Professional Documents
Culture Documents
Organisation of the lectures, appointed time between 1st to 12th of November 2016
1st week:
Tuesday
14h00 17h00
Wednesday 8h30 12h30 and 14h00 17h00
Thursday 8h30 12h30
Friday
8h30 12h30 and 14h00 17h00
Saturday
8h30 12h30
2nd week:
Tuesday
14h00 17h00
Wednesday 8h30 12h30 and 14h00 17h00
Thursday 8h30 12h30
Friday 8h30 12h30 and 14h00 to 17h00
Saturday
11h00or using e-mail: ulke@fh-aachen.de
Contact Prof. Ulke
after 8h30
the lectures
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
C: Unit Cost
10
C: Unit Cost
11
C: Unit Cost
12
C: Unit Cost
13
C: Unit Cost
14
15
Other Considerations:
Coffee breaks, trips to the bathroom, a drink of water, the big game or date last
night, lunches that start a little early and may end a little late etc. will cause a
average working time of 30-50 minutes per hour
Sufficient equipment like prompt awarding of material contracts, sufficient
restroom facilities and water containers, and anything else that may help are
necessary to run the project and to make it convenient to work
C: Unit Cost
16
productivity rate
1 = initial skill adaptation training
2 = loss of time with increasing height (vertical transports)
17
quantity of
workers
quantity of
workers
max. capacity
C: Unit Cost
max.
capacity
18
500 m2
= 500 m x 1.56 work hours per m
= 780 work hours
5 skilled workers
156 h
This can also be used to calculate the duration of work, which is important for the
time schedule and the date of finalizing the project:
780 work hours / 5 workers / 9 work hours per day ~ 17,5 days of execution time
C: Unit Cost
19
20
Fig.: Casting and compacting the concrete and smoothing surface subsequently
C: Unit Cost
21
0.1 h/m
= 624.0 m
= 62.4 h
=137.3 h
C: Unit Cost
22
23
C: Unit Cost
24
Wagegroup/
Number of workers
description
basic wage
6/1
4/2
3/2
2/1
Further informations:
1. The charged hand can only work 50% of the time productivly because of his
supervisory work
2. Rateable pay rise from 6% for 100% of the construction period
3. Overtime allowance is 25% of the average basic wage, 40 working hours per
week are fixed in the contracts of employment, effective work hours are 44 per
week
4. Social costs are 89% of the AF (average wage incl. foreman) is given from
payroll accounting of the company as an average value
5. There is a meal allowance for 5 labourers (except the charged hand) of 5 N$/day
for 5 days per week (voluntary for the employer)
C: Unit Cost
25
C: Unit Cost
26
C: Unit Cost
27
C: Unit Cost
28
C: Unit Cost
29
C: Unit Cost
30
C: Unit Cost
31
C: Unit Cost
32
Material Costing
For each project being bid, the contractor will request quotations from materials
suppliers and manufacturers' representatives for all materials required
He should obtain written quotations that spell out the exact terms of the freight,
taxes, time required for delivery, materials included in the price, and the terms
of payment (figure)
The written proposals should be checked against the specifications to make
certain that the specified material was bid
For each item the estimator has to select from the quotation the required
material, identify the used material per unit and has to insert the cost into the
estimate
C: Unit Cost
33
C: Unit Cost
34
Quantity take-off: 500 m masonry walls, height 3.00m, thickness 24 cm, (double)
erected by concrete bricks
Material from
quotation:
Material costs
per unit:
C: Unit Cost
N$ 508.20 + N$ 61.88
= N$ 570.08 per m
35
C: Unit Cost
36
37
38
C: Unit Cost
39
C: Unit Cost
40
41
42
43
44
C: Unit Cost
45
46
Operators' wages and mobilisation costs are not included in equipmentoperation costs
Cost for power equipment are usually based on the horsepower of the
equipment
A gasoline engine will use between 0.18 to 0.24 litre of gasoline per horsepower
per hour when operating at full capacity
An electric powered engine will need from 0.10 to 0.25 KWh per KW installed
performance and work hour
47
N$ 10 per litre
0.18 l per hp per hour
= hp rating x consumption rate x fuel cost
= 120 hp x 0.18 l per hp per hr x 10 $/l
= 216.00 N$/h
Lubrication
The amount of oil and grease required by any given piece of equipment varies
with the type of equipment and job conditions
A piece of equipment usually has its oil changed and is greased every 100 to 150
hours
Under severe conditions the equipment may need much more frequent servicing
(oil consumed between oil changes must also be included in the cost)
C: Unit Cost
48
A piece of equipment has its oil changed and is greased every 120 hours. It requires
6 litres of oil for the change. The time required for the oil change and greasing is
estimated at 2.5 hours.
