You are on page 1of 74

Abbott Risk Consulting Limited

Woodfibre PMC Project Safety Studies


HAZID Study Report

Prepared for:

Woodfibre PMC
111 Dunsmuir Street
Vancouver, B.C.
Canada, V5B 5W3

ARC-579-002-R01
Issue 02
April 2015
Page 1 of 50

Abbott Risk Consulting Limited

APPROVAL AND REVISION RECORD


Issue
No.

Date

Prepared

01

October 2014

S Cowie

02

April 2015

S Cowie

Reviewed

Approved

Revision Notes

C Rettie

M OFlaherty

First Issue

C Rettie

M OFlaherty

Minor editorial
comments
addressed

Abbott Risk Consulting Ltd.


11 Albyn Place
Edinburgh
Scotland
EH2 4NG
United Kingdom
Phone: +44 (0) 131 220 0164

www.consultarc.com
ARC-579-002-R01
Issue 02
April 2015
Page 2 of 50

Abbott Risk Consulting Limited

Executive Summary
Abbott Risk Consulting Ltd. (ARC) was contracted by Woodfibre PMC to conduct a
HAZID (HAZard IDentification) study of the Woodfibre LNG project. The workshop
was held from the 6th October to the 9th October 2014 at the AMEC Offices in
Vancouver, B.C.
The HAZID covers the Woodfibre LNG facility site as a whole and was conducted in
accordance with BC OGC Liquefied Natural Gas Facility Permit Application and
Operations Manual [Ref 1], CSA Standards Liquefied Natural Gas Production,
Storage and Handling Z276-11 [Ref 2] and the associated Z276-11 update 01 [Ref
3].
The HAZID forms part of a series of Safety Studies which have been performed in
order to reduce risk to a level as low as reasonably practicable (ALARP) and to
demonstrate compliance with the above requirements.
The HAZID consisted of a review and update of the previous HAZID/ ENVID study
of the process areas (conducted for previous the Woodfibre facility FLNG-based
design), which was carried out in April 2014 [Ref 4], with additional nodes
considered, in order to extend the HAZID to cover the site as a whole.
A total of 98 recommendations were made during the HAZID study, provided in
Appendix B.
Completed worksheets for the HAZID study are provided in Appendix A.

ARC-579-002-R01
Issue 02
April 2015
Page 3 of 50

Abbott Risk Consulting Limited

Abbreviations
ALARP

As Low As Reasonably Practicable

AFP / PFP

Active Fire Protection / Passive Fire Protection

AR

Approval Required

ARC

Abbott Risk Consulting Ltd.

BC

British Columbia

BOG

Boil Off Gas

BOP

Balance Of Plant

BLEVE

Boiling Liquid Expanding Vapour Explosion

COC

Certificate Of Compliance

CR

Confirmation Required

DAL

Design Accidental Load

EA

Environmental Assessment

EIA

Environmental Impact Assessment

EERA

Escape, Evacuation and Rescue Assessment

ENVID

Environmental [hazard] Identification

ESD / EDP

Emergency Shut Down / Emergency Depressurisation

ESDV

Emergency Shut Down Valve

FERA

Fire and Explosion Risk Assessment

FLNG

Floating Liquefied Natural Gas vessel

FSO

Floating Storage and Offloading vessel

HAZID

Hazard Identification

HAZOP

Hazard and Operability

IGG

Inert Gas Generator

KO

Knock Out

LE

Linde Engineering

LER

Local Equipment Room

LNG

Liquefied Natural Gas

LP / HP

Low Pressure / High Pressure

OGC

[BC] Oil and Gas Commission

OSBL

Outside Battery Limit

PMC

Project Management Company

PMT

Project Management Team

ARC-579-002-R01
Issue 02
April 2015
Page 4 of 50

Abbott Risk Consulting Limited

Abbreviations (Continued)
PPE

Personnel Protective Equipment

PSV

Pressure Safety Valve

QRA

Quantified Risk Assessment

RPT

Rapid Phase Transition

SCE

Safety Critical Element

SIS

Safety Instrumented System

TERMPOL

Technical Review Process of Marine Terminal Systems


and Transhipment Sites

VCE

Vapour Cloud Explosion

WLNG

Woodfibre LNG

ARC-579-002-R01
Issue 02
April 2015
Page 5 of 50

Abbott Risk Consulting Limited

Contents
1.0
1.1
1.2
1.3
2.0
2.1
2.2
2.3
2.4
3.0
4.0
5.0
6.0
7.0

Introduction ................................................................................................................ 7
Overview ................................................................................................................... 7
Objective of the Study................................................................................................ 7
Scope of the Study .................................................................................................... 7
HAZID Study Methodology ........................................................................................ 9
Purpose ..................................................................................................................... 9
Methodology .............................................................................................................. 9
Guidewords ............................................................................................................. 10
Recording and Reporting ......................................................................................... 11
Study Team ............................................................................................................. 12
Nodes ...................................................................................................................... 13
Drawings ................................................................................................................. 15
Results ....................................................................... Error! Bookmark not defined.
References .............................................................................................................. 16

Appendices
Appendix A HAZID Worksheets
Appendix B HAZID Recommendations

ARC-579-002-R01
Issue 02
April 2015
Page 6 of 50

Abbott Risk Consulting Limited

1.0

Introduction

1.1

Overview
Abbott Risk Consulting Ltd. (ARC) was contracted by Woodfibre PMC to conduct a
HAZID (HAZard IDentification) study of the Woodfibre LNG project. The workshop
was held from the 6th October to the 9th October 2014 at the AMEC Offices in
Vancouver, B.C.
The HAZID study consisted of a multi-disciplined team review of the Woodfibre LNG
facility phase 1 design. The study used a step-by-step methodology and a checklist
of guide words to identify hazards and assess the influence these hazards may have
on the project development strategy.
The relevant causes of the accidental events leading to hazardous situations were
analysed and recorded in the HAZID Worksheets, provided in Appendix A.

1.2

Objective of the Study


The objective of the Study was to review all elements of the engineering design of
the Woodfibre LNG facility. The HAZID covered safety and environmental hazards.
Where improvements could be made to mitigate or eliminate these hazards or to
improve the level of risk reduction provided by safety functions, recommendations
were outlined and assigned to relevant departments in order to reduce risk to a level
as low as reasonably practicable (ALARP). A full list of recommendations is provided
in Appendix B.

1.3

Scope of the Study


The HAZID study reviewed the engineering design of the Woodfibre LNG project,
as represented on the project drawings listed in Table 5.1.
The HAZID covers the Woodfibre site as a whole and was conducted in accordance
with BC OGC Liquefied Natural Gas Facility Permit Application and Operations
Manual [Ref 1], CSA Standards Liquefied Natural Gas Production, Storage and
Handling Z276-11 [Ref 2] and the associated Z276-11 update 01 [Ref 3].
The HAZID forms part of a series of Safety Studies which have been performed in
order to reduce risk to a level as low as reasonably practicable (ALARP) and to
demonstrate compliance with the above requirements, and has raised specific
recommendations, where required, in order to address any issues that the team
identified.
The HAZID consisted of a review and update of the previous HAZID/ ENVID study
of the process areas (conducted for the previous FLNG-based design of the
Woodfibre facility), which was carried out in April 2014 [Ref 4], with additional nodes
considered, in order to extend the HAZID to cover the site as a whole.
The following nodes were reviewed as part of the HAZID study:
General node ( to record hazards that are ubiquitous throughout the facility);
LNG train, updated from previous HAZID/ ENVID study:
o
o
o

Inlet Facilities;
Liquefaction and Refrigeration;
Refrigerant Make-up and Fractionation Area;
ARC-579-002-R01
Issue 02
April 2015
Page 7 of 50

Abbott Risk Consulting Limited

LP Compression, End Flash and Fuel Gas System; and

o Substation.
Additional nodes considered, in order to extend the HAZID to cover the site as
a whole.
o

BOP (Balance of Plant);

Flare Systems;

FSO (Rundown and Storage Mode); and

LNG Offloading.

Complete node listings and information on what each node covers are shown in
Table 4.1.
The HAZID considered only the operational phase of the site. Construction and
commissioning activities will be considered separately.
It is also noted that marine operations, including the berthing of LNG carriers at the
FSO, will be assessed in a TERMPOL study. The HAZID did not consider marine
operations.

ARC-579-002-R01
Issue 02
April 2015
Page 8 of 50

Abbott Risk Consulting Limited

2.0

HAZID Study Methodology

2.1

Purpose
The overall purpose of HAZID study is to focus the attention of the Project team on:
The impact of the operations on surroundings;
The impact of the surroundings on the operations;
The interferences between the main items;
The general hazards and particular aspects of the project which require special
development in order to contain any hazards identified; and
Any further analysis required to produce an effective design (separation
distances, toxicity of materials, flammability limits, etc.).
A HAZID study provides a structured and analytical approach to hazard
identification. It is a brainstorming exercise, guided by a typical set of guidewords,
and taking benefit from the previous experience of the HAZID study team members.
The HAZID study is used to identify hazards associated with the project operations
and recommend improvements, modifications, or further studies where preventative
/ mitigative safety measures are required.
Conducting the HAZID study allows inherently safe features to be adopted as the
design evolves. Hazards can then be eliminated or, if this is not possible, have their
consequences reduced and taken into account in early design, rather than later in
the project lifecycle, in order to reduce risk to a level as low as reasonably
practicable (ALARP).
The concept of ALARP is defined by BC OGC [Ref 1] as follows:
The concept of ALARP defines how the Commission measures risk mitigation and
gives a goal to the risk management process. Demonstrating ALARP is a critical
element to satisfying the Commission that all safety and environmental risks have
been appropriately managed. A design that can demonstrate ALARP will have
reduced the risk until the incremental sacrifice (in terms of time, effort, cost, or other
expenditure of resources) is grossly disproportionate to the value of incremental risk
reduction achieved.
It is to be noted that a HAZID study is not an audit. Also, a HAZID study does not
preclude the need for further hazard assessment; instead, it is a precursor to
subsequent hazard analyses and risk assessments.

2.2

Methodology
HAZID studies are systematic, multi-disciplinary reviews carried out on a process
design to identify major hazards (and thereby potential major accident events
safety or environmental related) associated with the site or operation of the process.
The technique exhaustively considers each review area, by reference to an agreed
set of guidewords.
This HAZID study applied the Guideword Method, where the operation was broken
down into manageable sections (nodes), and a set of standard guidewords was

ARC-579-002-R01
Issue 02
April 2015
Page 9 of 50

Abbott Risk Consulting Limited

applied. The structure of the HAZID was to only consider events / concerns that
arise within the node being reviewed at the time.
Once all the events had been identified then the ultimate consequences of each
event / concern was identified irrespective of any safeguards that may be in place.
The HAZID team then considered the risk, taking into account existing safeguards,
and, where necessary, recommended additional safeguards as actions.
The HAZID methodology can be summarised by the following sequential steps:
Select a Sub-operation (referred to as a node);
Apply a guideword to act as a prompt;
Identify the events relevant to that guideword;
Identify the ultimate consequences associated with the events irrespective of
safeguards;
Identify the existing safeguards;
Decide on any actions to eliminate or mitigate the identified problem if
necessary;
Repeat for other guidewords as relevant; and
Repeat for all sub-systems.

2.3

Guidewords
The HAZID study methodology followed a set of standard guidewords.
It is noted that these guidewords are not necessarily exhaustive and are intended
to prompt the team to consider as broad a range of potential scenarios as possible.
The team were encouraged to think outside the box and challenge the design in
any way they could, regardless of whether a challenge falls under one of the specific
guidewords.
Two sets of generic guide words were selected for use in this HAZID study; one set
for the general node to record any hazards that are ubiquitous throughout the facility
and another set which was applied for each specific node. These are shown in Table
2.1 and Table 2.2, respectively.
Table 2.1 HAZID General Node Guidewords
Guidewords
Pressure and Temperature Safeguarding Concept
Concept for Safety Instrumented System (SIS)
Explosion Protection Concept
Fire & Gas Detection Concept
Fire Protection Concept
Concept for Block-in and Depressurising System
Flare Concept

ARC-579-002-R01
Issue 02
April 2015
Page 10 of 50

Abbott Risk Consulting Limited


Guidewords
Concepts for Occupational Health and Safety
e.g.
- Escape Route and Rescue Concept
- Eye and Emergency Shower Concept
- PPE Concept
- Safe Location Concept
- Safety Sign Concept
Concepts for Environmental Protection
e.g.
- Noise Control Concept (including noise control - marine)
- Emission Control Concept
- Drainage & Effluent Treatment Concept
- Waste Management Concept
Impact of the site on the human environment
Communication links with the facility
Effects on the plant of environmental constraints

Table 2.2 HAZID Specific Node Guidewords


Guidewords
External Fire
Internal Fire
External Explosion
Internal Explosion
Exposure to harmful substances (acute/chronic)
Noise
Environmental Pollution
HAZARD from OSBL
Continuous / frequent plant discharges to air
Continuous / frequent plant discharges to water
Continuous / frequent plant discharges to soil
Emergency / upset discharges

2.4

Recording and Reporting


During the study each hazard identified by the Team, together with the potential
consequences, designed safeguards and required actions, were recorded in a

ARC-579-002-R01
Issue 02
April 2015
Page 11 of 50

Abbott Risk Consulting Limited

HAZID worksheet, using the process hazard analysis software package PHA-Pro
version 8.3.2.0.
The HAZID worksheets were displayed at all times via a data projector, to enable
the entire team to view the study documentation in real-time. This allowed any
corrections to be made as and when required, and an overall consensus to be
achieved from the participants, and hence the HAZID record is considered to be a
direct representation of the views of all personnel present during the workshop
discussions.

3.0

Study Team
A list of personnel that participated in the HAZID study and their attendance is listed
in Table 3.1.
Table 3.1 HAZID Study Team
Team Members
Full Name

Department

Sessions
Company 06/10/2014
PMC

Present

07/10/2014

08/10/2014

Present

09/10/2014

Penny Armitage

Eng Manager

Paul Baluch

Civil Project Engineer PMC

Present

Peter Barry

Structural Lead

PMC

Present

Charles Casgrain

Project Engineer

BOP

Gurprit Chahal

Water Treatment

BOP

Steve Cowie

Scribe

ARC

Present

Sepidah Dalil

Process

BOP

Present

Frank Hamilton

Technical Manager

PMT

Partial

Meetal
Khanderia

Project Engineer

BOP

Ken Leong

Process Engineer

Solaris Flare

Michelle Ng

Project Engineer

M&N

Colin Rettie

Chairman

ARC

Present

Present

Present

Paul Robinson

Integration manager PMC

Present

Present

Present

Dietrich Roeben

Operations and Start- PMC


up Manager

Cristian Ruilova

Prject Manager

PMT

Jim Ryan

Tech Safety Lead

PMC

Farhad
Shushtarian

Project Manager

M&N

Partial

Alex Taimuri

BOP Engineering

BOP

Partial

Mario Tancredi

Project Manager

Solaris Flare

Present

Present

Present

Present

Partial
Present

Present

Present

Present
Present

Present

Present

Partial

Partial

Partial

Partial

Partial

Present

Partial
Partial
Present

Present

Partial
Present

Present
Partial

Present

Present

Partial

ARC-579-002-R01
Issue 02
April 2015
Page 12 of 50

Abbott Risk Consulting Limited


Team Members
Full Name

4.0

Sessions

Department

Company 06/10/2014

Joan Wang

Process

PMC

Yan Zhang

Engineering Manager PMT

Amanda Zinter

Regulatory
Compliance

PMT

Present

07/10/2014

08/10/2014

Present

Present

Present

Present

Partial

Partial

Partial

Present

09/10/2014

Nodes
The HAZID study was broken down into nodes, as described in Table 4.1.
It is noted that nodes 1 to 6 are nodes were carried out by a review and update of
the previous HAZID/ ENVID study of the process areas (conducted for an FLNGbased design), which was carried out between the 23rd April and the the 25th April
2014 at the Linde Engineering offices in Pullach, Munich, Germany [Ref 4]. Nodes
7 to 10 are additional nodes considered, in order to extend the HAZID to cover the
site as a whole.
Table 4.1 HAZID Node List
Nodes

Comment

1. General Node

This node addresses external hazards affecting the whole site area in general, and
general site philosophies which apply to multiple areas.

