85
M2
M2
570114
MR
581516
MR
9741731
Rs. 9742000
Rupees Ninety Seven Lakhs Forty Two Thousand only/.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
126
Cost Estimate
1.1
1.1.1
1.1.2
1.2
1.2.1
1.2.2
1.3
1.3.1
1.4
1.4.1
33400
23170
7160
7160
4320
550
2
1820
3.1.1
3.1.2
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
28690
1070
230
210
1030
260
690
39.5
135
M3
M3
1319300
3127950
23+28/2
33+38/2
47.5
166.5
M3
M3
340100
1192140
24+29/2
34+39/2
199.5
M3
861840
35+40/2
252.5
M3
138875
36+41/2
1170
M3
2129400
616/2
130
190
RMT
RMT
3729700
203300
855/3
855/4
256
RMT
58880
906
602
RMT
126420
918
638
RMT
657140
919
707
RMT
183820
920
1133
RMT
781770
921-A
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
127
No.
Qty
Item
4.1
4.1.1
632
4.1.2
70
4.2
4.2.1
361
4.2.2
260
4.3
4.3.1
Cost Estimate
46
4.3.2
30
5
19420
6
759
Rate
Per
Amount
SOR
2640
NOS.
1668480 608/1
1632
RMT
114240 608/2
4960 NOS.
1790560 608/3
2604
RMT
677040 608/4
15456 NOS.
710976 608/5
4068
33
RMT
M3
1
690 PAIR
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
122040 608/6
640860
712
523710
659+
660
128
No.
Qty
7
260
9
9.1
9.2
10
10.1
10.2
11731
11731
35550
23463
Cost Estimate
Item
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 20 T,MD
Breaking of pavement surface
Conventional Asphalt surface
Paver Asphalt surface
Re- instating the road surface
WBM
Asphalt
Rate
Per
1
900 PAIR
18
26
M2
M2
55
85
M2
M2
Amount
SOR
234000
666+
668
211158
305006
43
44
1955250
MR
1994355
MR
25798310
Say..Rs..25800000
Rupees Two Crore Fifty Eight Lakhs.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
129
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
130
No.
3.1.8
Qty
260
4.1
4.1.1
262
4.1.2
30
4.2
4.2.1
138
4.2.2
130
4.3
4.3.1
4.3.2
32
30
9
10
Item
for 600 mm dia RCC & NP-3 class
pipes
providing & constructing sewer
manholes, scraper manholes & unit
house connection chamber, as per the
type design in brick masonry in CM
1:3 & out side plastering CM 1:3
necessary coping in RCC M200,
fixing CI steps & fixing manhole
frame & covers. (but excluding
supply of manhole frame &
covers)over manholes & house
connections, chambers & fixing
manhole covers (but excluding supply
of manhole covers) over scraper
manholes etc. complete, providing &
fixing safety chain wherever
necessary as per the stipulation in the
type design complete (excl.
excavation)
Manhole type "A" circular type
having inside dia. of 1200 mm for
depth upto 1.50 mt. for 150 mm to
500 mm dia sewer.
Manhole type "A" as above but upto
1.00 mt. depth.
Extra depth beyond 1.00 mt. but upto
1.50 mt. depth for "A" type manhole
above.
manhole type "B" circular type
having inside dia of minimum 1500
mm & for depth from 1.5 mt to 4.00
mt. (for 150 mm to 600 mm dia
sewer)
Manhole type "B" as above but upto
1.50 mt. depth.
Extra depth beyond 1.50 mt. but upto
4.00 mt. depth for "B" type manhole
above.
manhole type "C" circular type
having inside dia of minimum 1500
mm & for depth from 4.0 mt to 6.00
mt. (for 150 mm to 1800 mm dia
Manhole type "C" as above but upto
4.0 mt. depth.
Extra depth beyond 4.00 mt. but upto
6.00 mt. depth for "C" type manhole
Manhole type "D1" as above but upto
6.0 mt. depth.
Extra depth beyond 6.00 mt. but upto
10.00 mt. depth for "D1" type
manhole above.
Cost Estimate
Rate
Per
Amount
SOR
1133
RMT
294580
921-A
2640
NOS.
691680
608/1
1632
RMT
48960
608/2
4960
NOS.
684480
608/3
2604
RMT
338520
608/4
15456
NOS.
494592
608/5
4068
RMT
122040
608/6
22764
NOS.
204876
608/7
2592
RMT
25920
608/8
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
131
No.
Qty
5
12460
6
331
7
110
9
9.1
9.2
10
10.1
10.2
5239
5239
15874
10477
Cost Estimate
Item
Removing the surplus earth after
refilling the trenches as directed with
in the Municipal Corporation limits
incl. spreading etc. complete
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 10 TMD
Providing, supplying & fixing the
manhole frames & covers in CC 1:2:4
incl. finishing etc. complete. 20 TMD
Breaking of pavement surface
Conventional Asphalt surface
Paver Asphalt surface
Re- instating the road surface
WBM
Asphalt
Rate
Per
Amount
SOR
33
M3
411180
712
690
1 PAIR
228390
659+66
0
900
1 PAIR
99000
666+66
8
18
26
M2
M2
94293
136201
43
44
55
85
M2
M2
873082
890543
MR
MR
13159627
Say..Rs13160000
Rupees One Crore Thirty One Lakhs Sixty Thousand Only.
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
132
Cost Estimate
22030
36150
1930
4
4.1
3254
4.2
5
6
7
8
9
10
11
39.5
M3
870185
23+28/2
RMT
3072750
855/2
1170
M3
2258100
616/2
770
NOS.
2505195
614
1000
NOS.
1084500
612
600
18
20
1 PAIR
M2
NOS.
2602800
495540
57840
657+659
43
592
33
M3
450780
712
55
85
M2
M2
1514150
1404030
85
MR
MR
16315870
Say Rs. 16316000
Only Rupees One Crore Sixty Three lakhs Sixteen thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
133
Cost Estimate
BILL OF QUANTITIES OF HOUSE CONNECTION WORK FOR T.P. SCHEME NO. 1 Part 2 & T.P. 4
No.
Qty
41190
3600
67600
4
4.1
6084
4.2
2028
5
6
7
8112
51480
5408
8
9
10
11
20850
51480
30888
Item
Excavation in all soils, soft & hard
murrum etc. complete with refilling
the trenches.
Providing c.c. bedding in 1:3:6
(M100) using 12 to 25 mm machine
crushed metal incl. consolidation,
curing, etc complete. ( c type
bedding as per type design)
Providing, supplying, lowering &
jointing of 100 mm dia. Salt glazzed
stone ware pipe class "A" incl.
jointing material.
