You are on page 1of 84

GOVERNMENT OF

MALAYSIA

MALAYSIAN HIGHWAY
AUTHORITY

JAMBATAN KEDUA
PTD. LTD.

Bridges Asia
22-25 February 2010
Sustainable Bridge Construction Practices
Case Study: Second Penang Bridge,
Malaysia

Presented by: Dato Prof. Ir. Dr. Ismail Mohamed Taib


Managing Director
Jambatan Kedua Ptd. Ltd.

Sustainable Bridge Construction Practices


Case Study: Second Penang Bridge,
Malaysia
PROJECT INTRODUCTION
UNDERSTANDING FAST-TRACK CONSTRUCTION
PROCESSES OF LONG BRIDGE

APPRECIATING INCREASING ENVIRONMENTAL


CONCERNS IN BRIDGE CONSTRUCTION
IDENTIFYING ALTERNATIVE MATERIALS AND
COMPOSITES FOR BRIDGES

Location Map

We Are Here

Location of Second
Penang Bridge,
Malaysia

Project Alignment
Legend:

Existing Penang Bridge

Existing Penang Bridge


North South Highway (PLUS)

PENANG
ISLAND
(Batu Maung)

Package 1&2
Package 3
Marine Bridge
Land Expressway

PULAU
JEREJAK

0.

NAVIGATIONAL
SPAN

0.

4+
00

6+
23
+0

12
+0

000

00
.

00

+0

000

11

10+

9+000

8+000

0.

7+00

0.

00

00
.

000
21+
.

0.

20+00

0.

19+00

0.

18+00

0.

0.

17+00

0.

16+00

00
.

15+00

14
+0

.
00

0.

5+
00

22+

+0
13

00
0.

3+

0.

00

2+

0.

00

1+

PULAU
AMAN

MAIN LAND
(Batu Kawan)

Background

Being a major transportation hub, Penang has witnessed a fast economic


growth over the past 15 years.

The traffic flow to the island has reached 65,000 vehicles per day. Despite
the existing Penang Bridge has been expanded, the number of vehicles
are expected to rise to 80,000 vehicles per day in two years time.

It is imminent that the existing Penang Bridge will not be able to cope
with the manifold increase of traffic volume.

The construction of the Second Penang


Bridge is aimed to alleviate the current
overloaded traffic at the existing
bridge and to meet the future traffic
demand, apart from being the key
catalyst
for
the
sosio-economic
development in the region.

Introduction

The Second Penang Bridge was designed to resemble the existing


cable-stayed Penang Bridge, which span on the straits of Penang from
Batu Kawan on the mainland to Batu Maung on the island.

The bridge is expected to reduce traffic on the First Penang Bridge by


20% and will transform Penang into key logistic and transportation hub
for the northern region of Malaysia under the Northern Corridor
Economic Region (NCER) programme
and Growth Triangle comprising
Indonesia, Malaysia and Thailand
(IMTGT).

The iconic bridge when completed


will be the longest in South-East Asia
with the total length of 16.9km and
an estimated cost of RM 4.5 billion.

Overall Project Organization

Distribution of Contract Packages


Integrated Toll System

Package 3A:
Conventional
Contract

Package 1 : Main Navigation Span &


Substructure & Foundation Works for Approach
Spans.
Package 2: Superstructure Works of Approach
Spans.

Package 3B,3C,3D,3E, 3F & 3G :


Conventional Contract

Design & Build


8

Design Features

Length of Bridge

16.9km

Length of Expressway

7.1km

Lane Configuration

Dual 2 lanes traffic + emergency lane +


1 motorcycle lane each direction.

Main Navigation Span

Cast in-situ Cable-Stayed Bridge


P24 to P27 = 117.5m + 240m + 117.5m
= 475m.
Height Clearance: 30m
Navigation Channel: 150m

Approach Span
Substructure

P0 to P24

Superstructure

Pre-cast Prestressed Segmental Box Girder


= 8,092 nos.

