Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

UNIT 7

CONSTRUCTION OF RIGID/CONCRETE PAVEMENT

OBJECTIVES
General Objective
To understand the general element in constructing rigid/concrete pavement

Specific Objectives
At the end of the unit you should be able to:

identify the structural element of rigid pavement.

describe the functions of each layer in the rigid pavement.

explain the construction process of the rigid pavement.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

INPUT

7.0

INTRODUCTION
Cement concrete roads are very high standard. They are costliest than all

other types of roads. These roads provide excellent riding surface and pleasing
appearance. They are called rigid pavements because they do not allow any
flexibility.
These roads although require initial heavy expenditure but because of
their long span of life, excellent riding surface and negligible maintenance cost,
they prove cheaper than bitumen roads. Moreover engineers have more
confidence in cement concrete material and they also like to construct these
roads.

7.1

ADVANTAGES AND DISADVANTAGES OF CONCRETE ROADS


The following are some of the advantages and disadvantages of cement

concrete roads:
Advantages
a.

They provide excellent smooth surface for driving.

b.

They can deal with very heavy traffic.

Highway Engineering
c.

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Considering their life span, maintenance cost etc, cement concrete


roads prove cheaper than bituminous roads.

d.

Maintenance cost is negligible.

e.

Their life span is very large.

f.

Even after their span of life, they can be used as base course and
surfacing can be provided of bituminous materials.

g.

Heating of aggregates and cement is not to be done.

h.

They provide better visibility.

i.

Working with cement concrete is much easier and safer than with
bituminous materials.

j.

Cement concrete roads offer comparatively less attractive


resistance.

k.

In high class cement concrete roads heavy rollers are not required
for compaction.

l.

Handling of cement is easier than bitumen.

m.

They perform quite satisfactorily when laid on poor types of sub


grades.

Disadvantages
a.

They involve heavy initial investment.

b.

Lots of joints are to provide which prove additional places of


weakness.

c.

28 days curing is required after completion before they can be


opened to traffic.

d.

It is not possible to adopt stage construction programmed in these


roads.

e.

Cement concrete road surface after some time of use becomes


very smooth and slippery.

f.

It is a noisy road, as bullock carts or steel tyred vehicles cause lot


of noise while moving on them.

Highway Engineering

7.2

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

CLASSIFICATION OF CEMENT CONCRETE ROADS


Cement concrete roads can be of following types. Out of all these types,

cement concrete slab roads, are most commonly used, and hence construction
details of this type of road are discussed in this topic.
a.

Cement concrete slab pavements

b.

Cement grouted macadam pavements

c.

Roller concrete layer pavements.

d.

Cement-bound macadam sandwich type.

e.

Crete-ways.

a. Cement Concrete Slab Pavements.


In this type of cement concrete roads, cement, sand, coarse
aggregate water are premixed in batch mixtures to form cement concrete.
Cement concrete so prepared is spread on the prepared sub grade or sub
base and consolidated with the help of vibrators or tamper and surface
finished smooth.
In this construction, joints at frequent intervals both longitudinally
and transversely are provided to nullify the harmful effects of contraction
and expansion due to variation in temperature and also during setting.
b. Cement Grouted Macadam Pavements.
In this type of construction, Water Bound Macadam layer or
stabilized soil is used as foundation. Existing foundation layer is
reconditioned to correct grade and profile and a loose layer of road metal