House connection chamber as per
type design
Up to 0.60 mt. depth
Above 0.60 mt. depth
Providing, supplying & fixing precast RCC frame & cover 5 MT
capacity.
Breaking of pavement surface
Making holes in manholes
Removing surplus earth from the site
etc. complete as directed
Re-instating the road surface
WBM
Asphalt
Rate
Per
Amount
SOR
No.
39.5
M3
1627005
23+28/2
1170
M3
4212000
616/2
85
RMT
5746000
855/2
770
NOS.
4684680
614
1000
NOS.
2028000
612
600
18
20
1
PAIR
M2
NOS.
4867200
926640
108160
657+659
43
592
33
M3
688050
712
55
85
M2
M2
2831400
2625480
MR
MR
30344615
Rs. 30345000
Only Rupees Three Crore Three Lakhs Forty five thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
134
Cost Estimate
5
6
7
8
9
10
11
1000
NOS.
1290000
600
18
20
1 PAIR
M2
NOS.
33
M3
399960
55
85
M2
M2
1801250
1670250
612
3096000 657+659
589500
43
68800
592
712
MR
MR
19264860
Rs19265000
Only Rupees One crore ninty two lakhs Sixty five thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
135
Cost Estimate
No.
4.2
5
6
7
8
9
10
11
1000 NOS.
1
600 PAIR
18 M2
20 NOS.
873000
612
2095200 657+659
398880
43
46560
592
33
M3
397650
55
85
M2
M2
1218800
1130160
712
MR
MR
13164215
Say Rs.13165000
Only Rupees One crore Thirty One lakhs Sixty Five thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
136
No.
3
4
4.1
4.2
5
6
7
8
9
10
11
Cost Estimate
1000
600
18
20
NOS.
1
PAIR
M2
NOS.
913500
33
M3
407550
55
85
M2
M2
1275450
1182690
612
2192400 657+659
417420
43
48720
592
712
MR
MR
13775990
Rs13776000
Rupees One Crore Thirty Seven Lakhs Seventy Six Thousand Only/.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
137
Cost Estimate
1000
600
18
20
NOS.
1
PAIR
M2
NOS.
738000
33
M3
363660
55
85
M2
M2
1030700
955740
612
1771200 657+659
337320
43
39360
592
712
MR
MR
11156565
Say Rs.11157000
Rupees One Crore Eleven Lakhs Fifty Seven Thousand Only/-
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
138
Cost Estimate
5
6
7
8
9
10
11
1000
NOS.
414000
600
18
20
1 PAIR
M2
NOS.
33
M3
128700
55
85
M2
M2
578050
536010
612
993600 657+659
189180
43
22080
592
712
MR
MR
6188955
Say Rs. 6189000
Only Rupees Sixty one lakhs eighty nine thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
139
Cost Estimate
5
6
7
8
9
10
11
1000
NOS.
1558500
600
18
20
1 PAIR
M2
NOS.
33
M3
569910
55
85
M2
M2
2175800
2017560
612
3740400 657+659
712080
43
83120
592
712
MR
MR
23364330
SayRs23365000
Only Rupees Two crore thirty six lakhs five thousand.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
140
No.
Qty
13440
22050
1175
4
4.1
1985
4.2
5
6
7
8
9
10
11
Cost Estimate
39.5
SOR
No.
M3
530880
23+28/2
RMT
1874250
855/2
1170
M3
1374750
616/2
770
NOS.
1528065
614
1000
NOS.
661500
612
600
18
20
1 PAIR
M2
NOS.
33
M3
205260
55
85
M2
M2
924000
856800
85
1587600 657+659
302400
43
35280
592
712
MR
MR
9880785
Say Rs.9881000
Rupees Ninety Eight Lakhs Eighty One thousand Only/___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
141
Cost Estimate
Quantity
Rate
Per
Amount
SOR
No.
EXCAVATION
0.00 to 1.5 mt depth
39.50
cum
3160.00
135.00
210.00
240.00
295.00
337.00
421.25
526.56
1230.00
cum
cum
cum
cum
cum
cum
cum
cum
4050.00
15750.00
18000.00
22125.00
25275.00
31593.75
10531.20
13530.00
23+28/
2
33+38/
2
39
40
11
42
42+55
12+55
278
1059.00
cum
10590.00
114
2358.00
cum
4716.00
294
60.00
1059.00
cum
cum
7800.00
26475.00
103
114
1890.00
cum
4725.00
300
2222.00
2358.00
2660.00
2422.00
2440.00
59.00
cum
cum
cum
cum
cum
Sq. Mt
17220.50
3772.80
3857.00
14410.90
3416.00
11800.00
291
294
295
292
293
157
42.00
Sq. Mt
6762.00
146
12.25
Sq. Mt
1972.25
168
17.00
Sq. Mt
3400.00
170
810.00
Sq. Mt
12150.00
327
80.00
30.00
75.00
75.00
75.00
75.00
75.00
20.00
11.00
3
10.00
4
2.00
5
6
Description
130.00
25.00
7
2.50
8
9
10
11
12
13
7.75
1.60
1.45
5.95
1.40
200.00
14
161.00
15
16
161.00
200.00
17
15.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
142
Sr.
No.
Cost Estimate
Description
Rate
Per
Amount
Quantity
18
SOR
No.
20.00
770.00
Sq. Mt
15400.00
353
30.00
40.00
240.00
159.00
Sq. Mt
Sq. mt
7200.00
6360.00
178.00
rmt
4450.00
191
202
gwssb
17/160
22.00
138.00
No
No
176.00
4140.00
1091
39.80
Kg
7960.00
2319.00
cum
46380.00
4000.00
2868.00
3003.00
77.00
cum
cum
Sq. mt
Sq. mt
284000.00
11902.20
8258.25
2564.10
823
gwssb
d411+5
do 1v1
291
294
208
59.00
21.00
2000.00
rmt
No
No
18585.00
2436.00
2000.00
157
gwssb
MR
2450.00
No
2450.00
50.00
3600.00
Kg
Qtl
75000.00
540000.00
gwssb
WWB
302
gwssb
--
100000.00
1416343.95
19
20
21
25.00
22
23
24
8.00
30.00
200.00
25
20.00
26
27
28
29
30
31
32
33
71.00
4.15
2.75
33.30
315.00
116.00
1.00
1.00
34
35
1500.00
150.00
36
--
LS
Say
Rs.
