Professional Documents
Culture Documents
Plant Kops II
The new pump storage plant
of Vorarlberger Illwerke AG
in Gaschurn-Partenen
The Vorarlberger Illwerke AG (Illwerke) operate in total nine Alpine Hydroelectric Power Plants in the most western part of Austria in Vorarlberg (Montafon and Walgau) . The first power plant, the Vermunt plant
started operation in 1930. In the course of different extension programs
a compound group of Hydroelectric Power Plants and water resources
was implemented until 1984.
The liberalization of the electricity market and the rapid development
of wind energy with wind-forces that cannot be influenced have led
to an increasing demand for peak and control energy as well as for the
possibility of a pump storage in large Alpine reservoirs. Illwerke responded to this demand by developing and constructing the highly efficient
pump storage Power Plant Kops II.
In March 2003 the supervisory boards of the Illwerke made the policy
decision to build Hydropower Plant Kops II into the existing Upper Ill
Lner Reservoir scheme ( = power plants in the Montafon) for the generation of highly efficient peak and control energy. Hydropower Plant
Kops II increases the capacity of Illwerke in pumping mode by 85% and
in turbine operation by 36%. No additional water resources are needed,
as Kops II uses the existing Kops Reservoir as upper reservoir and the
existing balancing reservoir Rifa as lower reservoir.
Geographical situation
April 2003
September 2003
March 2004
July 2004
August 2004
September 2004
Start of construction
End of 2007/
beginning 2008
June 2008
Construction time
3.5 years
Sum invested
the concept
Hydropower Plant Kops II has been designed as pump storage plant. The
power plant uses the head between Kops Reservoir (1,800m) and Partenen-Rifa (1,000 m). In turbine mode the water from Kops Reservoir
will flow through a pressure tunnel and a pressure shaft to the power
house. The hydroelectric generating sets, consisting of turbines, pumps
and generators are situated in an underground power house, the transformers are situated in the adjacent transformer cavern. The water used
in Hydropower Plant Kops II then flows through a tailrace tunnel into
the balancing reservoir Rifa, that serves as tailrace balancing reservoir
and as pump water reservoir.
The 220kV switching station for Hydropower Plant Kops II is designed
in space saving indoor SF6 technology and is located near the existing
switching yard of Rifa Plant. The energy is transported between Hydropower Plant Kops II and the switch yard Brs using the existing 220 kV
line from Partenen to Brs.
Gaschurn
Versalspitze
2,000 m
valve
Kops
Reservoir
1,809 m
cham
surge tank
ber
Rifa
Access to underground
power house
press
ure tu
nnel
press
u
shaft re
access tunnel
L 188
balancing reservoir
Rifa 1,005 m
Partenen
Characteristic data
n
450 MW
450 MW
Capacity of generators
600 MVA
Height of fall
approx. 800 m
the technology
The Hydropower Plant Kops II is a pump storage plant that can be used
to regulate the grid in turbine mode as well as in pump mode and is
located parallel to Hydropower Plant Kops I.
surge tank
pressure tunnel
System components
n Intake / outlet structures in Kops Reservoir
n
Pressure shaft
Tailwater system
- 3 compressed air surge chambers
- tailrace to Rifa balancing reservoir
- two chamber trailrace surge tank
- low pressure manifold pipes
gallery Tafamunt
pressure shaft
the technology
Headrace
Pressure tunnel Versal tunnel II
The pressure tunnel runs parallel to the existing pressure tunnel of Hydropower Plant Kops I and was excavated mechanically by a doubleshield tunnel boring machine. The favourable geological and hydrogeological conditions permitted a lining of the 5.5 km long pressure tunnel
with precast concrete elements. This type of lining is a construction method perfectly adapted to the high-alpine location of the construction
site.
n Length
5,552 m
Internal diameter
4.90 m
Longitudinal gradient
0.4 %
surge tank
pressure tunnel
race system, certain amounts of water can get out towards the surge
tank. The surge tank is sort of an equalizing reservoir reducing the pressure fluctuations and/or limiting the high dynamic pressures in the entire headwater.
