You are on page 1of 25

Review Test Submission: Quiz 2 Brainstorming

Question 1
What sort of people would help at a brainstorming
session? (HINT: 4 answers are correct)
Correct
Answers:

People with an interest in the outcome of the


brainstorm
Any number of people but divided into
groups of 6 and 10
People with skill in the area but from diverse
backgrounds
Someone famous from from outside the
company (eg. a motivatoinal speaker or a
celebrity chef)

Question 2
A Brainstorming session should have two phases
(select one correct answer):
Correct Answer:

Create ideas and then analyse the


ideas

Question 3
Select all the things below that will kill creativity in a
brainstorm (HINT: more than one answer is correct)
Correct
Answers:

Have no clear objectives for the brainstorm


session
Discuss the fesibility, costs and risks
immediately an idea is generated
Aim for quality of ideas rather than quantity
of ideas
Ideas are not evaluated and there is no
action taken on the good ideas after the
brainstorm

Question 4
Dreamer Realist Critic - put the activities in the

correct order for a brainstorm session


Correct Answer
1. Form an external view of the challenge
2. Use divergent thinking to conceive ideas
3. uUse convergent thinking to review ideas
4. Identify weaknesses, obstacles or risks

Review Test Submission: Quiz 3 Concept Development


Question 1

Design Thinking Stages - match the labels to


the diagram below:

Correct Answer

1. Empathy
2. Define
3. Ideate
4. Prototype

5. Test

Question 2
Divergent thinking ...(select each correct
answer):
Correct
Answers:

produces new ideas by exploring


many possible solutions
creates multiple answers to a set
problem
is used to explore the solution space

Question 3
Prior to the moment of insight (select
each correct answer):
Correct
a person may go through
Answers:
Incubation and Intimation
the right side and the visual
cortex of the brain is used
you may get the feeling you
are on the right track

Question 4

Put the following stages of problem


solving in the correct order

Correct Answer
1. Define
2. Generate
3. Decide
4. Implement
5. Evaluate
Wednesday, 28 October 2015 4:19:09 PM EST

Review Test Submission: Quiz 4 Requirements


Question 1

A Stakeholder Requirement ... (select all that are


true)
must state something that can be verified by
inspection, analysis, test, or demonstration.
is a statement of something someone needs
must be technically feasible.
expresses a single thought in a way that
cannot be misunderstood
is used to validate that a completed design
meets the stakeholder needs
states what is needed but is missing detail on
how to provide it
should be rated and ranked (highest to
lowest) based on value to the stakeholder
Question 2
For the following diagram "Developing the Stakeholder
Requirements Specification" select the best answer for the
missing labels shown with (......) and numbered in red.

Correct Answer

1. Needs
2. Problem / Benefit
3. Requirements
4. Specification

Question 3
True or False - With a formal change
management process, stakeholder
requirements can be added, changed or
removed any time up to the start of the
testing phase.
Correct Answer:

True

Question 4
Which of the following indicate poor quality
Stakeholder Requirements (select all that are
true)
Correct
The design team spends time arguing
Answers: about the meaning of a requirement.

Requirements are abstract and are not


verifiable
Requirements are ambiguous
The development team has frequent

meetings with the the stakeholders to


rewrite the requirements.
The development team is free to

interpret the unwritten assumptions


about the requirements.

Review Test Submission: Quiz 5 - High


Level Design
Question 1
High Level Design ... (select all that are true)

Correct
Answers:

Develops the solution concept


Considers the system functions needed to meet
the requirements
Identifies the core problem to be solved by the
system
Uses block diagrams or similar tools to
determine the functions delivered by system
components
Can optimise the design by early consideration
of design tradeoffs

Question 2
Put the following High Level Design Steps in the
correct order
Correct Answer
1. Analyse Requirements List for specific needs
(functions, constraints, value statements)
2. From the specific needs extract the core Problems to
be Solved or "Capability Gaps"
3. Describe the Problems or Gaps in their General Form
4. Divergent search for generic functional solutions to
the problem/gap
5. Rate generic functional solutions against the specific
needs
6. Select functional solution with best fit

7. Establish high level function-structures (Block


Diagram)
8. Divergent search for appropriate physical solutions
(working principals)
9. Evaluate physical design variations
10. Verify high level design meets requirements
11. Document the high-level design

Question 3
In the Weighted Criteria Matrix diagram below fill in the values
shown (A.AA, BB%, C.CC, D):

Question

Correct Match
II.

Weighted Score A.AA

0.45
Weight BB%

IV.

20%

I.

Total score C.CC

3.10
Ranking D

III.

