You are on page 1of 4

March 2012

By David Rodighiero, Partner


and Marnie Carroll, Solicitor

Protect yourself against adverse interpretation: recommended


amendments to standard form construction contracts
Introduction Payments Act 2004 (Qld) (BCIP Act) on 26 May
2008 and then a further payment claim on 31 July
With 2012 in full swing, it is an appropriate time to 2008 (July Payment Claim). While Jedfire
consider two recent issues which have led us to disputed the July Payment Claim on the basis
recommend amendments to standard form that more than one payment claim had been
contracts. These issues are: served for the same reference date, it did not
serve a Payment Schedule within the time
the identification of reference dates (when stipulated under the BCIP Act.
payment claims may be made under security
of payment legislation) in a contract; and In response, Tailored Projects applied to the
Supreme Court for summary judgment with
a superintendents discretion to extend time respect to the July Payment Claim on the basis
for the benefit of a contractor. that a Payment Schedule had not been served
within the timeframe provided under section 18(4)
Time for Issuing Payment Claims the BCIP Act. In support of its application,
Tailored Projects submitted that clause 14 of the
After the unanimous decision of the Qld Court of QMBA Contract established a contractual regime
Appeal in Daysea Pty Ltd v Watpac Aust Pty Ltd, similar in effect to the statutory regime.
2

it was commonly accepted that following the


issue of a progress claim upon practical Before Justice Douglas, Jedfire argued that more
completion under contracts in a form comparable than one payment claim had been made in
to AS 2124-1992, contractors were not entitled to respect of the same reference date (being the
issue further progress claims until final date of practical completion). Jedfire argued that
completion. this was contrary to section 17(4) of the BCIP Act,
which states:
However, a more recent decision of the Supreme
Court of Queensland demonstrates the A payment claim may be served only within
uncertainty of this principle. the later of:
This issue was considered by His Honour Justice (a) The period worked out under the
Douglas in the matter of Tailored Projects Pty Ltd construction contract; or
1
v Jedfire Pty Ltd . The claim in that matter was (b) The period of 12 months after the
based on a Queensland Master Builders construction work to which the claim
Association LSC2 August 2006 form contract relates was last carried out or the related
(QMBA Contract). goods and services to which the claim
Under the QMBA Contract, monthly progress relates were last supplied.'
claims were to be submitted by Tailored Projects A 'reference date' is (in part) defined in Schedule
on the last day of the month. Clause 14(a) of the 2 of the BCIP Act as:
QMBA Contract provided:
(a) A date stated in, or worked out under, the
14. PAYMENT contract as the date on which a claim for a
(a) The Contractor shall submit payment progress payment may be made for
claims to the Proprietor by the following construction work carried out or undertaken to
reference dates: be carried out, or related goods and services
supplied or undertaken to be supplied, under
(i) the times stated in the Schedule (or, the contract
if any time stated in the Schedule is
not a Business Day, the next Accordingly, Jedfire submitted that the July
Business Day) or the last Business Payment Claim was invalid and that, on the basis
Day of each month, whichever is the of clause 14(a), the only relevant reference dates
earlier; and were the date of completion and the expiry date
of the defects liability period (in accordance with
(ii) on the Works reaching Practical clause 25 of the QMBA Contract). In reply,
Completion. Tailored Projects argued that section 17(4)
Practical Completion was achieved on 12 May
2008. Tailored Projects submitted a payment 2
See Daysea Pty Ltd v Watpac Aust Pty Ltd [2001]
claim under the Building and Construction QCA 49 at [17]-[19] (which is discussed below).