MR
1416400.00
415400.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
1831800.00
143
Cost Estimate
Quantity
205.00
11.50
61.50
34.00
2.00
15.00
22.50
7
8
9
10
11
12
7.50
2.00
1.10
9.00
84.00
13
75.00
14
15
11.00
51.00
455.00
16
17
462.00
18
19
390.00
825.00
20
21
22
23
24
142
1.40
1.00
1.00
34.00
25
300.00
26
19.00
27
33.00
Description
Excavation for foundation in soft and
hard murrum with average rate and
depth up to 1.50 mt. with clearing the
site by shifting & spreading
excavated stuff up to 90 mt. lead, as
per instruction.
~~Do~~ In soft & hard rock (Ave.)
~~Do~~ 1.51 to 3.0mt. In soft & hard
rock (Ave.)
~~Do~~ 3.01 to 4.50mt. In soft &
hard rock (Ave.)
Supplying & Fixing R.C.C. pre-cast
Frame & cover (Pair) 20 ton cap.
Supplying, lowering laying & jointing
RCC pipe 600mm Dia NP_3 Class
Supplying, lowering laying & jointing
RCC pipe 600mm Dia NP_2 Class
C.C. Bedding Type C in 1:3:6
Constructing Manhole Type "C"
~~Do~~ Extra depth in Type "C"
P.C.C. 1:4:8 in foundation
Foundation masonry with rubble
cement mortal in 1:6 cement :sand
proportion
Rubble plinth masonry work in C.M.
1:6 & with cement pointing 1:3
C.C. Coping work 1:2:4
Brick masonry with C.M. 1:6
Sand face cement plaster 20mm
thick In C.M. 1:3 ( Double Coat)
Water Proof cement paint two coat
or base coat
Steel work as per instruction
TOR steel work comp. for R.C.C.
work
Patta work on plaster 10cm wide
C.C. in 1:2:4
C.C. in 1:2:4 for beam
C.C. in 1:2:4 for chajja
Fixing steel angle on proper
alignment
Supplying & Fixing Barbed wire in
Fencing
Oil paint work for Door, Windows,
Grills etc. with two coats
Cement plaster Rough cast in C.m.
1:3
Rate
Per
Amount
SOR
No.
39.50
Cu. Mt.
8097.50
135.00
Cu. Mt.
1552.50
166.50
Cu. Mt.
10239.75
199.50
Cu. Mt.
6783.00
900.00
Pair
1800.00
23+28/
2
33+38/
2
34+39/
2
35+40/
2
666+6
68
1133.00
532.00
Rmt.
Rmt.
16995.00
11970.00
921
913
1170.00
15456.00
4068.00
922.00
494.00
Cu. Mt.
Nos.
Rmt.
Cu. Mt.
Cu. Mt.
8775.00
30912.00
4474.80
8298.00
41496.00
616/2
608/5
608/6
58
64
536.00
Cu. Mt.
40200.00
70
1459.00
1059.00
Cu. Mt.
Cu. Mt.
16049.00
54009.00
136
114
57.00
Sq. Mt.
25935.00
150
17.00
39.80
Sq. Mt.
Kg.
7854.00
15522.00
170
823
33.00
19
1500.00
2358.00
2660.00
Kg.
Rmt.
Cu. Mt.
Cu. Mt.
Cu. Mt.
27225.00
2698.00
2100.00
2358.00
2660.00
302
162
281
294
295
8.00
Nos.
272.00
540
7.00
Rmt.
2100.00
538
23.00
Sq. Mt.
437.00
473
37.00
Sq. Mt.
1221.00
352033.50
147
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
144
Cost Estimate
Name of Work : Design, Construction, testing and commissioning of civil component of sewage
pumping station under sewage project phase-III ( Part-1) for
Kalawad Road pumping station APS-02
Abstract-A
Sr. No. Quantity
Description
Rate
Per
Amount
SOR No.
1
1.1
1.1.1
1.1.2
1.2
293
572
835.00
1.3
1.4
1.5
1.6
1.7
2
830.00
825.0
825.00
800.00
76.00
260.00
3
4
76.00
590.00
5
6
7
8
9
10
11
12
13
657.00
16.00
18.00
57.00
19.00
44.00
13.00
3.00
9.00
14
15
16
2.00
95.00
2510.00
17
435.00
18
780.00
19
295.00
20
21
460.00
18.00
EXCAVATION
0.00 to 1.5 mt depth
in all soil soft/hard murrum
-do- in soft/hard rock
1.51 to 3.0 mt depth in hard
rock
3.01 to 4.5 mt -do4.51 to 6.0 mt -do6.01 to 7.5 m -do7.51 to 9.0 m -do9.01 to 10.5 m -doAnchor fastener 32 mm dia
CRS Fe 500 with drill hole and
supply fixing with pull out test
complete item
PCC in M 100
CC M250 for base slab
without centering
CC M250 for wall
CC M250 for column
CC M200 for column
CC M250 for beams
CC M200 for beams
CC M200 for top slab
CC M250 for top slab
CC M200 for chajja
CC
M200
for
motor
foundation
CC M200 for lintel 2110+110
Brick masonry in CM 1:4
Cement plaster 20 mm thick
with niru finishing (water
proof)
Cement plaster 20 mm thick
with sand fase finishing (water
proof)
Cement plaster 13 mm thick
with niru finish
Kota stone flooring 15 to 25
mm thick with 50 mm c.m.
bedding in 1:3
IPS flooring 50 mm thick
Rolling shutter supplying and
fixing with bearing and top
cover complete
39.5 Cum
135.00 Cum
210.00 Cum
240.00
295.00
337.00
421.25
526.56
850.00
Cum
Cum
Cum
Cum
Cum
No.s
123.00 Cum
2319.00 Cum
1000.00
3067.00
2655.00
3003.00
2590.00
2868.00
2156.00
2800.00
1920.00
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
11573.5 (23+28)/2
77220.00 (33+38)/2
175350 39
204100.00
213375.00
278025.00
337000.00
10018.56
221000.00
40
11
42
42+55
12+55
MR
93480.00 278
1386762.00 GWSSB
d4-11+5
2628000.00 do 1-VI
49072.00 292-B
47790.00 292-A
171171.00 291
49210.00 294
126192.00 291
105608.00 291
8400.00 295
17200.00 202
2580.00 Cum
1059.00 Cum
59.00 sq mt
5160.00 293
100605.00 114
140090.00 157
59.00 sq mt
25665.00 157
42.00 sq mt
32760.00 116
240.00 sq mt
70800.00 191
77.00 sq mt
770.00 sq mt
35120.00 208
13860.00 353
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
145
Sr. No.
22
23
24
25
26
27
28
28.1
28.2
29
30
31
31.1
31.2
32
33
34
35
36
37
38
39
40
41
42.1
42.2
43
Quantity
Cost Estimate
Description
Rate
Per
50.00 Kg
22.00 No.s
36.00 Kg
332.00 sq mt
Amount
SOR No.