2. Inlet Facilities

Streams: Feed gas, amine, CO2, waste water.

Feed gas is treated by mercury removal bed, then acid gas removal by amine system,
finally dehydrated by molsieves.

Acid gas stream is treated in catalytic oxidiser and vented to atmosphere.

System located in modules 1 and 2.


3. liquefaction and

Two identical trains in modules 4 and 6.

Refrigeration.
Inventories: Feed gas producing LNG, mixed refrigerant cycle with gas and liquid
phases (methane, ethane, N2, butane, traces of propane).

Electrical drive compressors.


4. Refrigerant Make-up and

Located in module 5.

Fractionation Area.
Inventories: Butane and ethane/ ethylene storage in LP tanks - ethane at low
temperature.

ARC-579-002-R01
Issue 02
April 2015
Page 13 of 50

Abbott Risk Consulting Limited


Nodes

Comment
Fractionation produces required refrigerants from feed gas and removes heavier
condensate.

Flare KO drums are also located in the module.


5. LP Compression, End

Located in module 3.

Flash and Fuel Gas


System.

BOG from storage and flash gas from end flash drum are compressed and returned
to the main process.

End flash drum for LNG product and LNG transfer pumps are also in this area.
6. Substation

Includes substation and electrical equipment, within a building.

Note: Originally considered utility area on the FLNG. Apart from hot oil, these have
been relocated into the utility area - See BOP node. Hazards relating to the hot oil
heater are now considered in node 2.
7. BOP

Includes:
-Utilities (instrument air / plant air, N2, plant water, tempered cooling water, sea water
cooling system)
-Chemical storage
-Effluent / waste water treatment
-Substations (x3)
-Condensate storage and truck loading
-Utility gas supply to building heating and flare
-Diesel storage and truck filling
-Emergency generation
-Non-process buildings (warehouse and storage areas, maintenance building, admin
building, control room and lab, temporary construction and engineering building,
canteen)
-firewater tank and water supply, including water source from Henriette dam
-Landfill and leachate treatment
-Access to site (small craft and material jetties)

It is noted that flares/ LNG rundown system/ feed gas pipeline, although part of BOP
scope, are considered in relevant specific nodes (flare node 8 / LNG offloading 10).
8. Flare Systems

4 x elevated flares- HP warm and cold, LP warm and cold, located on a common
support structure.

Currently KO drums etc. are located in the LNG train.

Flares are air-assisted, smokeless flares, with N2 purge and continuous pilots.
9. FSO (Rundown and
Storage Mode)

Two existing LNG carriers will be converted into a single floating storage and
offloading unit. The hulls will be welded into a single structure and manifolds will be
combined in a single system.

ARC-579-002-R01
Issue 02
April 2015
Page 14 of 50

Abbott Risk Consulting Limited


Nodes

Comment
Storage consists of 10 Moss-type tanks, each with two offloading pumps and
associated manifold systems. New boil off gas recovery compressors and inert gas
generator / dry air system will be provided.

Utilities are primarily provided from shore via hoses on the utility bridge, but backup
N2 generation/ emergency power will be onboard.

Existing ships fire water system will be retained and upgraded.

The FSO will be controlled by a common control system with the plant. Local control
will also be provided onboard.

The FSO is permanently moored by vertical piles and LNG rundown, BOG and other
process connections are connected via permanently connected flexible loading arms.

Personnel access points are provided at fore and aft ends. The aft access is also
suitable for small mechanical handling (2.5 T)
10. LNG Offloading

5.0

This node considers the FSO during the operation to offload LNG into an adjacent
LNG Carrier.

Drawings
Table 5.1 lists all drawings referred to during this study.
Table 5.1 Drawings Used in the HAZID Study
Drawing

Description

Place(s) Used

3861-MM-PD-101-001 Rev 03

FSO Layout Drawing

Nodes: 9, 10

176258-0000-DD10-LYD-1201 Rev A

Civil - Plan -Site Layout

Nodes: 1

176258-0300-DD00-BLD1001.001 Rev C Block Flow Diagram

Nodes: All

176258-0300-DD10-LYD-1501 Rev D

Site Layout Drawing

Nodes: All

&AA-05-P-FF 01 Rev C1

Inlet Facilities - Inlet Facilities

Nodes: 2

&AA-12-P-FF 01 Rev C1

Sour Gas Removal/ Mercury Removal - Sour Gas Nodes: 2


Removal/ Mercury Removal

&AA-12-P-FF 02 Rev C1

Sour Gas Removal/ Mercury Removal - Solvent


Removal

Nodes: 2

&AA-16-P-FF 01 Rev C1

Dehydration - Gas Dehydration

Nodes: 2

&AA-16-P-FF 02 Rev C1

Dehydration - Regeneration Cycle

Nodes: 2

&AA-23-P-FF 01 Rev C1

liquefaction - Main Cryogenic Heat Exchanger 1

Nodes: 3

&AA-23-P-FF 02 Rev C1

liquefaction - Main Cryogenic Heat Exchanger 2

Nodes: 3

&AA-23-P-FF 03 Rev C1

liquefaction - HHC Removal Column 1

Nodes: 3

ARC-579-002-R01
Issue 02
April 2015
Page 15 of 50

Abbott Risk Consulting Limited


Drawing

6.0

Description

Place(s) Used

&AA-23-P-FF 04 Rev C1

liquefaction - HHC Removal Column 2

Nodes: 3

&AA-23-P-FF 05 Rev C1

liquefaction - End Flash

Nodes: 5

&AA-41-P-FF 01 Rev C1

Refrigeration -Refrigerant Cycle Compression 1

Nodes: 3

&AA-41-P-FF 02 Rev C1

Refrigeration -Refrigerant Cycle Compression 2

Nodes: 3

&AA-47-P-FF 01 Rev C1

Refrigerant Make Up System - Refrigerant Make


Up Tanks 1

Nodes: 4

&AA-47-P-FF 02 Rev C1

Refrigerant Make Up System - Refrigerant Make


Up Tanks 2

Nodes: 4

&AA-50-P-FF 01 Rev C1

Fractionation System - Deethanizer

Nodes: 4

&AA-50-P-FF 02 Rev C1

Fractionation System - Debutanizer

Nodes: 4

&AA-78-P-FF 01 Rev C1

Tank Return Gas System - LP Tank Return Gas


Compression

Nodes: 5

&AA-78-P-FF 02 Rev C1

Tank Return Gas System - HP Tank Return Gas


Compression

Nodes: 5

&AA-84-P-FF 01 Rev C1

Fuel Gas System - Fuel Gas Distribution

Nodes: 4

&AA-90-P-FF 01 Rev C1

Flare Gas and Vent System - Warm Flare System Nodes: 4

&AA-91-P-FF 01 Rev C1

Flare Gas and Vent System - Flare Package

Nodes: 4

Conclusions and Recommendations


The complete HAZOP worksheets are provided in Appendix A.
A total of 98 recommendations were made during the course of the HAZID study.
The complete list of recommendations, along with the responsible party are provided
in Appendix B.
It is concluded that a comprehensive HAZID review has been conducted appropriate
to the current stage of design, and that major accident hazards have been identified
and will be managed by addressing the recommendations.

7.0

References
BC Oil & Gas Commission: Liquefied Natural Gas Facility Permit Application
and Operations Manual, July 2014, Version 1.0
CSA Standard Z276-11: Liquefied Natural Gas (LNG) - Production, Storage,
and Handling, December 2011
CSA Standard Z276-11: Update 1, February 2014
Woodfibre FLNG HAZID/ ENVID Study Report, ARC-027-103, Abbott Risk
Consulting, April 2014 Issue-01.

ARC-579-002-R01
Issue 02
April 2015
Page 16 of 50

Abbott Risk Consulting Limited

Appendix A
HAZID Worksheets

ARC-579-002-R01
Issue 02
April 2015
Page 17 of 50

Abbott Risk Consulting Limited


Node: 1. General Node
Guide
Word/Deviation
Pressure and
Temperature
Safeguarding
Concept

Causes

Consequences

1.1. Exceeding design


1.1.1. Loss of containment leading to
conditions in process
fire/ explosion hazard.
upset.

Safeguards

Recommendations

Resp

1.1.1.1. &AA S-PC 1001 - Pressure and 67. Confirm that consistent pressure and PMC temperature process
temperature safeguarding
Process
safeguarding philosophy for
philosophies are developed for BOP,
LNG train, has been prepared
flare and FSO scopes, and cover
and aligned with CSA Z276.
interfaces with the LNG train.

Category
CR

1.1.1.2. HAZOP study at later design


stages.
Concept for Safety
Instrumented
System (SIS)

2.1. Incompatible safety 2.1.1. Loss of safety functions.


systems.

2.1.1.1. &AA S-PC 1002 - Safety


Instrumented Systems
philosophy for LNG train.

1. Ensure that Safety Instrumented


Systems (SIS) philosophies for all
areas are compatible, as these form
part of a single plant SIS.

PMC

CR

Previous HAZID Recommendation 1


Explosion Protection 3.1. Ignited gas release
Concept
on LNG train

3.1.1. Escalation to SCEs (Safety


Critical Elements), risk to
personnel.

3.1.1.1. Low-manned facility.


3.1.1.2. Manned buildings remote from
LNG.

68. Confirm that consistent fire and


PMC CR
explosion protection philosophies are Fire
developed for BOP, flare and FSO
Protection
scopes, and cover interfaces with the
LNG train.

3.1.1.3. Siting study to be carried out,


including separation of
equipment.
3.1.1.4. &AA S-PC 1008 - Explosion
protection philosophy defines
requirements for ignition
prevention for LNG train.
Fire & Gas Detection 4.1. Hydrocarbon release 4.1.1. Fire/ explosion hazard.
Concept

4.1.1.1. &AA S-PC 1009 - Fire and gas 69. Confirm that consistent fire and gas PMC CR
detection philosophy, specifies
detection philosophies are developed Fire
detector coverage requirements
for BOP, flare and FSO scopes, and Protection
(number, location, setpoints,
cover interfaces with the LNG train.
types, actions.) for LNG train.

ARC-579-002-R01
Issue 02
April 2015
Page 18 of 50

Abbott Risk Consulting Limited


Fire Protection
Concept

5.1. Loss of containment 5.1.1. Hazard to personnel, damage to 5.1.1.1. Fire zones.
and fire.
equipment, escalation to other
inventories (including BLEVE of
liquids).

2. Conduct AFP and PFP study to identify PMC the benefits and hazards of deluge in Linde
each area.

AR

Previous HAZID Recommendation 2


5.1.1.2. Potential to blowdown entire
plant in sequences.

70. Confirm that consistent PFP and AFP PMC philosophies are developed for BOP, HSE
flare and FSO scopes, and cover
interfaces with the LNG train.

CR

6.1.1.1. Each module is an ESD zone.

71. Confirm that blowdown philosophy


has been updated to the latest LNG
train configuration, and blowdown
study remains valid.

CR

6.1.1.2. Liquid inventories are not


removed, but fire case relief
loads are considered and
inventories can be
depressurised.

72. Confirm that consistent ESD and EDP PMC philosophies are developed for BOP, Process
flare and FSO scopes, and cover
interfaces with the LNG train.

5.1.1.3. PFP on equipment supports/


structure, as required to meet
DAL (Design Accidental Load)
conditions.
5.1.1.4. Drainage system to minimise
pool fire potential. Very limited
warm liquid inventory.
5.1.1.5. Cryogenic liquid spill
containment system routes
spillages to a spill basin.
5.1.1.6. &AA S-PC 1007 - Active and
passive fire protection (AFP /
PFP) philosophy for the LNG
train.
Concept for Block-in 6.1. Loss of containment. 6.1.1. Loss of multiple inventories
and Depressurising
System

PMC Linde

CR

6.1.1.3. &AA S-PC 1010 - Process


safeguarding ESD isolation and
depressurising systems
philosophy for the LNG train.

ARC-579-002-R01
Issue 02
April 2015
Page 19 of 50

Abbott Risk Consulting Limited


Flare Concept

7.1. Routine and


emergency flaring See flare node

8.1. Working
Concepts for
Occupational Health
environment.
and Safety

8.1.1. Health and safety risks to


workers.

- Escape Route and


Rescue Concept

8.1.1.1. &AA S-PC 1031 - Working


3. Ensure that BC Work Safe BC OHS
Environment Philosophy for the
regulations are complied with in &AA
LNG train.
S-PC 1031 - Working Environment
Philosophy.

- Eye and
Emergency Shower
Concept

PMC Linde

CR

Previous HAZID Recommendation 4


73. Confirm that consistent working
PMC
environment philosophies are
developed for BOP, flare and FSO
scopes, and cover interfaces with the
LNG train.

- PPE (Personal
Protective
Equipment) Concept
- Safe Location
Concept

8.1.2. Inability to escape in a fire


scenario.

- Safety Sign
Concept

8.1.2.1. Multiple escape routes - at least 74. Consider the philosophy for
2 from each area.
evacuation and mustering of whole
site area, including remote locations
such as metering station, flare area,
8.1.2.2. EERA (Escape and Evacuation
fire water tank, etc.
Risk Analysis) will be conducted
for LNG train.

PMC HSE

CR

AR

8.1.2.3. Facility has at least two escape


routes from each main plant
area, including means to
evacuate trapped personnel
from the north end and to
evacuate the main manned area
at the south end.
Concepts for
Environmental
Protection
- Noise Control
Concept (including
noise control marine)
- Emission Control
Concept

9.1. Environmental
considerations.

9.1.1. Atmospheric discharges and flue 9.1.1.1. Plant power is external electric
gasses.
source, to minimise combustion
exhausts.
9.1.1.2. Burners selected for low
emissions.
9.1.1.3. Thermal oxidiser on acid gas
removal discharge.
9.1.1.4. No flaring concept.

ARC-579-002-R01
Issue 02
April 2015
Page 20 of 50

Abbott Risk Consulting Limited


- Drainage & Effluent
Treatment Concept

9.1.1.5. Waste Discharge Permit to be


prepared to meet BC Air Quality
Objective (expected discharges
are well below allowable).
Includes dispersion modeling
assessment.

