Professional Documents
Culture Documents
. Crawford, R.
annin, and C.
Abstract: A section of Highway 97, west of Vernon, B.C., is located over a soft-to-firm,
compressible, silty clay subsoil. In addition to an extensive site investigation, the performance of two
test embankments was observed for 2 years before construction was begun on the highway grade
between them. When the highway fill reached a maximum thickness of about 10 m a failure
occurred. The design was then changed to include berms on either side, but a second failure occurred
when the grade was rebuilt. An undrained back-analysis of the first failure shows the influence of
various variables on the factor of safety and illustrates the difficulty of choosing appropriate strength
values for design when the site has a strong crust overlying a weaker layer and there is potential for
progressive failure. Observations of settlements, pore pressures, and lateral movements in the subsoil
describe the performance of the embankment during construction and reveal the importance of strain
softening as a factor in the failures. Comparisons with a variety of similar failures in Canada,
Scandinavia, and southeast Asia provide some guidance for future construction over similar
materials.
Key words: case history, embankment failure, field observation, pore pressures, stability, strength,
undrained analysis.
RCsumC : Une section de l'autoroute 97 B l'ouest de Vernon, Cofombie Britannique, est situCe sur
un substrat d'argile silteuse, compressible, de consistance molle B ferme. Aprtts une
reconnaissance de site approfondie on a observC le comportement de deux remblais d'essai sur la
partie de l'autoroute situCe entre eux, pendant les deux ans qui ont prCcCdC la construction.
Lorsque le remblai de l'autoroute a atteint une Cpaisseur maximale d'environ 10 m, une rupture
s'est produite. On a alors change, le profil transversal pour inclure des bermes de chaque cBtC
mais une seconde rupture a eu lieu lorsque la fondation a CtC reconstruite. Une analyse B rebours
de la premikre rupture avec une hypothkse de non-drainage illustre l'influence de diverses
variables sur le coefficient de sCcuritC et montre qu'il est difficile d'obtenir des valeurs
appropriCes de rCsistance pour le calcul lorsque le site prCsente une croQte ferme surmontant une
couche plus faible avec possibilite de rupture progressive. Des observations de tassement,
pressions interstitielles et mouvements latCraux dans le sous-sol dCcrivent le comportement du
remblai pendant la construction et rCvklent I'importance du ramollissement comme facteur de
rupture. Des comparaisons avec diverses ruptures de mEme type au Canada, en Scandinavie et en
Asie du sud-est apportent quelques fils directeurs pour les constructions futures sur de tels
matCriaux.
Mots cle's : Ctude de cas, rupture de remblai, observation sur le terrain, pressions interstitielles,
stabilitC, rksistance, analyse en condition non-drainCes.
[Traduit par la redaction]
Introduction
A new roadway intersecting Highway 9 7 from the west at
the north end of Vernon, B.C., is located over a silty clay
subsoil. T h e s i t e w a s first explored b y t h e Ministry of
Transportation and Highways in 1960, but the decision to
Received May 13, 1994. Accepted November 17, 1994.
proceed was delayed until 1985; some new site investigations w e r e carried o u t at that time. O n t h e basis of t h e
available soil information it w a s decided t o extend t h e
investigation by constructing t w o test embankments along
the centre line of the proposed road, o n e with wick drains
to a depth of 24 m (West Abutment fill) and o n e without
drains (Waterline fill). T h e site conditions and the perform a n c e of t h e t w o test e m b a n k m e n t s a r e described i n a
recent paper (Crawford e t al. 1992).
The observations of settlements and pore pressures under
the test embankments indicated that the embankment
between them could b e built without the expense of wick
drains. Construction, with piezometric monitoring, began
Fig. 1. Site plan showing location of test fills and failure zones.
LIMIT OF
WATERLINE
TEST FILL
SCALE
Fig. 2. Profiles of.water contents, Atterberg limits and shear strengths. See text for explanation of
points and lines.
*-
STIFF
-?,
(;
/'A
O
\-I
1985
0 TESTS
960 TESTS
- . .. .
TO
VERY STIFF
CLAY
20
40
60
80
100
0
20
40
60
80
Crawford et al.
Fig. 3. CPTU (cone penetration test with pore pressure) profiles.