6180.00 327
13770.00 327
8400.00 327
119100.00 823
1140.00
15000.00 MR
11330.00 MR
61840.00 MR
11330.00 177
61840.00 170
11330.00 921-1
61840.00 927
6052.00 17/160
450000.00 MR
1056.00 15/160
GWSSB
14350.00 543
2460.00 D16/66
GWSSB
75000.00 ww b 302
550.00 1091
3726000.00 32-b
3320.00 201
270.00 Nos.
27.00 834
49.00 Rmt
980.0 931
101.00 Rmt
133.00 Nos.
1010.00 933
133.00 951
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
146
Sr. No.
44
45
46
47.1
48
Quantity
Cost Estimate
Description
Rate
Per
Amount
SOR No.
49.00 No.s
147 939
141.00 Rmt
1410.00 885
264.00 No.s
264.00 835
493.00 No.s
493.00 825
536.00 Cum
Total
8040.00 70
11743967.06
11745000.00
Rs.1,17,45,000-00
Rs. 5,40,000-00
Rs.1,22,85,000-00
Rs. 13,15,000-00
Rs.1,36,00,000-00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
147
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
148
Sr. No.
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
34
35
36
37
Quantity
Cost Estimate
Description
Rate
Per
240.00
159.00
Sq. M
Sq. mt
Amount
7200.00
6232.80
SOR
No.
191
202
rmt
0.00
22.00
138.00
No
No
176.00
4140.00
1091
39.80
Kg
11542.00
823
cum
cum
cum
Sq. mt
Sq. mt
66323.40
555000.00
11902.20
8258.25
2564.10
gwssb
d4-11+5
do 1-v1
291
294
208
59.00
rmt
18998.00
88.00
21.00
2000.00
63.55
2450.00
No
No
No
No
No
2640.00
2436.00
2000.00
1906.50
2450.00
157
gwssb
15/160
gwssb
MR
gwssb
gwssb
50.00
Kg
75000.00
WWB
302
3600.00
Qtl
831600.00
gwssb
LS
--
100000.00
2108705.40
2109000.00
MR
2319.00
4000.00
2868.00
3003.00
77.00
Say
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
149
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
150
Sr.
Quantity
Description
No.
17
36.00 steel work for window and
ventilation
18
26.00 Rolling shutter of approved
design and quality with two
coat of oil paint etc
complete.
19
286.00 Kota stone polished tiles of
average 18 to 25 mm thick
etc complete
20
1088.00 Mosaic tiles
21
130.00 Rain water pipe CI 100 mm
dia comp
22
Fan hooks from MS bar of
30.00 12 mm dia
23
60.00 Fixing CI steps etc complete
MS section of various size
24
30.00 channel,
angle girder etc
25
395.00 CC in M25 for bottom slab
without centering
26
353.00 CC in M25 for vertical walls
27
50.75 CC in M25 for top slab
28
2.50 CC in M15 for RCC stair
29
19.70 CC in M-25 for beams
30
572.00 Bottom IPS 50 mm thick
Cement plaster 20 mm thick
in CM 1:3 with water
31
1429.00 proofing to RCC wall inside
32
40.00 Providing and supplying CI
coevals
Providing CI MH cover &
33
1800.00 frames
fixing of MH frame and
34
2.00 cover
35
60.00 Fixing coevals in the slab
providing and fixing water
36
1.00 level indicator
37
5000.00 Supplying MS special flange
38
1175.00
Providing, cutting, placing,
TOR steel including binder
wires etc comp
39
-Gates misc. and job work
Cost Estimate
Rate
Per
Amount
SOR No.
810.00
Sq. M
29160.00
327
770.00
Sq. M
20020.00
353
240.00
159.00
Sq. M
Sq. mt
68640.00
172992.00
178.00
rmt
23140.00
191
202
gwssb
17/160
22.00
138.00
No
No
660.00
8280.00
1091
39.80
Kg
1194.00
823
916005.00
1412000.00
145551.00
4640.00
59159.10
44044.00
gwssb
d4-11+5
do 1-v1
291
299
294
208
2319.00
4000.00
2868.00
1856.00
3003.00
77.00
cum
cum
cum
cum
Sq. mt
Sq. mt
59.00
rmt
84311.00
88.00
No
3520.00
157
gwssb
15/160
21.00
No
37800.00
gwssb
2000.00
63.55
No
No
4000.00
3813.00
MR
gwssb
2450.00
50.00
No
Kg
2450.00
250000.00
gwssb
WW 302
3600.00
LS
Qtl
--
4230000.00
500000.00
10337642.80
10338000.00
gwssb
MR
Say Rs.
Plus Compound wall
as per Abstract-B
Total Amount Rs.
776000.00
11114000.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
151
Cost Estimate
80.00
44.00
142.00
4
5
6
7
57.00
36.00
34.00
2874.00
903.00
39.50
Cu. Mt.
3160.00
23+28/2
494.00
Cu. Mt.
21736.00
64
536.00
Cu. Mt.
76112.00
70
1459.00
1890.00
2422.00
33.00
31.80
Cu. Mt.
Cu. Mt.
Cu. Mt.
Kg.
Kg.
83163.00
68040.00
82348.00
94842.00
28715.40
136
300
292
302
301
1059.00
141.00
Cu. Mt.
Rmt.
152496.00
3948.00
114
883
8
9
10
144.00
28.00
11
93.00
101.00
Rmt.
9393.00
882
12
1247.00
57.00
Sq. Mt.
71079.00
150
13
1236.00
17.00
Sq. Mt.
21012.00
170
14
15
985.00
720.00
39.80
7.00
Kg.
Sq. Mt.
39203.00
5040.00
823
538
16
75.00
8.00
Nos.
600.00
540
17
70.00
6.00
Rmt.
420.00
1029
18
25.00
23.00
Sq. Mt.
575.00
473
19
20
11.00
35.00
1097
37.00
Cu. Mt.
Sq. Mt.
12067.00
1295.00
61
147
21
16.00
P.C.C. 1:3:6
Cement plaster Rough cast in C.m.
1:3
Cement plaster with niru finishing
42.00
Sq. Mt.
672.00
146
775916.40
Say .Rs..776000.00
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
152
Cost Estimate
Rate Rs.
Per
Amount
39.50
135.00
166.50
cu mt.
cu mt.
cu mt.
40290.00
34425.00
70762.50
11.00
27.50
1431.00
cu mt.
cu mt.
Rmt.
693.00
1732.50
1202040.00
SOR No.