- Waste
Management
Concept

9.1.2. Water discharges of hydrocarbon 9.1.2.1. See BOP node for water
contamination.
treatment systems.
9.1.3. Water discharges of cooling
9.1.3.1. Discharge consent to meet BC
water with biocide and increased
requirements.
temperature can harm marine
species (See, also, BOP node). 9.1.3.2. Deep intake to minimise biocide
demand.
9.1.3.3. Continuous online monitoring for
temperature and biocide
residue.
9.1.3.4. Outfall location design and depth
to minimise impact to marine life.
9.1.4. Water-borne noise, potentially
9.1.4.1. Equipment designed to control
leading to disturbance to marine
noise and vibration.
life.
9.1.4.2. Water-borne noise modelling
has been carried out and results
submitted with the EIA.
9.1.5. Air-borne noise - Hazard to
personnel/ disturbance to
environment.

9.1.5.1. &AA S-PC 1501 - Noise control 75.


philosophy to meet requirements
of BC OHS and BC noise control
best practice guideline for LNG
train.

Confirm that noise control


PMC
philosophies are developed for BOP,
flare and FSO scopes, and cover
interfaces with the LNG train and that
this meets the requirements of the
site noise limits.

CR

9.1.6.1. Preliminary light pollution impact 86. Confirm that requirements for the EIA PMT
assessment has been carried
are incorporated in the basis of
out for all continuous plant light
design. Note this applies to all
sources.
environmental issues, not just lighting.

CR

9.1.5.2. Initial noise study has been


conducted for the site
9.1.6. Light pollution

9.1.7. Waste generation and transport. 9.1.7.1. Maintenance waste to be


collected for disposal.
ARC-579-002-R01
Issue 02
April 2015
Page 21 of 50

Abbott Risk Consulting Limited


9.1.7.2. Minimal routine waste - no
routine solid process waste
generated by LNG train.
9.1.7.3. All solid waste from BOP areas
(e.g. waste water treatments and
domestic buildings) is
transported off site.
9.1.7.4. EIA has identified all waste
streams and means of disposal.
This will be controlled by waste
management plan.
9.1.8. Hazardous maintenance waste
(e.g. molsieve materials).

9.1.8.1. Transfer to competent contractor 87. Ensure the operations philosophy


PMT
off-site for disposal, under
complies with the requirements of the
EA, for the handling of hazardous
specific procedure.
materials.

Impact of the site on 10.1. Operation of facility 10.1.1. Impact on other users of the
the human
area, e.g. leisure, tourism,
environment
fishing, agriculture.

10.1.1.1. Human health impact


assessment and assessment
of other impacts will be
included in EA.

Communication links 11.1. Ferries


with the facility

11.1.1.1. Sheltered location.

11.1.1. Possible lack of access due to


weather conditions

11.1.1.2. Marine travel procedure.

4. Consider operation for scenario where PMT


site access is not available (due to
weather conditions, boat failure, etc.)
Ensure that safe operation can be
maintained, with personnel on site.

CR

AR

Previous HAZID Recommendation 10


11.1.2. Any attendant vessel accident
(e.g. personnel vehicle ferries,
supply deliveries, etc.)
11.2. Helicopters

11.1.2.1. TERMPOL study, including


marine operation safety in the
area.

11.2.1. Helicopter crash on equipment. 11.2.1.1. Canadian Aviation Regulations 5. Confirm that the helipad locations are
requirements
suitable and meet regulations.
11.2.1.2. Presence of facility and flare
notified to NAV Canada to
inform aviation.

BOP

CR

Previous HAZID Recommendation 11

ARC-579-002-R01
Issue 02
April 2015
Page 22 of 50

Abbott Risk Consulting Limited


Effects on the plant 12.1. Dangerous wildlife 12.1.1. Personnel hazard.
of environmental
(e.g. bears)
constraints

12.1.1.1. Site fence.

76. Confirm location, extent and


specification of site perimeter fence
and control of access at road
crossings and river crossing.

BOP

CR

12.1.1.2. Waste management to avoid


attracting wildlife.

77. Develop wildlife management plan


(including bear hazards).

PMT

CR

12.2. Sea birds.

12.2.1. Build up of guano - personnel


health hazard.

12.2.1.1. Routine cleaning.

12.3. Sabotage

12.3.1. Damage to plant - fire and


explosion hazard.

12.3.1.1. Site fence - no land access, all 76. Confirm location, extent and
personnel are under access
specification of site perimeter fence
control.
and control of access at road
crossings and river crossing.

BOP

CR

12.3.1.2. Exclusion zone, monitored by


patrol vessel.

78. Develop project safety and security


plan, including potential for public
protest.

PMT

CR

78. Develop project safety and security


plan, including potential for public
protest.

PMT

CR

12.3.2. Public protest affecting site or


site personnel.
Extreme Wind/
Wave

13.1. Extreme weather


conditions

13.1.1. Risk of damage to marine


mooring and transfer system See FSO node.
13.1.2. Risk of damage to structures
and buildings on site.

Extreme
Temperature

13.1.2.1. Structures designed for 1/100 79. Confirm that structural/ marine/ civil PMC CR
year wind load combinations.
design criteria are consistent with the Structural
basis of design requirements, for all
areas of the site.
13.1.2.2. Shore protection for the 1/100
year wave conditions

14.1. Ambient conditions. 14.1.1. High ambient temperature 14.1.1.1. Design basis covers expected
possible process disturbance
extreme conditions.
but no hazardous consequence.
14.1.2. Low ambient temperature - Risk 14.1.2.1. Winterisation philosophy to
of freezing in liquid systems.
address low temperature
Potential process hazards.
hazards.

Seismic

15.1. Earthquake.

15.1.1. Damage to structures. Potential 15.1.1.1. Stored inventory on the FSO is


loss of containment.
floating and largely isolated See FSO node.

ARC-579-002-R01
Issue 02
April 2015
Page 23 of 50

Abbott Risk Consulting Limited


15.1.1.2. Design criteria comply with
national building code, with
appropriate importance factor
for LNG.
15.1.1.3. Soil study has been conducted.
LNG train sited in a preferred
zone.
Earthquake
Landslip

17.1. Ground liquefaction 17.1.1. Loss of foundations and


17.1.1.1. Soil study has been conducted.
due to earthquake.
damage to the LNG train, loss of
LNG train sited in a preferred
zone.
containment.
17.1.1.2. Ground improvement
incorporated in to design to
meet building code.
17.1.2. Damage to existing landfill
leading to possible impact on
the plant area.
17.2. Landslip above the 17.2.1. Damage to buildings and
site.
equipment on site. Loss of
containment in process.

17.1.2.1. Landfill has been assessed to


current seismic standards and
show to withstand liquefaction,
with the addition of a berm.
17.2.1.1. Geotechnical terrain hazard
assessment has been
conducted and found rockfall
hazards to be low.
17.2.1.2. New cut slopes designed to
geotechnical
recommendations, including
anchoring where required.

17.3. Subsea landslip in 17.3.1. Damage to waterfront


the foreshore area.
structures. Loss of process
equipment.
17.3.2. Damage to cooling water inlet
and diffusers.

17.3.1.1. LNG train is far enough from


the foreshore not to be affected
by credible subsea landslip.
17.3.2.1. Major marine structures,
81. Conduct additional study into the
including sea water intake are
likelihood and consequences of
located in a lower risk area.
marine landslip, and identify
additional design protection if
practicable.
17.3.2.2. FSO moorings are rock
socketed and designed for
lateral spreading of soil.

BOP

AR

ARC-579-002-R01
Issue 02
April 2015
Page 24 of 50

Abbott Risk Consulting Limited


Tsunami

18.1. Submarine
earthquake or
landslip.

18.1.1. Wave damage to site.

Other extreme
weather

19.1. Drought.

19.1.1. Dust generation leading to


reduced visibility. Hazard to
personnel.

18.1.1.1. Tsunami study has been


conducted and shown that the
credible wave is not significant
compared with the extreme
wind and wave conditions.
82. Ensure that civil design includes
requirements to control dust from
external areas.

Ice/Snow

20.1. Failure of Henriette 20.1.1. Flood down Woodfibre creek


dam.
valley. Possible damage to
south-end of the site.

CR

83. Ensure that operational management PMT


plan includes dust control measures.

CR

85. Review if raw water supply from Mill


creek is sufficiently reliable to avoid
operational upsets in the event of
drought, considering the buffer
volume available in the raw water
tank.

BOP

AR

20.1.1.1. Dam inspection and


80. Review the consequences of failure of PMT
maintenance will be
the Henriette dam, and identify any
undertaken by WLNG, to meet
additional safeguards required.
BC dam safety regulations.

AR

19.1.2. Loss of water in Mill creek


19.1.2.1. Design to retain minimum
leading to loss of supply to plant
firewater volume in the raw
and firewater.
water tank (as required by
code).

Flooding

PMC Civil

20.2. Flooding of Mill


creek, e.g. high
rainfall or
temporary debris
flow.

20.2.1. Potential flooding of plant area 20.2.1.1. Flood protection measures


and damage to pipebridges and
incorporated at Mill creek.
equipment.

21.1. Weather
conditions.

21.1.1. Build up of load on structures.

84. Study potential flooding of Mill creek


and confirm that flood protection
measures are appropriate for the
hazard.

PMT

CR

98. Conduct avalanche hazard


BOP
assessment, as required by Worksafe
BC, and comply with requirements.

CR

21.1.1.1. Will be covered by


winterisation philosophy.

21.1.2. Falling ice hazard to personnel. 21.1.2.1. Will be covered by


winterisation philosophy.
21.2. Avalanche from
uphill

Fog/ Visibility

21.2.1. Hazard to personnel and


equipment.

22.1. Fog, smoke, snow 22.1.1. Interference with LNGC marine 22.1.1.1. Marine operation procedures to
storm.
operations.
be confirmed by TERMPOL.

ARC-579-002-R01
Issue 02
April 2015
Page 25 of 50

Abbott Risk Consulting Limited


22.1.2. Interference with transport to
and from site.

22.1.2.1. Ferries designed for all


weather operation, including
poor visibility.
22.1.2.2. Helicopter is an unusual
operation and would not be
operated in unsuitable
operation.

ARC-579-002-R01
Issue 02
April 2015
Page 26 of 50

Abbott Risk Consulting Limited


Node: 2. Inlet Facilities
Guide
Word/Deviation
External Fire

Causes

Consequences

1.1. Other inventories in 1.1.1. Exposure to fire, risk of


train.
overpressure leading to
escalation.

Safeguards

Recommendations

Resp

Category

1.1.1.1. PSVs sized for fire case in the


area.
1.1.1.2. Fire and gas detection.
1.1.1.3. ESD and EDP of the feed gas
inventory.
1.1.1.4. Active and passive fire
protection - see general node.
1.1.1.5. FERA to be carried out.

1.2. Leak from hot oil


system within the
unit.

1.2.1. Pool fire.

1.2.1.1. Vents and relief from hot oil to 6. Check if hot oil is always below its flash PMC closed system to prevent hot oil
point, and therefore is non-hazardous Linde
relief feeding a fire.
in case of leak. If not practicable,
review area classification for hot oil
system area.

AR

Previous HAZID Recommendation 12


1.3. Leak of feed gas
within the unit.

1.3.1. Jet fire, flammable cloud, flash


fire.

1.3.1.1. PSVs sized for fire case in the


area.
1.3.1.2. Fire and gas detection.
1.3.1.3. ESD and EDP of the feed gas
inventory.
1.3.1.4. Active and passive fire
protection - see general node.
1.3.1.5. FERA to be carried out.

1.4. Leak from upstream 1.4.1. Jet fire, flammable cloud, flash
pipeline.
fire.

1.4.1.1. PSVs sized for fire case in the


area.

34. Review the detection and isolation of PMC leaks at the inlet startup heater area, Linde
which is upstream of the ESDV.

AR

1.4.1.2. Fire and gas detection.

ARC-579-002-R01
Issue 02
April 2015
Page 27 of 50

Abbott Risk Consulting Limited


1.4.1.3. ESD of the feed gas inventory
and EDP
1.4.1.4. ESD of feed gas at plant
boundary, downstream of
metering station.
1.4.1.5. Active and passive fire
protection - see general node.
1.4.1.6. FERA to be carried out.
Internal Fire

2.1. Malfunction of
catalytic oxidiser

2.1.1. Loss of burner control, risk of fire 2.1.1.1. Burner management system.
and overheating in oxidiser,
2.1.1.2. Oxidiser located outside
possible ignition source.
hazardous area.

External Explosion

3.1. Gas leak.

3.1.1. Overpressure, hazard to


3.1.1.1. Fire and gas detection.
personnel, damage to equipment,
potential hazard to other facilities 3.1.1.2. Hazardous area classification.
and buildings on site.
3.1.1.3. ESD and EDP to reduce
duration and extent of clouds.
3.1.1.4. FERA to be carried out.

Internal Explosion

4.1. Malfunction of
catalytic oxidiser See above.

Exposure to harmful 5.1. Harmful substances 5.1.1. Risk to personnel, risk of spill.
substances
for desalination.
(acute/chronic)
5.2. Contact with amine. 5.2.1. Health hazard to personnel.

5.2.1.1. Procedures for handling.

7. Review the open drains from the amine PMC area, consider means to prevent amine BOP
spills contaminating the general water
5.2.1.2. Segregated amine drain system
for draining.
treatment system.

AR

Previous HAZID Recommendation 13


5.3. Sour gas discharge. 5.3.1. Health hazard to personnel.

5.3.1.1. Release point located to safe


8. Check if credible leak from stripping
location, to be confirmed by gas
column overhead system discharge
dispersion study.

PMC Linde

AR

ARC-579-002-R01
Issue 02
April 2015
Page 28 of 50

Abbott Risk Consulting Limited

5.3.2. Environmental discharge.


Noise

6.1. See general node.

Environmental
Pollution

7.1. See general node


and cases above.

HAZARD from
OSBL

8.1. Landslip/
earthquake.

8.1.1. See general node.

8.2. Sea level change


(e.g. storm surge,
tsunami effects).

8.2.1. See general node.

8.3. Extreme wind and


wave.

8.3.1. See general node.

8.4. Lightning.

8.4.1. Standard design consideration.


No additional hazard identified.

8.5. Ice storm / freezing


rain.

8.5.1. Build up of ice falling and causing


structural damage or direct
overload.

5.3.1.2. Primary discharge is through


catalytic oxidiser, to oxidise any
residual hydrocarbon and H2S.

could lead to a health hazard, if so


consider detection requirements.

5.3.1.3. Secondary discharge is to flare.

Previous HAZID Recommendation 14

5.3.2.1. Discharge permit.

9. Establish criteria for ice build up to be


considered in design and concept for
dealing with ice build up, including
potential dropped object during thaw.

PMC

AR

Previous HAZID Recommendation 17


Continuous /
frequent plant
discharges to air

9.1. No new scenarios


identified.

Continuous /
10.1. No new scenarios
frequent plant
identified.
discharges to water
Continuous /
frequent plant
discharges to soil

11.1. No new scenarios


identified.

ARC-579-002-R01
Issue 02
April 2015
Page 29 of 50

Abbott Risk Consulting Limited


Emergency / upset
discharges

12.1. All discharges to


flare system - see
general node.
12.2. Hot oil spill or leak. 12.2.1. Release to environment and
hazard to personnel.

12.2.1.1. Area containment and drainage 39. Ensure that liquid hydrocarbon
BOP
system to a sump and pumped
entering the surface drains in each of
to treatment system.
the train areas is separated before the
water is discharged.