STATION 25
+ 60
STATION 28
>
SAND,
SILT
& CLAY
+ 60
SAND,
SILT
& CLAY
SILTY
CLAY
1i
SILTY
CLAY
TIP RESISTANCE
FRICTION RATIO
Site conditions
The final alignment of the road fell between two earlier
proposals, and consequently the site investigations were
located on either side of the as-built centre line. The locations of the two test embankments along the new road
alignment are shown in Fig. 1 in relation to the 1960 bori n g ~to the south (H5, H6, and H7) and the 1985 borings to
the north (TH1, TH2, TH3, and TH28). The groundwater
table (GWT) was observed to be between the surface and
a depth of 2 m.
The natural water contents and Atterberg limits from
the two sets of borings are given in Fig. 2n. Each solid
circle represents an average of 10-15 measurements of
water content and each solid horizontal line represents the
average of three Atterberg limit tests (one from each of
the three test holes) done in 1960. The open circles represent average water contents of the samples from the four
boreholes made in 1985. In September 1990, soil samples
were obtained from four boreholes at stations 27+25 and
27+75, (see Fig. 1). Atterberg limit tests on these samples are shown as broken horizontal lines and average
water contents are shown as solid triangles.
In the 1960 site investigation field vane shear strengths
were measured to depths of more than 30 m, and approximately 9 0 unconfined compression tests were made on
Shelby tube samples obtained to the same depth. Most of
the unconfined tests failed at more than 5 % strain and
even after the specimens that failed at high strains were
eliminated, the remainder still gave much lower strengths
than the field vane values. It was concluded that the laboratory specimens were somewhat disturbed, and for stability
FRICTION RATIO
PORE PRESSURE
274
FAILURE
WEST
FAILURE
- 3 0 JUNE
1 0 MAR. ' 9 0
'89
SURVEY STATION
EAST
Station
Original
surface
elevation
Settlement
(m)
Fill
thickness"
(m)
Au,
(kPa)
11
(kPa)
Au
(kPa)
Au,
(kPa)
AL~Au,
35
168
166
182
179
174
84
151
155
193
193
207
0.42
1.11
1.07
0.94
0.93
0.84
Test embankments
390.2
390.8
390.8
390.5
390.5
391.9
0.1
0.4
0.4
0.5
0.5
0.8
4.4
7.9
8.1
9.9
9.9
11.0
89
160
164
201
201
223
30, 1989
125
264
262
275
272
- 281
10, 1990
NOTES:
An,, applied stress due to embankment: ri, pore-water pressure measured at elevation 380 m;
Au, assumes ground-water table initially at a depth of 1 m; An,, change in vertical stress at elevation 380 m.
"Includes settlement.
In 1986 before construction of the test embankments,
two cone penetration tests were made along the centre line
at Stations 25+60 and 28+60. The CPTU (cone penetration
test with pore pressure) profiles shown in Fig. 3 indicate a
significant variation between the two locations in the upper
8 m but more uniform conditions below this depth.
Test embankments
The two test embankments provided useful information
on the consolidation properties of the ground and on the performance of wick drains but gave no information on the
ultimate strength of the subsoil. They were built during a
4 week period without any sign of distress: a linear relationship was observed between applied load and settlement under both embankments during fill placement, with
most of the compression occurring in the upper 4 m. The
larger (West Abutment) embankment, with wick drains,
was built to a height of 12.4 m, 1 m higher than the final
roadway elevation. It settled 3 m within the first year, but
pore pressures in the ground dissipated quickly through
the wick drains. The smaller (Waterline) embankment was
built in two sections to a height of 6 and 11.4 m, respectively. The maximum settlement after 1 year was only
0.7 m, but in the absence of wick drains the pore pressure
dissipation was much slower. Based on observed settlements
Crawford et al
Fig. 6. Cross section showing probable failure surface of 30 June 1989 at station 27+80.
I
405
P/
I
FAILURE EL.
1
29
ill
SURFACE
of the test embankments, it was concluded that the subsoil below the crust was overconsolidated by about 145 kPa
(Crawford et al. 1992). The implications of these observations will be discussed later in the paper.
276
Fig. 7. Height of fill, settlement, and piezometric surface at centre line during construction at
station 27 +30.
415
JAN.
FEE. IMAR.
1 JAN.
FEE. 'MAR. I
1989
1990 c,$
xm
410
Ur:
ZE
PIEZOMETRIC SURFA
-E
-z
...... i
.........
....;
405
400
395
..... E z3
....,..' 3
& 7
....
2 Om
.............