= 24 span x 55m
= 1,320m.
P27 to P292 = 265 span x 55m
= 14,575m.
Height Clearance :
Low Piers: 6m
High Piers: 6m to 21.6m

UNDERSTANDING FAST-TRACK CONSTRUCTION


PROCESS OF LONG BRIDGE
Case Study: Second Penang Bridge

ELEMENTS
DESIGN & BUILD CONTRACT vs Conventional
Contract
DESIGN CONCEPT

CONSTRUCTION METHODS

10

DESIGN & BUILD CONTRACT vs Conventional Contract

Due to time constraint to complete and to


open the bridge for the traffic by end of
2013, a fast-track strategy was crucial.
Design and Build contract is a combination of

all (running parallel), depending on the size,


scope, and complexity.

In Second Penang Bridge, the contracts are

divided into 2 types:

Design and Build Contract


Conventional Contract
12

DESIGN & BUILD CONTRACT vs Conventional Contract

Design & Build contract for project delivery

system was adopted for Package 1 and 2 to


reduce the delivery schedule by overlapping the
design phase and the construction phase.

The

interfacing works between the two


packages and the Land Expressway packages
are clarified and incorporated under the
Interfacing Agreement of both Contracts.

13

DESIGN & BUILD CONTRACT vs Conventional Contract

Design and Build Contract

Package 1 & 2 RM3.75 billion or 83% of the Total


Project Cost

Package 1 Main Navigation Span and Substructure and


Foundation Works of Approach Span.
o

o
o
o

Date of Site Possession


Date of Completion
Completion Period
Contract Amount

: 8 Nov 2008
: 8 Mar 2013
: 52 Months
: RM2.2 billion

Package 2 Superstructure Works of Approach Span.


o
o
o
o

Date of Site Possession


Date of Completion
Completion Period
Contract Amount

: 8 Jun 2009
: 8 Sept 2013
: 51 Months
: RM1.55 billion

14

DESIGN & BUILD CONTRACT vs Conventional Contract


Due to stringent Project timeframe , most of the major Project
Scopes will be implemented on a Fast Track Basis

TIME

Oct 08

Technical Proposal

Nov 08
Sep 13

Nov 13

Design
Completed

Design
Procurement

Construction
Drawings
Completed

Construction
Completed

Construction Drawings

Construction
Commissioning

Overlap between
Design & Construction

15

DESIGN & BUILD CONTRACT vs Conventional Contract

The Design & Build contract implemented in the

Second Penang Bridge Project, provides the


following advantages:

Singular Responsibility concept


Better Quality of product
Time Saving for the project
Improved Risk Management

16

DESIGN & BUILD CONTRACT vs Conventional Contract


CONSESSIONAIRE /
PROJECT MANAGER

Singular
Responsibility
Concept

JAMBATAN KEDUA
Ptd. Ltd.
Ptd.

INDEPENDENT EIA CONSULTANT

INDEPENDENT CHECKING
INDEPENDENT
CHECK ENGINEER
ENGINEER

ERE CONSULTING
GROUP Ptd. Ltd.

ARUP Jururunding
Ptd. Ltd.

Package 1, 2 & 3

Package 1 & 2

FISHERIES IMPACT ASSESSMENT


CONSULTANT
FANLI MARINE AND
CONSULTING Ptd. Ltd.

Package 1, 2 & 3
CONTRACTORS

PACKAGE 1

PACKAGE 2

CHEC
Construction (M)
Ptd. Ltd.

CONSULTANT
(Designer)
HPDI Consultants
Co. Ltd

UEM Builders
Ltd.

CONSULTANT
(DESIGN REVIEW &
SUPERVISION)

MMSB Consult Ptd. Ltd

EIA CONSULTANT
R-SYNC Tech.
Resources Ptd. Ltd.

EIA CONSULTANT
DR. Nik & Associates
Ptd. Ltd.

CONSULTANT
(DESIGNER)
RB Perunding Ptd. Ltd.

EIA CONSULTANT
YES Enviro Services
Ptd. Ltd.

16

DESIGN & BUILD CONTRACT vs Conventional Contract


Client, Independent Checking Engineer and Contractor - Roles and Responsibilities

Employer s Requirement (ER)


ER was introduced by JKSB to outline the scope of Design & Build (D&B) Contract
for general, contractual & technical requirements and contractor shall comply with
all the requirements within the stipulated time up to as well as defect liability
period.