23+28/2
33+38/2
34+39/2
15/A p-66
15/B p-67
MR
48.00
Rmt.
40320.00
9/4/61
58.75
Kg.
293750.00
WW/345
1170.00
cu mt.
23400.00
1500.00
cu mt.
22500.00
36415.00
cu mt.
36415.00
616/2
ww/A/135
350.00
cu mt.
350.00
ww/B/73
2645.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
No.s
13225.00
ww/A/147
153
Item
Quantity
Description
No.
11
5.00 Fixing double acting Air valve of
150 mm dia incl. all fitting materials
etc. comp.
12
6.00 Construction of valve chamber in 23
cm thick Brick masonry in CM 1:6
Fdn C.C. 1:4:8, inside 12 mm
cement plaster in C.M. 1:3 etc. incl.
RCC slab 100 mm tk. With Key hole
in two parts, each with handles of
M.S. bars etc upto depth of 1 mt
from G.L. to pipe invert. Excluding
cost of excavation. For chamber size
1.3m * 0.90m and 1 mt deep.
13
185.00 Remove surplus earth within the
corporation limits including
spreading etc. comp.
14
800.00 Breaking of Aphalt pavement
surface
Conventional
15
800.00 Road re-instating work.
WBM
16
800.00 Asphalt
Cost Estimate
Rate Rs.
Per
85.00
No.s
Amount
SOR No.
425.00
ww/B/83
3390.00
No.s
20340.00
C/B/1
33.00
6105.00
712
18.00
14400.00
43
55.00
44000.00
85.00
68000.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
MR
MR
1933173.00
19,34,000.00
154
Cost Estimate
Detailed Estimate for Pumping Main Pipeline For Auxiliary Pumping Station Of Kalawad Road
( APS - 2 )
Item
Quantity
Description
Rate Rs.
Per Amount Rs.
SOR No.
No.
1
Excavation of pipeline
trenches and valve chamber
incl. all safety provisions using
rails etc including refilling the
trenches & stacking the
excavated stuff upto a lead of
90mt as directed
In all sorts of soil, soft
murrum, hard murrum &
macadam roads.
3776.00 up to 0 - 1.50 mt.
39.50 cumt.
149152.00
23+28/2
958.00 Do- in soft & hard rock
135.00 cumt.
129330.00
33+38/2
3192.00 Up to 1.50 to 3.0 mt.
166.50 cumt.
531468.00
34+39/2
Do- in soft & hard rock
2
Providing sand or murrum
bedding incl. comp.
235.00 From selected excavated earth
11.00
2585.00 15/A p-66
235.00 From outside beyond 2.0 km
27.50
6462.50
15/B p-67
lead
3
1566.00 Providing & supplying 900
5341626.00
3411.00 Rmt.
mm dia. ISI standard P.S.C.
pipes in standard lengths of 12
20/D/5
kg/cm2 class of 900 mm dia as
per I.S. 784-1989 incl. Rubber
ring joints incl. All taxes etc
supply at site.
4
1566.00 Lowering laying & jointing
219240.00
140.00 Rmt.
P.S.C. pipes & specials of 900
mm dia. Including all required
materials in proper position,
9/12/61
grade and alignment as
directed incl. Giving hydraulic
test etc. comp.
5 10000.00 Providing M.S. specials like
587500.00
58.75 Kg.
Bends, Flanged Tee, etc.
WW/345
suitable to P.S.C. 900 mm pipe
incl. all taxes etc. comp.
6
70.00 1:3:6 CC (M 100) for encasing
81900.00
1170.00 cumt.
616/2
the pipes incl. Finishing etc.
comp.
7
25.00 1:3:6 CC (M 150) for RCC
37500.00
1500.00 cumt.
thrust blocks over the pipes
281
with centering incl. Finishing
etc. comp.
8
1.00 Providing Sluice valve 900
299000.00
299000.00 cumt.
WW/A/141
mm dia PN-1 class IS 2906 ISI
marked incl. all taxes.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
155
Item
No.
9
10
11
12
13
14
15
16
17
Quantity
Cost Estimate
Description
Rate Rs.
Per
785.00 cumt.
Amount Rs.
SOR No.
785.00
WW/B/80
5700.00
No.s
68400.00
85.00
No.s
1020.00
WW/A148
WW/B/84
12000.00
156000.00
MR
33.00
75900.00
712
18.00
56736.00
43
26.00
40716.00
55.00
85.00
173360.00
133110.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
MR
MR
8091790.50
80,92,000.00
156
Cost Estimate
6
7
9
10
Qty
Description
Rate Rs.
Per
39.50
cumt
.
cumt
.
cumt
.
135.00
166.50
11.00
27.50
1431.00
cumt
.
cumt
.
Rmt.
Amount
Rs.
31205.00
26730.00
54945.00
SOR
No.
23+28/
2
33+38/
2
34+39/
2
48.00
Rmt.
31200.00
9_4_61
58.75
Kg.
235000.00
1170.00
cumt
.
cumt
.
23400.00
36415.00
cumt
.
36415.00
350.00
cumt
.
No.s
350.00
1500.00
2645.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
WW/3
45
616/2
22500.00
13225.00
ww/A/
135
ww/B/
73
ww/A/
147
157
Ite
m
No.
11
12
14
15
16
17
18
Qty
Cost Estimate
Description
Amount
Rs.
Rate Rs.
Per
85.00
No.s
425.00
3390.00
No.s
20340.00
SOR
No.
ww/B/
83
C/B/1
33.00
18.00
cumt
.
4125.00
m2
5850.00
712
43
26.00
55.00
85.00
m2
m2
m2
3432.00
35750.00
38675.00
MR
MR
1515642.00
Say Rs.
15,16,000.00
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
158
Cost Estimate
Qty
4872.00
1218.00
4060.00
2
300.00
Description
Excavation of pipeline trenches and
valve chamber incl. all safety
provisions using rails etc including
refilling the trenches & stacking the
excavated stuff upto a lead of 90mt
as directed
In all sorts of soil, soft murrum,
hard murrum & macadam roads.
up to 0 - 1.50 mt.
Do- in soft & hard rock
Up to 1.50 to 3.0 mt.
Do- in soft & hard rock
Providing sand or murrum bedding
incl. comp.
From selected excavated earth
6
7
Rate Rs.
Per
Amount Rs.
SOR No.
39.50 cumt.
135.00 cumt.
166.50 cumt.
192444.00 23+28/2
164430.00 33+38/2
675990.00 34+39/2
11.00 cumt.
25.30 cumt.
3411.00
Rmt.
20/D/5
140.00
Rmt.
280000.00
9_12_61
58.75
Kg.
