RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH

GRAND SUMMARY

ITEM DECRIPTION AMOUNT

1 PRELIMINARIES 517,500.00

2 EARTH WORKS 136,116.00

3 PILE WORKS 839,542.00

4 SUB STRUCTURE WORKS 527,460.00

5 SUPER STRUCTURE WORKS 2,536,500.00

6 BLOCK WORKS 811,266.00

7 ROOFING WORKS 662,973.20

8 CARPENTRY & JOINERY WORKS 721,682.50

9 METAL WORKS 1,562,487.50

10 FINISHES 1,859,010.20

11 PAINTING 254,317.80

12 EXTERNAL WORKS 242,760.00

13 LIFTS 427,000.00

14 PLUMBING AND DRINAGE & SANITARY FIXTURES 611,240.00

15 ELECTRICAL AND FIRE ALARM SYSTEM 2,235,209.71

16 AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM 1,374,000.00

17 FIRE FIGHTING SYSTEM 514,500.00

TOTAL 15,833,564.91

18 PROVISIONAL SUM 955,254.40

GRAND TOTAL 16,788,819.31


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 01-PRELIMINARIES

ITEM DECRIPTION QTY UNIT RATE AMOUNT

GENERAL PRELIMINARIES
SETTING UP THE SITE
1 Site Setting up & Cleaning away 1 Item 3,000.00 3,000.00
2 Men and Instruments for Engineer 1 Item 5,000.00 5,000.00
3 Soil Investigation Report 1 Item By Client
4 Statutory Approval 1 Item By Client
5 Fees of Building Permit 1 Item By Client

USE AND PROTECTION OF SITE


6 Protection of Site 1 Item 10,000.00 10,000.00
7 Cleaning and Maintenance of Site 1 Item 5,000.00 5,000.00
8 Temporary covering & Barricade ect. 1 Item 2,000.00 2,000.00
9 Deodorizing of latrines after completion 1 Item 1,500.00 1,500.00

SITE OFFICE FOR THE ENGINEER


10 Site office for the Engineer 1 Item 20,000.00 20,000.00

PROTECTION OF THE WORKS


11 Covering up and Protection of Works 1 Item 3,500.00 3,500.00
12 Protection of finished work including Subcontractors 1 Item 5,000.00 5,000.00
13 Providing and Maintaining warning signs,Barricades ect. 1 Item 2,500.00 2,500.00

TELEPHONE
14 Telephone Installation, Bills and Removal Charges 1 Item 12,000.00 12,000.00

TOTAL CARRIED TO COLLECTION Page-01 Dhs 69,500.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 01-PRELIMINARIES

ITEM DECRIPTION QTY UNIT RATE AMOUNT

INSURANCE
15 Third party Insurance 1 Item 5,000.00 5,000.00
16 Insurance for work 1 Item 8,000.00 8,000.00
17 Workmen's accident insurance 1 Item 4,000.00 4,000.00

TEMPORARY WORKS
18 Temporary works necessary for the erection of works 1 Item 25,000.00 25,000.00
SAMPLE, TESTS ETC.
19 Sampling and Testing of Materials 1 Item 7,000.00 7,000.00
WATER FOR THE WORKS
20 Water,installing & removal of temporary Pipe works 1 Item 30,000.00 30,000.00
ELECTRICAL FOR THE WORKS
21 Installing and Removal of Temporary Electrical Works 1 Item 10,000.00 10,000.00
22 Diesel Consumption 1 Item 50,000.00 50,000.00
SIGNAGE
23 Site Sign Board 3000 x 3000 mm 1 Item 8,000.00 8,000.00
CLEARING AWAY AT COMPLETION
24 Clearing of Rabbish at the site at Complection 1 Item 5,000.00 5,000.00

TOTAL CARRIED TO COLLECTION Page-02 Dhs 152,000.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 01-PRELIMINARIES

