Professional Documents
Culture Documents
TAB
journal
Steve Young
........................
10
Don Butler
We are also pleased to feature Dr. James Rock and Dr. Swiki Anderson in a
far-ranging discussion regarding digital vs. analog controls. Also in this
issue are two articles on Indoor Air Quality, by William Beckwith and
Michael Price.
Gary Miller provides us with an analysis of the pros and cons of series fan
powered boxes. Finally, Joseph Flood provides the reader with a new and
innovative approach to validating cooling coil performance. This article
should be of particular importance to all test and balance professionals.
We hope you enjoy this issue of TAB Journal. Your comments are always
welcome!
B U I L D I N G P R E S S U R I Z AT I O N
Introduction
Test Procedure
This facility is a large steel frame
structure encased in precast concrete
wall panels. There are many access
and intentional openings in the building envelope. We employed the
depressurization method using the
buildings own air handling systems to
determine the air tightness of the
building envelope. This method actually allows the test engineer to look
Principal
The buildings exhaust air system is
the primary environmental assurance
system, as it draws all the buildings
air through an odor scrubber and
exhausts clean air into the atmosphere.
Air flows into the building through
loading doors, intentional openings for
motorized dampers, and the HVAC air
systems.
During testing performed while the
processing equipment was in operation, the odor scrubbers were set to
deliver full design constant-volume
airflows at a velocity required to
remove all odors (each scrubber can
move 50,000 CFM [23,600 l/s]).
Overhead loading doors were closed,
and the intentional openings at inlet
dampers were operated to maintain a
constant building pressure of 25 pa.
To determine the tightness of the
building envelope, all HVAC equipment was shut down. All overhead
loading doors were closed, and inlet
dampers were set to maintain a test
pressure of 50 pa. Smoke was then
generated and introduced to all building joints, connections, and uninten-
TAB Journal
trol office. Due to possible wind tunnel effects, all exterior exposures were
fitted with exterior pressure taps connected to a cylindrical pressure-averaging container, then to the pressuremeasuring instrument.
The operating engineers office is
manned 24 hours a day, and any variations in space negative conditions can
be monitored and adjusted to maintain
a constant negative pressure inside the
building regardless of outdoor conditions.
Test Results
The test results indicated that some
openings, such as overhead doors,
equipment exhaust pipes, and maintenance access doors, could not be
sealed to a 100% leak-free condition.
To overcome this problem during normal operation, the air inlet dampers
had to be controlled by a space pres-
Sketch #1
BOILER STACK
WELD TO STACK
ROLLER SEAL
ROOF
Sealing Major
Leaks in the
Building Envelope
(See Sketches 1 7)
Sketch #2
Sketch #3
PARAPET FLASHING
PRE-CAST PANEL
HINGED DOOR
GASKET
REQUIRE SEAL
ROOF
Access Hatch
Conclusion
Following our findings and recommendations, all major leaks found in
Sketch #5
Sketch #4
SEAL OPENING
SCREEN
1" CONDUIT
SILENCER
SEAL WITH
SILICONE
MOTORIZED
DAMPER
LIGHT
SEAL AROUND
MOTORIZED
INLET DAMPER
ROD
Inlet Louvers
Sketch #6
EXTERIOR WALL
Sketch #7
INLET LOUVER
EXTERIOR WALL
SEAL
OVERHEAD DOOR
SCREEN
DUCT
NEOPRENE DOOR
SWEEP SEAL
MOTORIZED
SMOKE DAMPER
SEAL
Overhead Doors
EXTERIOR WALL
TAB Journal
B U I L D I N G P R E S S U R I Z AT I O N
TAB Journal
-Steve Young
lator at 3500 CFM to cool the equipment room. With the fan on the roof, a
30 x 30 intake is located about five
feet off of the floor to cross-ventilate
the room. In addition to this ventilation, two additional propeller exhaust
fans had been added to help cool the
penthouse.
To further help the cooling, a piece of
plywood had been placed over the 30
x 30 intake. With the outside air
source for make-up cut off, all the
exhaust air was being pulled up
through the top of the elevator shafts,
through the cable and electrical penetrations. We measured 8.42 square feet
of openings with an average velocity
of 855 feet per minute. The elevator
penthouse was being cooled by the
exhausted, conditioned air out of the
hospital.