1
[2009] QSC 32

Carter Newell 2012 www.carternewell.com


of the BCIP Act permitted payment claims to be substance in the submissions that Progress Claim no 18
submitted within a period of 12 months after the was invalid, agreed that the court understood the
completion of the relevant construction work. On that argument that multiple payment claims had been
basis, Tailored Projects submitted that the two payment submitted after the date of practical completion and
claims were made with respect to different reference dismissed it.
dates.
At paragraph [17], Justice Douglas determined that the Isis v Clarence
relevant reference date should be determined in The issue was further considered by Master Macready
accordance with the contract, stating that the claim in the New South Wales Supreme Court decision of Isis
made in reliance on the Act fails as more than one 4
v Clarence . The contract in that case was based on
payment claim was made in relation to the reference AS2124-1992, but within the scope of the Building and
date for practical completion under the contract. Construction Industry Security of Payments Act 1999
Although the wording within clause 14 of the QMBA (NSW).
Contract differs to the equivalent payment provisions in, Isis argued that the contractual ability to make progress
for instance, Australian Standard form contracts, the claims continued after practical completion. Clarence
function of the clauses is similar. Accordingly, if the contended that the proper construction of clause 42.1 of
decision of Justice Douglas in the Jedfire case is the contract provided the right to issue monthly claims
followed, it is arguable that equivalent payment only continues until the issue of a certificate of practical
provisions only provide for payment claims to be completion.
submitted up to and upon the issue of a Certificate of
Practical Completion. A further progress claim issued The relevant provisions of the contract provided:
after Practical Completion will be invalid, except for the 42.1 Payment Claims, Certificates, Calculations
Final Payment Claim submitted at the expiry of the and Time for payment.
defects liability period.
At the times for payment claims stated in the
Daysea Pty Ltd v Watpac Australia Pty Ltd Annexure and upon issue of Practical Completion
and within the time prescribed by Clause 42.7, the
While the decision of Justice Douglas in Jedfire is clear Contractor shall deliver to the superintendent claims
on its face, it requires consideration in light of the for payment supported by evidence of the amount
3
decision in Daysea Pty Ltd v Watpac Australia Pty Ltd . due to the Contractor and such information as the
In that decision, the Queensland Court of Appeal superintendent may reasonably require. Claims for
considered the validity of progress claims submitted payment shall include the value of the work carried
after practical completion in relation to AS4300-1995. out by the Contractor in the performance of the
The case concerned an application for summary Contract to that time together with all amounts then
judgment for payment of a progress claim where a due to the Contractor arising out of or in connection
Payment Certificate was not issued in accordance with with the Contract or for any alleged breach thereof.
clause 42.1 of the contract.
42.7 Final payment claim
In Daysea, practical completion was achieved on 30
November 1999. Watpac issued progress claims Within 20 days after the expiration of the defects
subsequent to practical completion on 3 December 1999 liability period, or where there is more than one, the
and 22 February 2000. However, those claims for last to expire, the contractor shall lodge with the
payment included claims in relation to the performance superintendent a final payment claim and endorse it
of variations directed by the superintendent after final payment claim.
practical completion. Macready M at [20] found that on the face of the
The superintendent failed to issue a Payment Certificate above clauses, there is nothing in them to give any
for the claim made on 22 February 2000 within time and indication that multiple payment claims may not be
Watpac sought full payment on that basis. issued after the issue a certificate of practical
completion.
Daysea argued that the progress claim was invalid
because it was submitted after the date of practical Implication of the above decisions
completion.
If the decision of Justice Douglas in the Jedfire is
Justice Williams, who delivered the leading judgment, followed, it is arguable that AS2124-1992, AS2545-1993
stated at paragraph [27] that given the fact that work and AS4300-1995 standard form contracts only provide
had to be carried out at least on variations thereafter, it for payment claims to be submitted up to and upon
was certainly not unreasonable to expect there would be practical completion. No further payment claims within
one further Progress Claim lodged. the defects liability would be valid, except for the final
The reasoning in Daysea at paragraphs [26] to [28] payment claim submitted upon final completion.
appeared to be in light of the specific surrounding factual However, in light of the observations of Williams JA of
circumstances in that case (namely, the performance of the Queensland Court of Appeal in Daysea, which
extra works after practical completion). It is apparent appears to be opposed to such argument and the
from the leading decision of Williams JA in Daysea, who decision of Master Macready in Isis (which did not
stated at [29] In the circumstances there is no consider Daysea but in a reasoned decision came to the

