Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

(60 )
(Vapor-compression Cycle)
2 2547 (Absorption Cycle)
(60 )
(60 )




Member ASHRAE
.
chakrapan_pw@eec.co.th
2
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

HVAC&R for mankind HVAC&R FOR MANKIND


Comfort / /
Productivity /

/
/

HVAC&R : Heating, Ventilating, Air-


conditioning & Refrigerating

3 4
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

FUTURE Professional Links


Comfort
www.coe.or.th
Productivity /
www.eit.or.th
Clean Environment
/ www.acat.or.th
////
www.mect.or.th
ASHRAE : American Society of Heating, Refrigerating, and Air-
Refrigeration : conditioning Engineers
/ www.ashrae.org
www.ashraethailand.org [Thailand Chapter]
5 6
2 2547 2 2547

1
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

Condenser

Expansion
Compressor
Valve

Evaporator

7 8
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand




Pressure

2
3
Condenser
Expansion
Compressor
Valve
4
Evaporator 1

Enthalpy
P-H Diagram
9 10
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand



Pressure

Pressure

Enthalpy Enthalpy
P-H Diagram P-H Diagram
11 12
2 2547 2 2547

2
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


(Suction Line) Saturated Suction Temperature = 40-45 F
- Friction loss < 2 F Equivalent

- Velocity = 900-4,000 fpm

Condenser
Pressure
- Low side = 60-70 psi (Drain)
- High side = 260-280 psi - Slope 1:100
Evaporator



(Liquid Line)
- Friction loss < 2 F Equivalent
- Velocity < 300 fpm
13
Condensing Temperature = 125 F 14
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Split type
Air-cooled Packaged Unit
Water-cooled Packaged Unit
Air-cooled Chiller
Water-cooled Chilled

15 16
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

17 18
2 2547 2 2547

3
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

19 20
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

21 22
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

23 24
2 2547 2 2547

4
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

25 26
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

FCU

27 28
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

CDU
CFC
R-11, R-12, R-113, R-114, R-115 : 1996
HCFC
R-22 : 2020
R-123 : 2030
HFC
R-134a :

29 30
2 2547 2 2547

5
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


The Miracle of Fire

Source: http://www.dupont.com/suva/na/usa/literature/prodsel 31 32
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

33 34
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

Absorption
Machine




Cooling Preheat
Tower Boiler Water

35 36
2 2547 2 2547

6
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


1. When maintained at high vacuum, water will boil and flash cool itself 2. Consentrated Lithium Bromide solution has affinity towards water. The
solution absorbs vaporised refrigerant water

37 38
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


3. As Lithium Bromide becomes dilute it loses its capacity to absorb water 4. This heating causes the solution to release the absorbed refrigerant in the
vapor. It thus needs to be reconcentrated using a heat source form of vapor. This vapor is cooled in a separate chamber to become liquid
refrigerant

39 40
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


5. The basic operation cycle of the single effect vapor
absorption chiller

41 42
2 2547 2 2547

7
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

43 44
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

45 46
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

47 48
2 2547 2 2547

8
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Absorption Chiller Gas Turbine
Natural Gas
Turbine Inlet
Air Cooling

Plant Load

DC & Cogen Plant Cogeneration



Cooling Electrical Power

80%

(Gas Turbine)
Absorption Chiller 49 50
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

12 C



7C 24C
12 C AHU
Cooling Tower 12 C

37 C


32 C 24C

AHU

Condenser Pump Chiller Chilled Water Pump 51 52


2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand




End Suction
Horizontal Split Case

53 54
2 2547 2 2547

9
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


(Cooling Tower) (Cooling Tower)
Wet bulb temperature

Temperature 83/90/100 F

100 F
Range =100-90
Water (Temp.) =10 F
90 F
Approach Temp
Air (Wet-bulb Temp.)
83 F =90-83
=7 F

Entering Leaving
Counter Flow Cross Flow 55 56
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Counter Flow : 3%
Cross Flow : 2%


: Fan Coil Unit (FCU)
Film Fill : Air Handling Unit (AHU)
: Built-up AHU

Splash Bar Natural Draft 57 58


2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


12-14 C
3-6 0.60 m
12-14 FPI (Fin per Inch) 80% Arrestance
500 fpm
25,000 cfm
Trap
50 mm Total Static Pressure

59 60
2 2547 2 2547

10
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

CDU


Condensing Unit (CDU)

FCU 10

(Vertical Shaft)
(Equipment Access)

61 62
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


(Fancoil Unit)
Forward Curve
Backward Curve
Axial
Propeller

63 64
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

65 66
2 2547 2 2547

11
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Horizontal Split
Case
End Suction

67 68
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

Combined Heat and Power (CHP) ROPPONGI HILL REDEVELOPMENT


CENTRAL TOKYO

CHP Plant

69 70
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

KLCC Twin Tower /Putra Jaya /Cyber Jaya /KLIA


/Petronas U - Malaysia

71 72
2 2547 2 2547

12
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand



=







Mean Radiant
Temperature



24 C/ 55%rh


73 74
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand



CLTD/CFL
Transfer Function Method (TFM)
Heat Balance Method (HB)

Radiant Time Series Method (RTS)

75 76
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Time delay effect
People Direct Solar
Lighting Diffuse Solar
Electric Motor Conductive Heat Gain
Electrical Equipment

77 78
2 2547 2 2547

13
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


: www.tmd.go.th
ASHRAE Fundamental Handbook

.
95 Fdb/83 Fwb 35 Cdb/28.3 Cwb

79 80
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


: = 10 W/m2

500-800 BTU/pers
: = 20 W/m2
, , ,
81 82
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand



Description W/sqm BTU/sqm Percentage
Building Envelop 60 205 38
Lighting 20 68 13


Equipment 10 34 6
People 20 68 13
Outdoor Air 50 171 31

Indoor Environment
Total 160 546 100

Building Envelop
Lighting
Equipment
People
Outdoor Air

83 84
2 2547 2 2547

14
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand


Comfort Zone



24 C/55%rh

85 86
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

87 88
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand




VAV becomes
popular

Ventilation

Use of mechanical
Comfort Health ventilation begin

89 90
2 2547 2 2547

15
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

91 92
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

93 94
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

95 96
2 2547 2 2547

16
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

97 98
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

99 100
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

= 10 ..
= 20,000
= 2,000 ..
= 24,000 ..

= 500 ..

/ = 48

101 102
2 2547 2 2547

17
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

103 104
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

105 106
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

107 108
2 2547 2 2547

18
Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

109 110
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand

111 112
2 2547 2 2547

Air-conditioning Engineering Association of Thailand Air-conditioning Engineering Association of Thailand



www.thaihvac.com : HVAC Knowledge
www.eit.or.th : Engineering Institute of Thailand
www.acat.or.th : Air-conditioning Engineering
Association of Thailnad
www.ashraethailand.org : ASHRAE Thailand
Chapter
113 114
2 2547 2 2547

19

You might also like