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

or coarse aggregate of 36 to 50 mm size is laid in 125 cm thickness. This


coarse aggregate layer is rolled lightly dry to a compacted thickness of
about 10 cm. Minimum size of coarse aggregate should not be less than
20 mm as sufficient void spaces are to be deliberately left in this rolled
layer.
Cement and sand are taken in ration of about 1:2 and grout is
prepared by adding sufficient quantity of water in it. Cement-sand mix,
having one bag cement, requires about 35 liters water to form a fluid
mortar to be used as grout. The grout so prepared is poured over the
lightly rolled macadam layer and allowed to seep into the voids
deliberately left in the macadam layer.
After grouting, stone chippings of size 5 mm and above, are spread
to smoothen the top finished surface and also to help rolling so that grout
is further helped in the process of penetration. Finished surface is checked
for trueness, camber and profile. The surface is lastly cured as usual.
Longitudinal and transverse joints should be provided at suitable interval.
c. Rolled Concrete Pavement
This construction consists of a lean premix of cement concrete
which is laid on the prepared sub grade of sub base and rolled with light
roller just like Water Bound Macadam Road construction. Rolling
operation should be finished before the final setting time of the cement.
Curing has to be done for 28 days as usual.
d. Cement Bound Macadam Sandwich Type
In this type of construction, Water Bound Macadam existing layer or
stabilized soil base are used as foundation or base. The base layer is
reconditioned by carrying out all sorts of repairs. Now take coarse

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

aggregate varying in size between 36 mm and 50 mm and spread it on the


prepared base. This layer is rolled dry to get a compacted thickness of
about 5 cm. Cement and sand are taken ratio of 1:2 and a stiff mortar is
made, using appropriate quantity of water (30 liters / cement bags).
This mortar is spread on the rolled surface in about 4 cm thick
layer. Now lay an other layer of coarse aggregate of the same size and
grading as is used below mortar layer, in a loose thickness of about 6 cm.
After spreading the second layer of coarse aggregate over stiff mortar
layer, rolling is done using heavy roller about 12 ton. By rolling, the mortar
layer is squeezed in to the voids of both the layers of coarse aggregate
(one layer above and another below mortar layer) and about 10 cm thick
combined layer developed.
Rolling should be stopped as soon as the mortar works up just to
the surface. After rolling, the surfacing is finished and checked for camber
and profile. Joints are provided at suitable intervals. This type of
construction is superior to the grouted macadam roads. These roads
exhibit rough texture on the surface and hence are useful in hilly areas,
where gradients are steep and other types of roads become slippery and
dangerous for use.
e. Crete-ways
Crete ways are track ways made with the help of cement concrete.
In village roads there is generally bullock cart traffic. It was originally
thought that if only that portion of the road is treated with concrete where
wheels of cart are to move lot of savings can be affected because width of
treatment to be provided shall be very small. In Crete ways, only 60 70
cm wide two parallel concrete strips, at centre to centre spacing of about
1.5 meters are constructed. The space between strips is left untreated or

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

may be treated with very inferior type of material. Thickness of strip may
vary from 10 15 cm.
Crete ways strips may be pre cast and then laid on the prepared
sub grade or they may be constructed by laying concrete directly at the
site, just in the same way as ordinary cement concrete roads. Crete ways
did not become popular due to following reasons:
a. While crossing, vehicles coming from opposing directions have
so get down crete way strips. Getting down and coming up, the
crete way is very difficult, since space between strips and out
side the strips is soft and bullock carts get entrenched in it.
b. During rainy season, water may be held up in the kutcha portion
between strips. This may affect the foundation of the crete-ways
strips and may result is their subsequent settlement.
c. In dry weather, loose soil from kutcha space is blown off and a
trench type hollow space may be formed in between the strips.
In place of track ways of cement concrete, stone slabs covered with
bitumen surfacing can also be used. Sometimes, in case of city roads,
central part of the road is made from asphalt or bitumen surfacing, for use
of motor traffic, and on both of its sides there may be crete ways for
carrying bullock carts traffic. Such road in which some width is made from
bitumen and remaining from cement concrete, is known as conphalt road.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

INPUT
STRUCTURAL PARTS OF CEMENT CONCRETE
ROADS AND CONSTRUCTION
7.3

STRUCTURE OF CEMENT CONCRETE ROADS


Concrete roads consist of following layers:

Cement concrete
pavement
Sub base course

Sub grade
Figure 8.1
Sub grade is concerned its most important property is not the actual
strength but uniformity of support. Sub base course of concrete road may be
made of Water Bound Macadam, granular material, or stabilized soil. In the case
of Water Bound Macadam base, thickness should be at least 15 cm and any new
layer of sub base should have been under traffic for some days to get properly
compacted.
Construction of cement concrete slab can be done in following two ways:
a.