: " Y
..........................
..............................:
/
("
HEIGHT OF FILL
.................
'II
-E
I-
5
2
W
0-*
, c P I E Z O M E T R I C SURFACE
......................................
I
0.5-
c n .
1.o
0
100
200
300
400
500
TIME IN DAYS
Crawford et al.
Fig. 8. Height of fill, settlement, and piezometric surface at centre line during construction at
station 27+80.
1 JAN. FEB.[MAR.APR.
410
MAY JUNE
1 JULY
405
-E
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Western Ontario on 09/14/16
For personal use only.
-z
1989
PIEZOMETRIC SURFACE
(TIP EL. = 380 m)
AUG.
1 SEPT.
1 OCT.
1 NOV.
1 DEC.
I JAN.I rrs. I MAR.I
\i.''.'''
"
m
i'
...........:
I r n
HEIGHT OF FlLL
F 400 4
-I
LU
395
--E
2
L
FINAL PAVEMENT
.
0.5
U
E :
E :
l.O
EL.
1.5
0
-\
!
I
200 TIME
100
IN DAYS 300
400
500
Fig. 9. Height of fill, settlement, and piezometric surface at centre line during construction at
station 30f50.
,..".
........
............ ........
.........
PHREATIC SURFACE
..............................TJ'! ......EL.
380 m)
.......................
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.................................
HEIGHT OF FlLL
I
100
200
I
300
I
400
500
TlME IN DAYS
LEFT (NORTH)
Lateral movements
The lateral movement relative to the bottom of a slope
indicator casing at station 27+80, 33 m north of centre
line is shown in Fig. 11. There was relatively little lateral
movement at the toe of the slope until the major construction work began at the middle of March, but a trend had
developed by mid-April. The last observation, on June 19,
showed an accumulated movement of 6 mm into the slope
at a depth of 4 m and movement of 10 mm away from the
slope at a depth of 12 m. Although the lateral movement is
very small it coincides with the beginning of an increase in
the rate of settlement shown in Fig. 8. It is thought that
lateral movements would have increased significantly as
the rate of settlement increased but unfortunately there are
no measurements after June 19 to confirm it.
Probable reasons for failure
This postfailure assessment suggests that two main factors contributed to the discrepancy between design and
performance. Firstly, the observations on the smaller test fill
8 MAR. ' 8 9
1 8 APR. ' 8 9
Crawford et al.
Crawford et al.
i
+go0
<
0.44
10
20
30
- 45 O
- 90 O
c,=
SHEAR STRENGTH OF
SILTY CLAY LAYER
Undrained analysis
The postulated geometry of the first failure of the embankment (see Fig. 6) shows most of the slip circle to pass
more or less horizontally between elevations 382 and
376 m. A circular surface matches well with the physical
evidence from pre- and postfailure observations, and preliminary back-analyses indicated a circular surface yielded
lower factors of safety than a noncircular surface. The
profile of undrained shear strength with depth (Fig. 2)
indicates a relatively strong crust layer between ground
40
Sb
282
Fig. 15. Excess pore pressures at elevation 380 m caused by surface loads at station 27+30.
I
I SECOND FAILURE
MAR. 1 0 ,
FIRST FAILURE
DAY 283
371
50
100
150
200
250
General discussion
In an invited lecture to the ASCE Conference on Stability
a n d P e r f o r m a n c e of S l o p e s a n d Embankments-2,
Morgenstern (1992) noted that "while the progress over
the past 25 years is encouraging, much more remains to
be accomplished in order to reduce the landslide devil's
laugh to a smile." Full-scale field cases of failure a r e
important reference points for engineering practice a n d
there are several features of this case that can contribute to
future understanding.
It is seldom justified to carry out sophisticated analyses
of highway embankments, but it is always wise to provide sufficient instrumentation to monitor performance at
difficult sites. Such instrumentation adds little to the overall cost but contributes enormously to the understanding
of the state of stability during and after construction. In
particular, the development of pore pressures during loading and at failure is of considerable interest. It has been
established that when shear stresses approach the ultimate
resistance of a strain-softening clay, the structure of the
clay begins to break down and the load is progressively
transferred to the pore water. This results either in continuing consolidation at constant effective stress (shown
for example by Crawford and Bozozuk 1990) or in a progressive shear failure, as illustrated by several case records
described earlier. The transfer of stresses from the soil
structure to the pore water is indicated by the ratio of
changes in pore pressure to changes in the applied stress,
as shown for station 27+30 in Fig. 15. It should be noted
that the change in pore pressure is measured at elevation
380 m, as in Table 1, while values of applied pressure of the
embankment (Au,) are calculated at the original surface
Crawford et al
of the ground, and the increment of stress at the piezometer level is believed to be about 5% less than the imposed
surface stress.