470000.00
WW/345
1170.00
cumt.
175500.00
1500.00
cumt.
60000.00
616/2
281
299000.0
0
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
No.s
598000.00
WW/A/1
41
159
Ite
m
No.
9
10
11
12
13
14
15
16
Qty
Cost Estimate
Description
Rate Rs.
Per
785.00
cumt.
5700.00
No.s
85.00
No.s
12000.00
No.s
Amount Rs.
1570.00
SOR No.
WW/B/8
0
68400.00 WW/A14
8
1020.00
WW/B/8
4
168000.00
MR
1300.00 RM
33.00 cumt.
18.00
m2
13000.00 MR
97020.00
712
9000.00
43
55.00
85.00
m2
m2
MR
27500.00
42500.00 MR
9877264.00
98,78,000.00
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
160
Cost Estimate
Design, procurement, manufacture supply, erection & commissioning with sludge handling
pumps & pump house piping for Three Auxiliary Pumping Stations APS - 1, APS - 2, APS - 3 &
Main pumping station for drainage Phase-III
BILL OF QUANTITIES FOR PUMPING MACHINERY
Item
No.
1.0
2.0
3.0
4.0
Description
Design procurement, manufacture supply, storage at site loading,
unloading, transporting, erection, testing and commissioning of
Submersible Sewage handling pumps & pump house piping etc.
complete.
For MAVDI APS - 1 pumping station
Sets of 67 LPS 15 mt. head (2+1 sets).
Approx. H.P. 30/pump.
For GANDHIGRAM APS - 3 pumping station
Sets of 28 LPS 17 mt. head (2+1 sets).
Approx. H.P. 25/pump.
Design procurement, manufacture supply, storage at site loading,
unloading, transporting, erection, testing and commissioning of
Horizontal split casing non clogged Solid handling pumps & pump
house piping etc. complete.
For KALAWAD ROAD APS - 2 pumping station
Sets of 82 LPS 17 mt. head (4 + 2 sets).
Approx. H.P. 65/pump.
For MPS - near village Raiya Main pumping station
Sets of 331 LPS 15 mt. head (4+2 sets).
Approx. H.P. 105/pump.
TOTAL COST OF PUMPING MACHINERY
Amount Rs.
22,50,000.00
18,75,000.00
78,00,000.00
1,26,00,000.00
2,45,25,000.00
Total KW
Auxillary Load = 97 KW
Total
= 981 KW
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
161
Cost Estimate
Particulars
PART - A
Design, Procurement, manufacture, supply at site including transportation,
storage at site loading and unloading, erection, testing and commissioning of
Submersible Sewage handling pumps with motors, each of capacity 67 LPS and
head 15 mt. make Aqua, Kishor, ABS, Pullen.
Design, Procurement, manufacture, supply at site including transportation,
storage at site loading and unloading, erection, testing and commissioning of all
suction, delivery an other pipe work C.I. double flanged including specials,
specials, spectacle blinds gaskets, nuts bolts etc. and painting as per approved
pump house piping drawing, with bypass arrangement of each pump.
Design, Procurement, manufacture, supply at site including transportation,
storage at site loading and unloading transportation, storage as site, loading &
unloading, erection, testing and commissioning of all sluice valve, reflux valve
etc. complete as per valve schedule.
Design, Procurement, manufacture, supply at site including transportation,
storage at site loading and unloading, erection, testing and commissioning of
pressure gauges with necessary piping, isolation valves & drain valves
complete.
Qty.
3 Nos.
1 Lot.
1 Lot.
2 Nos.
1 Nos.
1 Nos.
7
8
10
Sr.
No.
1
3
4
2 Nos.
1 Nos.
2 Sets.
3 Sets.
Particulars
PART - B
Design, Procurement, supplying, erection and commissioning of 415V motor
control center including required AMP capacity M.C.C.B./ACB with fuse unites
fully automatic start delta starters, protection relays and all delta starters,
protection relays and all measuring instrument bus bars and bus coupler.
Capacitor bank etc. complete one unit for 3 sets.
Design, Procurement, supply, Erection, Testing and Commissioning of 1.1 KV
grade PVC Insulated power and control cable of Unistar / CCI / INCAB / FORT
Gloster make with accessories.
Design procurement, Supply, Erection, Testing and Commissioning of earthing
system for complete pumping station installation.
Design, procurement, Supply, Erection, Testing and Commissioning of lighting,
system (Indoor and Outdoor both) for complete pumping station installation
fixtures shall be of Philips / Crompton / Bajaj.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Qty.
1 Lot.
1 Lot.
1 Lot.
1 Lot.
162
Cost Estimate
APS-3 (GANDHIGRAM).
Sr.
No.
1
1 Nos.
2 Nos.
3 Sets.
8
9
10
Sr.
No.
1
3
4
Particulars
PART - B
Design, Procurement, supplying, erection and commissioning of 415V motor
control center including required AMP capacity M.C.C.B./ACB with fuse unites
fully automatic start delta starters, protection relays and all delta starters,
protection relays and all measuring instrument bus bars and bus coupler.
Capacitor bank etc. complete one unit for 3 sets.
Design, Procurement, supply, Erection, Testing and Commissioning of 1.1 KV
grade PVC Insulated power and control cable of Unistar / CCI / INCAB / FORT
Gloster make with accessories.
Design procurement, Supply, Erection, Testing and Commissioning of earthing
system for complete pumping station installation.
Design, procurement, Supply, Erection, Testing and Commissioning of lighting,
system (Indoor and Outdoor both) for complete pumping station installation
fixtures shall be of Philips / Crompton / Bajaj.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
2 Nos.
1 Nos.
2 Sets.
Qty.
1 Lot.
1 Lot.
1 Lot.
1 Lot.
163
Cost Estimate
1 Lot.
1 Lot.
1 No.
2 No.
1 No.
2 Sets.
3 Sets.
10
Sr.
No.
1
4
5
Particulars
PART - B
Design, Procurement, supplying, erection and commissioning of 415V motor
control center including required AMP capacity M.C.C.B./ACB with fuse unites
fully automatic start delta starters, protection relays and all delta starters,
protection relays and all measuring instrument bus bars and bus coupler.
Capacitor bank etc. complete one unit for 6 sets.
Design, Procurement, supply, Erection, Testing and Commissioning of 415 KV,
1500 RPM Syn, Speed, Squirrel Cage induction motors of Kirloskar, Jayoti
,Crompton, Siemens, NGEF make suitahble for pumping duty.
Design procurement, Supply, Erection, Testing and Commissioning of 1.1 KV
grade PVC Insulated power and control cable of Unistar / CCI / INCAB / FORT
Gloster make with accessories.