Restoring Neutral
Pressure
As noted in the beginning of the article, a building under a negative pressure will induce air through every
crack and crevice to satisfy the pressure. In this case, the central elevator
shafts acted like a large plenum,
depressurizing each level equally. The
upper levels, however, are well sealed,
TAB Journal
out, however, the cost of our investigation had a payback which was easy to
calculate.
Not only did we thwart possible IAQ
complaints, lawsuits, etc. which cannot have an estimated dollar amount,
we saved energy.
We measured approximately 7200
CFM of condition air being needlessly
exhausted out of the hospital complex.
It costs approximately $1.50 per CFM
to heat, cool, and dehumidify outside
air in a hospital. Since the facility
operates 24 hours per day, 365 days
Real Savings
This experience shows one example of
how a depressurized building causes
problems that can be far reaching.
Fortunately, there were no formal
complaints or sick employees. The
problem was identified in a one-day
investigation, but it took us over a
week to track down and locate the
source of the problem. As it turned
TAB Journal
LIFE SAFETY
Benefits Of Testing
As in the test and balance of an HVAC
system, the life safety system needs to
be checked by a qualified independent
firm. As has often been said of the
10
testing and balancing of HVAC systems, life safety checks are also the
cheapest insurance policy owners can
have for their systems (of course, an
insurance company may offer a better
rate to the owner if it knows that the
life safety system has been confirmed
as operable). Local fire departments
are also pleased when systems are
checked, and they tend to be more
cooperative when they feel that the
building owner cares about accident
prevention and safety.
Testing Methods
Initial
TAB Journal
On-Site Testing
Verify that the systems are completely installed. If the system you are
testing is in a stair tower, walk the
tower from top to bottom. Look for
the obvious missing door sweeps, gaping holes due to pipe penetrations, or
debris or material stored in the tower
or behind an emergency door. Visually
inspect the fan; again, look for the
obvious, such as a cracked fan belt,
improper duct connections, torn flex,
or signs of leakage (such as dirt lines
coming from the joints). Remember,
you have not started the system yet.
You are only looking for obvious
problems.
Next, call the local fire department to inform them of your test and
TAB Journal
Smoke Evacuation
The smoke evacuation system can
consist of several types of design,
including a separate exhaust system
dedicated solely to the removal of
smoke in case of an emergency and an
air handling system that, when activated in emergency mode, will go to full
relief, drawing from the return system.
The latter is the most difficult to test.
11
Smoke Tests
First, evaluate the area to be tested for
the amount of smoke to be generated.
If we are simply igniting a smoke candle in a hall or room, we set the candle
in a metal bucket, which is then set in
a larger bucket filled with water to
help absorb the heat. It is a good idea
to keep a bucket of water nearby to
douse the candle if the amount of
smoke is too great or if the smoke is
still being generated after the test is
completed. Also confirm that your
candles are non-toxic and will not
damage the area.
I recommend having a video camera
and stop watch. Whether the time limit
is 30 seconds, 1 minute, or 3 minutes
(which most fire departments consider
the maximum), you need to be accurate for the actual test. If time documentation is critical, I may hold a
newspaper up in front of the camera to
verify the date or ask a representative
from outside of my firm to verify the
correct date on film. Some may consider this overkill, but documentation
in this type of testing is critical.
When an existing building is being
smoke tested, careful consideration
must be given to the owner and tenants. If notification has not already
been given, try to avoid this test. A
panic could result if people see or
smell the smoke and are unaware of
the test. (An interesting example of this
is the first test that our organization
ever conducted. It was in a new tunnel
on the Pennsylvania Turnpike. Smoke
removal was to be confirmed prior to
opening, and the testing was being
performed the morning of the opening
ceremonies. We were able to record
the smoke removal with and without
the fans running. Everything went
12
Airflow Tests
First, remember that damper operation,
control sequence of operation, etc.,
must still be considered.
Airflows can be confirmed under
proper mode by either traverse or terminal readings; testing at both is recommended. A traverse will confirm
the capacity, but the bottom line here
is whether or not the space is removing the air. This is where duct leakage
plays a major part in whether a system
passes or fails the test.