Question 4

For Stage-Gate process, match the following stage names


with their description:

Question

Correct Match

Discovery

B.
Pre-work designed to uncover opportunities
and generate New Product ideas

Scoping

A.
A quick, preliminary investigation and scoping
of the project largely desk research

Build the Business


Case

D.
A much more detailed investigation involving
primary research both market and technical
leading to a business case, including product
and project definition, project justification, and
a project plan

Development

C.
The actual detailed design and development of
the new product, and the design of the
operations or production process

Testing and
Validation

F.
Tests or trials in the marketplace, lab, and
plant to verify and validate the proposed new
product, and its marketing and
production/operations

Launch/commerciali
sation

E.
Beginning of full operations or production,
marketing, and selling

Review Test Submission: Quiz 6 - DFMA


and Ind Design
Question 1
Design for Assembly (DFA)... (select all correct answers)
Correct Answers:

Reduces the cost by reducing


the number of parts in a
product

Is used at the early design stages to compare different


assembly techniques

Can result in a reduction in


specialised tooling used in
assembly

Question 2
Design for Manufacture (DFM)... (select all correct
answers)

Correct
Answers:

Can reduce the cost of production by reducing the


number of production tools, moulds, dies or jigs
Is used at the early design stages to evaluate
tooling and fabrication strategies
Includes techniques to assess and improve the
quality of production

Question 3
Industrial Designers ... (select all correct answers)
Correct
Answers:

Can collect and analyse user needs


Are part of the concept development team
Understand the properties of materials and
design for manufacturing
Consider ergonomics early in the design
Can be used to evaluate the effect of product
design decisions on end users

Question 4
Design Reviews ... (select all correct answers)
Correct
Answers:

Assess the maturity of the


design/development effort

Clarifying design requirements


Check proposed design against technical
requirements
Check requirements against the ConOps
Check proposed design configuration could
meet the targets for DFM, DFA and DFx
Evaluate if the design can schedule and
cost targets at different lifecycle stages
Check proposed design against customer
needs
Help ensure robust, efficient or safe design

Review Test Submission: Quiz 7 - Robust


Design
Question 1

Hazard versus Risk. (select all correct answers) 0.25


points

Correct
Answers:

A hazard is any source of potential harm


A hazard should be further assessed only if it
can (somehow) create an impact
A risk is the chance of something happening
that will have an impact on objectives
Risks should include the chance of not
achieving the expected performance of a
design
The likelihood of delays and cost overruns are
risks to a development project
Uncertainty about development scope, cost or
time increases the overall project risk

Question 2
Likelihood versus Consequences versus Risk.
(select all correct answers) 0.25 points

Correct
Answers:

Likelihood is the expected occurrence of an


incident
Consequence can be measured as the amount
of money you expect to lose per incident
Risk can be measured as expected dollar loss
per annum

Risk can be measured as expected injuries or


deaths per annum

Question 3

Which of the following statements true according to the


Enhanced Risk Matrix shown below.... (select all
correct answers)
Red =

Unacceptable without risk reduction


Amber = Senior Mgr Approval required
Yellow = Local Mgr Approval required
Green = Acceptable with periodic review

Correct
A production equipment failure with a severity of
Answers: Critical and Likelihood of Occasional has a Risk Level of
6
An accident that is likely to occur and has catastrophic
consequences has a Risk Level of 2
The annual loss expectancy from an accident with
Occasional / Critical can be lowered by reducing the

impact when the incident occurs


The consequences of an incident can be reduced by
effective controls that detect the incident, contain
damage and/or assit the business to recover
An Enhanced Risk Matrix should be developed by
stakeholders and formally agreed by senior
management
An Enhanced Risk Matrix can be used to communicate
the risk tolerance levels
An Enhanced Risk Matrix can be used to determine risks
that cannot be accepted without further treatment that
reduces likelihood, reduces consequences or reduces
both.
The risk matrix can be used to determine risk priority
(relative importance)

Review Test Submission: Quiz 8 - Safety


Engineering
Question 1
Pair up definitions with the terms listed below
Question

Correct Match

An accident
is

C.
An undesired and unplanned event that results in
a specified level of loss.

Reliability is

E.
Freedom from failures.

An error is

F.
A flaw or deviation from a desired or intended
state

Safety is

G.
Freedom from accident or loss.

A failure is

A.
Non-performance or inability of the system or
component to perform its intended function.

A hazard is

B.
A state or set of conditions of a system that
together with other conditions in the environment
will lead inevitably to an accident.

A near miss
(incident)

D.
An event that involves no loss but with the
potential for loss in other circumstances

Question 2

ALARP ... (select all correct answers)


Correct
Answers:

Means the residual risks to health and safety of


people are reduced to a level that is as low as
reasonably practicable
Is achieved when there are no other practical
measures that could reasonably be taken to further
reduce risks to life or limb
Can be used as a criteria when making a choice
between differing design concepts

Means much the same thing as So Far As Reasonably


Practicable (SFARP)
Question 3

A Safety Case ... (select all correct answers)


Correct
Answers:

Is a snapshot of the Safety Management System at


a point in time
States the known hazards and risks
Defines the tolerable level of risk
States the controls that are in place and how they
reduce the risk
Justifies the controls are sufficient to mitigate risk to
a tolerable level

Would be required to operate a Major Hazard Facility


Would be required to permit operation of the
Prelude Floating Liquefied Natural Gas (FLNG)
Facility

Question 4
Bow-Tie diagrams display of the relationship between Hazards

and Outcomes and are used to document the cause and consequence
analysis in a Safety Management System. For the Bow Tie Diagram below,
find the label that best matches the blanks marked A, B, C, D, E, F, G, H.