CR

12.3. Spill or leak of


12.3.1. Release to environment.
pentane fuel for hot
oil heater.

12.3.1.1. Area containment and drainage 39. Ensure that liquid hydrocarbon
BOP
system to a sump and pumped
entering the surface drains in each of
to treatment system.
the train areas is separated before the
water is discharged.

CR

40. Conduct drainage philosophy review, PMC


to ensure that the safety and
environmental hazards for
hydrocarbon into the drain system are
addressed.

CR

It is noted that an LNG train


philosophy is available from Linde,
but has not been integrated into the
plant water treatment philosophy.
12.3.2. Pool fire hazard. Vapour
generation and fire / explosion
hazard.
12.4. PSV relief from hot 12.4.1. Potential hydrocarbon vapour
oil system or
release to atmosphere.
tempered water
(e.g. heat
exchanger leak
from the process).

35. Review the hazard from pentane fuel PMC in module 2, near the fired equipment. Linde

AR

16. Route hot oil and tempered water


PMC expansion vapour vent and PSVs to Linde
flare system (LP warm flare), to avoid
hydrocarbon release to atmosphere.

CR

Previous HAZID Recommendation 28

ARC-579-002-R01
Issue 02
April 2015
Page 30 of 50

Abbott Risk Consulting Limited


Node: 3. Liquefaction and Refrigeration.
Guide
Word/Deviation
External Fire

Causes

Consequences

1.1. Other inventories on 1.1.1. Exposure to fire, risk of


the train.
overpressure leading to
escalation. Potential for BLEVE
(in particular mixed refrigerant
buffer vessels).

Safeguards

Recommendations

Resp

Category

1.1.1.1. PSVs sized for fire case in the


area.
1.1.1.2. Fire and gas detection.
1.1.1.3. ESD.
EDP of the gas inventories.
1.1.1.4. Active and passive fire
protection - see general node.
1.1.1.5. Liquid leaks routed away from
process area by bunding
arrangement, to minimise pool
fire potential.
1.1.1.6. FERA to be carried out.

1.2. Leak of feed gas


within the unit.

1.2.1. Jet fire, flammable cloud, flash


fire.

1.2.1.1. PSVs sized for fire case in the


area.
1.2.1.2. Fire and gas detection.
1.2.1.3. ESD and EDP of the feed gas
inventory.
1.2.1.4. Active and passive fire
protection - see general node.
1.2.1.5. FERA to be carried out.

1.3. Leak of cryogenic


liquid.

1.3.1. Jet fire, flammable cloud, flash


fire.

1.3.1.1. PSVs sized for fire case in the


area.
1.3.1.2. Fire and gas detection.
1.3.1.3. ESD and EDP of the feed gas
inventory.

ARC-579-002-R01
Issue 02
April 2015
Page 31 of 50

Abbott Risk Consulting Limited


1.3.1.4. Active and passive fire
protection - see general node.
PFP for cryogenic area designed
for cold shock and fire case.
1.3.1.5. FERA to be carried out.
1.3.2. Direct hazard to personnel from
temperature.

1.3.2.1. Spray protection e.g. flange


shields to control likely leak
sources.

1.3.3. Damage to structures and


equipment, risk of escalation.

1.3.3.1. PFP designed to protect steel


against low temperature in areas
with cryogenic liquid.

1.3.4. Evaporating pool at spill basin,


leading to flammable cloud.

10. Provide means to limit evaporation


PMC
from LNG spill pit, e.g. high expansion
foam or floating block systems.
Assess the impact of the resulting
cloud in a spill event when the pit
location is defined.

AR

Previous HAZID Recommendation 18


1.3.5. Spill in to water leading to RPT.

1.3.5.1. All drains lead to a sump with a 41. Confirm the design of LNG
BOP
low water level to minimise
catchments and the means to prevent
evaporation and ensure the
LNG ingress to the drain system.
volume is available.
Select a passive means if practicable.

Internal Fire

2.1. No new scenarios


identified.

External Explosion

3.1. Gas leak or flashing 3.1.1. Overpressure, hazard to


3.1.1.1. Fire and gas detection.
liquid leak.
personnel, damage to equipment,
potential hazard to other facilities 3.1.1.2. Hazardous area classification.
and buildings on site.
3.1.1.3. ESD and EDP to reduce
duration and extent of clouds.

11. Check the requirements for rotating PMC equipment in hazardous areas as
Linde
potential ignition source (e.g. bearing
temperature monitoring). Concern is
that the only known standard is EN13463, which may not be applicable
in BC.

CR

CR

3.1.1.4. FERA to be carried out.


Previous HAZID Recommendation 20

ARC-579-002-R01
Issue 02
April 2015
Page 32 of 50

Abbott Risk Consulting Limited


Internal Explosion

4.1. No new scenarios


identified.

Exposure to harmful 5.1. Contact with water / 5.1.1. Hazard to personnel health.
substances
glycol.
(acute/chronic)

5.1.1.1. Low hazard fluid.


5.1.1.2. Handling procedures.

Noise

6.1. See general node.

Environmental
Pollution

7.1. Spill of tempered


cooling water.

7.1.1. Potential release of glycol to the 7.1.1.1. Glycol will not be added to
environment.
tempered water. System is water
only.

HAZARD from
OSBL

8.1. Landslip/
earthquake.

8.1.1. See general node.

8.2. Sea level change


(e.g. storm surge,
tsunami effects).

8.2.1. See general node.

8.3. Extreme wind and


wave.

8.3.1. See general node.

8.4. Lightning.

8.4.1. Standard design consideration.


No additional hazard identified.

8.5. Ice storm / freezing


rain.

8.5.1. Build up of ice falling and causing


structural damage or direct
overload.

9. Establish criteria for ice build up to be


considered in design and concept for
dealing with ice build up, including
potential dropped object during thaw.

PMC

AR

8.6. Lifting operations for 8.6.1. Dropped load on plant, leading to 8.6.1.1. Material handling philosophy
12. Establish position of cranes/ lifting
PMC
maintenance.
loss of containment.
(including Dropped object study
equipment for plant maintenance,
) to be prepared.
consider minimising requirements for
lifting over live plant (e.g.
maintenance of one liquefaction train
with the other in operation).

AR

Previous HAZID Recommendation 17

Previous HAZID Recommendation 21

ARC-579-002-R01
Issue 02
April 2015
Page 33 of 50

Abbott Risk Consulting Limited


Continuous /
frequent plant
discharges to air

9.1. No new scenarios


identified.

Continuous /
10.1. No new scenarios
frequent plant
identified.
discharges to water
Continuous /
frequent plant
discharges to soil

11.1. No new scenarios


identified.

Emergency / upset
discharges

12.1. All discharges to


flare system - see
general node.

ARC-579-002-R01
Issue 02
April 2015
Page 34 of 50

Abbott Risk Consulting Limited


Node: 4. Refrigerant Make-up and Fractionation Area.
Guide
Word/Deviation
External Fire

Causes

Consequences

Safeguards

1.1. Other inventories on 1.1.1. Exposure to fire, risk of


1.1.1.1. PSVs sized for fire case in the
the train.
overpressure leading to
area.
escalation. Potential for BLEVE.
1.1.1.2. Fire and gas detection.
Potential to impair flare system
and prevent safe disposal from
FSO and other inventories.

Recommendations

Resp

36. Review the segregation of refrigerant PMC


storage and flare system from plant
hazards.

Category
AR

1.1.1.3. ESD.
EDP of the HP gas inventories.
1.1.1.4. Active and passive fire
protection - see general node.
1.1.1.5. Liquid leaks routed away from
process area by bunding
arrangement, to minimise pool
fire potential.
1.1.1.6. FERA to be carried out.

1.2. Leak of feed gas


within the unit.

1.2.1. Jet fire, flammable cloud, flash


fire.

1.2.1.1. PSVs sized for fire case in the


area.
1.2.1.2. Fire and gas detection.
1.2.1.3. ESD and EDP of the feed gas
inventory.
1.2.1.4. Active and passive fire
protection - see general node.
1.2.1.5. FERA to be carried out.

1.3. Leak of cryogenic


liquid.

1.3.1. Jet fire, flammable cloud, flash


fire.

1.3.1.1. PSVs sized for fire case in the


area.
1.3.1.2. Fire and gas detection.
1.3.1.3. ESD and EDP of the feed gas
inventory.

ARC-579-002-R01
Issue 02
April 2015
Page 35 of 50

Abbott Risk Consulting Limited


1.3.1.4. Active and passive fire
protection - see general node.
PFP for cryogenic area designed
for cold shock and fire case.
1.3.1.5. FERA to be carried out.
1.3.2. Direct hazard to personnel from
temperature.

1.3.2.1. Spray protection e.g. flange


shields to control likely leak
sources.

1.3.3. Damage to structures and


1.3.3.1.
equipment due to embrittlement
or thermal stress and bowing, risk
of escalation.
1.3.3.2.
1.3.4. Evaporating pool at spill basin,
leading to flammable cloud.

PFP designed to protect steel


against low temperature in areas
with cryogenic liquid.
HAZOP to consider thermal
stress cases.
10. Provide means to limit evaporation
PMC
from LNG spill pit, e.g. high expansion
foam or floating block systems.
Assess the impact of the resulting
cloud in a spill event when the pit
location is defined.

AR

Previous HAZID Recommendation 18


1.3.5. Spill in to water leading to RPT.

1.4. Leak of hydrocarbon 1.4.1. Build up of hydrocarbon


condensate.
condensate in drain system and
effluent treatment, risk of
flammable vapour, fire and
explosion.

1.3.5.1. All drains lead to a sump with a 41. Confirm the design of LNG
BOP
low water level to minimise
catchments and the means to prevent
evaporation and ensure the
LNG ingress to the drain system.
volume is available.
Select a passive means if practicable.
13. Ensure that effluent drainage and
AMEC
treatment is designed for the
possibility of hydrocarbon condensate
leakage (low flashpoint hydrocarbon)
from any condensate handling areas
in the LNG train.

CR

AR

Previous HAZID Recommendation 22


Internal Fire

2.1. No new scenarios


identified.
ARC-579-002-R01
Issue 02
April 2015
Page 36 of 50

Abbott Risk Consulting Limited


External Explosion

3.1. Gas leak or flashing 3.1.1. Overpressure, hazard to


3.1.1.1. Fire and gas detection.
liquid leak.
personnel, damage to equipment,
potential hazard to other facilities 3.1.1.2. Hazardous area classification.
and buildings on site.
3.1.1.3. ESD and EDP to reduce
duration and extent of clouds.

11. Check the requirements for rotating PMC equipment in hazardous areas as
Linde
potential ignition source (e.g. bearing
temperature monitoring). Concern is
that the only known standard is EN13463, which may not be applicable
in BC.

CR

3.1.1.4. FERA to be carried out.


Previous HAZID Recommendation 20
Internal Explosion

4.1. No new scenarios


identified.

Exposure to harmful 5.1. Contact with water / 5.1.1. Hazard to personnel health.
substances
glycol.
(acute/chronic)
Noise

6.1. See general node.

Environmental
Pollution

7.1. See general node.

HAZARD from
OSBL

8.1. Landslip/
earthquake.

8.1.1. See general node.

8.2. Sea level change


(e.g. storm surge,
tsunami effects).

8.2.1. See general node.

8.3. Extreme wind and


wave.

8.3.1. See general node.

8.4. Lightning.

8.4.1. Standard design consideration.


No additional hazard identified.

8.5. Ice storm / freezing


rain.

8.5.1. Build up of ice falling and causing


structural damage or direct
overload.

5.1.1.1. Low hazard fluid.


5.1.1.2. Handling procedures.

9. Establish criteria for ice build up to be


considered in design and concept for
dealing with ice build up, including
potential dropped object during thaw.

PMC

AR

Previous HAZID Recommendation 17

ARC-579-002-R01
Issue 02
April 2015
Page 37 of 50

Abbott Risk Consulting Limited


8.6. Lifting operations for 8.6.1. Dropped load on plant, leading to 8.6.1.1. Material handling philosophy
12. Establish position of cranes/ lifting
PMC
maintenance.
equipment for plant maintenance,
loss of containment.
(including Dropped object study)
to be prepared.
consider minimising requirements for
lifting over live plant (e.g.
maintenance of one liquefaction train
with the other in operation).

AR

Previous HAZID Recommendation 21


8.7. Filling of refrigerants 8.7.1. Potential for spill of refrigerant,
leading to fire / explosion risk and
(e.g. for startup)
hazard to personnel.

Continuous /
frequent plant
discharges to air

37. Establish the means for refrigerant


PMT
supply to site and filling of refrigerant
makeup storage.

AR

38. When refrigerant delivery method is PMC defined (refer to recommendation 37), BOP
review the hazards and controls
required.

AR

9.1. No new scenarios


identified.

Continuous /
10.1. No new scenarios
frequent plant
identified.
discharges to water
Continuous /
frequent plant
discharges to soil

11.1. No new scenarios


identified.

Emergency / upset
discharges

12.1. All discharges to


flare system - see
general node.

ARC-579-002-R01
Issue 02
April 2015
Page 38 of 50

Abbott Risk Consulting Limited


Node: 5. LP Compression, End Flash and Fuel Gas System.
Guide
Word/Deviation
External Fire

Causes

Consequences

Safeguards

Recommendations

Resp

Category

1.1. Other inventories on 1.1.1. Exposure to fire, risk of


1.1.1.1. PSVs sized for fire case in the
the train.
overpressure leading to
area.
escalation. Potential for BLEVE in
end flash drum.
1.1.1.2. Fire and gas detection.
1.1.1.3. ESD.
EDP of the gas inventories.
1.1.1.4. Active and passive fire
protection - see general node.
1.1.1.5. Liquid leaks routed away from
process area by bunding
arrangement, to minimise pool
fire potential.
1.1.1.6. FERA to be carried out.
1.2. Leak of feed gas
within the unit.

1.2.1. Jet fire, flammable cloud, flash


fire.

1.2.1.1. PSVs sized for fire case in the


area.
1.2.1.2. Fire and gas detection.
1.2.1.3. ESD and EDP of the feed gas
inventory.
1.2.1.4. Active and passive fire
protection - see general node.
1.2.1.5. FERA to be carried out.

1.3. Leak of cryogenic


liquid.

1.3.1. Jet fire, flammable cloud, flash


fire.

1.3.1.1. PSVs sized for fire case in the


area.
1.3.1.2. Fire and gas detection.
1.3.1.3. ESD and EDP of the feed gas
inventory.

ARC-579-002-R01
Issue 02
April 2015
Page 39 of 50

Abbott Risk Consulting Limited


1.3.1.4. Active and passive fire
protection - see general node.
PFP for cryogenic area designed
for cold shock and fire case.
1.3.1.5. FERA to be carried out.
1.3.2. Direct hazard to personnel from
temperature.

1.3.2.1. Spray protection e.g. flange


shields to control likely leak
sources.

1.3.3. Damage to structures and


equipment, risk of escalation.

1.3.3.1. PFP designed to protect steel


against low temperature in areas
with cryogenic liquid.

1.3.4. Evaporating pool at spill basin,


leading to flammable cloud.

10. Provide means to limit evaporation


PMC
from LNG spill pit, e.g. high expansion
foam or floating block systems.
Assess the impact of the resulting
cloud in a spill event when the pit
location is defined.