Keep in mind that the return may have
throttled terminals due to a prior balance. This should not be a problem if
the total CFM required is equal to the
return requirements. If there is a difference, however, the customer may
require some readjustment to the system so that both will be satisfied.
Documentation
Times, dates, system conditions, operating modes, and the names of any
witnesses should be carefully documented. When selling this type of
work, stress that your recommendations to owners will carry more weight
than recommendations from their own
maintenance personnel, whose recommendations may simply go on a to
do list and be completed as part of
the overall maintenance plan.
Most importantly, stress that the testing is accurate for the day of the test,
but that you are not giving a guarantee
TAB Journal
IN BALANCE
and
TAB Journal: Today well be discussing laboratory ventilation equipment, and our emphasis will be on the
design and maintenance of VAV flow
controllers for hoods equipped with
sash position sensors. There are two
groups of manufacturers: those who
advocate using analog control loops
and those who sell only digital controllers. First, lets define the terms
analog and digital.
TAB Journal
TAB: You make it sound like the digital system is more complex than the
analog system.
13
14
Measured Flow
Exhaust
Flow
Sensor
Flow
Error
Predict
Flow
Set-point
Move
Actuators
Fan Speed
& Damper
Sash
Position
Sensor
Figure 1. This sketch shows the different kinds of controllers working together to control hood
flow. The Sash Position Sensor feeds a model-predictive controller to create the exhaust flow setpoint. The Exhaust Flow is subtracted from the Set-Point Flow to create the closed-loop controller
error. The error feeds forward to move damper position and change motor speed to maintain setpoint flow. When exhaust flow is too large, the damper is closed and the fan is slowed; when
exhaust is too small, the dampers are opened and the fan is accelerated.
Rock: The simple fact is that all components of any ventilation control system can be either analog or digital.
Take a look at my sketch (Figure 1).
The sash position sensor creates the
set-point for exhaust flow. If the flow
is too low, the controller sends a signal
that moves the actuator to increase the
exhaust flow. If the flow is too high,
the controller sends a signal to reduce
the exhaust flow. When the flow is set
properly, no actuator motion is commanded.
The nice thing about this concept is
that the controller doesnt need to
know anything about how far to move
the actuator; it only needs to know
which way to move it. Ultimately,
cost and performance must determine
which type of system must be used.
TAB Journal
Table #1
Differences
Analog
Digital
Continuous control
Intermittent control
Hierarchy of nested
control loops
Sequential servicing of
control loops
Diagnose with
multimeter
Repair by simple
module replacement
Technology stable;
long life expectancy
Technology rapidly
evolving
Table 1
TAB Journal
15
16
DC
TAB Journal
Introduction
TAB Journal
Cost Factors
There are two operating cost factors
involved with reheat. First is the obvious electrical power consumption by
the electric heat strips, or fuel consumption for a hot water system. Less
obvious is the additional power consumption required by the air conditioner to remove the reheat heat load.
Besides increased annual operating
costs, capital costs are higher.
Overcooling the moist air and handling the supplemental heat load
requires an air conditioner two to five
times larger than a unit that does not
overcool and actively reheat.
17
References
SCADR
Coil
DX Coil
SubCool
Reheat
Circuit
Desuperheat
Reheat
CLosed Loop
Fan
air
control valve
suction
line
control valve
Heat
Exchanger
hot gas
Heat
Exchanger
Compressor
to compressor
liquid line
Condenser
Figure 1
18
TAB Journal
TAB Journal
19
SYSTEM COMMISSIONING
Introduction
20
TAB Journal
It would be useful if
we had an acceptable
method to relate tests
executed at field
found conditions
to the design stipulated
conditions similar
to the cooling tower
performance procedure
developed by
George Young.
-Joseph Flood
TAB Journal
Have an
opinion?
An interesting
case study?
A new method?
Tell us about it.
TAB Journal welcomes
submissions for publication. TAB Journal is
published quarterly by
the Associated Air
Balance Council. Send
letters or articles to:
Editor
TAB Journal
1518 K Street, NW
Suite 503
Washington, DC
20005
21
The entering and leaving surface temperatures are dependent upon the coil
face velocity and the velocity of the
water in the tubes. As the air face
velocity increases, the coil surface
temperature approaches the air temperature; likewise, as the water tube
velocity increases, the surface temperature approaches the water temperature.