Independent Checking Engineer (ICE)


ICE is appointed by JKSB for the following scope of works to ensure the specific
clients requirements & high quality of work are delivered:

Review design input parameters adopted to confirm on fundamental design


issue

Review & comment design brief & final design report

Prepare design check report & certification

Verify & endorse progress payment

Audit construction works

Design & Build Contractors


Contractors hold most of the responsibility for the design, construction and
supervision of the project
17

DESIGN & BUILD CONTRACT vs Conventional Contract

Conventional Contract
Conventional Contract is adopted for Package 3 (Land Expressway
Portion) with the value of RM 750 mil or 17% of the Total Project Cost.
The objectives are:

to give the opportunity to local/Bumiputera Contractor/Consultant


to participate in such prestigious project

to expose local Contractor/Consultant in executing mega project

to encourage transfer of technology

to create job opportunities for local people

to spur economic development for the benefit of local businesses and


trades
18

Design Concept
Package 1 Main Navigation Span

Scope of D&B
Packages

m NGVD

117.5m

m NGVD

m NGVD

240m

m NGVD

m NGVD

NGVD

117.5m

m NGVD

m NGVD

m NGVD

P024

m NGVD

m NGVD
P025

P027

P026

Main Navigation Span


(Front Elevation)

19

Scope of Works for the Design and Build Contractor

Design Concept

Package 1 & 2 Approach Spans


14400
7300

3000

29800

Scope of D&B
Packages

PACKAGE 2
Superstructure

Horizontal Split

PACKAGE 1
Substructure

m NGVD

Approach Span
(Cross Section)

20

Design Concept
MAIN NAVIGATION SPAN
Foundation
Bored piles adopted for main and end piers at
thick layer of dense sand and silty
clayey below 45m of seabed level.
Total 66 pts. of 2.0m and 2.2m dia
Bored Piles with average length of
120m.

21

Design Concept
MAIN NAVIGATION SPANS
Substructure

Steel Fender vs Man-made Island (First Penang Bridge)


Steel Fender

Man-made Island

i) Easy to construct, hence


shorter construction period

i) Difficult to construct & much


longer construction period

ii) Compact thus does not restrict


the navigation passageway

ii) Occupy larger water area,


restricting navigation
passageway

iii) Low impact on the environment


and existing hydrological condition
due to its relatively small size

iii) Dredging and sand taking


greatly damage environment

Design Concept
MAIN NAVIGATION SPANS

Substructure

Total pilecap
: 4 nos
Pilecap size (P25 & P26): 48.1m x 17.5m x 6m
Pilecap size (P24 & P27): 42.7m x 10.6m x 4m

Steel Fender System


The steel fender system was adopted due to its environmental friendliness, cost
saving and shorter construction period.

Design Concept
MAIN NAVIGATION SPAN
Superstructure
Cable Stayed Bridge

The cable stayed bridge design is adopted for its advantages in the
aspects of performance, construction methodology, project duration
and cost competitiveness.
The main navigation is a 3-span twin tower fan-type cable stayed
bridge of continuous rigid beam and slab deck with span arrangement
of 117.5m + 240m + 117.5m and to be erected by the balanced
cantilever method.

Design Concept
SUPERSTRUCTURE FEATURES

Type of Structure: prestressed concrete beam and slab deck

Spans arrangement: 117.5m + 240m + 117.5m

Pylon type: H shape concrete tower

Pylon size: Upper 3.0m x 4.0m


Lower Gradually increase from top to
bottom (5.0m x 6.0m)

The pylon concrete grade: 50 N/mm

Main beam: table shape section (2 side web and 1 top flange)

Typical beam height : 2.8m

Deck slab thickness : 28cm

The main beam concrete


grade: 55 N/mm

Design Concept
APPROACH SPAN
Foundation
Prestressed Precast
Concrete Spun Piles

designed where the


overlaid deposit is thick
40m length for each pile
total 5166 pts of 1.0m dia
Spun Piles with average
penetration length of 55m

Tubular steel piles

adopted at deep water area


Total 368 pts of 1.6m dia
Steel Piles with
average length of 80m

Bored piles

applied at the shallow water


and thin deposit area
Total 80 pts of 1.5m dia Bored
Piles

Design Concept
APPROACH SPAN

Advantages of different types of foundation


a) Bored pile
- easily adapted to the various load and soil requirements due to large variety in dia
and construction techniques.
- enable the immediate in-situ evaluation of drilled soil layers to revise foundation
length due to changed soil conditions
- Absence of vibration will not disturb adjacent piles
b) Steel pile
- have high load-carrying capacity for a given weight of pile, which can reduce driving
costs
- can be driven in very long lengths and cause little ground displacement
- easy to splice

c) Spun pile
- Faster, prefabricated allows longer length with less joint
- Efficient mass to strength ratio
- Piles can be withstand higher tension forces which make them suitable for cater
wind load & earthquake problem
27

Design Concept
APPROACH SPAN
Foundation

Prestressed precast concrete spun piles


Out of total of 292 piers, 248 piers or 85% adopted prestressed precast concrete spun piles.