3 4
[2001] QCA 49 [2004] NSWSC 73

Carter Newell 2012 www.carternewell.com


same conclusion), it would appear that the decisions of under the contract. However, the burden still remains
Daysea and Isis would likely be followed. on the contractor to prove its entitlement.
Suggested amendments The judgment of Justice McMurdo in the matter of
Hervey Bay (JV) Pty Ltd v Civil Mining and Construction
As the above decisions all turned on the interpretation of 8
Pty Ltd provides that it is possible to draft extension of
the contractual entitlements of a contractor to deliver a time provisions to remove the obligation placed on
payment claim, it is recommended that contracts be superintendents to exercises their discretionary power.
amended to expressly provide whether progress claims
can be submitted during the defects liability period. The case concerned an adjudicators determination of
delay damages under an amended AS 2124-1992
Extension of Time Provisions contract. While the superintendent did not grant
extensions of time, the adjudicator, standing in the
Over the past 10 years, it has generally been accepted shoes of the superintendent determined that the
that Australian Standard form contracts provide the contractor was entitled to those extensions and awarded
superintendent with a unilateral discretionary power to delay damages. The Hervey Bay contract had
grant extensions of time. This discretionary power specifically removed the clause 23 obligations from
exists notwithstanding whether a contractor has a acting on the discretion to extend time unilaterally.
contractual entitlement or has not made a claim.
In that case, the superintendent was relieved from an
Following on from the decision of the New South Wales obligation to exercise the discretionary power.
Court of Appeal in Peninsula Balmain v Abigroup
5
Contractors Pty Ltd , a line of authorities have The Contractors argument, which the adjudicator
confirmed that the superintendent under an Australian accepted, was that the adjudicator was entitled to allow
Standard form contract must exercise its discretion delay costs absent the grant of an extension of time
under clause 35.5 of AS2124-1992 by extending the from the superintendent if the adjudicator concluded, as
time for completion where they are required to act he did, that the Contractor was entitled to an extension
honestly or fairly. of time.

Peninsula Balmain involved an unmodified clause 35.5 However, Justice McMurdo of the Supreme Court of
of AS 2124-1992. In that case, the contractor had not Queensland however said:
made any claim for an extension of time. A court- In my view there is no tenable construction of cl
appointed Referee nevertheless found that a 35.5A by which the Superintendent could be said to
superintendent, acting honestly and fairly, should have be under any obligation and in particular an
exercised his discretion and extended time for obligation to extend time if it would be fair to do so.
completion. The Court of Appeal agreed with the primary Absent such an obligation there was no entitlement
judges acceptance of the Referees conclusion, opining in any sense to an extension of time, if there had not
that the superintendents power to grant an extension of been compliance with cl 35.5. So in the adjudicators
time is capable of being exercised for the benefit of both calculation, he was wrong to have included delay
the contractor and principal. costs for which extensions of time have not been
The Court further determined that the power to extend granted and for which there was no entitlement to an
time survived the termination of the contact. The Court extension under cl 35.5 or cl 35.5 A.
reasoned that as the liquidated damages mechanism His Honour (in obiter) commented that whether the
expressly operates after the termination of a contract, Superintendent had refused or postponed consideration
there must be a date of practical completion after of the extensions of time, the adjudicator was entitled to
termination for that clause to operate. Accordingly, the include delay costs if the Contractor was entitled to
Court found that the superintendents power is not lost those extensions.
on termination, even if the claim for exercise of the
power to extend notwithstanding non-compliance had Accordingly, the obligation to exercise its discretion for
not been made until after termination [at 80]. the benefit of the Contractor is absolute. Should a
contract not be expressly amended to remove the
The decision in Peninsula Balmain gave rise to the discretion of the Superintendant (in the Contractors
principle that a superintendent, who is given an favour) the position in Peninsula Balmain may prevail.
unqualified power to extend time, should (if required to
act reasonably or in good faith) do so for the Principals may also consider amending any contractual
contractors benefit even where the contractor has not provisions which may entitle a contractor to delay
made a claim or has not otherwise strictly complied damages (i.e. GC 36 of AS 2124-1992) to ensure the
with the requirements of a contract. This principle has entitlement only arises when the contractual
been subsequently followed in Kane Construction Pty requirements have been complied with.
6
Ltd v Sopov and 620 Collins Street v Abigroup Pty
7
Limited (No 2) .
Accordingly, a superintendent may be required to grant
an extension of time where it is fair and reasonable to
do so, even though a contractor has not complied with
the notice and time requirements for extension of time
5
[2002] NSWCA 211
6
[2005] VSC 237
7 8
[2006] VSC 491 [2008] QSC 58