ITEM DECRIPTION QTY UNIT RATE AMOUNT

PHOTOGRAPHS

25 Preparation & Submission of Photo graphics Reports 1 Item 3,000.00 3,000.00

CLEANING AT COMPLECTION

26 Clearing the Building ready for Occupation 1 Item 3,000.00 3,000.00

27 CRANAGE- Loading and Unloading 1 Item 60,000.00 60,000.00

28 Project Engineers and Staf 15 Month 15,000.00 225,000.00

29 As-Built Drawing 1 Item 5,000.00 5,000.00

TOTAL CARRIED TO COLLECTION Page-03 Dhs 296,000.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 01-PRELIMINARIES

ITEM DECRIPTION QTY UNIT RATE AMOUNT

COLLECTION

TOTAL FROM PAGE NO.01 Dhs. 69,500.00

TOTAL FROM PAGE NO.02 Dhs. 152,000.00

TOTAL FROM PAGE NO.03 Dhs. 296,000.00

BILL NO. 01- PRELIMINARIES TOTAL CARRIED TO


Page-04 Dhs 517,500.00
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 02-EARTH WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

A Site Clearance

Preparation of site for construction work including


leveling, compaction,as necessary 1.0 Item 3600.00 3600.00
B Shoring

Contractor designed permanent shoring/earth retaining


system complete as detailed in the structural drawing
and in complete accordance with the specification
complete and FM approval including concrete panels Item Excluded
C Dewatering

Dewatering as required (The contractor will study the


soil investigation report and determain the scope and
extent of dewartering required) Item Excluded
D Excavation and Earthwork:
1 Excavation around Pile depth 2.5m average 2040.0 m3 30.00 61200.00

2
Disposal of unsuitable and surplus excavated material 470.0 m3 18.00 8460.00
Backfilling around pile cap and above with selected
3 excavated material 1570.0 m3 24.00 37680.00
4 Compact all surface in the bottom of pile caps 816.0 m3
6.00 4896.00
Filling with selected material in layers including
5 compaction (primary sand ) below floor slab 180.0 m3 36.00 6480.00
1000 Gauge Polythene Sheet under pile caps and
6 Ground slab as Specification 1100.0 m2 6.00 6600.00
F Termite Treatment:

Anti termite treatment to horizontal & vertical surface 1.0 Item 7200.00 7200.00

BILL No.02-EARTH WORKS TOTAL CARRIED TO SUMMARY Page-01 Dhs


136116.00
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 03-PILE WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

PILE WORKS

1 Mobilization and Demobilization 1.0 LS 33,000.00 33,000.00

2 Construction of Preliminary test pile and load test on pile


up to load od 2.0Xworking load- Pile Dia 600mm 1.0 No. 41,800.00 41,800.00

Drilling of piles from working platform at an elev.of 0.5m


3 up to the pile toe elevation. Fabrication & installation of
reinforcement cage. Supply and casting of concrete. Pile
Dia 600mm Toe-15.0m 84.0 No. 7,865.00 660,660.00

4 Static Load test on working piles up to 1.5xWorking


load.-Pile Dia 600mm 2.0 No. 27,500.00 55,000.00

5
100% Integrity testing on pile 84.0 No. 60.50 5,082.00

6 Boulder's Works 1.0 Item 44,000.00 44,000.00

BILL No.03-PILE WORKS TOTAL CARRIED TO SUMMARY Page-01 Dhs. 839,542.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 04-SUB-STRUCTURE WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

A Plain Cement Concrete as Detailed in the Drawings

1 Binding under all Substructure including Pile cap,STB,Tie


Beams,Solid Block and under ground water tank 50.0 m3 480.00 24,000.00

Reinforced in situ concrete 40N/mm2 Sulphate


B Resistant Cement as detailed on drawings and
specifications including all formworks and
reinforcement to:

1 Pile Caps bottom Level -240 cm 167 m3 1,140.00 190,380.00


2 STB 40.0 m3
1,140.00 45,600.00
3 Neck Column 13.0 m3 1,440.00 18,720.00
4 Shear Wall (Stair & Lift wall) 19.0 m3 1,440.00 27,360.00
5 Tie Beam 26.0 m3 1,320.00 34,320.00