Alternate bay system

b.

Continuous construction.

a. Alternate Bay System

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

In this method of laying concrete, width of the road is divided into


longitudinal strips. The longitudinal strips are further sub-divided into
panels by providing transverse formwork. If the width of the road is just
one lane, full width is adopted as one longitudinal strip, but in the case of
more than one lane width, each lane is adopted as one longitudinal strip.
In short, the road surface is divided into panels. After this cement
concrete is filled in alternative panels or bays both longitudinally and
transversely. Size of the bay may be anything like 4 X 4 m, 3.6 X 4.6 m or
so. After a lapse of about one weak, remaining left out bays are also filled
with cement concrete. The object of adopting alternate bay system of
construction is to allow sufficient time to settle and shrink before adjoining
bays are filled. The method reduces the possibilities of developing
shrinkage base cracks. This system of construction suffers from following
draw backs:
i.

A large number of joints are developed which


increase the labour cost and also reduce the smooth
riding qualities of the resulting surface.

ii.

During rain, water gets collected in the unfilled bays.

iii.

Works are not finished at a stretch but a large length


of the road remains occupied at any moment. If full
width is involved, diversions for traffic will have to be
provided, thus causing difficulties to traffic and
increase in the cost over of all construction.

iv.

Fully mechanized construction is not possible.

v.

Progress of the work is very slow.

Highway Engineering

C3010 / UNIT

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

The only advantage of this method of construction is that joints can be


easily constructed. Figure 8.2 shows formation of bays on the surface of the
road. A, B, C bays are filled first and A, B, C bays subsequently after a laps of
about one week.

Longitudinal Joint

Transverse Joint

C
C

Figure 8.2
b. Continuous Construction
In this system of construction, continuous longitudinal strips are
constructed without any break. Width of the strip is generally kept one
lane. This method also helps in marking the traffic lanes after completion,
since longitudinal joints will demarcate the limit of each lane. The
construction joints are provided at the end of the days work. This method
of construction is preferred because of the following reasons:
i.

Very few joints will be formed

ii.

In case of roads having more than one lane width, no


diversion is required to be constructed. One lane may

Highway Engineering

C3010 / UNIT

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

be adopted for construction at a time and remaining


lanes may continue to be used by the traffic. Although
traffic will face difficulties but there is no need
diversion.

Slab to be laid
Laid cement concrete
slab
Figure 8.3 plan of continuous system.
7.4

CONSTRUCTION STEPS OF CEMENT CONCRETE SLAB


PAVEMENTS.
Construction of cement concrete pavement involves following stages:
a. Preparation of sub grade.
b. Preparation of sub base.
c. Fixing of farm.
d. Batching of materials and mixing.
e. Carrying and placing concrete.
f. Compaction and finishing.
g. Floating and edging.
h. Belting and edging.
i. Curing.
All these operations have been discussed one by one.

a. Preparation Of Sub Grade

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Where formation soil is of very good quality, cement slab may


directly be laid over the prepared sub grade. The top 15 cm layer of the
sub grade should be compacted and checked for trueness by mean of
scratch template. Unevenness of the surface should not exceed 12 mm in
3 m length. Sub grade should be prepared and checked at least two days
in advance of concreting. It is desirable to lay a layer of water proofing
paper then even concrete can be laid directly over the soil sub grade.
Prepared sub grade should complete the following requirements:
i.

There should not be any soft patches on the prepared


sub grade.

ii.

