You are on page 1of 3

Birla Institute of Technology & Science, Pilani

Work Integrated Learning Programmes Division


M.S. Software Engineering at Wipro Technologies (WASE)
Second Semester 2013 - 2014 (March 2014 to September 2014)
Comprehensive Test (Regular)
Course Number

SEWP ZC132

Course Title

LINEAR ALGEBRA & OPTIMIZATION

Type of Exam

Open Book

Weightage

60 %

Duration

180 minutes

Date of Exam

Saturday, 20.09.2014

No. of Pages : 2
No. of Questions : 8

Session : FN

Note:
1. Please read and follow all the instructions given on the cover page of the answer script.
2. Start each answer from a fresh page. All parts of a question should be answered consecutively.
3. Please answer the questions in the order in which they appear in the question paper.

1. (a)

Let

u={ ( a , b , c ,d ) such that a+ c+ d=0, b+d=0 } be a subspace of

R4 . find the

the basis
of the subspace.
marks)
(b) Solve the following system of equations using Gauss Siedel method correct up to two

x+ y+ 54 z=10,27 x +6 y z=85 ,

2.

6 x+ 15 y +2 z=72

dimension and
(2

iterations:
(4 marks)

Reduce the following to row echelon form and find the Rank of the matrix

1 1 0 0
0
0
2 3
A=
4 0
2 1
3 1
0 4

(6 marks)

3.

A small business makes 3-speed and 10-speed bicycles at two different factories. Factory A produces 16 3-speed
and 20 10-speed bicycles in one day. Factory B produces 12 3-speed and 20 10-speed bicycles daily.It costs
$1000.00 per day to operate factory A and $800.00 per day to operate factory B. An order for 96 3-speed bicycles
and 140 10-speed bicycles has just arrived. Using Graphical method find how many days should each factory be
operated in order to fill this order at a minimum cost. What is the minimum cost of operation?
(8 marks)

4. (a)

Let

If

| A+ I |=0 where I denotes the 3X3 identity matrix then find the eigen value of A.

be a 3 x 3 matrix with real entries such that det ( A )=6 and the trace of A is 0.

(b) Does there exist a 3x3 symmetric matrix with eigen values
and corresponding eigen vectors

[ ] [] []
0
1
1

1
0
0

0
1
1

= -1

, 2=3, 3 =7

(3 marks)

. If so, find such a matrix; if not,

explain why not?


(5marks)
5.

For the following LP find three alternative optimal basic solutions, and then write a general expression for all the
non-basic alternative optima comprising these three basic solutions.
Maximize

z=x 1+ 2 x 2 +3 x 3

subject to

x 1+2 x 2+ 3 x 3 10
x 1+ x 2 5
x1 1
x1 , x2 , x3 0

(8

marks)

6.

Solve the following LPP for primal and dual values by generalized simplex iterative method.
Minimize

z=x1 +5 x 2

subject to

2 x 13 x 2 1
x 1+ x 2 3
x1 , x2 0

7.

Solve the following LPP.

(8 marks)

Minimize

Z =x1 + x 2 + x3

Subject to

x 13 x2 + 4 x 3=5
x 12 x 2 3
2 x 2x 3 4 , and

(8 marks)
8.

A factory can produce four products denoted by

each of two

x 1 , x 2 0 , x 3 is unrestricted.

P1 , P2 , P3 and

workshops. The processing times are given by following table

P1
WORKSHOP 1
WORKSHOP 2

3
6

P2
4
2

P3
8
5

P4
6
8

P4 . Each product must be processed in

The profit margin are 4,6,10 and 9 dollars per unit of

P1 , P2 , P3 and

P4 . 400 hours of labours are

available in each workshop. The LP model formulated for determining the optimal mix is as follows

Max z =4 x 1 +6 x 2+10 x 3 + 9 x 4

Sub. To the constraints ,

3 x1 + 4 x 2+ 8 x 3 + 6 x 4
x 1+2 x 2+ 5 x 3

400

400

x4

I I ntroducing slack variables

S 1 and S 2 respectively and using simplex method, we get the final table

as

Cj
B.V.
x2
S2

(a)

CB

XB

6
0

Assume that 20 units of

x2

x1

100
200

10

0.75
4.5

1
0

x3
2
1

0
S1

x4
1.5
5

0.25
-0.5

S2
0
1

P3 have been produced by mistake. What is the resulting decrease in profit?


(1

mark)

P1 vary without changing the optimal basis

(b)

In what range can the profit margin per unit of

(c)

In what range can the profit margin per unit of P2 vary without changing the optimal basis?

(d)

What is the marginal value of increasing the production capacity of Workshop 1?

(1 mark)
(2 marks)

(e)

Management is considering the production of a new product

P5 that would require 2 hours

in Workshop 1 and ten hours in Workshop 2. What is the minimum profit margin needed on
this new product to make it worth producing?

(2 marks)

(2 marks)

You might also like