6 120mm thick Slab on Grade with BRC Mesh A142 502.0 m2


90.00 45,180.00

7 Concrete Work for Septic tank and Soak away 1 Item N.A
Under Ground Water Tank, Size (33,750GL), 30cm wall
8 and slab thick 91.0 m3 1,320.00 120,120.00

9 Trenches 3.0 m3 1,260.00 3,780.00

10 Connection with Tanqia line 1 Item 6,000.00 6,000.00

11 Construction and Expansion joints. 1 Item 12,000.00 12,000.00


Special concrete additives waterproof for all Substructure
12 works Not Required
BILL No.04-SUB-STRUCTURE WORKS TOTAL CARRIED TO
Page-01 Dhs. 527,460.00
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 05-SUPER-STRUCTURE WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Reinforced in suit concrete 60 N/mm2 as deitailed


A on drawings and specifications including all
formworks ans reinforcement to:
1 Column 165.0 m3 1,260.00 207,900.00
2 Lifts wall and staircases wall 360.0 m3
1,200.00 432,000.00
3 Beams 82.0 m3 1,320.00 108,240.00

4 Solid Slab 25cm thick 163.0 m3 1,140.00 185,820.00


5 Solid Slab 26cm thick 1190.0 m3 1,140.00 1,356,600.00
6 Entrance step & ramp 4.0 m3
1,200.00 4,800.00
7 Staircase & Steps 70.0 m3
1,200.00 84,000.00
8 Parapets 63.0 m3 1,320.00 83,160.00

9 Lintel 1.0 LS 24,000.00 24,000.00

10 Transformer trench, manholed and AC unite foundation 35.0 m3 1,320.00 46,200.00

11 Up stand for balconies 20cmx20cm 3.5 m3


1,080.00 3,780.00

BILL No.04-SUPER-STRUCTURE WORKS TOTAL CARRIED


Page-01 Dhs. 2,536,500.00
TO SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 06-BLOCK WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Solid Concrete Block work bedded, jointed and


A pointed in cement and sand mortar including
anchor, metal laths, wall ties, ect complete
1 200mm wall 655.0 m2 84.00 55,020.00

External Hollow Thermal Concrete Block work form


B
Fujairah Factory, bedded,jointed and pointed in
cement and sand mortar as per Architect's
requirement including anchor (Fujairah Factory)
1 200mm wall 2891.0 m2 96.00 277,536.00

Supply and Construct for Hollow blocks


C bedded,jointed and pointed in cement and sand
mortar including anchor,metal laths, wall ties, ect.
Complete
1 100mm thich Hollow block for internal wall 4380.0 m2 60.00 262,800.00
2 200mm thich Hollow block for internal wall 2205.0 m2 72.00 158,760.00
3 150mm thich Hollow block for internal wall 275.0 m2 66.00 18,150.00

D DCP 200mm wide 1 Item 12,000.00 12,000.00

Galvanized fixtures and anchors between concrete


E members and masonary work 1 Item 9,000.00 9,000.00

F Sealant between wall and slab 1 Item 18,000.00 18,000.00

BILL No.06-BLOCK WORKS TOTAL CARRIED TO SUMMARY Page-01 Dhs. 811,266.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 07-ROOFING SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

THEARMAL & MOISTURE PROTECTION

Material: Modified Waterproofing bitumen membrane


Brand: Dermabit, Rhoflex polybit or equv
Thickness: 4mm. Thick

Waterproofing to Substructure: Allow for providing


A wateproofing and protection board on side to concrete
with contact to soil as detailed on drawings & as
specified

Prepared and primer one coat of buituminous paint and


1 two layer 4mm. Thick, SBS waterproofing memberane to
horizontal and vertical side of raft, neck columns, solid
block, tie beam , under ground water tank and all
concrete contact with soil from outside.
i Vertical and Horizontal 1757.0 m2 72.00 126,504.00

2 Polythene Sheet to all horizontal concrete sides contact


with the soil 900.0 m2 6.00 5,400.00

4mm thick protection board to all vertical concrete sides


3 contact with the soil 860.0 m2 24.00 20,640.00

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 152,544.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 07-ROOFING SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