AR

Previous HAZID Recommendation 18


1.3.5. Spill in to water leading to RPT
(Rapid Phase Transition).

1.3.5.1. All drains lead to a sump with a 41. Confirm the design of LNG
BOP
low water level to minimise
catchments and the means to prevent
evaporation and ensure the
LNG ingress to the drain system.
volume is available.
Select a passive means if practicable.

Internal Fire

2.1. No new scenarios


identified.

External Explosion

3.1. Gas leak or flashing 3.1.1. Overpressure, hazard to


3.1.1.1. Fire and gas detection.
liquid leak.
personnel, damage to equipment,
potential hazard to other facilities 3.1.1.2. Hazardous area classification.
and buildings on site.
3.1.1.3. ESD.
3.1.1.4. Low pressure of systems.
Limited compressed gas
inventory.
3.1.1.5. FERA to be carried out.

11. Check the requirements for rotating PMC equipment in hazardous areas as
Linde
potential ignition source (e.g. bearing
temperature monitoring). Concern is
that the only known standard is EN13463, which may not be applicable
in BC.

CR

CR

Previous HAZID Recommendation 20

ARC-579-002-R01
Issue 02
April 2015
Page 40 of 50

Abbott Risk Consulting Limited


Internal Explosion

4.1. No new scenarios


identified.

Exposure to harmful 5.1. No new scenarios


substances
identified.
(acute/chronic)
Noise

6.1. See general node.

Environmental
Pollution

7.1. See general node.

HAZARD from
OSBL

8.1. Landslip/
earthquake.

8.1.1. See general node.

8.2. Sea level change


(e.g. storm surge,
tsunami effects).

8.2.1. See general node.

8.3. Extreme wind and


wave.

8.3.1. See general node.

8.4. Lightning.

8.4.1. Standard design consideration.


No additional hazard identified.

8.5. Ice storm / freezing


rain.

8.5.1. Build up of ice falling and causing


structural damage or direct
overload.

9. Establish criteria for ice build up to be


considered in design and concept for
dealing with ice build up, including
potential dropped object during thaw.

PMC

AR

8.6. Lifting operations for 8.6.1. Dropped load on plant, leading to 8.6.1.1. Material handling philosophy
12. Establish position of cranes/ lifting
PMC
maintenance.
loss of containment.
(including Dropped object study
equipment for plant maintenance,
) to be prepared.
consider minimising requirements for
lifting over live plant (e.g.
maintenance of one liquefaction train
with the other in operation).

AR

Previous HAZID Recommendation 17

Previous HAZID Recommendation 21

ARC-579-002-R01
Issue 02
April 2015
Page 41 of 50

Abbott Risk Consulting Limited


8.7. Shutdown on
storage unit.

8.7.1. Possibility of surge in LNG


transfer line, leading to
overpressure.

8.8. Starting or stopping 8.8.1. Potential for exceeding cool down 8.8.1.1. Continuous cool down using
LNG flow.
limits, leading to damage and
dedicated liquid return line.
possible loss of containment from
transfer line.
8.8.1.2. cool down procedures.

42. Conduct transient analysis of flow in PMT


the rundown line from LNG train to
FSO, including surge and other upset
conditions.

CR

14. Confirm isolations on LNG transfer


PMC
lines to limit LNG spill in the case of
leakage, particularly for flexible joints
at the moorings.

CR

Previous HAZID Recommendation 23


Continuous /
frequent plant
discharges to air

9.1. No new scenarios


identified.

Continuous /
10.1. No new scenarios
frequent plant
identified.
discharges to water
Continuous /
frequent plant
discharges to soil

11.1. No new scenarios


identified.

Emergency / upset
discharges

12.1. All discharges to


flare system - see
general node.

ARC-579-002-R01
Issue 02
April 2015
Page 42 of 50

Abbott Risk Consulting Limited


Node: 6. Substation
Guide
Word/Deviation
External Fire

Causes

Consequences

Safeguards

1.1. Fire in adjacent


process area.

1.1.1. Impairment of substation.


damage to equipment. Potential
loss of emergency power and
control to the plant.

1.1.1.1. Fire and gas and ESD from


process area.

1.2. Electrical fault.

1.2.1. Risk of fire in, or close to,


substation leading to loss of
power and control, risk to
personnel.

1.2.1.1. Fire detection and fire fighting


system.

1.2.2. Potential for transformer


explosion, causing impact
damage to process plant and loss
of containment.

Recommendations

Resp

43. Confirm that fire and explosion


protection of substation in the train
area is adequate to mitigate against
1.1.1.2. Fixed fire fighting system for the
common cause loss of power and
plant area.
control to train and equipment.

15. Review potential for transformer


failure leading to a hazard to the
process plant. If required, consider
additional safeguards.

Category

PMC

CR

PMC

AR

Previous HAZID Recommendation 25


Internal Fire

2.1. No new scenarios


identified.

External Explosion

3.1. No new scenarios


identified.

Internal Explosion

4.1. No new scenarios


identified.

Exposure to harmful 5.1. No new scenarios


substances
identified.
(acute/chronic)
Noise

6.1. See general node.

Environmental
Pollution

7.1. See general node.

HAZARD from
OSBL

8.1. See process nodes.

ARC-579-002-R01
Issue 02
April 2015
Page 43 of 50

Abbott Risk Consulting Limited


Continuous /
frequent plant
discharges to air

9.1. No new scenarios


identified.

Continuous /
10.1. All routed to
frequent plant
effluent treatment discharges to water
see general node.
Continuous /
frequent plant
discharges to soil

11.1. No new scenarios


identified.

Emergency / upset
discharges

ARC-579-002-R01
Issue 02
April 2015
Page 44 of 50

Abbott Risk Consulting Limited


Node: 7. BOP
Guide
Word/Deviation
External Fire

Causes
1.1. Condensate spill at
tank.

Consequences
1.1.1. Pool fire at condensate tank.
Damage to tank. Risk of
escalation to LNG area.

1.1.2. Potential gas cloud and VCE


hazard in LNG area.

Safeguards

Recommendations

Resp

Category

1.1.1.1. Containment bund designed for 17. Review fire fighting means for pool
PMC 110% tank volume.
fires at the condensate tank or diesel BOP
storage, e.g. foam or dry powder
system.

CR

1.1.1.2. Process causes to be addressed 18. Review segregation distance between PMC through HAZOP.
condensate tank and LNG area.
BOP
Confirm that code requirements are
1.1.1.3. AFP and PFP in LNG area.
met.

AR

1.1.2.1. Gas detection area.


1.1.2.2. Control of ignition sources.

1.2. Overpressure of
condensate tank.

1.2.1. Release of condensate,


flammable atmosphere. Risk of
fire.

1.2.1.1. Tank relief protection,


discharging to flare.
1.2.1.2. N2 blanketing.

1.3. Spill during truck


loading of
condensate.

52. Check overpressure protection of the PMC AR


condensate tank. If routed into the LP Interface
flare system, this has a design
pressure greater than the tank, but if
routed to atmosphere, there may be a
flammable hazard in the area of the
train.

1.3.1. Pool fire at loading area. Damage 1.3.1.1. Designated loading area with
17.
to tank. Risk of escalation to LNG
containment.
area.
1.3.1.2. Process causes to be addressed
through HAZOP.

Review fire fighting means for pool


PMC fires at the condensate tank or diesel BOP
storage, e.g. foam or dry powder
system.

CR

1.3.1.3. AFP and PFP in LNG area.


1.3.2. Potential gas cloud and VCE
hazard in LNG area.

1.3.2.1. Gas detection area.


1.3.2.2. Control of ignition sources.

1.4. Utility gas supply


leak.

1.4.1. Potential gas cloud and fire /


explosion hazard.

1.4.1.1. All utility gas installed in


accordance with BC Natural Gas
Code.

ARC-579-002-R01
Issue 02
April 2015
Page 45 of 50

Abbott Risk Consulting Limited


1.4.1.2. Utility gas is reduced to normal
supply pressure at Fortis station,
and includes mercaptan as leak
indication.
1.5. Diesel tank leak or
diesel loading spill.

1.5.1. Pool fire at diesel storage.


Damage to tank.

1.5.1.1. Containment bund designed for 17. Review fire fighting means for pool
PMC 110% tank volume.
fires at the condensate tank or diesel BOP
storage, e.g. foam or dry powder
system.

CR

1.6. Forest fire.

1.6.1. Fire spread to plant area. Risk of 1.6.1.1. Emergency response, including 19. Consider safeguards against external PMC escalation.
fire water / fire fighting
forest fire (e.g. fire break at plant
BOP
equipment to protect essential
boundary and/or perimeter boundary
areas (e.g. LNG train).
and vegetation control around plant
area).
1.6.1.2. Ability to shutdown and
depressurise plant.

AR

1.7. Electrical fire.

1.7.1. Potential ignition of hazardous


inventories.

1.7.1.1. In BOP area, electrical


20. Select equipment for piperack area as PMC equipment is segregated from
minimum of Zone 2, or equivalent.
BOP
hazardous inventories, except at
piperack area.

CR

1.8. Fire on road truck.

1.8.1. Risk of escalation to plant.


Potential ignition source for gas
leaks.

1.8.1.1. Control of vehicles on site - only 21. Develop standards for external
diesel vehicles associated with
vehicles (e.g. condensate trucks)
the plant.
within the safety management plan.

CR

1.9. Fire on attendant


vessel.

1.9.1. Hazard to personnel on vessel.

1.9.1.1. Dedicated ferry vessels, meeting


Transport Canada requirements.

PMT BOP

1.9.1.2. Selection of suitable vessels for


infrequent operations (e.g.
material transport), meeting
Transport Canada requirements.
1.9.2. Potential hazard to FSO and
1.9.2.1. All routine marine transport is
remote from FSO and process
carrier, and exposed inventories.
area.
Internal Fire

2.1. Warehouse fire.

2.1.1. Damage to equipment. Risk to


personnel in the area. Risk of
escalation to adjacent buildings
and vegetation.

2.1.1.1. Fire protection design criteria.


2.1.1.2. Static and mobile fire fighting
equipment and water supply
available.

ARC-579-002-R01
Issue 02
April 2015
Page 46 of 50

Abbott Risk Consulting Limited


2.1.1.3. Evacuation plans in the safety
management plan.
2.2. Chemical storage
fire.

2.2.1. Damage to equipment. Risk to


personnel in the area. Risk of
escalation to adjacent buildings
and vegetation.

2.2.1.1. Fire protection design criteria.


2.2.1.2. Static and mobile fire fighting
equipment and water supply
available.
2.2.1.3. Evacuation plans in the safety
management plan.

2.2.2. Potential health risk to personnel


fighting the fire.

2.3. Substation fire.

2.3.1. Damage to equipment. Risk to


personnel in the area. Risk of
escalation to adjacent buildings
and vegetation.

22. Review hazards from stored


PMC chemicals in the case of fire, and
BOP
include mitigation requirements in the
building basis of design.

AR

24. Review common cause loss of normal PMC


and emergency power, particularly to
process plant, and the required
system integrity.

AR

2.3.1.1. Fire protection design criteria.


2.3.1.2. Static and mobile fire fighting
equipment and water supply
available.

2.3.2. Internal explosion (e.g. batteries,


transformers, etc.)
2.3.3. Risk of escalation to rundown
piperack from north substation.
2.3.4. Loss of supply to the plant.
Potential hazards from loss of
power and control.

2.4. BC hydro substation 2.4.1. Loss of power supply.


fire.

2.4.1.1. Two segregated transformers


and supply routes.
2.4.1.2. Emergency power from the site
does not pass through the same
switch gear.

ARC-579-002-R01
Issue 02
April 2015
Page 47 of 50

Abbott Risk Consulting Limited


2.5. Fire at interim
substation.

2.5.1. Loss of power supply.

2.6. Non-process building 2.6.1.


(i.e. admin building,
workshop, guard
house building,
emergency response
building, canteen)
fire.

Damage to equipment. Risk to


personnel in the area. Risk of
escalation to adjacent buildings
and vegetation.

2.7. Process building (i.e. 2.7.1.


utility building,
cooling water pumps
building, effluent and
water treatment
shelter) fire.

Damage to equipment. Risk to


personnel in the area. Risk of
escalation to adjacent buildings
and vegetation.

58. Review scenario of prolonged loss of BOP


power if the interim substation
transformer fails. In this case, the
plant could require to be maintained
in a safe condition without external
power for a period of months.
Consider if offloading remaining
stored inventory is possible without
external power.

AR

23. Review hazards from fire in BOP


PMC systems and buildings adjacent to the BOP
rundown piperack and provide
separation where required.

AR

59. Review the alternative means of


control and shutdown, in the event
that the control room has to be
evacuated due to internal hazard.

AR

2.6.1.1. Fire protection design criteria.


2.6.1.2. Static and mobile fire fighting
equipment and water supply
available.
2.6.1.3. Evacuation plans in the safety
management plan.
2.7.1.1. Fire protection design criteria.
2.7.1.2. Static and mobile fire fighting
equipment and water supply
available.
2.7.1.3. Evacuation plans in the safety
management plan.

2.7.2. Risk of escalation to rundown


piperack from cooling water
system buildings,
2.7.3. Loss of supply to the plant.
Potential hazards.
2.8. Control room fire.

2.7.3.1. Utility failures to be addressed in


HAZOP.

2.8.1. Loss of control and management 2.8.1.1. Fire and smoke detection.
functions, if evacuated.
2.8.1.2. Fire suppression / protection
systems.

PMC BOP

2.8.1.3. Designated emergency


response room, outside the
control room.

ARC-579-002-R01
Issue 02
April 2015
Page 48 of 50

Abbott Risk Consulting Limited


External Explosion

3.1. See relevant process


area nodes.

Internal Explosion

4.1. Vapour cloud from


process area.

4.1.1. Flammable atmosphere in


4.1.1.1. Electrical rooms and substations 55.
buildings and confined spaces in
are ventilated with positive
the utility areas. Risk of
pressure and ventilation
explosion.
shutdown on gas detection.

Review requirement for enclosed


BOP
buildings in the utility and cooling
water areas. Eliminate, where
possible, to minimise the potential for
vapour clouds inside buildings.

AR

56. Review the hazard from temporary


BOP
substation as a source of ignition, or a
fire hazard which might affect process
equipment.

AR

5.1.1. Health hazard to personnel.

54. Identify the hazards from chemicals to BOP


be stored, when they are selected,
and ensure that handling and storage
arrangements are suitable to protect
personnel and releases to the
environment.

CR

5.1.2. Environmental hazard.

54. Identify the hazards from chemicals to BOP


be stored, when they are selected,
and ensure that handling and storage
arrangements are suitable to protect
personnel and releases to the
environment.

CR

5.2.1. Personnel asphyxiation hazard.

53. Review the hazard of N2 in utility


BOP
building, and ensure that asphyxiation
hazard is addressed.

CR

60. Confirm that physical protection is


BOP
provided around process areas and
structures (e.g. pipe and cable
bridges), to protect against accidental
impacts from vehicles and handling
operations.

CR

4.1.1.2. Separation distance between


process area and manned
buildings. To be confirmed by
siting study.
Loss of Containment 5.1. Chemical leak.

5.2. N2 leak inside


building.

Cryogenic Hazard

6.1. Not applicable.

Impact/Mechanical
Damage

7.1. Vehicle movements 7.1.1. Risk of collision with and damage


on site.
to structures and process
equipment.