The surge tank Aussertafamunt is located in the transition area from the
pressure tunnel to the pressure shaft and consists of a lower chamber
with two connections to the pressure tunnel, an inclined shaft with a
throttle in its lower end, as well as of an upper chamber and a ventilation shaft leading into the access tunnel Tafamunt.
Lower chamber
Inclined shaft
length 185 m
internal diameter 5.10 m
longitudinal gradient 49
Upper chamber
length 235 m
internal diameter 6.20 m
discharge shaft
Kops Reservoir
valve chamber
gallery
Oberwald
gallery
Tafamunt
pressure shaft
the technology
inclined shaft
length 1,135 m
internal diameter 3.80 m
longitudinal gradient 80.0 % (38.7)
n Flat track
length 60 m
internal diameter 3.80 m
surge tank
upper chamber
pressure tunnel
ventilation shaft
gallery
Tafamunt
surge tank
lower chamber
mucking shaft
pre-assembling
cavern
pressure shaft
machine cavern
tailrace surge
tank
distribution pipes
access tunnel underground power house
tailrace tunnel
outlet structure
access portal
The cavity has to withstand the high forces that act on it from any side.
Sophisticated static calculations and mathematical simulations of the
geological conditions had to be made. Regular measuring provided information about the real situation. The cavity rock face was supported
by numerous rock anchors and a shotcrete lining. After completion of
the cavity solid concrete foundations, walls and ceilings were built for
the installation of the heavy machines. The underground power house
is equipped with a combined crane (2 x 130 tons) necessary for the installation of the machines and, after the commissioning, for the maintenance works.
the technology
turbine
Transformer cavern
Volume of rock excavated approx. 9,800 cubic meters, length approx.
35 m, width approx. 16 m, height approx. 19 m. Three transformers
connected via isolated-phase bus ducts with the generators.
valve tunnel
pressure shaft
generator
clutch
pump
pump intake
Machine cavern
Volume of rock excavated: approx. 113,000 cubic meters. Width max.
approx. 30.5 m, height max. approx. 60.5 m, length approx. 88 m.
The total height of the vertically installed hydroelectric generating sets
consisting of a three-stage storage pump, an hydraulic clutch, a motor
generator and a six-nozzled Pelton turbine is approx. 38 m.
Characteristic data
n
Nominal speed
500 rev/min
3 x 150 MW
3 x 150 MW
220-kV energy transport via cables to the indoor 220-kV-SF6 switching station next to the switching yard of Rifa Plant. The energy is
transported between Hydropower Plant Kops II and the transformer
station Brs using the existing 220 kV line from Partenen to Brs.
tailrace
surge tank
machine cavern
transformer
cavern
pressure shaft
shaft bottom cavern
distribution pipes
valve tunnel
access tunnel
ILL
L188
mucking tunnel
tailrace tunnel
reservoir outlet
cable subway
the technology
Tailrace
Tailrace tunnel
Total length: 267 m
Maximum internal diameter in the area of the rock: 7 m; internal diameter in the area of the steel lined track of alluvions: 5.8 m. Common
turbine discharge and pump feed works with roller gate in the balancing reservoir Rifa.
reservoir outlet
tailrace
surge tank
underground power house
pump water
tunnel
culvert
Power control
in pumping mode
Hydraulischer Kurzschluss
z.B.:
Storage pumps can only be used if operated with 100% load. With a
surplus of power in the grid the adaptation to the fluctuations have to
be compensated by a controllable pump. In order to be able to assure a
power control also in pump mode, the principle of the hydraulic shortcircuit is used in Hydropower Plant Kops II. The difference between the
steady take of full load of the pump and the lesser surplus of power in the
grid is compensated by the simultaneous operation of the turbines to the
necessary extent. Since the turbine is assuring a good control ability in the
complete range, a good control ability will also be given in pump mode.
In Hydropower Plant Kops II the time for changing between turbine operation and pump mode will be short in accordance with the requests of
the grid.
Kops Reservoir
G/M
Q with 50 MW
Q with 100 MW
T
50 MW
Q with 150 MW
Q with 150 MW
P
150 MW
G/M
Geology
Environment
Never before, such high ecological demands had to be satisfied in Vorarlberg for a construction project, as with Hydropower Plant Kops II. It
was the first time an Environmental Impact Assessment (EIA) was initiated and could be closed positively. Such a procedure guarantees that
during the construction and the operation of Hydropower Plant Kops II
man or nature are spared to the highest possible degree.