B Waterproofing system to wet area:

Clean down concrete or block work surface and


apply one components waterproofing membarane
as specified:

To Floors, toilets, kitchens, shafts, water meter


room, garbage room and the like including
carrying up walls as specified.
1 3-5 cm. Screed 1050.0 m2 29.45 30,922.50

Supply and apply of coat of waterproofing liquid


2 49.09 51,544.50
membrane. 1050.0 m2
3 Vertical (Skirting)150mm 1710.0 m 26.40 45,144.00

4 1000 Gauge Polytheen Sheet as Specified 1050.0 m2 6.00 6,300.00

C Waterproofing to full area for Ground Floor


Prepare and apply two coats of cold buituminious paint
1 600.0 m2 18.00 10,800.00
for all ground ffloor slab.

2 1000 Gauge Polytheen Sheet for all ground floor slab 600.0 m2 6.00 3,600.00

Supply and apply of two coat of waterproofing cold


D bituminous paint for backside of cladding at the
elevation 1250.0 m2 20.00 25,000.00

TOTAL CARRIED TO COLLECTION Page-02 Dhs. 173,311.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 07-ROOFING SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

E Waterproofing system to Roof:

1 50mm. Thickness foam concrete, laid to fall and cross 37.80 24,570.00
falls 650.0 m2

Supply and apply of one coat of primer and two layer of


2 4mm. Thick water proofing membrane (Dermabit or 650.0 60.48 39,312.00
equivalent) "APP" modified bitumen reinforced with non
Woven polyester torch applied m2
3 One coat of rubberized buitmen 650.0 m2 14.73 9,574.50

4 Supply and lay 3.2mm thick protection board 650.0 m2 17.67 11,485.50

5 50mm Thick Thermal insulation layer extruded 25.92 16,848.00


polystyrene 650.0 m2
6 Polythene Sheet to roof 650.0 m2 5.40 3,510.00

7 Polyester filter layer 100 G/M 650.0 m2 5.40 3,510.00

8 Skiriting membrane turned up and tackled into preformed


groove and sealed, protected with aluminium finished
torch on membrane and aluminium flashing 50mm wide 290.0 m 64.80 18,792.00

9 Gravel fill edging 290.0 m 44.18 12,812.20


10 Powder coated Aluminium patent copying 290.0 m2 129.60 37,584.00

10cm Aluminium flashing with mastic sealant to roof


11 parapet 290.0 lm 108.00 31,320.00
Allow for all working around cable penetrations Service
12 duct and the like 1 Item 37,800.00 37,800.00

13 Allow for all work at rainwater outlet 1 Item 27,000.00 27,000.00

F Roofing tiles

200x200x20mm Precast terrazzo tiles for main roof and m2


1 roof top 64.80

2 Roofing tiles skiting only for main roof top m2 27.00

3 Expansion joint 1 LS 21,600.00 21,600.00

TOTAL CARRIED TO COLLECTION Page-03 Dhs. 295,718.20


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 07-ROOFING SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

G Waterproofing to Water Tank 33,750 GL capacity:

1 144.00 38,160.00
4mm Thick GRP Lining for Water Tank Floors and Walls 265.0 m2

2 Water stopper for Water Tank 60.0 m 54.00 3,240.00

TOTAL CARRIED TO COLLECTION Page-04 Dhs. 41,400.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 07-ROOFING SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Collection

TOTAL FROM PAGE NO.01 Dhs. 152,544.00

TOTAL FROM PAGE NO.02 Dhs. 173,311.00

TOTAL FROM PAGE NO.03 Dhs. 295,718.20

TOTAL FROM PAGE NO.04 Dhs. 41,400.00

BILL No.07-ROOFING SYSTEM TOTAL CARRIED TO


Page-05 Dhs. 662,973.20
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 08-CARPENTRY & JOINERY WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

A CARPENTAY WORKS

DOOR SETS

Supply and fix of semi solid meraniti flush door with


Africa teak wood frame and architrave with beach
veneer for booth side with spray polyurethane clear
paint, including marine ply wood sub frame, door
shutter, door frame, Exclude ironmongery