7.2. Vessel collision with 7.2.1. See general node


personnel and
material access
jetties.

ARC-579-002-R01
Issue 02
April 2015
Page 49 of 50

Abbott Risk Consulting Limited


Exposure to harmful 8.1. Contamination from 8.1.1. Hazard to personnel.
substances
existing asbestos
(acute/chronic)
disposal site.

8.1.1.1. Site to be capped to meet the


requirements of COC (Certificate
Of Compliance), before
handover to Woodfibre.

Noise

9.1.1. Exposure of personnel.

9.1.1.1. Equipment and noise


attenuation (where required) to
be designed to meet Worksafe
BC requirements for noise.

9.1.2. Noise nuisance in area.

9.1.2.1. BOP equipment noise included


in noise model for off-site noise
(to meet OGC requirements).

10.1.1. Release to water or soil.

10.1.1.1. Tanks and loading areas are in


bunded areas.

10.1.2. Vapour from condensate


release to air.

10.1.2.1. No routine handling of


condensate in the open. Tank
is blanketed and connected to
flare system.

10.2.1. Possible contaminated water


running to surrounding
environment.

10.2.1.1. Runoff within BOP area is


collected and passed through
oily water separation.

Environmental
Pollution

9.1. Noisy equipment


(e.g. emergency
generators, utility
pumps,
compressors, etc.)

10.1. Spill of diesel or


condensate.

10.2. Runoff from plant


areas.

HAZARD from
OSBL

11.1. See general node


for external
hazards.

Continuous /
frequent plant
discharges to air

12.1. HVAC unit


refrigerant leak
(fugitive
emissions).

12.1.1. Release of refrigerant to


environment.

12.2. Landfill gas.

12.2.1. Release to environment.

30. Identify any chemicals handled in the PMC BOP area which may pass through
BOP
oily water separation. If any are
identified, provide separate
containment to prevent drainage into
the surface water system.

AR

10.2.1.2. Spill response procedures and 31. Review the disposal of lab drains to PMC local drip trays and catchments
ensure that they are correctly treated. BOP
around equipment.

AR

12.1.1.1. Maintenance and integrity.


12.1.1.2. Considered in EIA.

12.2.2. Potential build up of flammable


gas.

12.2.1.1. Considered in EIA.


32. Review if flammable gas hazard from PMC landfill is credible.
BOP

AR

ARC-579-002-R01
Issue 02
April 2015
Page 50 of 50

Abbott Risk Consulting Limited


12.3. Sea water
12.3.1. Local hazard at the release
chlorination
point.
hydrogen/ chlorine
discharge.

33. Review the potential hazards from


venting from chlorination system
when the technology has been
chosen.

BOP

AR

BOP

AR

57. Ensure that oxygen-rich gas from N2 BOP


generation is dispersed safely.

CR

Also consider the environmental


implications of any routine venting to
atmosphere from the process.
12.3.2. Release to environment.

33. Review the potential hazards from


venting from chlorination system
when the technology has been
chosen.
Also consider the environmental
implications of any routine venting to
atmosphere from the process.

12.4. Vapour displaced 12.4.1. Release of flammable


during condensate
hydrocarbon vapour.
truck filling
operation.

12.4.1.1. Closed vapour return to the


tank vapour space from the
truck.

12.5. Oxygen-rich offgas 12.5.1. Increased fire hazard in the


from N2
area.
generation.
Continuous /
13.1. Closed process
frequent plant
drains (produced
discharges to water
water).

13.2. Surface runoff.

13.1.1. Potential discharge of


hydrocarbons to the
environment.

13.1.1.1. All oily water drains from


process are treated in
biological treatment.

61. Consider if a buffer storage is


BOP
required for off-spec produced water,
to enable plant operation to continue
in an upset case at the treatment
13.1.1.2. Discharge monitoring system.
plant.

AR

13.2.1. Potential discharge of


hydrocarbons to the
environment.

13.2.1.1. All surface drains from open


plant contacted area are
collected in a surface runoff
pond, with sufficient capacity
for maximum rainfall event.

CR

62. Check the basis for the maximum


rainfall event used in sizing the
surface runoff retention pond.

BOP

13.2.1.2. Liquid from the pond and


drains from buildings with
potential hydrocarbon are
treated in biological treatment.
13.2.1.3. Discharge monitoring system.

ARC-579-002-R01
Issue 02
April 2015
Page 51 of 50

Abbott Risk Consulting Limited


13.3. Contamination of
non-process area
runoff (e.g. diesel
from vehicles,
chemical spill
during transport,
etc.)

13.3.1. Potential discharge of


hydrocarbons to the
environment.

13.3.1.1. Hydrocarbon containing areas 63. Consider if discharge points for runoff BOP
(e.g. transformers, diesel
to sea should be provided with valves
equipment) are locally bunded
to stop the runoff in the case of a spill,
and can be drained to the
e.g. on a roadway.
contacted area drainage
treatment system.

AR

13.3.1.2. Oily water separator at each


discharge point to intercept
hydrocarbon spills.
13.4. Discharge of
13.4.1. Discharge to the environment.
domestic sewage
from buildings and
FSO.

13.4.1.1. All sewage collected and


routed to sewage treatment
plant, to meet BC
requirements.

13.5. Discharge of sea


water cooling.

13.5.1.1. System designed to achieve


acceptable temperature at the
discharge dispersion. Location
confirmed by modeling.

13.5.1. High temperature at the


discharge, possible chlorite
content leading to
environmental hazard.

13.5.1.2. Dechlorination by a passive


aeration in the outflow, with
discharge monitoring.
13.5.1.3. Temperature and flow
monitoring of discharge.
Continuous /
frequent plant
discharges to soil

Emergency / upset
discharges

14.1. Leachate from


landfill.

14.1.1. Contamination of the soil and


ground water.

15.1. Damage to sea


15.1.1. Discharge of concentrated
water inlet
hypochlorite to sea at the inlet.
hypochlorite dosing
system or
maloperation.

14.1.1.1. Existing landfill is lined.


Leachate is collected and
treated.

64. Sample existing leachate to


PMT
determine the contaminants that are
present and ensure that treatment is
adequate.

CR

14.1.1.2. Sampling to confirm the


discharge quality.

65. Review the expected material to be BOP


added to the landfill and predict the
leachate composition and flow which
must be treated. Design the leachate
treatment appropriately.

AR

66. Consider if hypochlorite injection


BOP
pipework should be inside the sea
water intake, so that leakage is not to
the sea.

AR

ARC-579-002-R01
Issue 02
April 2015
Page 52 of 50

Abbott Risk Consulting Limited


Node: 8. Flare Systems
Guide
Word/Deviation
External Fire

Causes
1.1. Emergency flaring
case.

Consequences

Resp

Category

1.1.2.1. Clear area to be established


around the flare, based on flare
radiation study.

1.2.1. Inability to blowdown.

1.3. Fire affecting flare


1.3.1. Inability to vent gas from FSO to
piperack from FSO.
flare safely.

Internal Fire

Recommendations

1.1.1. Thermal radiation to plant areas, 1.1.1.1. Flare to be designed so that


personnel access routes, etc.
manned and accessible areas
are not exposed to excessive
radiation (to be confirmed by
flare study).
1.1.2. Risk of ignition for foliage.

1.2. Fire in LNG train


affecting flare
piperack.

Safeguards

25. Review the protection of flare headers BOP


and support structures against
process area fire, to ensure blowdown
duration is protected.

CR

26. Review the protection of flare headers BOP


and support structures from FSO
against process area fire. Ensure that
safe venting is available in the case of
impairment of the flare system.

CR

27. Review the implications of damage to BOP


the flare system in the event of a
vapour cloud explosion in the LNG
area. Identify if a design accidental
load for blast is required.

AR

2.1. Air ingress into flare 2.1.1. Fire or explosion in flare headers. 2.1.1.1. N2 purge.
system.
2.1.1.2. Flare design.
2.1.1.3. HAZOP to consider process
causes.

External Explosion

3.1. Explosion in process 3.1.1. Damage to piperacks, lines and


area.
flare structure. Inability to
depressurise unaffected
inventories and FSO off-gas.

Internal Explosion

4.1. No new scenarios


identified.

Loss of Containment 5.1. No new scenarios


identified.

ARC-579-002-R01
Issue 02
April 2015
Page 53 of 50

Abbott Risk Consulting Limited


Cryogenic Hazard

6.1. No new scenarios


identified.

Impact/Mechanical
Damage

7.1. No new scenarios


identified.

Exposure to harmful 8.1. No new scenarios


substances
identified.
(acute/chronic)
Noise

9.1. Flare noise.

Environmental
Pollution

10.1. See discharges,


below.

HAZARD from
OSBL

11.1. See general node.

Continuous /
frequent plant
discharges to air

12.1. No routine flaring.

9.1.1. Exposure of personnel.

9.1.1.1. Flares to be designed to meet


Worksafe BC requirements for
noise.

9.1.2. Noise nuisance in area.

9.1.2.1. Flare noise included in noise


model for off-site noise.

Continuous /
13.1. Not applicable.
frequent plant
discharges to water
Continuous /
frequent plant
discharges to soil

14.1. Not applicable.

Emergency / upset
discharges

15.1. Flare flame-out.

15.1.1. Unignited gas release. Risk of 15.1.1.1. Multiple pilots with flame
flammable gas cloud in process
monitoring and ignition
areas, particularly from cold
systems.
releases.

28. Conduct unignited gas dispersion


Solaris studies to confirm that emergency
Flare
flare releases, without ignition, do not
lead to an unsafe condition due to
flammable gas cloud formation.

AR

ARC-579-002-R01
Issue 02
April 2015
Page 54 of 50

Abbott Risk Consulting Limited


29. Review the reliability of utility gas
PMC supply to pilots, and if a backup
BOP
supply is required (e.g. from BOG or
local bottle supply). Concern is that
Fortis maintenance or defect may
require isolation of utility gas.
15.2. Build up liquid in
KO drums.

15.2.1. Liquid carryover through the


flare - "burning rain".

AR

15.2.1.1. KO drum volume and level


indication.
15.2.1.2. See HAZOP study for process
causes and safeguards.

15.3. Emergency flaring See External Fire,


above.

ARC-579-002-R01
Issue 02
April 2015
Page 55 of 50

Abbott Risk Consulting Limited


Node: 9. FSO (Rundown and Storage Mode)
Guide
Word/Deviation
External Fire

Causes

Consequences

1.1. Fire at substation or 1.1.1. Risk of escalation to adjacent


adjacent building
rundown and BOG pipework on
onshore.
the piperack. Potential loss of
ability to discharge BOG.

Safeguards

Recommendations

Resp

Category

1.1.1.1. ESD.
1.1.1.2. Fire and gas detection.
1.1.1.3. FSO is separated by distance.
1.1.1.4. In the event that the piperack is
lost, FSO tank pressure build up
can be contained for at least 3
days, before local relief to
atmosphere at each tank.

1.2. Major fire on LNG


1.2.1. Risk of escalation to FSO.
train or condensate
storage.

1.2.1.1. ESD / blowdown at the train.


1.2.1.2. Fire and gas detection.
1.2.1.3. FSO is separated by distance (to
be reviewed in siting study).
1.2.1.4. In the event that the piperack is
lost, FSO tank pressure build up
can be contained for at least 3
days, before local relief to
atmosphere at each tank.
1.2.1.5. Moss tank design has heat
protection capability.

1.2.2. Loss of normal BOG discharge


route.

1.2.2.1. Direct connection to LP flare.


1.2.2.2. In the event that the piperack is
lost, FSO tank pressure build up
can be contained for at least 3
days, before local relief to
atmosphere at each tank.

1.2.3. Loss of power / utilities to FSO.

1.2.3.1. Onboard emergency power


generation supplying safety
systems.

ARC-579-002-R01
Issue 02
April 2015
Page 56 of 50

Abbott Risk Consulting Limited


1.2.3.2. Onboard N2 generation,
supplied by emergency power.
1.2.4. Personnel on FSO are unable to 1.2.4.1. Two escape routes (fore and aft) 44. Consider if FSO control room should FSO
evacuate past the process area.
and evacuation by boat from the
be permanently manned, and if it
should remain manned in the case of
north end of the site.
a fire on the jetty or train. If so, review
fire and blast protection requirements.
45. Review evacuation routes from all
areas on the FSO.
1.3. Fire on vehicle on
jetty or utility ramp
area.

1.3.1. Escalation to rundown and BOG 1.3.1.1. Fire detection and fire fighting
lines. Fire adjacent to FSO.
system on jetty.
1.3.1.2. ESD on shore to FSO, on both
sides of flexible connections.

AR

FSO

AR

46. Review access and mechanical


BOP
handling for maintenance on transfer
arm between jetty and FSO, as this
may be conducted during operation
with the spare arm in use.

CR

1.3.1.3. Control of access, only required


for loading arm maintenance.
Internal Fire

2.1. Fire on FSO


equipment (e.g.
emergency
generator,
compressors or
equipment room).

2.1.1. Escalation to cargo systems,


2.1.1.1. Non-process (emergency
leading to major fire on the FSO.
generators, etc.) will be located
in compartments, outside the
cargo area and separate from
essential utilities (N2, control,
etc.)
2.1.1.2. Fire detection, fire protection
and fixed fire fighting systems to
class requirements
2.1.2. Loss of utilities, control, etc.
between FSO and shore.

2.1.2.1. Fire detection, fire protection


and fixed fire fighting systems to
class requirements
2.1.2.2. Non-process (emergency
generators, etc.) will be located
in compartments, outside the
cargo area and separate from
essential utilities (N2, control,
etc.)

ARC-579-002-R01
Issue 02
April 2015
Page 57 of 50

Abbott Risk Consulting Limited


External Explosion

3.1. Explosion in the LNG 3.1.1. Overpressure on the FSO. Risk


of damage leading to loss of
train.
containment.

3.1.1.1. Separation by distance and


44.
withstand capability of the Moss
tank system. To be confirmed by
siting study.

Consider if FSO control room should FSO


be permanently manned, and if it
should remain manned in the case of
a fire on the jetty or train. If so, review
fire and blast protection requirements.

AR

3.2.2. Cold damage to FSO hull, risk of 3.2.2.1. Compartmentalisation - double 47. Consider cold protection in the area of FSO
structural failure.
hull with ballast tanks - localised
the rundown line from shore to avoid
damage would not cause loss of
damage to the hull in case of leakage
stability or buoyancy.
(e.g. sacrificial splash plate).

AR

48. Consider cold protection in the area of Jetty


the rundown line from shore to avoid
damage to the jetty piles in case of
leakage.

AR

3.2. LNG release to sea 3.2.1. Possible RPT between jetty and 3.2.1.1. Inherent strength of ship's hull
from jetty to FSO
FSO. Risk of damage to
sufficient to withstand RPT
connection failure.
equipment.
pressure.

Internal Explosion

4.1. LNG leak into hold


space.

4.1.1. Flammable atmosphere, potential 4.1.1.1. No equipment or ignition


49.
sources in the hold space.
explosion in the hold space.
Escalation to other tanks.
4.1.1.2. Annular space between tank and
insulation is N2 purged and has
gas detection at the purge outlet.

Review reliability and availability of


hold space LNG secondary
containment sump pumps, and if
emergency power is required.

