Professional Documents
Culture Documents
Investment Appraisal
Chapter Outline
Project Viability 25
Return on Investment (ROI) 25
Net Present Value 26
Payback29
Internal Rate of Return (IRR) 29
Cost/Benefit Analysis 31
The investment appraisal, which is part of the business case, will, if properly structured,
improve the decision-making process regarding the desirability or viability of the project. It
should have examined all the realistic options before making a firm recommendation for the
proposed case. The investment appraisal must also include a cost/benefit analysis and take
into account all the relevant factors such as:
Capital costs, operating costs, and overhead costs
Support and training costs
Dismantling and disposal costs
Expected residual value (if any)
Any cost savings that the project will bring
Any benefits that cannot be expressed in monetary terms
To enable some of the options to be compared, the payback, return on capital, net present value,
and anticipated profit must be calculated. In other words, the project viability must be established.
Project Viability
Return on Investment (ROI)
The simplest way to ascertain whether the investment in a project is viable is to calculate the
return on investment (ROI).
If a project investment is 10 000, and gives a return of 2000 per year over 7 years,
(7 2000) 10000
7
= 4000 = 571.4
7
25
26 Chapter 6
The return on the investment, usually given as a percentage, is the average return over the
period considered 100, divided by the original investment, i.e.,
average return 100
return on investment % =
investment
= 571.4 100 = 5.71 %
10000
This calculation does not, however, take into account the cash flow of the investment, which
in a real situation may vary year by year.
119.10
1
1.191
The 0.840 is called the discount factor or present value factor and can be quickly found from
discount factor tables, a sample of which is given in Figure 6.1.
It will be noticed from these tables that 0.840 is the PV factor for a 6% return after 3 years.
The PV factor for a 6% return after 2 years is 0.890 or
= 0.890
1.06 1.06 1.1236
In the above example the income was the same every year. In most projects, however, the
projected annual net cash flow (income minus expenditure) will vary year by year, and to
=
1%
2%
4%
6%
8%
10%
12%
14%
15%
16%
18%
20%
22%
24%
25%
26%
28%
30%
35%
40%
45%
50%
....
....
....
....
....
0.990
0.980
0.971
0.961
0.951
0.980
0.961
0.942
0.924
0.906
0.962
0.925
0.889
0.855
0.822
0.943
0.890
0.840
0.792
0.747
0.926
0.857
0.794
0.735
0.681
0.909
0.826
0.751
0.683
0.621
0.895
0.797
0.712
0.636
0.567
0.877
0.769
0.675
0.592
0.519
0.870
0.756
0.658
0.572
0.497
0.862
0.743
0.641
0.552
0.476
0.847
0.718
0.609
0.516
0.437
0.833
0.694
0.579
0.482
0.402
0.820
0.672
0.551
0.451
0.370
0.806
0.650
0.524
0.423
0.341
0.800
0.640
0.512
0.410
0.328
0.794
0.630
0.500
0.397
0.315
0.781
0.610
0.477
0.373
0.291
0.769
0.592
0.455
0.350
0.269
0.741
0.549
0.406
0.301
0.223
0.714
0.510
0.364
0.260
0.186
0.690
0.476
0.328
0.226
0.136
0.667
0.444
0.296
0.198
0.132
6
7
8
9
10
....
....
....
....
....
0.942
0.933
0.923
0.914
0.905
0.888
0.871
0.853
0.837
0.820
0.790
0.760
0.731
0.703
0.676
0.705
0.665
0.627
0.592
0.558
0.630
0.583
0.540
0.500
0.463
0.564
0.513
0.467
0.424
0.386
0.507
0.452
0.404
0.361
0.322
0.456
0.400
0.351
0.308
0.270
0.432
0.376
0.327
0.284
0.247
0.410
0.354
0.305
0.263
0.227
0.370
0.314
0.266
0.225
0.191
0.335
0.279
0.233
0.194
0.162
0.303
0.249
0.204
0.167
0.137
0.275
0.222
0.179
0.144
0.116
0.262
0.210
0.168
0.134
0.107
0.250
0.198
0.157
0.125
0.099
0.227
0.178
0.139
0.108
0.085
0.207
0.159
0.123
0.094
0.073
0.165
0.122
0.091
0.067
0.050
0.133
0.095
0.068
0.048
0.035
0.108
0.074
0.051
0.035
0.024
0.088
0.059
0.039
0.026
0.017
11
12
13
14
15
....
....
....
....
....
