Professional Documents
Culture Documents
Project Zephyr
Progress Report 9
Vallabi Vallaban
Kelly Crocker
Noah Wong
March 9, 2017
Objective:
The time period was spent beginning the construction of the foam blimp frame as well as writing
Previous Objective:
This time was spent determining the Mylar and valve configurations and testing the solar panels.
PROJECT ZEPHYR PROGRESS REPORT 9 2
During this time the team received the order of foam board that had been previously
placed. One 8 ft by 4 ft board was cut into four more manageable sections of 2ft by 4ft. The other
was left untouched so that it could be returned if not needed for construction. The board is .75 in
thick.
For reasons of simplicity, the dimensions of the blimp were changed in relation to both
width and height; both are now 1.65 m. The length will stay the same at 2 m. This decision was
made because it would make all the rib sections of the blimp uniform and greatly simplify the
process of constructing the framework. The uniformity of the sections is due to the fact that the
cross section of the blimp would then be a circle instead of an oval or ellipsoid shape. With the
different dimensions, the volume of the blimp increases from 2.58 m3 to 2.85 m3, an increase and
The dimensions of each rib section can be broken down into six constituent parts. There
is one outer strut that is roughly 14 inches in length. This strut will be attached at an angle to two
pieces at either end of equal length (roughly 24 inches) according to the diagram shown in the
figure below. There will be one support piece (33 inches long) attached directly in the middle of
the outer strut for stability and bonded along with the outer angular pieces, to the center beam.
PROJECT ZEPHYR PROGRESS REPORT 9 3
Figure 1: The diagram of the rib section of the blimp shows the dimensions required for each
constituent part as well as the number of each part needed to construct all eight rib sections.
Over the course of the past week, the team has cut eight 12-inch by 1-inch sections,
thirty-two 24-inch by 1-inch sections, and eight 33-inch by 1-inch sections from the 4 ft by 2 ft
sections of foam board to make up the eight necessary rib sections. This is shown in the below
Figure 2.
PROJECT ZEPHYR PROGRESS REPORT 9 4
Figure 2: The sections labeled A1-A8 are 14-inch sections meant to be the outer ridges while the
sections labeled C1-C32 are the 24-inch sections that will constitute the angular sections of the
ridge construction.
In order for the center supports to connect with the outer ridges, they will need to be
epoxyed together. In an effort to increase the surface area that the epocy comes in contact with, a
shallow, rectangular hole was dug out in the center of each outer ridge section in the dimensions
of the end of each support strut, namely .75 in by 1 in. Epoxy will be applied to both surfaces
and joined in this manner in an effort to increase force necessary to separate the pieces by
Figure 3: The hole cut into the underside of the outer ridge piece will allow for an increased
bonding area and, therefore, increase the integrity of the structure as well.
Also during this time, a code meant to fly the blimp was started. At present, it can turn
one motor off and on while keeping another on constantly. This function is mainly meant to turn
the blimp in a particular direction depending on the motor being manipulated. It could also,
The third major undertaking of these past two weeks has been the center beam for the
structural system of the blimp. The beam will be composed of two 19-inch sections, two 7-inch
sections, two 12-inch sections, and ten 24-inch sections laid out as depicted in Figure 4. Each
section was cut out and arranged as shown in Figure 5, but the next step will be to epoxy them
together into the 2 m long beam needed to support the blimp structure. Then there can be holes,
similar to the ones cut into the outer ridges, placed in the center of each beam as a place for the
Figure 4: The center beam will be made up of 16 different sections of foam board joined together
Figure 5: The pieces of the center beam, laid out here, will need to be epoxied together during
In order to let the next few steps of the construction process be viable, the team needed to
test the epoxy they purchased for the foam. Through this process, they discovered that the epoxy
needs to be applied to both surfaces and let sit for 20-30 minutes before it can be joined to itself
or another surface. This, as well as the temperature constraint of above 68 degrees, greatly limits
the number of days the team will have to complete the epoxy process, especially when coupled
with the fact that it is a process best done out of doors. Another potential problem is the
necessary application of pressure onto the two foam pieces while they bond. Because the support
beam is being joined perpendicularly to the outer ridge, the team will need to consider how they
In testing the epoxy, the team bonded two scrap pieces of foam about 5 inches in length
flush to each other. After applying the epoxy in a thin coat to each piece of foam and observing
the necessary 20 minutes for the epoxy to be ready to bond, the team placed the two foam pieces
flush against each other and placed a text book on top of them to exert pressure. They were left
this way for the rest of the class (about 30 minutes). When examined at the end of class, the
result was found to be very satisfactory. Even without a long period of time to cure, the strength
of the expxy was great and one person alone could not separate the two pieces.
PROJECT ZEPHYR PROGRESS REPORT 9 7
Works Cited