FSO

AR

4.2. Air ingress into cargo 4.2.1. Possible explosive mixture inside 4.2.1.1. Maintenance procedures to inert 50. Identify if vacuum breakers on LNG FSO
tank due to
and refill tanks following
the tank.
tanks could be removed, as is current
underpressure or
maintenance.
practice for Moss tanks, and develop
incorrect operating
vacuum protection design.
(e.g. maintenance
release).
51. Review LNG tank protection against PMC
air ingress at HAZOP.

AR

4.1.1.3. Gas detection in the hold space,


with ability to inert the hold
space with inert gas or N2.
4.1.1.4. Liquid containment system with
recovery pump, to control
credible liquid leaks.

4.3. Malfunction of IGG 4.3.1. Potential explosion in the IGG.


(inert gas generator).

CR

4.3.1.1. IGG located in the machinery


area, in a dedicated
compartment.
ARC-579-002-R01
Issue 02
April 2015
Page 58 of 50

Abbott Risk Consulting Limited


4.3.1.2. Burner management system in
IGG package.
Loss of Containment 5.1. Loss of containment 5.1.1. Vapour release leading to
on cargo system or
flammable gas cloud.
jetty connection.

5.1.1.1. ESD for rundown lines and jetty


connections.
5.1.1.2. Gas detection system.
5.1.1.3. All vapour lines are low
pressure.
5.1.1.4. All lines and cargo headers are
freely ventilated, open area.
5.1.1.5. Compressor rooms provided
with forced ventilation and gas
detection to meet class
requirements.

5.1.2. LNG release leading to


flammable gas cloud and
cryogenic damage to structures
and equipment.

5.1.2.1. ESD for rundown lines and jetty 47. Consider cold protection in the area of FSO
connections.
the rundown line from shore to avoid
damage to the hull in case of leakage
(e.g. sacrificial splash plate).

AR

5.1.2.2. Gas detection system.

48. Consider cold protection in the area of Jetty


the rundown line from shore to avoid
damage to the jetty piles in case of
leakage.

AR

5.1.2.3. All lines and cargo headers are 88. Review the risk of cryogenic damage FSO
freely ventilated, open area.
to structures on the FSO from header
leaks, and identify if any additional
cryogenic protection is required.
5.1.2.4. Compressor rooms (containing
LNG vapourisor for gas up of
tanks) provided with forced
ventilation and gas detection to
meet class requirements.

AR

5.1.2.5. All connections have catchment


to protect against small
cryogenic leaks.
5.2. Loss of containment 5.2.1. Vapour release leading to
on rundown system
flammable gas cloud.
ashore.

5.2.1.1. ESD for rundown lines and jetty


connections.
5.2.1.2. Gas detection system.
ARC-579-002-R01
Issue 02
April 2015
Page 59 of 50

Abbott Risk Consulting Limited


5.2.1.3. All vapour lines are low
pressure.
5.2.1.4. All lines and cargo headers are
freely ventilated, open area.
5.2.2. LNG release leading to
flammable gas cloud and
cryogenic damage to structures
and equipment.

5.2.2.1. ESD for rundown lines and jetty 89. Review the possibility of LNG leak on BOP
connections.
the rundown line. If credible leak
sources are identified, provide LNG
5.2.2.2. Gas detection system.
leak containment.

AR

5.2.2.3. All lines and cargo headers are


freely ventilated, open area.
5.2.2.4. LNG jetty has containment
sloped to spill basin.
5.3. Loss of containment 5.3.1. Spill of diesel to the environment.
of diesel in
machinery area or
transfer.

90. Relocate FSO diesel bunkering point BOP


to the aft access bridge, to avoid
unnecessary vehicle operations near
the process connections. Ensure that
spill protection is provided.

CR

90. Relocate FSO diesel bunkering point BOP


to the aft access bridge, to avoid
unnecessary vehicle operations near
the process connections. Ensure that
spill protection is provided.

CR

5.5. Activation of CO2


5.5.1. Hazard to personnel in the area.
fire fighting system.

91. Review hazards from existing CO2


fire fighting system. Consider
upgrading to modern standards.

FSO

AR

6.1. Roll over.

92. Review the potential for roll over in


FSO
the FSO tank, considering the feed
composition. If required, confirm that
roll over is within the sizing basis for
FSO tank PSVs.

CR

5.3.2. Risk of damage to process


equipment during the transfer
due to vehicles on the jetty.

5.4. Loss of containment 5.4.1. Asphyxiation hazard on entry.


of N2 into a confined
space.

Cryogenic Hazard

5.4.1.1. Normally no entry. Confined


space entry procedures.

6.1.1. High pressure in the cargo tank, 6.1.1.1. Operating procedures to


risk of overpressure and failure.
circulate tanks to avoid
stratification.
6.1.1.2. Roll over requires static tank
conditions for prolonged period unlikely in a floating facility with
frequent loading / offloading.

ARC-579-002-R01
Issue 02
April 2015
Page 60 of 50

Abbott Risk Consulting Limited


6.1.1.3. LNG composition is reasonably
consistent, significant density
differences between
components are unlikely in this
feed.
Impact/Mechanical
Damage

7.1. Ship collision.

7.1.1. Damage to FSO hull. In extreme 7.1.1.1. Marine operation procedures


case, loss of containment.
and ship exclusion to be
confirmed by TERMPOL.
7.1.1.2. Double hull design with damage
stability criteria.
7.1.1.3. Fendering system reduces
impact energy.
7.1.1.4. Nav lights.

7.2. Mechanical handling. 7.2.1. Risk of damage to process lines 7.2.1.1. Material handling philosophy
95. Establish position of cranes/ lifting
FSO
leading to loss of containment.
(including Dropped object study
equipment for plant maintenance and
) to be prepared.
loading and offloading operation,
consider minimising requirements for
lifting over live plant .

AR

Exposure to harmful 8.1. Asbestos present in 8.1.1. Hazard to personnel if disturbed. 8.1.1.1. Hazardous material study to
substances
existing marine
identify existing hazardous
(acute/chronic)
equipment onboard.
material and prevent exposure
hazards.
Noise

9.1. See general node.

Environmental
Pollution

10.1. See general node.

HAZARD from
OSBL

11.1. Extreme wind and 11.1.1. Damage to mooring. Risk of


breakaway of FSO.
wave.

11.1.1.1. Designed for 1/100 year storm 93. Consider the margin available above BOP
event in normal operation.
the design storm event and confirm
that break away will not occur due to
small exceedance.

11.2. Seismic activity.

11.2.1.1. Designed for 1/475 year


seismic event in normal
operation, including
accelerations and ground
movement (lateral spreading).

11.2.1. Damage to mooring. Risk of


breakaway of FSO.

CR

ARC-579-002-R01
Issue 02
April 2015
Page 61 of 50

Abbott Risk Consulting Limited


11.2.1.2. Designed to survive 1/2475
year seismic event, including
accelerations and ground
movement (lateral spreading).
11.3. Incorrect attitude of 11.3.1. Possible load on mooring
FSO, e.g. damage,
system leading to damage.
ballasting or
loading error.
Continuous /
frequent plant
discharges to air

11.3.1.1. Damage stability analysis


identified maximum heel and
trim angles, in worst case
loading and damaged
conditions.

94. Confirm that mooring design can


FSO
accommodate maximum angles from
damage stability analysis, when
available.

CR

97. Consider requirement for dispersion


modelling of FSO tank PSVs to
ensure release to safe location.

AR

12.1. No new scenarios


identified.

Continuous /
13.1. Surface runoff from 13.1.1. Minor contamination (e.g.
frequent plant
FSO deck.
maintenance fluids).
discharges to water
Continuous /
frequent plant
discharges to soil

14.1. Not applicable.

Emergency / upset
discharges

15.1. Venting from FSO 15.1.1. Release of flammable gas


tank PSVs or vent
cloud.
mast.

13.1.1.1. Maintenance procedures and


local drip trays where required.

15.1.1.1. Designed to release to safe


location.

PMC

15.1.1.2. Hazardous area zoning of


FSO.

ARC-579-002-R01
Issue 02
April 2015
Page 62 of 50

Abbott Risk Consulting Limited


Node: 10. LNG Offloading
Guide
Word/Deviation
External Fire

Causes
1.1. Fire on LNGC.

Consequences
1.1.1. Risk of escalation to the FSO.

Safeguards

Recommendations

Resp

Category

1.1.1.1. Quick release mooring system.


1.1.1.2. Breakaway couplings.
1.1.1.3. Tugs available continuously
during loading operation with fire
fighting capability and LNG
carrier has wires readily
available for tugs.
1.1.1.4. Electrical supply to LNGC has
staged shutdown and
breakaway built in.
1.1.1.5. Emergency procedures to be
developed as part of TERMPOL.

Internal Fire

2.1. No new scenarios


identified.

External Explosion

3.1. No new scenarios


identified.

Internal Explosion

4.1. No new scenarios


identified.

Loss of Containment 5.1. Loading arm failure. 5.1.1. Release of LNG between FSO
5.1.1.1. Gas detection in the area.
and the LNGC. Risk of cryogenic
damage to both hulls. Formation 5.1.1.2. Loading operation is
of gas cloud and risk of fire /
permanently supervised,
explosion.
operator has ESD function.
5.1.1.3. Water curtain to protect both
hulls.
5.1.1.4. Spill protection at both manifolds
and joints.
5.2. Excess vessel
movement.

5.2.1. Exceeding motion limits of arms


leading to loss of containment.

5.2.1.1. Motion monitoring with alarms


and shutdown on arm positional
envelope.
ARC-579-002-R01
Issue 02
April 2015
Page 63 of 50

Abbott Risk Consulting Limited


5.2.1.2. Mooring load monitoring system
with alarm.
5.2.1.3. Operating procedure to restrict
weather conditions.
5.2.1.4. Breakaway coupling with
mechanical isolation at both
sides in the event of
uncontrolled breakaway.
5.2.2. Possible loss of electrical supply 5.2.2.1. Electrical supply to LNGC has
leading to LNGC blackout.
staged shutdown and
breakaway built in.
Cryogenic Hazard

6.1. No new scenarios


identified.

Impact/Mechanical
Damage

7.1. Collision during


berthing.

7.1.1. Damage to FSO LNGC and


mooring.

7.1.1.1. Mooring design and fendering


system.
7.1.1.2. Marine operation procedures to
be confirmed by TERMPOL.

7.2. Mechanical handling 7.2.1. Risk of damage to process lines 7.2.1.1. Material handling philosophy
95. Establish position of cranes/ lifting
FSO
- transport between
leading to loss of containment.
(including Dropped object study
equipment for plant maintenance and
FSO and LNGC.
) to be prepared.
loading and offloading operation,
consider minimising requirements for
lifting over live plant .

AR

Exposure to harmful 8.1. No new scenarios


substances
identified.
(acute/chronic)
Noise

9.1. See general node.

Environmental
Pollution

10.1. See general node.

HAZARD from
OSBL

11.1. No new scenarios


identified.

Continuous /
frequent plant
discharges to air

12.1. Venting from LNGC 12.1.1. Discharge from the LNGC to the 12.1.1.1. LNGC gassing up procedures 96. Consider if gassing up of LNGCs
PMT
and safe vent location.
(e.g. gassing up or
environment of inert gas and
should be considered as an operation
for the site, including the discharge
maloperation)
some hydrocarbon.
that this involves.

AR

ARC-579-002-R01
Issue 02
April 2015
Page 64 of 50

Abbott Risk Consulting Limited


12.1.2. Flammable gas release from the 12.1.2.1. Cargo area of FSO is a
hazardous zone and is a freely
LNGC, potentially affecting the
vented open area.
FSO.
12.1.2.2. Vent location on LNGCs to
disperse gas as far as
practicable.
Continuous /
13.1. No new scenarios
frequent plant
identified.
discharges to water
Continuous /
frequent plant
discharges to soil

14.1. Not applicable.

Emergency / upset
discharges

15.1. No new scenarios


identified.

ARC-579-002-R01
Issue 02
April 2015
Page 65 of 50

Abbott Risk Consulting Limited

Appendix B
HAZID Recommendations

ARC-579-002-R01
Issue 02
April 2015
Page 66 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

1. Ensure that Safety Instrumented Systems (SIS) philosophies for all areas are compatible, as these form part of a single Consequences: 1.2.1.1
plant SIS.

Responsibility

Category

PMC

CR

Consequences: 1.5.1.1

PMC - Linde

AR

Consequences: 1.8.1.1

PMC - Linde

CR

PMT

AR

BOP

CR

PMC - Linde

AR

PMC - BOP

AR

Previous HAZID Recommendation 1


2. Conduct AFP and PFP study to identify the benefits and hazards of deluge in each area.

Previous HAZID Recommendation 2


3. Ensure that BC Work Safe BC OHS regulations are complied with in &AA S-PC 1031 - Working Environment
Philosophy.

Previous HAZID Recommendation 4


4. Consider operation for scenario where site access is not available (due to weather conditions, boat failure, etc.) Ensure Consequences: 1.11.1.1
that safe operation can be maintained, with personnel on site.

Previous HAZID Recommendation 10


5. Confirm that the helipad locations are suitable and meet regulations.

Consequences: 1.11.2.1

Previous HAZID Recommendation 11


6. Check if hot oil is always below its flash point, and therefore is non-hazardous in case of leak. If not practicable, review Consequences: 2.1.2.1
area classification for hot oil system area.

Previous HAZID Recommendation 12


7. Review the open drains from the amine area, consider means to prevent amine spills contaminating the general water
treatment system.

Consequences: 2.5.2.1

Previous HAZID Recommendation 13

ARC-579-002-R01
Issue 02
April 2015
Page 67 of 50

Abbott Risk Consulting Limited


Recommendations
8. Check if credible leak from stripping column overhead system discharge could lead to a health hazard, if so consider
detection requirements.

Place(s) Used
Consequences: 2.5.3.1

Responsibility

Category

PMC - Linde

AR

PMC

AR

PMC

AR

PMC - Linde

CR

PMC

AR

Consequences: 4.1.4.1

AMEC

AR

Consequences: 5.8.8.1

PMC

CR

Previous HAZID Recommendation 14


9. Establish criteria for ice build up to be considered in design and concept for dealing with ice build up, including potential Consequences: 2.8.5.1,
dropped object during thaw.
3.8.5.1, 4.8.5.1, 5.8.5.1

Previous HAZID Recommendation 17


10. Provide means to limit evaporation from LNG spill pit, e.g. high expansion foam or floating block systems. Assess the Consequences: 3.1.3.4,
impact of the resulting cloud in a spill event when the pit location is defined.
4.1.3.4, 5.1.3.4

Previous HAZID Recommendation 18


11. Check the requirements for rotating equipment in hazardous areas as potential ignition source (e.g. bearing
temperature monitoring). Concern is that the only known standard is EN-13463, which may not be applicable in BC.

Consequences: 3.3.1.1,
4.3.1.1, 5.3.1.1

Previous HAZID Recommendation 20


12. Establish position of cranes/ lifting equipment for plant maintenance, consider minimising requirements for lifting over Consequences: 3.8.6.1,
live plant (e.g. maintenance of one liquefaction train with the other in operation).
4.8.6.1, 5.8.6.1

Previous HAZID Recommendation 21


13. Ensure that effluent drainage and treatment is designed for the possibility of hydrocarbon condensate leakage (low
flashpoint hydrocarbon) from any condensate handling areas in the LNG train.

