Rev: 00
Date: 29.09.16
Method Statement
1180 MW CCPP, Bhikhi
External Wall Treatment
Re
v
R0
Date
29.09.16
Prepared by:
Checked by:
Approved by:
Description
External Wall
Treatment
Doc. No
BK-HH-QAC-MS-0076
Moaz-ur-Rehman
(Dy. General Manager, HRL)
Chen Dong Hai
(Site In-charge, HEI)
Sajjad Haider
(RE Civil, NESPAK)
Status
For
Approval
Remarks
METHOD STATEMENT
External Wall Treatment
Rev.: 00
Date: 29.09.16
Table of Contents
1.
2.
3.
Material
4.
Equipment / Tools
5.
Methodology
6.
7.
1. Scope:
METHOD STATEMENT
External Wall Treatment
Rev.: 00
Date: 29.09.16
Schedule of Finishing
3. Material:
Sr #
Description
4. Equipment / Tools:
Sr #
Description
Drilling Machine
Hand Saw
Ladder
Hammer
Trowel
5. Methodology
i. Brick Surface will be cleaned with steel wire brush.
ii. Neat Layer of Cement Paste will be applied on the wall to make the surface
even.
METHOD STATEMENT
External Wall Treatment
Rev.: 00
Date: 29.09.16
6. Control Measures:
Experienced supervisory staff will be employed for carrying out the work.
METHOD STATEMENT
External Wall Treatment
Rev.: 00
Date: 29.09.16
Personal protective equipment: All operatives will wear the PPEs: safety wellington
boots whilst working, safety helmet, high visibility vest and gloves.
Site rules: All operatives will be informed (via a site induction / toolbox talk) of and
expected to comply with the site rules.
Access to the work area: The provision of a safe means of access to the work area is
the responsibility of the contractor / client.
Falls into excavation: The groundworks sub-contractor must provide and maintain
fencing to prevent operatives from falling into the excavation where required.
Welfare facilities: The contractor / client must provide access to the welfare facilities.
Working platforms with hand rails and cat walk ladders will be fixed to access and
work at higher levels.
Safety belts will be provided for all employees who work at higher level plat forms.