Question 1
Question

Correct Match

A newly developed product is likely to be more profitable for


[..A..]
longer inC.
the market if the product ... (select all correct answers)
Fault Tree Analysis

Correct

[..B..]
Answers:B.

Provides excellent value for the money spent.


Event Tree Analysis

[..C..]

[..D..]

Meets customers needs more fully than competing


products.
Unwanted Incident

A.
F.

Hazards
[..E..]

E.
Causes

Has highly visible useful benefits compared to the


competition.
Offers entirely new benefits that existing products do not.

[..F..]

Eliminates an important negative in existing market


products.
Proactive Controls

[..G..]

H.
Offers a higher-quality product at a higher price.
Reactive Controls

[..H..]

D.

G.
Outcomes

Review Test Submission: Quiz 9 New Product Development

For the assessment of an Innovation Portfolio risk, match the


consideration to the category

Qu
est
ion
2

Question
Product risk

Correct Match
B.
Our manufacturing and service delivery system

Revenue Risk

D.
Return on investment

Technology Risk

A.
Our Technology Competency

Intended Market
Risk

C.
The competency of our competitors (incumbents or
potential entrants)

Question 3
Match the "Real Win Worth-It" headings with their activities.

Question

Correct Match

Is the Product Real?

A.
Is there a clear product concept?

Is Investment worth it
today?

F.
Are forecasted returns greater than
costs?

Can the company win?

B.
Can we understand and respond to
the market?

Does it make Strategic


Sense?

E.
Does the product fit our overall
growth strategy?

Can the product win?

C.
Can the product advantage be
sustained?

Is the Market Real?

D.
Is there a need or desire for the
product?

Question 4
Which of the following deliverables are examined by a Gate
Review Committee for a product that has just completed the
Build the Business Case stage prior to the product entering the
"Development" stage? (select all correct answers)

Correct
Answers Market research studies that define the customers
needs, wants, and preferences.
:
Competitive analysis
Concept testing to validate the product concept
Detailed technical appraisal of the technical feasibility
of the project
A manufacturing (operations or source of supply)
appraisal
Definition of the winning new product including target
market definition, product concept, positioning
strategy, benefits to be delivered, the value
proposition, and product attributes, requirements and
high-level specifications.
A detailed business case and financial analysis
involving a discounted cash flow approach (NPV and
IRR), complete with sensitivity analysis to look at
possible downside risks.
A high level project plan

Review Test Submission: Quiz 10 - Integrated


Project Team
Question 1

0.25 out of 0.25 points

Concurrent Engineering ... (select all correct answers)


Selected
Answers:

Starts all tasks as early as possible.


Empowers individuals and teams to participate in
defining the objectives of their work.
Uses Integrated Project Teams to resolve problems as
they are discovered.
Makes lasting decisions in a single trade-off space
Develops trust among team mates and strives for
team consensus.
Is a major effort and can become unwieldy if the
concurrent engineering spans too much of the design
lifecycle.

Question 2
0.25 out of 0.25 points

Engineering Design Risk ... (select all correct answers)


Selected
Answers:

Assesses the risk from engineering activities to project


scope, time and cost
Assesses the risk from engineering activities to the
product's overall technical integrity
Identifies high-risk areas and critical parameters early
in the project.
Helps direct resources by providing insight into
potential consequences to allow for informed project
decision-making.
Identifies and tracks actions to minimize engineering
risk and ensure resolution of key issues.
Considers risks due to the uncertainty of the outcome
of an engineering activity

Question 3
0.25 out of 0.25 points

Innovation in Design - match the description with its label


Question

Selected Match

Creative
Design ...

D.
... starts with an abstract decomposition of the design
problem into a set of levels that represent choices for
the problem. An existing or obvious plan for the

problem does not exist.


Innovativ
e Designs
...

C.
...the decomposition of the problem is known, but the
alternatives for each of its sub-parts do not exist, and
must be synthesized. The Design might be an original
or unique combination of existing components. A
certain amount of creativity comes into play.

Routine
designs ...

A.
...an existing or obvious plan of the solution exists.
The sub-parts and alternatives are known in advance,
perhaps as the result of either a creative or
innovative design process. Involves finding the
appropriate alternatives for each sub-part that
satisfies the given constraints.

Redesign
...

B.
... an existing design is modified to meet the required
changes in the original functional requirements.

Question 4
0.25 out of 0.25 points

An Integrated Project Team (IPT) versus a Work Group select the correct description for the areas marked A, B, C, D, E, F, G
in the table below.

A.
Leader among peers
B.
Individual and mutual as a team
C.

The group's purpose is subject to little change


D.
Open-ended discussion and active problem solving involving the
entire team is essential
E.
Important meetings with absent team members can have serious
consequences
F.
Measures performance by task completion and quality of
individual outputs
G.
Team discusses, decides and delegates to various team members

You might also like