SUSTENTO DE FLETE TERRESTRE Y FLETE RURAL ALCANTARILLADO Y UBS C.P.

MACO

MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE E INSTALACIN DEL SERVICIO DE DESAGE EN EL CENTRO POBLADO DE MACO, DISTRITO DE TAPO TARMA
OBRA:
JUNN

1. CALCULO DE FLETE TERRESTRE

A-POR PESO

MATERIALES UNIDAD AFECTO IGV PESO.UNIT. PESO.TOTAL


CEMENTO BL. 8,316.00 42.50 353,430.00
FIERRO, CLAV. ETC KG 12,617.00 1.00 12,617.00
MADERA P2 14,465.00 1.50 21,697.50
PERNOS UN 10,000.00 0.10 1,000.00
LADRILLO UN 21,133.00 1.20 25,359.60
YESO BL 22.00 25.00 550.00
PINTURA, IMPERM GAL 657.00 4.50 2,956.50
TRIPLAY KG 15.78 10.00 157.80
CALAMINA KG 166.00 10.00 1,660.00
VALVULAS UN 72.00 8.00 576.00
ACCESORIOS TUB. UN 1,200.00 0.60 720.00
OTROS KG 500.00 1.00 500.00
UBS UN 22.00 50.00 1,100.00
PESO TOTAL (kg) 422,324.40

B-POR VOLUMEN

EN AGREGADOS Y MADERA
DESCRIPC. UNIDAD AFECTOS IGV SIN IGV
ARENA M3 2,797.00
PIEDRA 1/2 Y GRAVA M3 994.00
HORMIGN M3 22.00
OTROS M3 2,060.00
VOLUMEN TOTAL 3,817.86 100470.0421 BOLSAS 42.5
CAPACIDAD DEL CAMION (M3) 10.00
NUMERO DE VIAJES 381.79
REDONDEO 381.79

EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub de 1/2-3/4 5,040.00 U 453.00 90.60 0.02
Tub, 1" 3,360.00 U 0.00 0.00 0.00
Tub,1 1/2" 1,690.00 U 0.00 0.00 0.00
Tub 1/2" a 2:" 994.00 U 170.00 34.00 0.03
Tub, 3" 470.00 U 0.00 0.00 0.00
Tub 4": 259.00 U 861.00 172.20 0.66
Tub 6:" U-PVC 110.00 U 6,720.00 1,344.00 12.22
Tub 8" U-PVC 65.00 U 918.00 153.00 2.35
NUMERO TOTAL DE VIAJES 15.29
REDONDEO 0.00
TUBERIA EN VOLUMEN 0

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 6.00
COSTO POR VIAJE S/. 1,140.00
CAPACIDAD DEL CAMION (KG) 6,000.00
FLETE POR KG 0.19

SIN IGV
FLETE POR PESO 80,241.64
FLETE POR VOLUMEN
AGREGADOS
TUBERIA 17,429.54
COSTO TOTAL FLETE TERR. (S/.) 97,671.18
2- FLETE RURAL CON PEON

La tubera ser transportada por peones

Costos de transporte por viaje


Peon S/. 7.00

Cantidad Unidades de Capacidad de Nmero de Incidencia (%) Flete no


Carga Carga Viajes Afecto a IGV
Peso total tubera de agua 296.80 2 2 148.40 30% 623.28
Peso total tubera desague PVC 1,273.00 2 2 636.50 30% 2,673.30
Numero bolsas de cemento 8,316.00 1 2 4,158.00 40% 8,316.00
Agregados en bolsas de cemento (42.5 kg) 100,470.04 1 2 50,235.02 40% 100,470.04
Traslado de UBS 61.00 1 0.15 146.67 100% 1,026.67
COSTO TOTAL DEL FLETE RURAL EN ACEMILA - PEON S/. 113,109.29

RESUMEN FLETE TOTAL

SIN IGV
FLETE TERRESTRE 97,671
FLETE RURAL CON PEON 113,109
FLETES TOTALES S/. 210,780