Sub grade should present the uniform support to the


concrete slab.

iii.

Should be properly drained.

iv.

Minimum modulus of sub grade reaction obtained with


plate bearing test should be 5.5 kg / cm 2.

v.

If water proof paper is to be laid directly over the sub


grade, moistening of sub grade prior to placing of the
concrete over it, is not required. Moistening is
essential in case water proof papers is not used.

b. Preparation Of Sub Grade


When formation soil is very poor quality, or traffic load expected on
the pavement is very heavy, a 15 cm thick sub base layer may be used
over the prepared sub grade before lying of cement concrete slab. The
sub base slab may consist of:
i.

One layer of flat brick soling below one layer of Water


Bound Macadam.

Highway Engineering
ii.

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Two layers of Water Bound Macadam may consists of


stone, hard rock, dense blast furnace slag, brick
aggregate or any other granular material which is not
likely to soften under action of water.

iii.

Well graded soil gravel mixture.

iv.

Soil stabilized with 3 4 % lime or cement.

v.

Lime concrete or lean concrete giving 28 days


compressive strength in the field as 40 60 kg / cm 2.

vi.

Existing macadam sub base.

vii.

Existing black top surface sub base.

From i to v, all the points are for new constructions and can be
adopted as per design requirements. But vi and vii points are for existing
sub base and thus have been given in details:
Existing Macadam Sub Base .In case concrete slabs are to be
laid on existing Water Bound Macadam roads, it should be seen that
Water Bound Macadam should extend at least 30 cm beyond the
proposed concrete slab edges. Water Bound Macadam should be at least
15 cm thick. If Water Bound Macadam surface is smaller in width than the
proposed width of the concrete slab up to 30 cm on either side, the extra
width may be developed by placing 10 cm of 1: 4: 8 lean cement concrete.
Black Topped Surface. Where concrete slab is to be laid over
existing black topped surface no special treatment is necessary.
Concrete should not be laid on black topped surfaces having soft spots
caused by excessive bitumen or where thick premixed carpets have been
rutted badly under traffic. In such cases entire surfacing material should
be removed up to the top of compacted macadam and the surface should
be prepared as explained in existing Water Bound Macadam surfaces.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

c. Fixing Of Forms.
Forms may be made from mild steel channel sections or wooden
planks. Depth of the forms should be equal to the thickness of the slab to
be provided. Length of the section for side forms is kept at least 3 m
except on curves of less than 45 m radius where shorter lengths Wooden
forms should be dress on one side and should have a minimum base
width of 10 mm for slab thickness of 20 cm and have a minimum base
width of 15 mm for slabs over 20 cm thickness. Deviation of more than 3
mm in a length of 3 m should not occur when forms are filled with
concrete. Sufficient number of stakes or pins should be put at the back of
the form to impart sufficient support to it.
d. Batching Of Materials And Mixing.
Cement is measured in number of bags. If cement stored in silos is
used, its weight is taken as 1440 kg / m 3. Course aggregate and fine
aggregates are batched in weigh batching plant and put into the hopper of
the mixer along with required quantity of cement. Water is measured by
volume. The mixing of each batch should be at least for 1 minutes
counted after all the materials have been put into the mixer.