Advantages:

Suitable for the Project by dredging at the thick overlaid deposit area. Dredging is also
carried out to allow for the transportation of materials and movement of marine traffic.

More competitive on cost compared to steel piles or


bored piles.

Available locally from pile manufacturers and


Installers.
Easy to install in marine environment.

Able to safely withstand ship impact forces via


raking piles.

Does not involve usage of expensive steel casing.

Fast construction. One piling machine can


complete 1 pier in 5 days compared to bored piles
area which takes about 6 months to complete one
pier with 2 RCD drilling machines based on the
same number of quantity.

28

Design Concept
APPROACH SPAN
Substructure
Pile caps, Columns and Crossheads are

designed as reinforced concrete structures

Total no of Piers 289 nos at Approach Spans

The sections and shapes of the pile caps, columns and

crossheads are designed to enhance constructability,


construction time and aesthetically pleasing.

29

Design Concept
APPROACH SPAN
Superstructure
Segmental Box Girders
The precast segmental box girder is designed as a continuous single twin box of 14.08m width,

4.0m length and 3.20m depth structure with match cast joints, multiple shear keys and
prestressing tendons.

This type of box-girder was selected because of its size that does not require extensive casting

facilities, special heavy lifting equipment and storage as compared to a precast full-length box
girder.

The design of the segments is repetitive which allows the same formwork to be used
The depth is maintained constant to present aesthetically consistent soffit line.
Total 7 types of Segmental Box Girder are designed for each span.

30

Construction Methods
Main Navigation Span
1. Foundation & Substructures
a) Method of Reverse Circulation Drilling (RCD) drilling bored piles
b) Construction sequence of pile cap and installation of steel fender
2. Superstructures
a) Slip form system for pier column and pylon
b) Cable stayed system
c) Traveler form for deck
Approach Span
1. Foundation & Substructures
a) Precast RC Shell
b) 2 stage construction of pile cap (low tide or high tide)
2. Superstructure
a) 1 system steel formwork for the column and crosshead
b) Precast segmental box girder
c) Launching of SBG using span by span method
31

Construction Methods
MAIN NAVIGATION SPANS
Substructure

Method of Reverse Circulation Drilling (RCD) for bored pile

The first stage of the borehole is bored by rotary drill and lined with
a temporary steel casing.

Bentonite slurry is fed into the hole in order to maintain the


required counter pressure.

On reaching the required depth, reinforcement is lowered through


the bentonite slurry and concrete is placed using a tremie pipe. The
concrete displaces the slurry, which is pumped back into the storage
tank as it rises up the borehole.

Slurry waste and debris are then conveyed into mud container and
transported to centralized treatment.
32

Construction Methods
Construction Sequence of Bored Piling

Building Platform

Steel Cage Inspection

Installation of Steel Cage

Casing Installation

Inspection of Drilled Hole

Concrete of Bored Pile

Mixing of Bentonite Slurry

Drilling with Bentonite


slurry lining

33

Construction Methods
MAIN NAVIGATION SPANS
Substructure
Steel Fender
Fabrication : Factory Dongguan Yin Ji Heavy Industry Con. Ltd
Maximum dimension of Steel Fender (Main Pier P25 & P26) : 8.6m 9.1m.
Maximum dimension of Steel Fender (Transition pier P24 & P27): 8.69.1m.

Installation
Sequence For Steel
Fenders - Main Pier
P25 & P26

Installation
Sequence For Steel
Fenders - Transition
Pier P24 & P27

Construction Methods
Construction Sequence of Pile Cap

Construction Methods
Construction Sequence of Pile Cap Contd

Construction Methods
MAIN NAVIGATION SPANS
Superstructure

Slip Form System

Slip form is a self-climbing formwork that once set up as a desired-shaped


wall to be built, it ascends continually to the height of the structure.