More than 500 regulations assure that the construction will be made in
an environmentally friendly way and that also the later operation will
be technically safe and ecological.
In general, the geological conditions were favourable for the construction of the power plant, in several sections however, difficult geological
conditions were encountered, as anticipated.
The facilities of Hydropower Plant Kops II are located completely in the
rock series consisting of Silvretta crystalline. These series consist for the
most part in solid and hard rock as e.g. amphibolite, hornblende gneiss
and other types of gneiss. Other less solid mica-schists have also been
encountered.
Legende Legend
Hangschutt
talus material
Alluvium alluvium
Morne moraine
Schiefergneis
und
Migmatitgneis
schist
gneiss
and migmatite gneiss
mica-schist
Glimmerschiefer
and hornblende gneiss
Amphibolitamphibolite
und Hornblendegneis
granitegneiss and aplite gneiss
Granitgneis
und Aplitgneis
surge tank
Kops Reservoir
underground power
house
balancing reservoir
Rifa
pressure tunnel
l = 5.5 km
valve chamber
intake structure
pressure shaft
l = 1.1 km
Vorarlberger Illwerke AG
Vorarlberger Illwerke AG was founded in 1924 as a limited liability company (GmbH) and has been a joint stock company (AG) located in Bregenz since 1927. The primary shareholder of Illwerke is the Province of
Vorarlberg, holding 95.5% of the shares. 4.5 % of the shares are in the
possession of WEG-Wertpapiererwerbsgesellschaft m.b.H., Bregenz.
With nine power plants, four reservoirs and several pump storage reservoirs, the Illwerke hydroelectric scheme is the basis for generating electricity from alpine water resources in the Montafon and the Walgau.
Within the European grid that connects all power plants and consumers
concerned, Illwerke supplies peak energy to its consumers and contractual partners: Energie Baden-Wrttemberg AG (EnBW), the Province
of Vorarlberg/Vorarlberger Kraftwerke AG (VKW) and the Province of
Tyrol/TIWAG-Tiroler Wasserkraft AG, as well as the opportunity to take
advantage of pump storage and additional energy services.
Peak and control energy covers the peak demand periods that occur
briefly but often during any given day in order to maintain the balance between consumption and generation of electricity. During low demand periods in the grid, especially in case of a high supply of wind
energy, Illwerkes power plants take energy of the grid to operate the
pumps, a procedure known as pump storage. The water pumped into
high-altitude reservoirs is then available for periods of high demand for
peak and control energy. This practice of pump storage has proven to
be highly effective.
Illwerke provides its electricity customers with 1,248 MW turbine output
and a pump capacity of 533 MW. Following the commissioning of Hydropower Plant Kops II, this makes up 1,700 MW of turbine output and
980 MW of pump capacity.
Piz Buin
3.312 m
Brand glaciers
source of Ill
Vorarlberg
Tyrol
Silvretta Reservoir
Hydropower Plant
Obervermunt
Ischgl
Kops Reservoir
Galtr
Pumping Station
Kleinvermunt Hydropower
Plant Kops I
Paznaun
Hydropower
Plant Kops II
Vermunt
Reservoir
Hydropower
Plant Vermunt
Hydropower
Plant Rifa
Partenen
Montafon
Lnersee Reservoir
Hydropower
Plant Latschau
Hydropower
Plant Rodund I
Hydropower
Plant Lnersee
Hydropower
Plant Rodund II
Hydropower
Plant Walgau
Schruns
Bludenz
Walgau
group
ContaCt
Ulm
Stuttgart
Friedrichshafen
A7
Munich
A8
A96
Lindau
FRG
Bregenz
Altenrhein
Dornbirn
A1/A13
Zurich
A14
CH
Feldkirch
Bludenz
FL
S16
Innsbruck
Vienna
Schruns
L188
Partenen
group
Vorarlberger Illwerke Aktiengesellschaft
Weidachstrae 6, 6900 Bregenz, Austria
T +43/5574/601-0, F +43/5574/601-78526
www.illwerke.at
www.kopswerk2.at
info-kopswerk2@illwerke.at
Hydropower
Plant Kops II