Channel
Spike of
Needles

A
PLAN
Prepared Subgrade

Section at A-A

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

e. Carrying And Placing Of Concrete


Prepared premix is carried immediately to the place of actual use
by filling into wheel barrows, hand carts or baskets. While concreting, it
should be ensured that there is on segregation in the concrete. Concrete
put at site is spread uniformly as per requirements of the thickness of the
slab. While being placed, the concrete should be rodded so that the
formations of voids or honey comb pockets are prevented. The concrete
should be particularly well placed and tapped against the forms and along
all the joints.
f. Compaction And Finishing
After having uniformly spread, the concrete is compacted either
with the help of power-driven finishing machine or by vibrating screed. For
constrained areas like corners and junctions, hand compaction can be
done using tampers. Hand tamper is also known as hand tamping beam. It
consists of a wooden beam 10 cm wide and 25 cm depth. Length of the
tamping beam should be equal to the width of the slab plus 30 cm. A steel
plate is fixed at the under side of this beam. Tamper is used by placing it
on the side forms. Tampers are lifted and dropped to affect compaction.
Tamper beam is provided with handles to lift and drop.
g. Floating And Edging
After compaction, with vibrating screed or tamper, the concrete is
further compacted and smoothened by means of longitudinal floats. The
float is worked longitudinally with sawing motion from one edge of the
pavement to the other edge. After this operation, excess water gets

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

disappeared but while concrete is still plastic; the surface of the slab
should be tested for trueness with the help of 3 m straight edge.

h. Belting and Edging


Just before the concrete becomes non-plastic, the surface should
be belted with the help of a two-ply canvas belt which is usually 20 cm
wide and at least 1 m longer than the width of the slab. The belt is worked
on the surface in transverse direction in short forward and back ward
strokes.
After belting and as soon as surplus water disappears from the
surface, the pavement is given a broomed finish with an approved steel or
fiber broom not less than 45 cm wide. The broom should be pulled gently
over the surface of the pavement from edge with each stroke slightly over
lapping the adjacent one.
After belting and brooming and before the concrete has taken initial
set, the edges of the slab should be carefully finished with an edger of 6
mm radius.

25 CM

ELEVATION
10 CM

PLAN

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

i. Curing
Immediately after finishing, the entire surface of the newly laid
concrete should be covered against rapid drying with wetted burlap, cotton
or jute mat. Covering operation with wet burlap is known as initial curing.
Burlap curing is carried out for at least two days. After this, wet burlaps are
removed and surface is covered either with damp saturated sand or with
free water. Final curing can also be done by applying an impervious
membrane which does not impart slipperiness to the pavement.
Impervious membrane which is in form of liquid, is applied under pressure,
covering the entire surface uniformly. The liquid may be applied
immediately after finishing of the surface and before the set of the cement
has taken place. If the pavement is first covered with burlap it may be
applied upon removal of the burlap. This method of curing can be adopted
at places where there is scarcity of water.

k. Final Surface Check


This check is done after curing period when curing sand has been
removed from the surface. Undulations in the surface should not exceed 6
mm in length of 3 m.
l. Removing The Forms.
Forms should be removed after a lapse of about 12 hours from
placing of concrete. Forms should be removed carefully avoiding any
damage to the pavement edges.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

m. Sealing Of The Joints.


After curing period, and before the pavement is opened to traffic, all
the joints should be cleared of intruded materials and suitable sealing
material put into them.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

INPUT

7.5

JOINTS IN CEMENT CONCRETE ROADS


Effective system of joints is essential feature in the successful functioning

of the cement concrete roads. Tie bars and dowel bars are provided to maintain
the strength of the pavement at the joints and also to act as load transfer
devices. Joints in cement concrete pavements can be classified under three
headings:
a. Expansion joints
b. Contraction joints
c. Warping or hinged joints
Expansion joints provide space into which pavement can expand. These
joints release compressive stresses developed in the concrete slab. Expansion
joints also relieve stresses caused by construction and warping.
Contraction joints relieve tension developed in the concrete due to
contraction. They prevent formation of irregular cracks contraction joints also
relieve stresses due to warping.
Warping joints relieve stresses due to warping effect develops in the slab.
These joints are commonly used for longitudinal joints dividing the pavement into
lanes. Warping tendencies are set up in the concrete slab due to temperature
difference between top and bottom of the slab. At 12 noon the temperature at the
top surface of the slab will be higher than that at the bottom. This causes top
fibres of the slab to expand by larger amount than the bottom fibres and slab