Note: Suppy and fix of all wooden fire rated doors as


per civil defense requirement including architrave, sub
frame, frame ans shutter for doors is provisional sum
as the following

D1-for flat entrence door for typical floors and watchman


room, office in Ground floor and staircases doors in all floors.
1 30.0 P.S 2,000.00 60,000.00
With 90 min. fire rate paint size 110x220cm (supply & fix
P.S Dhs.2000/ each door)

D1a- for Staircase door for all typical floors and ground floor
2 with 120 min. fire rate paint size 110x220cm (supply & fix 16.0 P.S 2,000.00 32,000.00
P.S Dhs.2000/ each door)

D2- for Kitchen in typical floors and etisalate room in ground


3 floors with 90 min. fire rate paint size 110x220cm (supply 56.0 P.S 1,200.00 67,200.00
& fix P.S Dhs.2000/ each door)

D2- for Bed room, and Halls in typical floors. size


4 113.0 P.S 1,200.00 135,600.00
110x220cm (supply & fix P.S Dhs.2000/ each door)

D3- for O.T.S. door in Ground floor and bathroom in all


5 floors.size 800x220cm (supply & fix P.S Dhs.2000/ each 115.0 P.S 1,200.00 138,000.00
door)

D5- for small flat entrance door for all typical floors. With 120
min. fire rate paint size 110x220cm (supply & fix P.S P.S 2,000.00 56,000.00
Dhs.2000/ each door)
6 28.0

Supply and fix of ironmongery.(lock, cylinder, door, stoper,


B 358.0 nr(P.S) 150.00 53,700.00
hinges ect.)

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 542,500.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 08-CARPENTRY & JOINERY WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Supply and fixing wooden cupoards MDF milamain,


(Supply & Fix P.S Dhs. 750 / LM) for rooms complete
C
including all necessary frames and supports, Fixing
accessories hardware

1 WD1- (Size 1.65 x 2.9m) 28.0 LM (P.S) 1,237.50 34,650.00

2 WD2- (Size 2.4 x 2.9m) 28.0 LM (P.S) 1,800.00 50,400.00

D Add Civil and Builder's Work 1.0 LS 31,377.50 31,377.50

E Add for Attendance & Profit 1.0 LS 62,755.00 62,755.00

TOTAL CARRIED TO COLLECTION Page-02 Dhs. 179,182.50


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 08-CARPENTRY & JOINERY WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Collection

TOTAL FROM PAGE NO.01 Dhs. 542,500.00

TOTAL FROM PAGE NO.02 Dhs. 179,182.50

BILL No 08-CARPENTRY & JOINERY WORKS TOTAL


Page-03 Dhs. 721,682.50
CARRIED TO SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

ALUMINIUM DOOR & WINDOW

Supply and installation of window: frameless units,


double glazed panel, single glased panel, double
skin/sandwich panel, louvered panel all in heavy duty
gauges; super durable aluminium section; support
system,all by speciallist sub- contractor; including
glass and glazing accessories, iron-monger, fire stops,
angles, joints, sealants and fittings & fixtures as
required; including all associated works:
Powder coated Aluminium framed double glass
A
Window
Window W2: Size 65 x 100cm Top hinged window with
1 29.0 nr 467.50 13,557.50
fixed, Location: Typical floor kitchen

2 Window W3: Size70 x 100cm Top hinged window 58.0 nr 495.00 28,710.00

Window W4: Size 190 x 210cm 2 panel sliding window,


3 84.0 nr 2,640.00 221,760.00
Location: Typical floor Bed room & Hall
Window W5: Size 70 x 90cm bottom hinged window,
4 7.0 nr 440.00 3,080.00
Location: Typical floor staircases area
Window W6: Size 170 x 90cm 2 panel sliding window,
5 1.0 nr 1,017.50 1,017.50
Location: Ground floor O.T.S.