0.896
0.887
0.879
0.870
0.861
0.804
0.788
0.773
0.758
0.743
0.650
0.625
0.601
0.577
0.555
0.527
0.497
0.469
0.442
0.437
0.429
0.397
0.368
0.340
0.345
0.350
0.319
0.290
0.263
0.239
0.287
0.257
0.229
0.205
0.183
0.237
0.208
0.182
0.160
0.140
0.215
0.187
0.163
0.141
0.123
0.195
0.168
0.145
0.125
0.108
0.162
0.137
0.116
0.099
0.084
0.135
0.112
0.093
0.078
0.065
0.112
0.092
0.075
0.062
0.051
0.094
0.076
0,061
0.049
0.040
0.086
0.069
0.055
0.044
0.035
0.079
0.062
0.050
0.039
0.031
0.066
0.052
0.040
0.032
0.025
0.056
0.043
0.033
0.025
0.020
0.037
0.027
0.020
0.015
0.011
0.025
0.018
0.013
0.009
0.005
0.017
0.012
0.008
0.006
0.004
0.012
0.008
0.005
0.003
0.002
16
17
18
19
20
....
....
....
....
....
0.853
0.844
0.836
0.828
0.820
0.728
0.714
0.700
0.686
0.673
0.534
0.523
0.494
0.475
0.456
0.394
0.371
0.350
0.331
0.312
0.292
0.270
0.250
0.232
0.215
0.218
0.198
0.180
0.164
0.149
0.163
0.146
0.130
0.116
0.104
0.123
0.108
0.095
0.083
0.073
0.107
0.093
0.081
0.070
0.061
0.093
0.080
0.069
0.060
0.051
0.071
0.060
0.051
0.043
0.037
0.054
0.045
0.038
0.031
0.026
0.042
0.034
0.028
0.023
0.019
0.032
0.026
0.021
0.017
0.014
0.028
0.023
0.018
0.014
0.012
0.025
0.020
0.016
0.012
0.010
0.019
0.015
0.012
0.009
0.007
0.015
0.012
0.009
0.007
0.005
0.008
0.006
0.005
0.003
0.002
0.005
0.003
0.002
0.002
0.001
0.003
0.002
0.001
0.001
0.001
0.002
0.001
0.001
21
22
23
24
25
....
....
....
....
....
0.811
0.803
0.795
0.788
0.780
0.660
0.647
0.634
0.622
0.610
0.439
0.422
0.406
0.390
0.375
0.294
0.278
0.262
0.247
0.235
0.199
0.184
0.170
0.158
0.146
0.135
0.123
0.112
0.102
0.092
0.095
0.083
0.074
0.066
0.059
0.064
0.056
0.049
0.043
0.038
0.053
0.046
0.040
0.035
0.030
0.044
0.038
0.035
0.028
0.024
0.031
0.026
0.022
0.019
0.016
0.022
0.018
0.015
0.013
0.010
0.015
0.013
0.010
0.008
0.007
0.011
0.009
0.007
0.006
0.005
0.009
0.007
0.006
0.005
0.004
0.008
0.006
0.005
0.004
0.003
0.006
0.004
0.005
0.003
0.002
0.004
0.003
0.002
0.002
0.001
0.002
0.001
0.001
0.001
0.001
0.001
0.001
26
27
28
29
30
....
....
....
....
....
0.772
0.764
0.757
0.749
0.742
0.598
0.586
0.574
0.563
0.552
0.361
0.347
0.333
0.321
0.308
0.220
0.207
0.196
0.185
0.174
0.135
0.125
0.116
0.107
0.099
0.084
0.076
0.069
0.063
0.057
0.053
0.047
0.042
0.037
0.033
0.033
0.029
0.026
0.022
0.025
0.026
0.023
0.020
0.017
0.015
0.021
0.018
0.016
0.014
0..012
0.014
0.011
0.010
0.008
0.007
0.009
0.007
0.006
0.005
0.004
0.006
0.005
0.004
0.003
0.003
0.004
0.003
0.002
0.002
0.002
0.003
0.002
0.002
0.002
0.001
0.002
0.002
0.002
0.001
0.001
0.002
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
40 ....
0.672
0.453
0.208
0.097
0.046
0.022
0.011
0.005
0.004
0.003
0.001
0.001
50 ....
0.608
0.372
0.241
0.054
0.021
0.009
0.005
0.004
0.001
0.001
Figure 6.1
Discount factors
Investment Appraisal 27
1
2
3
4
5
28 Chapter 6
obtain a realistic assessment of the net present value (NPV) of an investment, the net cash
flow must be discounted separately for every year of the projected life.
The following example will make this clear.
Year
Income
Discount
rate
Discount
factor
1
2
3
4
10000
11000
12000
12000
5%
5%
5%
5%
1/1.05 = 0.9523
1/1.052 = 0.9070
1/1.053 = 0.8638
1/1.054 = 0.8227
Total
45000
NPV
One of the main reasons for finding the NPV is to be able to compare the viability of competing projects or different repayment modes. Again an example will demonstrate the point.