Slip form system is used for the construction of pylon and piers which are
more than 8m height.

Each lift will be 4m ~ 5m height

Working platform will be provided at the top of the formwork system

Slip form system provides high speed of erection (works execution speed
increases) and as a result, rapid completion of the project

There is no need to dismantling or re-assembling.


37

Construction Methods
MAIN NAVIGATION SPANS
Superstructure

Reasons for the selection of cable stayed bridge

1. Allow for a slim section


2. Enable for long spans bridge

3. Better aspect in performance


4. Construction methodology
5. Project duration faster
6. Cost optimization

38

Construction Methods
Deck Works
Construction using
Cantilever Method

Stage 1 Construct
piers and pylons

Stage 2 Erect temporary


falsework and cast first
deck segment
Stage 3 Remove
temporary falsework,
install cable, traveler form
and cast the next deck
segment.

Construction Methods
Deck Works
Construction using
Cantilever Method
Contd

Stage 4 and onwards The


process is repeated until all
the cables and decks are
installed.

Construction Methods
Traveler form for deck

MAIN NAVIGATION SPANS


Super Structure

For deck works construction at


main navigation span, traveler

formworks system is used. This


method will start with stay cable
erection followed by the casting
and prestressing of segments in
stages until it reaches the
maximum free cantilever mode.
Then the same procedures will be

repeated for the next segments.

41

Construction Methods
APPROACH SPAN
Pilecap Construction

Insitu construction is ruled out due to high cost and time


requirements of cofferdam.

Precast Concrete Shells are adopted for:

Minimisation of temporary works (no cofferdams).

Minimisation of insitu works


Speed of construction
Better surface finishing works

Precast Concrete Shells are used as a formwork for second layer


casting and permanently incorporated into the pile cap

6 pieces of Precast Concrete Shell are required for each pilecap.

Total of 3,468 nos of Precast Concrete Shell will be used

Casting and Curing are carried out in the Casting Yard

Transported to temporary jetty and delivered to


worksite by barge.

Two casting yards have been establish for overall production

Total 27 sets of precast mould are used which consist of 18 sets


of 9m dia. and 9 sets of 10m dia.

Construction Methods
APPROACH SPAN
Substructure
Two stage construction of pilecap
The pilecap is designed in accordance to method

construction sequence where 2 stages casting are


allowed.

The 1st layer is cast to act as a base for the installation

of precast concrete shell which is designed to act as


permanent formwork for the 2nd layer pile cap
construction. Both casting to be carried out during low
tide condition

43

Construction Methods
APPROACH SPAN
Substructure
Steel formwork
The bridge consists of 578 nos. of Piers i.e. P0(L/R) to P292 (L/R)
Piers are classified as Low (max height 6m) and High Piers (> 6m to

21.6m) from top of pile cap to top of crosshead - using self climbing
formwork.

60 nos. of high piers constructed using layer of prefabricated steel Pier

modules installed, cast, removed and installed for the next layer.
Process is repeated until crosshead level is reached.

518 nos. of low piers to be constructed using one continuous set

installation of pre fabricated steel formwork from pier to crosshead.

The crosshead forms are erected, fixed, cast and removed

44

Construction Methods
APPROACH SPAN
Superstructure
Casting of Segmental Box Girder (SBG)
Due to requirements of the project and
launching speed, short line match-casting
method is used for precasting of segmental box
girder.

Segments are being cast similar to cast of any


structure via moulds to specific shapes and
dimensions

Main components of the segments are


reinforcement bars and concrete.

Segment cast is allowed to cure prior to opening


of moulds section

Similar process is being adopted for casting of


next segment in the exception that frontal side
of the next segment shall be cast against the
previous cast segment. This term is match
casting. The shear keys act as the interlocking
shapes between the two segments.