The ratio of AulAu, was unity during application of the
first 40% of the load. During the application of the next
40% of load the ratio fell as low as 0.7 in periods of little
or no loading, but from day 192 to day 194 the ratio rose
rapidly to 2.5. This rapid rise occurred as the pressure at the
surface increased from 130 to 136 kPa. This is close to
the value for the overconsolidation stress (145 kPa) inferred
from the observations on the Waterline test fill and may
indicate that stresses in the subsoil had reached the normally consolidated range. From day 194 until failure on
day 202 the average value for AuIAu, was about 0.93.
Although the first failure followed quickly after some substantial increases in load, the second failure was preceded
by long periods at rest that were intended to reduce the
risk of failure.
When reconstruction began in July 1989, the fill was
raised easily to its elevation at failure on June 30 with only
slight increases in pore pressure. On day 409 (January 24,
1990) the fill was raised 0.3 m (Ao, = 6 kPa) and left at rest
until day 437 (4 weeks) when the excess pore pressures
had decreased by 14 kPa. On day 438 a further 0.4 m of fill
was added, and during the following 16 days the excess
pore pressures increased steadily from 139 to 156 kPa, and
the second failure occurred on day 454 (March 10, 1990).
T h e sensitivity of the failure region after January 2 2
(day 407) until failure 47 days later is remarkable. The
first small increment of load resulted in a small increase in
pore pressure followed by a substantial decrease and a
negative value for AulAo, = - 1416 = -2.3, but the second
small increment resulted in Aulhu, = 2218 = 2.7 before
failure. These observations indicate that on day 437 the
factor of safety was clearly greater than unity and increasing under an applied surface stress of 203 kPa, but on
day 438 when the applied stress was increased by 4% to
211 kPa the failure process was initiated. This observation is consistent with the development of a yield zone
approaching the critical state along the potential failure
surface similar to the case described by Indraratna et al.
(1992).
The increasing rate of settlement and the rapid rise in
pore pressures under a constant load indicate that the pore
pressures are being generated by shear strains along the
potential failure surface. The observations of lateral deflection (Fig. 11) support the view that most of the vertical
movements are caused by lateral strain at essentially constant volume. The pore pressure on the failure surface at the
moment of failure will increase to that value which is
required to reduce effective stresses to the failure condition
and it is unlikely that a piezometer would capture the value
even if it was located in that zone.
Conclusions
There was a reasonable expectation based on average soil
properties and on the performance of two test embankments, that the approximately 12 m high road embankment
at Vernon could have been built successfully as planned.
However, a rotational failure occurred in construction when
Acknowledgements
The authors are grateful to Mr. E.A. Lund, Chief Highway
Engineer of the Ministry of Transportation and Highways
of the Province of British Columbia, for permission to
publish this paper. The research was assisted by an operating
grant from the Natural Sciences and Engineering Research
Council of Canada.
References
Aas, G., Lacasse, S., Lunne, T., and Hereg, K. 1986. Use
of in situ tests for foundation design on clay. ASCE
Geotechnical Special Publication No. 6, pp. 1-30.
Bjerrum, L. 1972. Embankments on soft ground. ASCE
Proceedings of the Specialty Conference on Performance of Earth and Earth Supported Structures,
Purdue University, Lafayette, Ind., June 11-14,
Vol. 2, pp. 1-54.
Crawford, C.B., and Bozozuk, M. 1990. Thirty years of
secondary consolidation in sensitive marine clay.
Canadian Geotechnical Journal, 27: 3 15-3 19.
Crawford, C.B., and Eden, W.J. 1967. The performance
of an embankment on a deep deposit of varved clay.
Discussion. Canadian Geotechnical Journal, 4: 63-64.
Crawford, C.B., Fannin, R.J., deBoer, L.J., and
Kern, C.B. 1992. Experiences with prefabricated vertical (wick) drains at Vernon, B.C. Canadian Geotechnical Journal, 29: 67-79.
Dascal, O., and Tournier, J-P. 1975. Embankments on