Carter Newell 2012 www.carternewell.com


somewhat more difficult to conclude that a reference
A Contractors ability to issue payment claims
date occurs after termination. There is no longer a
upon termination contract under which there might be a reference date.
For the past eight years, the general consensus across all Ultimately, Justice Lyons found that it was [at 58]
Australian jurisdictions was that contractors were not
prevented from issuing payment claims under security of inconsistent with the statutory language to conclude that
payments legislation following termination of the contract a statutory right to a final payment accrues
regulating the works. independently of a reference date; or that a reference
date occurs after termination, at least where that would
This position was based on the New South Wales case of be contrary to the effect of the contract.
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport,9
where the Court of Appeal held that the NSW security of Queensland is the only jurisdiction which uses the expression
payments legislation (BCISPA) does not provide that under a construction contract. The definition of reference
reference dates cease on termination of a contract or date in Victoria, South Australia and Tasmania is similar to
cessation of work, unless the contract provides otherwise. the New South Wales legislation,12while the Australian Capital
BCISPA defines reference dates in relation to a Territory legislation uses the expression for a construction
construction contract 10Until recently, this interpretation of contract. 13 A reference date is not defined in Northern
reference dates was generally accepted in Queensland. Territory and Western Australian legislation.

The Supreme Court of Queensland in Walton Construction Therefore, in Queensland alone a payment claim issued after
(Qld) Pty Ltd v Corrosion Control Technology Pty Ltd & Ors termination of an Australian Standard form contract may be
11
held that the termination of a construction contract invalid for want of a reference date. If you want to preserve
deprives the claimant its entitlement to make a payment your right to issue payment claims following any termination
claim under the Queensland security of payments of a construction contract, you should amend any Australian
legislation (BCIP Act) as the termination prevents the Standard form contract to ensure the contract expressly
reference dates from occurring. provides for the issuing of payment claims following
termination.
Justice Lyons noted that the subcontract contained a
default clause common in Australian Standard form Authors
contracts which provides that the parties rights will be the
same as they would be at common law had the defaulting
party repudiated the subcontract. Accrued rights survive David Rodighiero
termination of a contract for repudiatory conduct, such as Partner
those arising under an arbitration or liquidated damages
clause. However, Justice Lyons said that the existence of T (07) 3000 8376
contractual terms which specifically survive termination E djr@carternewell.com
demonstrates that contractual terms typically do not operate
after termination. Accordingly, Justice Lyons found that the
effect of clause 44.10 of the contract was that reference
dates ceased to accrue with the exercise of a right to
terminate under clause 44 of the contract. Marnie Carroll
Solicitor
Walton was further distinguished from its NSW counterpart,
Brodyn on the basis that the wording in the relevant Acts
differed. Justice Lyons found that while the NSW Act T (07) 3000 8484
defines a reference date in relation to a construction E mcarroll@carternewell.com
contract:
the use of the expression under a construction
contract found in the Queensland definition makes it
12
Building and Construction Industry Security of Payment Act 2002
(Victoria) section 9(2); Building and Construction Security of
9
[2004] NSWCA394 Payment Act 2009 (SA) section 4; Building and Construction
10
Building and Construction Industry Security of Payment Act 1999 Industry Security of Payment Act2009 (TAS) section 4.
13
(NSW) section 8(2) Building and Construction Industry Security Act 2009 (ACT)
11
[2011] QSC 67 section 10(30.

You might also like