SEGMENT STORAGE AREA 1 & 2

WORK
BATCHING SHOP
PLANT
OPERATION
CENTRE
LAB

OFFICE

OPEN CASTING
YARD 1
(7 BAYS)

OPEN CASTING
YARD 2
(9 BAYS)

SEGMENT STORAGE AREA 3 & 4

Total area= 50 Acres

567m

REBAR
CUT
SHOP

COVER CASTING
YARD
(7 BAYS)

298m

Construction Methods
APPROACH SPAN
Superstructure
SBG Casting Requirements

Method of casting

Short Line Match-Casting

Concrete volume

260,000 cu.m Gd 55/20

Steel Reinforcement

60,000 metric tonne

Weight of each SBG

65 tonne to100 tonne

Total SBG required

8,092 numbers

Total moulds

21 moulds

Daily output

14 nos/day (at peak)

Casting Cycle

3 days/bay

Total casting duration

28 months

46

Construction Methods
Methods of Segmental Box Girder Casting
Shortline Casting (Match Cast)

Segmental Box Girders


Match Casting

Perfect Match

SBG match casting concept


applicable for every span.

Construction Methods
SBG Casting Sequence

Tying rebar to in the dedicated


reinforcement jig.

SBG storage yard

Placement of reinforcement
cage in the SBG mould using
overhead crane.

Completed SBG transported


to yard by Straddle Carrier

Final inspection prior


to concreting of SBG

Concreting of
SBG

Construction Methods
APPROACH SPAN
Launching of SBG using Span by Span Method
Features and Advantages

Flexibility to use overhead or under-slung gantries

Fast rate of erection due to use of external post tensioning

Segment delivery is possible along completed deck to rear of gantry or


at sea level

Smaller crew size is required


compared to balanced cantilever
construction

Good access provided within the


gantry to all work fronts

Construction Methods
APPROACH SPAN
Launching Requirements
Total Marine Bridge Span

578 spans

Total launching gantry

4 nos.

Total launching output/gantry 1.5 span/wk


Total segments required

84 nos/wk

Plant storage capacity

750 nos

Plant daily output

12~14 nos/day

Overall Planning
A dedicated jetty is also built near the
precast factory to facilitate the delivery of
SBG to the bridge via sea barges.
There will be 4 barges carrying 5 numbers

of SBG on each barges for delivery to the


4 launching gantries.

Each 55m span consists of 14 SBG which

are 1 type P1, 1 Type P2, 2 Type S1, 2


Type S2, 2 Type D1, 5 Type S3 and 1 Type
S3A.

Construction Methods
Segment Transportation Procedure
Approaching, berthing and mooring at Jetty

Tug barge loaded with segment to the erection front

51

Construction Methods
Mooring Barges At The Erection Fronts
Anchor Handling Tug Boat disengage from working barge

52

Construction Methods
Launching Sequence
Offloading of segment from Barge

Gluing and temporary stressing

53

Construction Methods
Launching Sequence contd
- Segments have been installed to form a full span
- First stage Post Tensioning & Incremental Load Transfer
to form simply supported span

- Release hanger bars and remove lifting beams after the span
supported on the temporary support on pier
- Launch Main Girder to next pier

APPRECIATING INCREASING IN
ENVIRONMENTAL CONCERNS IN
BRIDGE CONSTRUCTION

55

Introduction
Environmental concerns in bridge construction take into
account the health and marine ecosystem as well as to
reduce demands and complaints from fishermen and fish
farmers who ostensibly incurred losses as a result of the
bridge construction.

56

Environmental Management
Organization Chart

Fisheries
Overview Fisheries Industry in Penang

There are 17 fishing villages on the island and 14 fishing


landing point on the main land.

In 2007, marine fisheries catch in Penang amounted to


37,774 tonnes worth RM 218.9 million.

The industry provides livelihood to nearly 3,193 fulltime


fishermen.

58

Fisheries
Location of Fisheries Landing Points

Location of Cage Culture Farms

Location of Cockle Farms

59

Appreciating Increasing Environmental


Concerns In Bridge Construction
Independent Consultant of Fisheries Impact Assessment (FIA)
Fanli Marine & Consultancy Ptd. Ltd. (Fanli) is appointed by JKSB as

an Independent Consultant to monitor the Fisheries Impact


Assessment (FIA) for this project. Fanli had earlier completed the
base line study in 2007 for the Fisheries Department.

Fanli scope of works cover:


o
o
o

To assess on the impact of construction


activities on fishing, cockle farming
To advise for such measures as necessary
To propose the mitigation measures

60

Appreciating Increasing Environmental


Concerns In Bridge Construction
Result of Water Quality in the fisheries landing point

Temperature (C)
levels at Study
Area

Dissolved Oxygen
(mg/L) levels at
Study Area

pH level at Study
Area

1st Sampling
2nd Sampling

Generally, most parameters were recorded within suitable


range for marine environment and fisheries purposes

61

Appreciating Increasing Environmental Concerns


In Bridge Construction

In the Second Penang Bridge, aquatic life such


as algae and fishes are found around the driven
piles.