22
TAB Journal
ENTHALPY
EWT
LWT
EADB
EAWB
LAWB
EADP
LAST
EAST
42.0
58.7
80.0
68.5
55.5
62.7
46.6
61.7
16.17
25.58
BTUH = 540396.9
AIR ENT
32.84 AIR LV
23.52 LG DIFF
SM DIFF
18.42 LOG DL/DS
27.55
LMTD =
3.83
3.94
3.94
3.83
0.012297
Surface
Constant
143784.5
3.758380
CFM
12885
Coil is all WETTED
FIELD TEST RESULTS
ENTHALPY
EWT
LWT
EADB
EAWB
LAWB
EADP
LAST
EAST
43.8
53.5
77.0
61.8
53.0
54.9
46.5
55.9
17.05
22.3
BTUH = 323912.9
AIR ENT
27.69 AIR LV
22.02 LG DIFF
SM DIFF
18.42 LOG DL/DS
23.71
LMTD =
Surface
Constant
123403.3
2.84
2.59
2.84
2.59
0.040018
2.624831
CFM
12695
Coil is all WETTED
Coil Performance Index = 0.86
Coil Performance Index = 0.848534
Corrected for CFM
DESIGN
TEST
42.0 EWT
58.7 LWT
80.0 EADB
68.5 EAWB
55.5 LAWB
43.8
53.5
77.0
61.8
53.0
TAB Journal
23
S E R I E S FA N P O W E R E D B O X E S
24
-Gary L. Miller
TAB Journal
TAB Journal
I am convinced
that the best volume
control on Series FPBs
is a three-speed
switch and a
discharge damper.
Conclusion
At some point, the gap between recommended operating conditions from
manufacturers, design engineers, and
actual field operating conditions must
be closed. If Series FPBs are to be
used on projects, at least allow them to
operate at the most energy efficient,
low maintenance, and most reliable
method possible: using a three-speed
switch with a discharge damper.
-Gary L. Miller
25
ndoor air quality (IAQ) investigators are frequently called into buildings to conduct investigations as a
result of complaints from occupants
with symptoms such as eye and nose
irritation, fatigue, headaches, sore
throats, and general respiratory problems. The client generally assumes
that these symptoms are due to one
indoor airborne pollutant that is present within the building.
However, identical symptoms may be
found in individuals exposed to
formaldehyde, carbon monoxide, and
ozone. In addition, similar symptoms
are reported by individuals with allergies to specific fungi such as
Aspergillus and Cladosporium.
Symptoms can also be caused by
exposure to household dusts, cotton
fibers, and fibrous glass fragments.
An ever-increasing and similar problem is encountered due to low relative
humidities. Figure 1 depicts the overlapping symptomology of indoor airborne pollutants.
Since the cause of an IAQ-related
symptom can vary, it is generally not
productive to search for a single pollutant as the culprit of IAQ problems.
We advocate a solutions-based
approach to IAQ investigations that
examines all major sources within a
building, along with a thorough evaluation of the ventilation system to
ensure it is clean, balanced, and operating properly. We are convinced that
26
Ventilation System
Inspection
Because IAQ is, in part, a function of
outdoor air quality, examination of the
ventilation system usually starts with a
check of the outside air intake. In this
case, the outside air intake was found
to be inadequate for the number of
occupants in the space. Airflow measurements and calculation of ventilation rates based on occupancy found
the outside air ventilation rate to be
less than 5 cubic feet per minute
(CFM), per person. The outside air
intake was also positioned directly
above the loading dock area.
A detailed inspection was made of the
buildings air distribution system,
including the internal components and
chambers of the air handling units, the
air supply ductwork, and return air
systems. Where necessary, access was
gained to the ductwork by the installation of a small access port for viewing
with a video inspection system. The
air handling units were found to be
contaminated with dust, debris, and
visible biological contamination on the
internal insulation and within the condensate drain pans. The ductwork was
contaminated with a general buildup
of dust and debris to a point were
staining was evident around the diffusers from contamination.
TAB Journal