A company decides to invest 12000 for a project which is expected to give a total return of
24000 over 6 years. The discount rate is 8%.
There are two options of receiving the yearly income.
1. 6000 for years 1 and 2 = 12000
24000
24000
The DCF method will quickly establish the most profitable option to take as will be shown in
the following table.
Year
1
2
3
4
5
6
Total
Discount
factor
Cash flow A
NPV A
Cash flow B
NPV B
1/1.08 = 0.9259
1/1.082 = 0.8573
1/1.083 = 0.7938
1/1.084 = 0.7350
1/1.085 = 0.6806
1/1.086 = 0.6302
6000
6000
4000
4000
2000
2000
5555.40
5143.80
3175.20
2940.00
1361.20
1260.40
5000
5000
5000
5000
2000
2000
4629.50
4286.50
3969.00
3675.00
1361.20
1260.40
24000
19437.00
24000
19181.50
Investment Appraisal 29
Clearly, A gives the better return, and after deducting the original investment of 12000, the
net discounted return for A = 7437.00 and for B = 7181.50.
The mathematical formula for calculating the NPV is as follows:
If NPV
r
n
B1, B2, B3, etc.
NPV for year 1
for year 2
for year 3
=
=
=
=
=
=
=
If the annual net benefit is the same for each year for n years, the formula becomes
As explained previously, the discount rate can vary year by year, so the rate relevant to the
year for which it applies must be used when reading off the discount factor table.
Two other financial calculations need to be carried out to enable a realistic decision to be
taken as to the viability of the project.
Payback
Payback is the period of time it takes to recover the capital outlay of the project, having taken
into account all the operating and overhead costs during this period. Usually this is based on the
undiscounted cash flow. A knowledge of the payback is particularly important when the capital
must be recouped as quickly as possible as would be the case in short-term projects or projects
whose end products have a limited appeal due to changes in fashion, competitive pressures, or
alternative products. Payback is easily calculated by summating all the net incomes until the
total equals the original investment (e.g., if the original investment is 600 000, and the net
income is 75000 per year for the next 10 years, the payback is 600000/75000 = 8 years).
+NPV
30 Chapter 6
IRR%
NPV
Discount rate
%
Figure 6.2
Internal rate of return (IRR) graph
While it is possible to calculate the IRR by trial and error, the easiest method is to draw a
graph as shown in Figure 6.2.
The horizontal axis is calibrated to give the discount rates from 0 to any chosen value, say 20%.
The vertical axis represents the NPVs, which are + above the horizontal axis and below.
By choosing two discount rates (one low and one high), two NPVs can be calculated for the
same envisaged net cash flow. These NPVs (preferably one +ve and one ve) are then plotted
on the graph and joined by a straight line. Where this line cuts the horizontal axis, i.e., where
the NPV is zero, the IRR can be read off.
The basic formulae for the financial calculations are given below.
Investment appraisal definitions
NPV (net present value)
Net income
Payback period
=
=
=
Profit
Average return/annum
Cost
Benefit
Investment Appraisal 31
Time
Figure 6.3
Cost/benefit profile
Cost/Benefit Analysis
Once the cost of the project has been determined, an analysis has to be carried out which
compares these costs with the perceived benefits. The first cost/benefit analysis should be
carried out as part of the business case investment appraisal, but in practice such an analysis
should really be undertaken at the end of every phase of the life cycle to ensure that the
project is still viable. The phase interfaces give management the opportunity to proceed with
or, alternatively, abort the project if there is an unacceptable escalation in costs or a diminution of the benefits due to changes in market conditions such as a reduction in demand caused
by political, economic, climatic, demographic, or a host of other reasons.
It is relatively easy to carry out a cost/benefit analysis where there is a tangible deliverable
producing a predictable revenue stream. Provided there is an acceptable NPV, the project can
usually go ahead. However, where the deliverables are intangible, such as better service,
greater customer satisfaction, lower staff turnover, higher staff morale, etc., there may be
considerable difficulty in quantifying the benefits. It will be necessary in such cases to run a
series of tests and reviews and assess the results of interviews and staff reports.
Similarly while the cost of redundancy payments can be easily calculated, the benefits in
terms of lower staff costs over a number of years must be partially offset by lower production
volume or poorer customer service. Where the benefits can only be realized over a number of
years, a benefit profile curve as shown in Figure 6.3 should be produced, making due allowance for the NPV of the savings.
The following lists some of the benefits that have to be considered, from which it will be
apparent that some will be very difficult to quantify in monetary terms:
Financial
Statutory
Economy
32 Chapter 6
Risk reduction
Productivity
Reliability
Staff morale
Cost reduction
Safety
Flexibility
Quality
Delivery
Social