Design procurement, Supply, Erection, Testing and Commissioning of earthing
system for complete pumping station installation.
Design, procurement, Supply, Erection, Testing and Commissioning of lighting,
system (Indoor and Outdoor both) for complete pumping station installation
fixtures shall be of Philips / Crompton / Bajaj.
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
2 No.
1 No.
Qty.
1 Lot.
6 Nos.
1 Lot.
1 Lot.
1 Lot.
164
Cost Estimate
Particulars
PART - A
Design, Procurement, manufacture, supply at site including transportation,
storage at site loading and unloading, erection, testing and commissioning of
Horizontal centrifugal non clog solid handling type pumps, each of capacity 331
LPS and head 15 mt. make Kirloskar, Mahter Plat, Jyoti, Becon.
1 Lot.
1 Lot.
2 Nos.
1 No.
1 No.
2 No.
1 No.
2 Sets.
3 Sets.
10
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
Qty.
6 Nos.
165
Sr.
No.
1
Cost Estimate
Particulars
PART - B
Design, Procurement, supplying, erection and commissioning of 415V motor
control center including required AMP capacity M.C.C.B./ACB with fuse unites
fully automatic start delta starters, protection relays and all delta starters,
protection relays and all measuring instrument bus bars and bus coupler.
Capacitor bank etc. complete one unit for 6 sets.
Qty.
1 Lot.
6 Nos.
1 Lot.
1 Lot.
1 Lot.
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
166
Cost Estimate
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
167
Item
No.
1
Qty.
Cost Estimate
456.00 Rmt
39.50 Cumt
S.O.R.
Number
11,40,000/- MR
5727-50 23+28
2
1450.00 Cumt
2,10,250/- 62
74.00 Rmt
1,85,000/- MR
55.00 Cumt
Total
Say
8250/- 702
14,99,227-50
15,00,000-00
(Rupees Fifteen lakhs only)
___________
City Engineer
Rajkot Municipal Corporation
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
168
Cost Estimate
1
2
3
4
5
6
Phase-II (Part-I)
Collective system and house connections
600
Installation of additional non-clog C.F. pumping
285
machinery in existing pump house
Extension of sewage treatment plant with extended
1120
aeration process with sludge digester 44.5 mld capacity.
Additional power connection at Madhapar plant
30
Compound wall at Madhapar plant
15
Total..A
2050
Phase-III (Part-I)
Collective system
1860.76
House connections
1404.59
Pumping Station Civil Works
293.06
Pumping Station Rising Mains Works
139.60
Pumping Station Machinery Works
245.25
Sewage Treatment Plant
1328.81
5272.07
Total..B
7322.07
Total = Total A + Total B
Add 5% contingencies...
366.10
TOTAL Rs. in lakhs
7688.17
Say Rs. in Lakhs
7688
Rupees Seventy Six Crore Eighty Eight Lakhs only/-
******
Detail Project Report for Drainage Phase-II & III (Part-I) for Rajkot City
169
10
Financial Analysis
FFiinnaanncciiaall A
Annaallyyssiiss
10.1 General
This Detail Project Report on Phase-II & Phase-II (Part-I) envisages to meet requirements
of un developed area of the Rajkot city. This would involve substantial capital outlays and operation
and maintenance costs. AS part of JnNURM it is assumed that RMC has to make provision of 30% of
capital expenditure while, 50% contribution will be shared by Govt of India and remaining 20% by
the Govt of Gujarat. The total Operation and maintenance cost will be borne by Rajkot Municipal
Corporation.
Due to the constraints within the Corporation and heavy demands on the available funds
from a variety of development, it is necessary that drainage service becomes self sustainable in its
operation. A suitable drainage service tariff structure needs to be designed to meet the operation.
Other Incomes
Octroi Collections :Octroi contributes the largest share (over 56% of the total revenue income) to the
Revenue basket of RMC. Even a small percentage fall in Octroi Income could cause a bigger loss to
RMC and as Octroi being the largest income source, there is a greater sensitivity to fluctuations from
this source of income.
Property Tax: Property tax (House tax, Conservancy tax, Fire tax and Education cess) is the
second largest tax Revenue source and constitutes average 35-37% of the total revenue income and 25
percent of total income. The There are about 2, 08,000nos. Of built up properties are being assessed
within Rajkot Municipal Corporation limits. The average growth rate of assess is about 2%. As per
BPMC Act, 1949 Corporation can revise the ARV of properties once in four years however; last
revision was made during year 1992. The corporation levies a tax on bases of built-up area
measurement and thereby finding Annual Ratable Value (ARV) of the collection of tax. The current
demand of house tax is Rs58.01 millions where as there are outstanding arrears as on 31-12-2005 is
1702 millions.
Detail Project Report for Drainage Phase-II & Phase-II (Part-I) for Rajkot City
170
Financial Analysis
Theatre Tax: RMC collects theatre tax from theatres as well as professional entertainment
shows within RMC limits. It is very nominal tax of Rs.75.00 per cinema show... Average collection of
theatre tax is Rs.11.00 Lakhs per annum.
Vehicle Tax: From year 2002-03 RMC started to impose lifetime vehicle taxes. The tax structure
depends on type of vehicles and age of vehicles. Up to 1/10/2005 RMC have collected Rs.30 Lakhs
from about 60000 vehicles.
Other Incomes Income from penalty, administrative charges etc. is considered as other
Income. It largely depends upon the special charges or drives like administrative collection
charges for SWM etc.; it ranges from Rs.150 Lakhs to Rs.300 Lakhs.
Year
2001/02
2002/03
2003/04
2004/05
2005/06
Revenue Expenditure
The Corporation spends the resources for establishment, operation and maintenance and
debt servicing of obligatory and discretionary services provided by it. The major heads of revenue
expenditure include general administration, water works, drainage , conservancy, roads, streetlights,
public health, education, garden , fire brigade etc.,
Detail Project Report for Drainage Phase-II & Phase-II (Part-I) for Rajkot City
171
Financial Analysis
From above table, it reveals that every year, there is revenue surplus which is being diverted
to development work.
Capital Work :
For capital work, RMC used to raise the finance through Bank, debenture, bond etc. up to 60
to 65% of the project cost depending upon the magnitude of the work. The balance amount is being
made available from revenue surplus as well as capital income by selling the land of Town Planning
and Survey.
The billing system is computerized and decentralized. The collection of water charges is at
three different places viz., (i ) Main office building (ii) City Civic center, Amin Road (iii) City Civic
Center Krishnagar . Bills to all property holders are sent on yearly basis.