Assumptions:
Oil cost
Oiler labour rate
Lubrication cost
N$150 per l
N$ 17.50 per hour
= 6 l of oil x $ 150 per l
= N$ 900
Labour cost
Total cost for oil change
C: Unit Cost
= N$/h
7.87
49
50
51
= N$ 575,000
If the piece of equipment should last 10,000 machine work hours, the hourly cost would
be found as follows:
Depreciable cost per hour = depreciable cost / useful life (hours)
Depreciable cost per hour = N$ 575,000 / 10,000 depreciable cost per hour
= N$ 57.50 per machine work hour
C: Unit Cost
52
53
Because the estimator will want to have the interest costs in terms of cost
per hour, the projected useful life in terms of working hours must be
assumed. The formula used to figure the interest cost per hour would be:
Approximate interest cost = (C x I x L) / 2 x H
Where:
H = Useful life of equipment (working hours) 10,000 hrs
Interest Cost:
The last formula is the one used to determine interest costs toward the total
fixed cost per hour for a piece of equipment
Other fixed cost (insurance, taxes, storage, repairs, depreciation) are figured
in a manner similar to that used for figuring interest
These items are taken as percentages of the cost of equipment and are
expressed as decimals in the formula
When the expenses are expressed in terms of percent per year, they must be
multiplied by the number of years of useful life to determine accurate cost
C: Unit Cost
54
C: Unit Cost
55
N$ 476,000
150 hp
N$ 45,000
3%
7 years or 14,000 hours
8% per year
7 years
6% per year
N$ 7 per litre
0.18 litre per hp per hour
4 litres of oil at N$150
2 hours labour at $16.50
every 150 hours
4,000 hours
12% of depreciation
65% over useful life
Prof. Dr.-Ing. Thomas Krause
56
57
C: Unit Cost
58
C: Unit Cost
59
Rental Cost
Rental equipment can be used if:
A project is a long distance from the contractor's home base
The construction involves the use of equipment that the contractor does not
own (and will not likely use after the completion of this one project)
The estimator must investigate the available rental agencies for the type and
condition of equipment available, the cost, and the services the rental firm
provides
The estimator must be certain that all terms of rental are understood, especially
those concerning repair of the equipment
C: Unit Cost
60
C: Unit Cost
61
C: Unit Cost
62
63
64
Subcontractors
A subcontractor is a separate contractor hired by the prime contractor to
perform certain portions of the work
The amount of work that the prime contractor will subcontract varies from
project to project
Trades such as mechanical, electrical, sanitary installation and heating and air
conditioning have a tradition of being performed by subcontractors, due to their
specialised nature and licensing requirements
If specialty contractors are to be used, the contractor must be certain to notify
them early in the bidding period so they have time to prepare a complete,
accurate proposal
Otherwise the subcontractor tends to bid high just for protection against what
might have been missed
C: Unit Cost
65
C: Unit Cost
66
C: Unit Cost
67
68
C: Unit Cost
69
C: Unit Cost
70
C: Unit Cost
71
C: Unit Cost
72
C: Unit Cost
73
C: Unit Cost
74
Depreciation
Expenditures on office equipment,
calculators, typewriters, and any other
equipment. A certain percentage of the
cost is written off as depreciation each
year and is part of the general overhead
expense of running a business. A
separate account should be kept for
these expenses
Items that
should be
included in a
home office
overhead
budget
Salaries
Office employees such as
executives, accountants,
estimators, purchasing agents,
bookkeepers, and secretaries
Miscellaneous
Advertising, literature (magazines, books for
library), legal fees (not applicable to one particular
project), professional services (architects,
engineers), donations, travel (including company
vehicles), and club and association dues
C: Unit Cost
75
N$ / year
Extempt Employees
CEO
950,000
Controller
500,000
Estimator
250,000
200,000
Non-extempt Employees
Secretaries (2)
300,000
Payroll Clerk
120,000
120,000
2,440,000
2,440,000
Benefits @ 38 %
927,200
130,000
Telephone
36,000
Office Supplies
14,000
Office Equipment
Advertising
Trade Journals
Donations
115,000
50,000
2,262
150,000
Legal Services
20,000
Accounting Services
36,000
8,000
10,000
120,000
90,000
C: Unit Cost
4,152,462
76
77
Some contractors do not allow for the category "General Overhead Expense"
separately in their estimates; instead they figure a larger percentage for profit or
group overhead and profit together
This, in effect, "buries" part of the expenses. From the estimator's viewpoint, it is
desirable that all expenses be listed separately so they can be analysed periodically
C: Unit Cost
78
C: Unit Cost
79
Pricing
When the estimator has ascertained all cost for the specific project (unit cost
and total cost for each item as well as general cost) he has to prepare the bid
In consultation with the management there is to decide the method of covering
the general cost in special items or partially or totally by allocations on the
unit cost
Cost for overhead, risk and profit will allways be covered by allocations on unit
cost
Allocations very often will be defined by management on a yearly basis
In dependence from the kind of projects the allocations can be different for
different cost: labour cost, cost of material, equipment cost and subcontractor
cost
C: Unit Cost
80