Previous HAZID Recommendation 22


14. Confirm isolations on LNG transfer lines to limit LNG spill in the case of leakage, particularly for flexible joints at the
moorings.

Previous HAZID Recommendation 23

ARC-579-002-R01
Issue 02
April 2015
Page 68 of 50

Abbott Risk Consulting Limited


Recommendations
15. Review potential for transformer failure leading to a hazard to the process plant. If required, consider additional
safeguards.

Place(s) Used

Responsibility

Category

Consequences: 6.1.2.2

PMC

AR

Consequences: 2.12.4.1

PMC - Linde

CR

17. Review fire fighting means for pool fires at the condensate tank or diesel storage, e.g. foam or dry powder system.

Consequences: 7.1.1.1,
7.1.3.1, 7.1.5.1

PMC - BOP

CR

18. Review segregation distance between condensate tank and LNG area. Confirm that code requirements are met.

Consequences: 7.1.1.1

PMC - BOP

AR

19. Consider safeguards against external forest fire (e.g. fire break at plant boundary and/or perimeter boundary and
vegetation control around plant area).

Consequences: 7.1.6.1

PMC - BOP

AR

20. Select equipment for piperack area as minimum of Zone 2, or equivalent.

Consequences: 7.1.7.1

PMC - BOP

CR

21. Develop standards for external vehicles (e.g. condensate trucks) within the safety management plan.

Consequences: 7.1.8.1

PMT - BOP

CR

22. Review hazards from stored chemicals in the case of fire, and include mitigation requirements in the building basis of Consequences: 7.2.2.2
design.

PMC - BOP

AR

23. Review hazards from fire in BOP systems and buildings adjacent to the rundown piperack and provide separation
where required.

Consequences: 7.2.7.2

PMC - BOP

AR

24. Review common cause loss of normal and emergency power, particularly to process plant, and the required system
integrity.

Consequences: 7.2.3.4

PMC

AR

25. Review the protection of flare headers and support structures against process area fire, to ensure blowdown duration Consequences: 8.1.2.1
is protected.

BOP

CR

26. Review the protection of flare headers and support structures from FSO against process area fire. Ensure that safe
venting is available in the case of impairment of the flare system.

Consequences: 8.1.3.1

BOP

CR

27. Review the implications of damage to the flare system in the event of a vapour cloud explosion in the LNG area.
Identify if a design accidental load for blast is required.

Consequences: 8.3.1.1

BOP

AR

Previous HAZID Recommendation 25


16. Route hot oil and tempered water expansion vapour vent and PSVs to flare system (LP warm flare), to avoid
hydrocarbon release to atmosphere.

Previous HAZID Recommendation 28

ARC-579-002-R01
Issue 02
April 2015
Page 69 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

Responsibility

Category

28. Conduct unignited gas dispersion studies to confirm that emergency flare releases, without ignition, do not lead to an
unsafe condition due to flammable gas cloud formation.

Consequences: 8.15.1.1

Solaris - Flare

AR

29. Review the reliability of utility gas supply to pilots, and if a backup supply is required (e.g. from BOG or local bottle
supply). Concern is that Fortis maintenance or defect may require isolation of utility gas.

Consequences: 8.15.1.1

PMC - BOP

AR

30. Identify any chemicals handled in the BOP area which may pass through oily water separation. If any are identified,
provide separate containment to prevent drainage into the surface water system.

Consequences: 7.10.2.1

PMC - BOP

AR

31. Review the disposal of lab drains to ensure that they are correctly treated.

Consequences: 7.10.2.1

PMC - BOP

AR

32. Review if flammable gas hazard from landfill is credible.

Consequences: 7.12.2.2

PMC - BOP

AR

33. Review the potential hazards from venting from chlorination system when the technology has been chosen.

Consequences: 7.12.3.1,
7.12.3.2

BOP

AR

34. Review the detection and isolation of leaks at the inlet startup heater area, which is upstream of the ESDV.

Consequences: 2.1.4.1

PMC - Linde

AR

35. Review the hazard from pentane fuel in module 2, near the fired equipment.

Consequences: 2.12.3.2

PMC - Linde

AR

36. Review the segregation of refrigerant storage and flare system from plant hazards.

Consequences: 4.1.1.1

PMC

AR

37. Establish the means for refrigerant supply to site and filling of refrigerant makeup storage.

Consequences: 4.8.7.1

PMT

AR

38. When refrigerant delivery method is defined (refer to recommendation 37), review the hazards and controls required.

Consequences: 4.8.7.1

PMC - BOP

AR

39. Ensure that liquid hydrocarbon entering the surface drains in each of the train areas is separated before the water is
discharged.

Consequences: 2.12.2.1,
2.12.3.1

BOP

CR

40. Conduct drainage philosophy review, to ensure that the safety and environmental hazards for hydrocarbon into the
drain system are addressed.

Consequences: 2.12.3.1

PMC

CR

41. Confirm the design of LNG catchments and the means to prevent LNG ingress to the drain system. Select a passive
means if practicable.

Consequences: 3.1.3.5,
4.1.3.5, 5.1.3.5

BOP

CR

42. Conduct transient analysis of flow in the rundown line from LNG train to FSO, including surge and other upset
conditions.

Consequences: 5.8.7.1

PMT

CR

Also consider the environmental implications of any routine venting to atmosphere from the process.

It is noted that an LNG train philosophy is available from Linde, but has not been integrated into the plant water
treatment philosophy.

ARC-579-002-R01
Issue 02
April 2015
Page 70 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

Responsibility

Category

43. Confirm that fire and explosion protection of substation in the train area is adequate to mitigate against common cause Consequences: 6.1.1.1
loss of power and control to train and equipment.

PMC

CR

44. Consider if FSO control room should be permanently manned, and if it should remain manned in the case of a fire on Consequences: 9.1.2.4,
the jetty or train. If so, review fire and blast protection requirements.
9.3.1.1

FSO

AR

45. Review evacuation routes from all areas on the FSO.

Consequences: 9.1.2.4

FSO

AR

46. Review access and mechanical handling for maintenance on transfer arm between jetty and FSO, as this may be
conducted during operation with the spare arm in use.

Consequences: 9.1.3.1

BOP

CR

47. Consider cold protection in the area of the rundown line from shore to avoid damage to the hull in case of leakage
(e.g. sacrificial splash plate).

Consequences: 9.3.2.2,
9.5.1.2

FSO

AR

48. Consider cold protection in the area of the rundown line from shore to avoid damage to the jetty piles in case of
leakage.

Consequences: 9.3.2.2,
9.5.1.2

Jetty

AR

49. Review reliability and availability of hold space LNG secondary containment sump pumps, and if emergency power is Consequences: 9.4.1.1
required.

FSO

AR

50. Identify if vacuum breakers on LNG tanks could be removed, as is current practice for Moss tanks, and develop
vacuum protection design.

Consequences: 9.4.2.1

FSO

AR

51. Review LNG tank protection against air ingress at HAZOP.

Consequences: 9.4.2.1

PMC

CR

52. Check overpressure protection of the condensate tank. If routed into the LP flare system, this has a design pressure
greater than the tank, but if routed to atmosphere, there may be a flammable hazard in the area of the train.

Consequences: 7.1.2.1

PMC - Interface

AR

53. Review the hazard of N2 in utility building, and ensure that asphyxiation hazard is addressed.

Consequences: 7.5.2.1

BOP

CR

54. Identify the hazards from chemicals to be stored, when they are selected, and ensure that handling and storage
arrangements are suitable to protect personnel and releases to the environment.

Consequences: 7.5.1.1,
7.5.1.2

BOP

CR

55. Review requirement for enclosed buildings in the utility and cooling water areas. Eliminate, where possible, to
minimise the potential for vapour clouds inside buildings.

Consequences: 7.4.1.1

BOP

AR

56. Review the hazard from temporary substation as a source of ignition, or a fire hazard which might affect process
equipment.

Consequences: 7.4.1.1

BOP

AR

57. Ensure that oxygen-rich gas from N2 generation is dispersed safely.

Consequences: 7.12.5.1

BOP

CR

58. Review scenario of prolonged loss of power if the interim substation transformer fails. In this case, the plant could
require to be maintained in a safe condition without external power for a period of months. Consider if offloading
remaining stored inventory is possible without external power.

Consequences: 7.2.5.1

BOP

AR

ARC-579-002-R01
Issue 02
April 2015
Page 71 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

Responsibility

Category

59. Review the alternative means of control and shutdown, in the event that the control room has to be evacuated due to
internal hazard.

Consequences: 7.2.8.1

PMC - BOP

AR

60. Confirm that physical protection is provided around process areas and structures (e.g. pipe and cable bridges), to
protect against accidental impacts from vehicles and handling operations.

Consequences: 7.7.1.1

BOP

CR

61. Consider if a buffer storage is required for off-spec produced water, to enable plant operation to continue in an upset
case at the treatment plant.

Consequences: 7.13.1.1

BOP

AR

62. Check the basis for the maximum rainfall event used in sizing the surface runoff retention pond.

Consequences: 7.13.2.1

BOP

CR

63. Consider if discharge points for runoff to sea should be provided with valves to stop the runoff in the case of a spill,
e.g. on a roadway.

Consequences: 7.13.3.1

BOP

AR

64. Sample existing leachate to determine the contaminants that are present and ensure that treatment is adequate.

Consequences: 7.14.1.1

PMT

CR

65. Review the expected material to be added to the landfill and predict the leachate composition and flow which must be Consequences: 7.14.1.1
treated. Design the leachate treatment appropriately.

BOP

AR

66. Consider if hypochlorite injection pipework should be inside the sea water intake, so that leakage is not to the sea.

Consequences: 7.15.1.1

BOP

AR

67. Confirm that consistent pressure and temperature safeguarding philosophies are developed for BOP, flare and FSO
scopes, and cover interfaces with the LNG train.

Consequences: 1.1.1.1

PMC - Process

CR

68. Confirm that consistent fire and explosion protection philosophies are developed for BOP, flare and FSO scopes, and Consequences: 1.3.1.1
cover interfaces with the LNG train.

PMC - Fire Protection

CR

69. Confirm that consistent fire and gas detection philosophies are developed for BOP, flare and FSO scopes, and cover
interfaces with the LNG train.

Consequences: 1.4.1.1

PMC - Fire Protection

CR

70. Confirm that consistent PFP and AFP philosophies are developed for BOP, flare and FSO scopes, and cover
interfaces with the LNG train.

Consequences: 1.5.1.1

PMC - HSE

CR

71. Confirm that blowdown philosophy has been updated to the latest LNG train configuration, and blowdown study
remains valid.

Consequences: 1.6.1.1

PMC - Linde

CR

72. Confirm that consistent ESD and EDP philosophies are developed for BOP, flare and FSO scopes, and cover
interfaces with the LNG train.

Consequences: 1.6.1.1

PMC - Process

CR

73. Confirm that consistent working environment philosophies are developed for BOP, flare and FSO scopes, and cover
interfaces with the LNG train.

Consequences: 1.8.1.1

PMC

CR

PMC - HSE

AR

74. Consider the philosophy for evacuation and mustering of whole site area, including remote locations such as metering Consequences: 1.8.1.2
station, flare area, fire water tank, etc.

ARC-579-002-R01
Issue 02
April 2015
Page 72 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

Responsibility

Category

75. Confirm that noise control philosophies are developed for BOP, flare and FSO scopes, and cover interfaces with the
LNG train and that this meets the requirements of the site noise limits.

Consequences: 1.9.1.5

PMC

CR

76. Confirm location, extent and specification of site perimeter fence and control of access at road crossings and river
crossing.

Consequences: 1.12.1.1,
1.12.3.1

BOP

CR

77. Develop wildlife management plan (including bear hazards).

Consequences: 1.12.1.1

PMT

CR

78. Develop project safety and security plan, including potential for public protest.

Consequences: 1.12.3.1,
1.12.3.2

PMT

CR

79. Confirm that structural/ marine/ civil design criteria are consistent with the basis of design requirements, for all areas of Consequences: 1.13.1.2
the site.

PMC - Structural

CR

80. Review the consequences of failure of the Henriette dam, and identify any additional safeguards required.

Consequences: 1.20.1.1

PMT

AR

81. Conduct additional study into the likelihood and consequences of marine landslip, and identify additional design
protection if practicable.

Consequences: 1.17.3.2

BOP

AR

82. Ensure that civil design includes requirements to control dust from external areas.

Consequences: 1.19.1.1

PMC - Civil

CR

83. Ensure that operational management plan includes dust control measures.

Consequences: 1.19.1.1

PMT

CR

84. Study potential flooding of Mill creek and confirm that flood protection measures are appropriate for the hazard.

Consequences: 1.20.2.1

PMT

CR

85. Review if raw water supply from Mill creek is sufficiently reliable to avoid operational upsets in the event of drought,
considering the buffer volume available in the raw water tank.

Consequences: 1.19.1.2

BOP

AR

86. Confirm that requirements for the EIA are incorporated in the basis of design. Note this applies to all environmental
issues, not just lighting.

Consequences: 1.9.1.6

PMT

CR

87. Ensure the operations philosophy complies with the requirements of the EA, for the handling of hazardous materials.

Consequences: 1.9.1.8

PMT

CR

88. Review the risk of cryogenic damage to structures on the FSO from header leaks, and identify if any additional
cryogenic protection is required.

Consequences: 9.5.1.2

FSO

AR

89. Review the possibility of LNG leak on the rundown line. If credible leak sources are identified, provide LNG leak
containment.

Consequences: 9.5.2.2

BOP

AR

90. Relocate FSO diesel bunkering point to the aft access bridge, to avoid unnecessary vehicle operations near the
process connections. Ensure that spill protection is provided.

Consequences: 9.5.3.1,
9.5.3.2

BOP

CR

91. Review hazards from existing CO2 fire fighting system. Consider upgrading to modern standards.

Consequences: 9.5.5.1

FSO

AR

ARC-579-002-R01
Issue 02
April 2015
Page 73 of 50

Abbott Risk Consulting Limited


Recommendations

Place(s) Used

Responsibility

Category

92. Review the potential for roll over in the FSO tank, considering the feed composition. If required, confirm that roll over is Consequences: 9.6.1.1
within the sizing basis for FSO tank PSVs.

FSO

CR

93. Consider the margin available above the design storm event and confirm that break away will not occur due to small
exceedance.

Consequences: 9.11.1.1

BOP

CR

94. Confirm that mooring design can accommodate maximum angles from damage stability analysis, when available.

Consequences: 9.11.3.1

FSO

CR

95. Establish position of cranes/ lifting equipment for plant maintenance and loading and offloading operation, consider
minimising requirements for lifting over live plant .

Consequences: 9.7.2.1,
10.7.2.1

FSO

AR

96. Consider if gassing up of LNGCs should be considered as an operation for the site, including the discharge that this
involves.

Consequences: 10.12.1.1

PMT

AR

97. Consider requirement for dispersion modelling of FSO tank PSVs to ensure release to safe location.

Consequences: 9.15.1.1

PMC

AR

98. Conduct avalanche hazard assessment, as required by Worksafe BC, and comply with requirements.

Consequences: 1.21.2.1

BOP

CR

ARC-579-002-R01
Issue 02
April 2015
Page 74 of 50

You might also like