Detail Project Report for Drainage Phase-II & Phase-II (Part-I) for Rajkot City
172
Financial Analysis
The responsibility of repair and maintenance lies with the consumers. As per BPMC Act,
1949, if the consumer does not pay the bill within 15 days of the date of issue, 18% interest is to be
levied. A notice is to be issued for disconnection of water connection if the consumer does not pay
after next 30 days of the date of issue of the bill.
2005-06
JnNURM
GOI Fund (50%)
2006-
2007-
2008-
2009-
2010-
2011-
07
08
09
10
11
12
5854
642.5
1395
1269
600
497.5
700
750
2341.6
257
558
507.6
240
199
280
300
3512.4
385.5
837
761.4
360
298.5
420
450
11708
1285
2790
2538
1200
995
1400
1500
GOG contribution
(20%)
RMC'
Share
(30%)
Total
********
Detail Project Report for Drainage Phase-II & Phase-II (Part-I) for Rajkot City
173
11
Summing Up
S
Suum
mm
miinngg uupp....
12.1 Conclusion
Safe water supply and hygienic sanitation facilities are the two basic essential amenities the
community needs on a top priority for health living. The Sewerage services falls under essential
service category and by the BPMC Act. Because of the merging of the new area, coverage of
sewerage is about 65% (total of new + old area) too less in Rajkot.
Rajkot underground sewerage project costing Rs.40 crores covering area around 40 sq.km of
walled city was implemented by Govt. of Gujarat with loan assistance from World Bank during the
period 1984 to 1994 in which, following works were executed with the base year 1980-81.
1.
2.
3.
4.
5.
The project was conceived with base year 1980-81 with covering area of old city 69 sq.km.
but at that time the city was not fully developed and as such in stage-I the only developed area
covering 40 sq.km was considered splitting the work of pumping machinery, sewage treatment plant
and collective system.The project was prepared by Consultant M/s.Paramount Pollution Control
Pvt.Ltd., Baroda.
Subsequently, after implementation of the work of Phase-I, the development of the city was
very fast and most of the earlier left out area has been developed fully and Rajkot Municipal
Corporation has decided to implement underground sewerage system for all these developed area of
walled city covering additional 20 sq.km wherein following works are proposed as a Phase-II (Part-I):
o
Providing and fixing additional pumping machinery in the existing pump house total 9
sets.
As per original project report, twin pipeline each of 900 mm dia prestressed is to be laid from
Popatpara main pumping station to Madhapar treatment plant as a rising main.
In view of above,
the estimated cost of Phase-II part-I covering about 20 sq.km of walled city has been worked out
which is as under:
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
174
Sr
No
1
2
3
4
5
Summing Up
2000-01 covering 10 sq.km area. Collective system for remaining 10 sq.km area is yet to be taken up
in hand for which the estimated cost would be around Rs.600 lacs. Rajkot is located on besalt. The
excavation is the main problem and because of which the progress in the drainage system is not as per
the requirement. For work of sewage treatment plant RMC has finalized the process design and
tenders are to be invited shortly.
On completion of the Phase-II work, the total coverage of walled city under Underground
Sewerage System would be around 60 sq.km (40 Phase-I + 20 Phase-II). The remaining 9 sq.km area
will be covered as when same gets developed.
The works of Phasde-II part-II are proposed to be taken up in the year 2008-09. The detailed
project report is yet to be prepared.
In view of above, the present situation of walled city covering 69 sq.kms is as under:
Sr
No
1
Item
World Bank assisted sewerage
system commissioned in the year
1994-95 under Phase-I
Implementation of underground
sewerage system for the developed
area under Phase-II part-I
Area in
sq.km
40
20
Cost (Rs. in
Remarks
lakhs)
4000.00 Completed
commissioned
and
Implementation
of
the
9
underground sewerage system for
the area to be developed in future.
The approval is needed under Jawaharlal Nehru National Urban Renewal Mission is for
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
175
Summing Up
The city limit was extended by the Govt. of Gujarat in June 1998 by adding 35.60 sq.km area
in west direction of the walled city by merging outskirt 3 villages namely Mavdi, Nana Mava and
Raiya. At the time of merger, the newly merged area was not having any infrastructure facility and
thus RMC has taken up the works of implementation of all infrastructure projects viz; water supply,
sanitation, roads, underground sewerage system, street light etc. on priority basis. so far, RMC has
pumped about Rs.125 crore for development work in newly merged area. For above newly merged
area, RMC had engaged consultant who has prepared a detailed project report of underground
sewerage system covering 15 sq.km area at the first instant where development has taken place. The
work is to be executed as a Phase-III Part-I. The remaining 20.6 km area the project is yet to be
conceived as in this region, the development is very slow and likely to be saturated in the year 200809. At that time, the project will be conceived to cover under underground sewerage system.
The estimated cost of the project for covering 15 sq.km area of newly merger works out as
under:
Sr
No
1
2
3
4
Collective system
House connections
Pumping Station Civil Works
Pumping Station Rising Mains Works
1860.76
1404.59
293.06
139.60
5272.07
Total
As stated above the balance 20.6 sq.km (35.6 - 15) area is yet to be developed for which
detailed project report will be prepared later on. Thus, the final situation of underground sewerage
project for newly merged area is as under:
Sr
Item
Area in sq.km
Amount in lacs
No
1
15
Rs.5272.07 Lakhs
20.6
under
Jawaharlal
Nehru
conceived.
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
176
Summing Up
In view of above, following detailed project reports are submitted for consideration under
JNNURM for the year 2005-06 to 2007-08.
Sr
No
1
2
3
4
5
1
2
3
4
5
6
Phase-II (Part-I)
Collective system and house connections
600
Installation of additional non-clog C.F. pumping
285
machinery in existing pump house
Extension of sewage treatment plant with extended
1120
aeration process with sludge digester 44.5 mld capacity.
Additional power connection at Madhapar plant
30
Compound wall at Madhapar plant
15
2050
Total..A
Phase-III (Part-I)
Collective system
1860.76
House connections
1404.59
Pumping Station Civil Works
293.06
Pumping Station Rising Mains Works
139.60
Pumping Station Machinery Works
245.25
Sewage Treatment Plant
1328.81
Total..B
5272.07
7322.07
Total = Total A + Total B
Add 5% contingencies..
366.10
TOTAL Rs. in lakhs
7688.17
Say Rs. in Lakhs
7688
Rupees Seventy Six Crore Eighty Eight Lakhs only/Thus, the submitted DPR for Rajkot Under ground Drainage Phase-II & Phase-III ( Part-I )
*********
Detail Project Report for Drainage Phase-II & Phase-III (Part-I) for Rajkot City
177