They become food for fish like the Longfin


Bannerfish
(Heniochus
acumiratus),
Rock
Grouper (Epinephelus fasciatomaculosus) and
White Cheeked Monocle Bream (Scolopsis
vosmeri) and
the local udang lipan
(Stomatopod Crustacean).
Research by Lund University in Sweden has
discovered that the Oresund Bridge connecting
Denmark and Sweden have improved the Marine
Environment in 10 years since it was built.

Appreciating Increasing Environmental


Concerns In Bridge Construction
Package 1: EMA Consultant
R- Sync Technical Resources Ptd. Ltd is appointed as the EMA
Consultant for the monitoring of dredging and offshore disposal
Of spoils during construction phase.
The Scope of works cover:
o
o

o
o

o
o

TSS mapping via satellite imagery


Marine water quality monitoring at disposal site
Marine water quality monitoring along transportation on route
Composition of dredged materials
Bathymetric survey at disposal site
Final Environmental Audit

Equipment used:
o

Garmin GPS Receiver ( Model GPSMAP 76 CSx)


64

Appreciating Increasing Environmental


Concerns In Bridge Construction
Dredging activities at Package 1

The dredging activities have to be carried out due to shallow


water conditions at certain portions of the bridge alignment
which affect the barges movement for piling, pier and
launching activities.

The estimated amount of spoil to be dredged is 11,000,000 m3.

Location of dredge channel

Dredging Works
65

Appreciating Increasing Environmental


Concerns In Bridge Construction
CROSS SECTION OF MAIN DREDGED CHANNEL
CL

Viaducts

Sea Water
Level
Sea Bed Level

-3.0m ACD

-3.5m ACD

1:5

1:5 Barges Navigation1:5


Channel (BNC)

60m

170m
270m

40m

Main Dredged Channel


(MDC)

Note:
National Geodetic Vertical Datum (NGVD)
Admiralty Chart Datum (ACD)
(+0.00 NGVD = +1.72m ACD)

66

Appreciating Increasing Environmental


Concerns In Bridge Construction
Package 1 : Location of Water Quality Sampling by R-Sync Ptd Ltd

Water Quality sampling location


at disposal route

Disposal Area
67

Appreciating Increasing Environmental


Concerns In Bridge Construction
Result of Water Quality Sampling by R-Sync Ptd Ltd

All sampling locations generally


recorded a significant decrease in
TSS level compared to the baseline
level. This shows that the spoils
disposal activities are being carried
out in a proper manner.

Appreciating Increasing Environmental


Concerns In Bridge Construction
Package 1: Environmental Monitoring (EM) Consultant
Dr Nik & Associates Ptd Ltd is appointed to carry out the
environmental monitoring which cover the following scope
of work:
Environmental Impact Assessment (EIA)
Environmental Management Plan (EMP)

Total Suspended Solids (TSS) - Marine


69

Appreciating Increasing Environmental


Concerns In Bridge Construction
Package 1 : Location of Water Quality
Sampling by Dr Nik & Associates Ptd Ltd

Activities Location : Batu Kawan

Water Quality Sampling


stations
Activities Location : Batu Maung

Appreciating Increasing Environmental


Concerns In Bridge Construction
Water Quality : Comparison data between baseline
and actual for total suspended solids (TSS)

Above baseline TSS level at


station W18 may be caused by
surface run-off originated from
northern coastline.

71

Appreciating Increasing Environmental


Concerns In Bridge Construction
Package 2: EIA Consultant
YES Enviro Services Ptd Ltd is appointed to carry out the
EIA monitoring and preparing the reports which cover the
following scope of work:

Marine Water Quality during construction of load out jetty


River Water Quality
Air Quality
Noise Level
Discharge from Sedimentation Ponds
Discharge from Septic Tank

72

Appreciating Increasing Environmental


Concerns In Bridge Construction
Location of sampling YES Enviro Services Ptd Ltd

At the load out jetty

Sampling location for dredging activity

At the casting yard

Appreciating Increasing Environmental


Concerns In Bridge Construction
Results of sampling YES Enviro Services Ptd Ltd

Generally, suspended solids and turbidity values were


below the baseline conditions although the values
showed fluctuations

Appreciating Increasing Environmental


Concerns In Bridge Construction
Independent EIA Auditor / Consultant
To ensure the compliance to Department of Environmental

(DOE) requirements, ERE Consulting Group Ptd. Ltd. is


appointed by JKSB as an Independent EIA
Auditor/Consultant for the overall project.