B Aluminium curtain Wall with Doors


Exterior glazed curtain wall system Aluminium
section powder coated, with 6mm tempered high
performanance reflective tempered
glass+A12+6mm clear tempered glass, all
complete.

FG1- Aluminium powder coated framed double glass


1 curtain wall with double leaf door, size: 720x350cm 1 nr 18,040.00 18,040.00
Location: Ground floor shop-2
FG1- Aluminium powder coated framed double glass
2 curtain wall with double leaf door, size: 580x350cm nr 29,040.00
Location: Ground floor shop-1&3 2 14,520.00

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 315,205.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

FG3- Aluminium powder coated framed double glass


3 curtain wall with double leaf door, size: 405x350cm 1 nr 10,147.50 10,147.50
Location: Ground floor shop-4

FG4-Aluminium powder coated framed double glass


4 curtain wall with double leaf door : size: 490 x 350cm 1 nr 12,265.00 12,265.00
Location: Ground floor shop -6

FG5-Aluminium powder coated framed double glass


5 curtain wall with 2 no's of single leaf door: size: 705 x 1 nr 17,655.00 17,655.00
350cm,Location: Ground floor shop-5

FX 1-Aluminium powder coated framed double glass


fixed
6 2 nr 11,330.00 22,660.00
curtain wall : size: 490 x 350cm
Location: Ground floor shop -1&3

FX 2-Aluminium powder coated framed double glass


fixed
7 2 nr 6,242.00 12,484.00
curtain wall : size: 270 x 350cm
Location: Ground floor shop -1&3

FX 3-Aluminium powder coated framed double glass


fixed
8 2 nr 96,250.00 192,500.00
curtain wall : size: 600 x 2430cm
Location: Typical floor hall

DG1-Aluminium powder coated framed double glass


9 curtain wall with double leaf door: size: 435 x300cm, 1 nr 9,350.00 9,350.00
Location: Ground floor entrance

D4-Aluminium powder coated framed double glass


curtain
10 28 nr 6,710.00 187,880.00
wall with sliding door: size: 280 x 335cm
Location: Typical floor balcony

W1-Aluminium powder coated framed double glass


11 curtain wall with 7 nos. of top hinged window size: 8 nr 12,182.50 97,460.00
70x 2430cm, Location: Typical floor elevation

W7-Aluminium powder coated framed double glass


12 curtain wall : size: 70x 190cm, Location: Typical floor 28 nr 880.00 24,640.00
staircase

TOTAL CARRIED TO COLLECTION Page-02 Dhs. 587,041.50


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

C Aluminium Louver Doors:

Door units Aluminium louver; including supply and


fixing of ironmongery, anchors Aluminium
threshold to ext. doors; all complete

Door - ALD1: Spray painted: size: 250 x 260cm


1 Aluminium Powder coated framed double leaf hinged 2 nr 3,767.50 7,535.00
louver door

Door - ALD2: Spray painted: size: 150 x 260cm


2 Aluminium Powder coated framed single leaf hinged 1 nr 2,255.00 2,255.00
louver door

Door - ALD4 Spray painted: size: 80 x 215cm


3 Aluminium Powder coated framed single leaf hinged 30 nr 1,017.50 30,525.00
louver door

Door - ALD5: Spray painted: size: 200 x 260cm


4 Aluminium Powder coated framed single leaf hinged 1 nr 3,025.00 3,025.00
Aluminium panel door

D Aluminium Cladding:

4mm thick Aluminium composite panel cladding in


powder coated finish, complete with fixing
accessories, sealant, bracket and necessary
fittings.

Aluminium cladding - for External wall; refer to plan and


1 1019 m2 275.00 280,225.00
elevation.(local made)

Supply and fix of Aluminum Cladding suspended


2
ceiling to celling:

For balcony and building projection and Main Entrance at


a) 195.0 m2 286.00 55,770.00
the first floor

b) For Main Entrance at Ground floor 28 m2 286.00 8,008.00

c) For we Entrance at Ground floor 3 m2 286.00 858.00

TOTAL CARRIED TO COLLECTION Page-03 Dhs. 388,201.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

E Aluminium Handrail

AHR - Aluminium balustrade hand rail location: staircase (


1 2 nr 275.00 550.00
Size: 37 X 1 m).