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

warps down wards at the edges. Similarly at 12 night, the temperature of the
bottom of the slab is higher than the temperature at the top of the slab and slab
warps upwards at the edges. Weight of the slab tries to prevent this warping of
the slab and thus warping stresses are set up. Intensity of warping stress is
maximum at the interior and minimum at the edges.
Joints in concrete slab pavement can also be classified according to their
direction in relation to the road alignment. Joints constructed in the direction,
perpendicular to the alignment of the road are termed as transverse joints. Joints
constructed in the direction of alignment known as longitudinal joints.
a. Tranverse Joints
Arrangements of tranverse joints may be staggered, square or
skew. All these arrangements are shown in figure below. Out of these
arrangements, square arrangement is the best.

Dowel Bars

Tie Bars

Expansion Joints

Contraction Joints

Figure : Square System Of Joints

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

Dowel Bars

C3010 / UNIT

Staggered Transverse Joints


Longitudinal Joints

Cracks

Figure : Staggered System Of Joints

Skew Joints

Cracks

Tie Bars

Figure : Skew System Of Joints


In case of staggered arrangement, it is seen that cracks known as
sympathetic cracks are developed in the adjoining longitudinal strip just in front of
transverse joints already provided skew arrangement should not be adopted
because in this case acute corners generally get crushed away. Transverse
joints can be further classified as follows:

iv.

i.

expansion joints

ii.

contraction joints

iii.

warping joints

construction joints

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

b. Longitudinal Joints.
Spacing of longtudinal joints are determined by the lane widths. If
during consruction of the slab, hand tamping or vibrating hand screeds
have been used, the spacing should be limited to 4 m. Where machines
have been used for all the process involved in concreting and at the time,
more than 6 m width is being laid, an intermediate longitudinal joints
should be provided either by sawing a dummy joint or inserting a mild
steel T-iron to the depth varying from 1/3 to 1/6 of the depth of the slab.
These joints may be plain butt type or butt with tie bars in them. Tie bars
should be bonded in the slabs across longitudinal joints and whilst casting
the first slabs thay may be bent so that one end of them lies along the
forms. After removal of the forms, bars should be straightened so that they
may extend into the concrete placed on the other side of the joint.
Tongued and grooved joints are also sometimes used as the longotidinal
joints.
7.6 JOINT FILLERS AND SEALERS
Joints are place where continuity of the concrete slabs is broken. These
joints if not filled with proper material and allowed to remain open, grit may be
filled in them and subsequently during hot day, the slab may be pushed apart
due to expansion in the slab. Expansion not being allow at the joint due to muck
filled in it. During rains, water will infiltrate through joints into the soil sub grade
thus damaging it. This also results in mud pumping, specially where sub-grade is
made of expensive soils.
Due to above mentioned difficulties; the joints must be filled with such a
material which is compressible, elastic and durable. A material, which is used for
filling the joints, is known as fillers. Some depth at the top of the joints is filled

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

with a material which could seal the joints completely against the entrance of
water. The material which is used for sealing the joint is known as sealer.
Essential properties for fillers are elasticity, compressibility and durability,
where as for sealers adhesion with cement concrete, ductility, resistance to
ingress of dust and durability are the desirable properties.
Material most commonly used as fillers are:
a.

cork or cork bound with bitumen

b.

soft wood

c.

impregnated fibre boards

The recommendations has been made that filler is considered satisfactory


which can be compressed to 50 % of its original thickness by applying a pressure
varying between 7 to 53 kg/cm2 and material should recover at least 70 % of
original thickness after three cycles of applying and removing the load. Also
when compressed to 50 % thickness, the free edge of the filler should not
extrude by more than 6.5 mm, when all other three edges are restrained.
Bitumen either alone or with mineral filler is mostly used as a sealing
compound. Rubber bitumen compound, air blown bitumens etc. can also be
used.

Highway Engineering
7.7

C3010 / UNIT

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

FUNCTIONING OF FILLERS AND SEALERS


Sealer

1.

