Professional Documents
Culture Documents
Introduction
Project
Temporary endeavors undertaken to create a
unique product or service
Project Management
Application of knowledge, skills, tools and
techniques to project activities to meet project
requirements
Project Characteristics
Single unit
Many related activities
Difficult production planning and inventory control
General purpose equipment
High labor skills
Uncertainty
Low
Euro
project
Antarctic
expedition
Military
campaign
Channel
Tunnel
Airport
Product
development
Novel
writing
Individual
Low
Advertising
campaign
Wedding
Company
audit
Group
Organization
Thames
Barrier
Airbus
Chemical
plant
Motorway
Oil
tanker
Multiorganization
Complexity
Car plant
Nation
Multi-nation
High
Project life-cycle
Five stages involved:
Initiate
Plan
Execute
control and
close
Management of Projects
1. Planning - goal setting, defining the
project, team organization
2. Scheduling - relates people, money, and
supplies to specific activities and activities
to each other
3. Controlling - monitors resources, costs,
quality, and budgets; revises plans and
shifts resources to meet time and cost
demands
Objectives
Scheduling
Resources
Project activities
Work break-down
structure
Organization
Controlling
Network
Understanding
the project
environment
Stage 2
Project definition
Changes
Stage 3
Project planning
Corrective action
Stage 5
Stage 4
Technical execution
Project control
Project A
Project B
Department
1
Department
2
Department
3
Matrix Organization
Marketing
Project 1
Project 2
Project 3
Project 4
Operations
Engineering
Finance
New aircraft
project
Music festival
Fixed grant
research project
Cost
Time
Adjust as necessary
Identify
the
activities
in the
project
Estimate
times and
resources
for the
activities
Identify the
relationships
and
dependencies
between the
activities
Identify time
and resource
schedule
constraints
Fix the
schedule for
time and
resources
Training
Form and
train user
group
Specify
sales
training
Installation
Install
systems
Design initial
screen
interface
Testing
Test
interface in
pilot area
Modify
interface
Figure 3.1
Before
project
Start of project
Timeline
During
project
Time/cost
estimates
Project Planning,
Scheduling,
and
Budgets
Controlling
Engineering diagrams
Cash flow charts
Material availability details
Budgets
Delayed activities report
Slack activities report
CPM/PERT
Gantt charts
Milestone charts
Cash flow schedules
Figure 3.1
Before
project
Hall
Start of project
Timeline
During
project
2.
3.
4.
The people assigned to the project receive motivation, direction, and information
Project managers should be:
Good coaches
Good communicators
Ethical Issues
Project managers face many ethical decisions
on a daily basis
The Project Management Institute has
established an ethical code to deal with
problems such as:
1.
2.
3.
4.
Project Scheduling
Identifying precedence
relationships
Sequencing activities
Determining activity times &
costs
Estimating material & worker
requirements
Determining critical activities
Scheduling Techniques
1. Ensure that all activities are planned for
2. Their order of performance is accounted
for
3. The activity time estimates are recorded
4. The overall project time is developed
Gantt chart
Project to design an information interface for a new sales knowledge
management system in an insurance company
Activity
b Install systems
c Specify sales training
d
10
20
30
Time
(days)
40
50
60
3.
4.
5.
6.
2.
3.
4.
5.
6.
Is the money spent equal to, less than, or greater than the budget?
7.
8.
Latest
Start
Figure 3.10
ES
EF
LS
LF
2
Earliest
Finish
Latest
Finish
Activity Duration
Activity duration
1
1
Event number
An event
f
1
6
d
4
2
Activity on arrow
Using dummy activities to describe a relationship
that could not be expressed any other way
1
Forward Pass
Begin at starting event
and work forward
Earliest Finish Time Rule:
The earliest finish time
(EF) of an activity is the
sum of its earliest start
time (ES) and its activity
time
EF = ES + Activity time
Backward Pass
Begin with the last event
and work backwards
Latest Finish Time Rule:
If an activity is an immediate
predecessor for just a single activity, its
LF equals the LS of the activity that
immediately follows it
If an activity is an immediate
predecessor to more than one activity,
its LF is the minimum of all LS values
of all activities that immediately follow
it
LF = Min {LS of all immediate following activities}
Slack = LS ES
or
Slack = LF EF
18 31
A
0
0
B
10
H
7
8
E
10
10 10
L
8
27 27
I
4
F
9
C
1
G
3
19 19
3J
22 22
M
4
35 35
Probability
3
Optimistic time
Activity duration
13
Expected time
Most likely time
Pessimistic time
Probability
Expected time:
Figure 3.12
t = (a + 4m + b)/6
Probability
of
Variance
of
times:
1 in 100 of
Probability of
< a occurring
in 100 of > b
v = [(b a)/6]2 1occurring
Activity
Time
Optimistic
Time (a)
2011 Pearson
Most Likely
Time (m)
Pessimistic Time
(b)
= (variances of activities
on critical path)
Compute the crash cost per time period. If crash costs are linear over time:
Crash cost
per period
2.
3.
Using current activity times, find the critical path and identify the critical activities
If there is only one critical path, then select the activity on this critical path that
(a) can still be crashed, and
(b) has the smallest crash cost per period.
If there is more than one critical path, then select one activity from each critical
path such that
(a) each selected activity can still be crashed, and
(b) the total crash cost of all selected activities is the smallest.
Note that the same activity may be common to more than one critical path.
4.
Update all activity times. If the desired due date has been reached, stop. If not, return to
Step 2.
Advantages of PERT/CPM
1. Especially useful when scheduling and controlling large projects
2. Straightforward concept and not mathematically complex
3. Graphical networks help highlight relationships among project
activities
4. Critical path and slack time analyses help pinpoint activities that
need to be closely watched
5. Project documentation and graphics point out who is
responsible for various activities
6. Applicable to a wide variety of projects
7. Useful in monitoring not only schedules but costs as well
Limitations of PERT/CPM
1. Project activities have to be clearly defined,
independent, and stable in their relationships
2. Precedence relationships must be specified and
networked together
3. Time estimates tend to be subjective and are
subject to fudging by managers
4. There is an inherent danger of too much
emphasis being placed on the longest, or critical,
path
Actual expenditure
CV
ACWP
Actual
expenditure
SV
Schedule variance
CV:
Cost variance
Project
planning
Multi-project analysis
Complex resource
scheduling
Real-time reporting
Project portal
Web-based collaboration
Document management
E-mail notification
Integration
Resource levelling
Resource availability
Skills scheduling
Communi
-cation
Budgeting
Cost management
Earned value control
2011 Pearson
Education, Inc.
publishing as Prentice
Hall
Primavera
MacProject
Pertmaster
VisiSchedule
Time Line
Microsoft Project