The scopes and objectives of the EIA Auditor are to:


o
o
o

Check the implementation of environmental mitigation


measures
Review environmental monthly report
Review methodology, sampling and testing
Identify potential environmental issues and recommend
the mitigation measures
75

Appreciating Increasing Environmental


Concerns In Bridge Construction
Implementation of Environmental Monitoring Control

Location of Water Quality


Sampling Works

Location of Ambient
Environmental Monitoring
Station
76

Appreciating Increasing Environmental


Concerns In Bridge Construction
Best Management Practices At Site
PACKAGE 1

PACKAGE 1

Piling Barge Pier 200

Dredging Work Pier


276

Proper rubbish bins


was provided on the
barge

Silt curtain was erected


and maintained properly

PACKAGE 2
Piling Barge Pier 200
Good housekeeping on
the barge

Domestic bins was


provided at the working
area and site office

77

77

Appreciating Increasing Environmental


Concerns In Bridge Construction
Embodied Energy

Embodied energy is the total amount of energy required for the processes of
extraction, processing, construction, and disposal of a material

The design of Segmental Box Girder is optimized by adopting higher


reinforcement ratios and less concrete with a higher strength concrete

High performance concrete with silica fume and pfa cement is used to give the
durability required

Effective use of embodied energy; designs to be efficient and reduce waste

Silica Fume

78

IDENTIFYING ALTERNATIVE
MATERIALS AND COMPOSITES
FOR BRIDGES

79

Identifying alternative Materials And


Composites For Bridges
High Damping Rubber Bearing (HDRB)
The Employers Requirement (ER) requires no

damage criteria for a 500 years return period. In


addition to this, a requirement of no collapse
criteria for the most credible earthquake (2500
years return period) was also introduced. First
Penang Bridge was design on a similar
requirement.

HDRB Layout

Based on ICEs comments on the detail design,

spun piles at the approach bridge of Package 1


could only cater for the 500 years return period
earthquake. No plastic hinge forms as required
for no collapse criteria of 2500 years return
period.

HDRB Section

Identifying alternative Materials And


Composites For Bridges
HDRB Contd

Considering the current progress of works, it


was decided that a change of bridge bearing
system shall be the best solution. The
original Pot Bearing system has to be
replaced with High Damping Rubber Bearing
to provide an effective seismic isolation
system.

Environment Friendly Natural Rubber


The Malaysian Rubber Board (MRB) is
positioning the Malaysian rubber industry to
be the leader in technology and
environmental conservation.

Prototype testing - Shear


Test for 240 mm
displacement

81

Identifying alternative Materials And


Composites For Bridges
HDRB Contd

HDRB provide a simple and economical isolation system. It


possesses the low horizontal stiffness needed and are capable
of safely withstanding the large horizontal displacements
imposed during an earthquake. The bearing was design to
meet two set of action as per below:
o
o

SLS non-seismic actions conformance with BS5400


SLS non-seismic actions simultaneous with a 2500year return period seismic event conformance with
EN15129

82

Identifying alternative Materials And


Composites For Bridges
HDRB Contd
The design of the HDRB is by

Tun Abdul Razak Research


Centre (TARRC), a laboratory of
the Malaysian Rubber Board
(MRB). MRB works with the
Andre Rubber Company and W S
Atkins Consulting Engineers to
implement the concept of
laminated rubber bridge
bearings in earthquake
engineering in the 70s.

Prototype testing Compression test

83
83

Conclusion Remarks
Despite its implementation in a fast track manner, the
Penang Bridge Second Crossing is being constructed to the highest
quality, considering health, safety, cost, sustainability and
environmental conservation.
The Second Penang Bridge when completed will be the
longest bridge in Malaysia and South East Asia when it
opens for traffic in 2013.

84

Thank You
For Your Kind Attention

* JKSB acknowledges the assistance of CHEC & UEMB for the preparation of this
presentation.

You might also like