2.

Figure shows the positions of


the filler and sealer at normal
temperature.

Joint Filler

Sealer
Oughing Out

During hot day, pavement


expands due to rise in
temperature and the open gap
gets reduced. In this condition,
filler gets compressed and
sealer compound may spill out
of joint.
Sealer
Broken

3.

During cold night, the edges of


the pavements move back due
to contraction and open gap will
formed.

Similarly, due to increase gap, sealing film will become thin. If sealer
material is extensible, it will maintain continuity and if its elongation capacity is
poor, it may crack as shown above. So, if defective materials have been used as
fillers and sealers, the difficulty shown above may arise and render the joint
permeable, through which water or other foreign matter may enter the gap and
may affect sub-grade or displace the slabs.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

ACTIVITY 7

TEST YOUR UNDERSTANDING BEFORE YOU CONTINUE WITH THE NEXT


INPUT

Question

1.

State three types of cement concrete roads.


a. _____________________________
b. _____________________________
c. _____________________________

2.

State the stages of cement concrete pavement construction.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

FEEDBACK ON
ACTIVITY 7
Answer

1.

2.

i.

Cement concrete slab pavements

ii.

Cement grouted macadam pavements

iii.

Roller concrete layer pavements.

Construction of cement concrete pavement involves following


stages:
a.

Preparation of sub grade.

b.

Preparation of sub base.

c.

Fixing of farm.

d.

Batching of materials and mixing.

e.

Carrying and placing concrete.

f.

Compaction and finishing.

g.

Floating and edging.

h.

Belting and edging.

i.

Curing.

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Question
1.

Joints in cement concrete pavements can be classified into three


categories. Describes them.

2.

Describe the preparation of sub-on a good soil formation

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Answer
1.

Expansion joints provide space into which pavement can expand.


These joints release compressive stresses developed in the
concrete slab. Expansion joints also relieve stresses caused by
construction and warping.
Contraction joints relieve tension developed in the concrete due to
contraction. They prevent formation of irregular cracks contraction
joints also relieve stresses due to warping.
Warping joints relieve stresses due to warping effect develops in
the slab. These joints are commonly used for longitudinal joints
dividing the pavement into lanes. Warping tendencies are set up in
the concrete slab due to temperature difference between top and
bottom of the slab. At 12 noon the temperature at the top surface of
the slab will be higher than that at the bottom. This causes top
fibres of the slab to expand by larger amount than the bottom fibres
and slab warps down wards at the edges. Similarly at 12 night, the
temperature of the bottom of the slab is higher than the
temperature at the top of the slab and slab warps upwards at the
edges. Weight of the slab tries to prevent this warping of the slab
and thus warping stresses are set up. Intensity of warping stress is
maximum at the interior and minimum at the edges.

2.

Preparation Of Sub Grade

Highway Engineering

CONSTRUCTION OF
RIGID/CONCRETE PAVEMENT

C3010 / UNIT

Where formation soil is of very good quality, cement slab may


directly be laid over the prepared sub grade. The top 15 cm layer of
the sub grade should be compacted and checked for trueness by
mean of scratch template. Unevenness of the surface should not
exceed 12 mm in 3 m length. Sub grade should be prepared and
checked at least two days in advance of concreting. It is desirable
to lay a layer of water proofing paper then even concrete can be
laid directly over the soil sub grade. Prepared sub grade should
complete the following requirements:
i.

There should not be any soft patches on the prepared


sub grade.

ii.

Sub grade should present the uniform support to the


concrete slab.

vi.

Should be properly drained.

vii.

Minimum modulus of sub grade reaction obtained with


plate bearing test should be 5.5 kg / cm 2.

viii.

If waterproof paper is to be laid directly over the sub


grade, moistening of sub grade prior to placing of the
concrete over it, is not required. Moistening is
essential in case waterproof papers are not used.