F Glass Handrail:

GHR - Aluminium railing with glass balustrade hand rail-


1 78 lm 605.00 47,190.00
location: Typical floor balcony ( Size: 2.8 X 1.1 m )

G Other iteams

G.I steel Ladder with Chequered Plate stand every floor


1 6 nr 16,500.00 99,000.00
for O.T.S

2 Aluminium Powder coated ladder for water tank 1 nr 3,300.00 3,300.00

6 mm thick Chequered Plate for trench at substation and


3 1 LS 22,000.00 22,000.00
electrical room.

H Builder's Works 1 LS 100,000.00 100,000.00

TOTAL CARRIED TO COLLECTION Page-04 Dhs. 272,040.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Aluminium Specification:

Aluminium Extrusion: Alloy 6063 T6 Tempered


Exposed Aluminium Extrusion: RAL finish Power
Coated
Non exposed Parts: Mill finish/ GI

Curtain Wall: Heavy Duty Section

Glass works: 6mm temQered high Qerformance


reflective tempered glass + A12+6mm clear annealed
Glass

Doors & windows: Non Thermal break, 105 mm &


45mm series

All Doors/ glass works: Automatic mechanism/ Non fire


-rated.

Iron Mongery : Giesse or Lavaal or equivalent

Cladding: Fire-rated Aluminum panel (Alcobond or


Alucobond or equivalent) having total thickness 4 mm,
including 0.4 mm Aluminium skin both sides

Supports & brackets: Galvanized and fixing detail as


per our method statement

Gaskets & Friction stay: EPDM gaskets & 304 s/s

Protection: Protection tape will be used at the outer


frame only

Wind load for AI profiles: Able to withstand 1.2 KPA


wind load.

Seismic/acoustic resistance: Not considered

Notes:
1) All the glazing to be processed locally i.e. cutting,
double glazing, tempering etc.

2) All glazing are to be facetted. No curved units are


considered

TOTAL CARRIED TO COLLECTION Page-05 Dhs.


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 09-METAL WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Collection

TOTAL FROM PAGE NO.01 Dhs. 315,205.00

TOTAL FROM PAGE NO.02 Dhs. 587,041.50

TOTAL FROM PAGE NO.03 Dhs. 388,201.00

TOTAL FROM PAGE NO.04 Dhs. 272,040.00

TOTAL FROM PAGE NO.05 Dhs. -

BILL NO. 09 - METAL WORK TOTAL CARRIED TO SUMMARY Page-06 Dhs. 1,562,487.50
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

INTERNAL FINISHES

A Floor Finishes

Supply & fixing Granite/Marble bedded on and


1 including cement sand mortar (1:3) cleaning and
polishing upon completing

Granite for Main Entrance, Lobby, Lift Lobby and Outside


a) toilet entry only in ground floor. As shown on floor layout. 75.0 m2 420.00 31,500.00
2 cm. (Rate for supply not more than Dhs. 300/m2)

for ramp Granite - 2 cm. (Rate for supply not more


b) 2.20 m2 480.00 1,056.00
than Dhs. 300/m2)

Tread - 3 cm with Riser -2 cm for the main entrance


c) 16.00 LM 312.00 4,992.00
(Rate for supply not more than Dhs. 200/LM)

Landings floors for two stairs in Ground floor (Rate for


d) 52.0 m2 420.00 21,840.00
supply not more than Dhs. 300/m2)

Tread and Riser for two stairs in Ground floor


e) 57.0 LM 432.00 24,624.00
(Rate for supply not more than Dhs. 200/LM)

Triangle Tread and Riser for two stairs in Ground


f) 7.5 LM 312.00 2,340.00
floor(Rate for supply not more than Dhs. 200/LM)

Tread 30cm- 3 cm thk with Riser -2 cm thk for External


g) door opening in Ground floor 67.0 LM 300.00 20,100.00
(Rate for supply not more than Dhs.200/LM)

Supply & fixing Non-slip Ceramic Granite floor


tiles finishes; laid on and including cement sand
2
mortar (1:3)and pointing with approved coloured
grout:

Location: Shops and shop store and Office floors in


a) Ground Floor (Rate for supply not more than Dhs. 298 m2 114.00 33,972.00
651m2).

Location: Watchman, Garbage room and Pump room in


b) Ground Floor (Rate for supply not more than 55 nr 60.00 3,300.00
Dhs.20/m2).

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 143,724.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

All Main Corridor between flats and All Flats Corridors,


c) Entries and Halls in all typical floors (PC supply rate 1720.0 m2 90.00 154,800.00
Dhs. 45/m2)

All Bed Rooms and balcony floors in all typical floors, (PC
d) 1290.00 m2 78.00 100,620.00
supply rate Dhs. 35/m2) Size 60 X60 cm

Non-slip Ceramic Floor tiles laid on and including


cement sand mortar (1:3) and pointing with
3
approved coloured grout: By RAK Ceramics or
equv.

Location: Office Bath, W.C , in Ground & All Bathrooms


a) and Kitchens in typical floors (PC supply rate Dhs. 900.0 m2 78.00 70,200.00
35/m2)

Location: Watchman Pantry and Bath in Ground floors,


b) 10.0 m2 57.60 576.00
(PC supply rate Dhs. 18/m2)

Mosaic Tiles size 25X25X2.5 cm, laid on and


4 including cement sand mortar (1:3) and pointing
with approved coloured grout

Fire Fighting room/Elec. Room/ Etisalat room/Water room /


a) OTS floors in Ground & typical floors and Machine room in 150.0 m2 66.00 9,900.00
Roof floor, (PC supply rate Dhs. 25/m2)

China Granite tiles, bedded on and including


cement sand mortar (1:3) cleaning and polishing
5
upon completion, selection to engineers approval
for internal staircase for all floor

Tread -2 cm with Riser - 3 cm , (PC supply rate


a) 352.8 LM 156.00 55,036.80
Dhs.80/LM)

Triangle Tread -2 cm with Riser - 3 cm , (PC supply rate


b) 52.6 LM 156.00 8,205.60
Dhs.80 /LM)

Landing ( 30 X 60X 2.5 cm), (PC supply rate Dhs.


c) 55.0 m2 138.00 7,590.00
80/m2)

Staircase Skirting for typical floor ,(PC supply rate


d) 279.4 LM 72.00 20,116.80
Dhs.50/LM)

TOTAL CARRIED TO COLLECTION Page-02 Dhs. 427,045.20


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

B Skirting

Marble/Granite skirting. (PC supply rate Dhs. 60/m)


1
size 15X2 cm

For Main Entrance , Ramp , Main steps, Lobby, Lift Lobby


a) 63.60 LM 84.00 5,342.40
and Outside toilet entry only in ground floor.

b) For Main Corridor between Flats in all Typical floors 255.5 LM 84.00 21,462.00

c) For Landings for two stairs in Ground floor 77.0 m2 84.00 6,468.00

d) For steps in two stairs in Ground floor 38.0 LM 84.00 3,192.00

2 Ceramic Granite Tile Skirting to match Flooring

Size 25 x 10 em. For Fire Fighting room/Elec. Room/


Etisalat room/Water room /OTS floors in Ground & typical
a) 341.6 LM 18.00 6,148.80
floors and Machine room in Roof floor (PC supply rate
Dhs.10 /m)

For Shops and shop store and Office floors in Ground


b) 186.7 LM 36.00 6,721.20
Floor (Rate for supply not more than Dhs. 25/m2).

For All Flats Entry, internal corridors, Halls in Typical


c) 1832.9 LM 24.00 43,989.60
Floor (PC supply rate Dhs. 15 / m)

Size 60 x 10 em. For All bed rooms and balcony in all


d) 1425.2 LM 18.00 25,653.60
typical floors, (PC supply rate Dhs. 10/m)

For Watchman Room in Ground floor, (PC supply rate


e) 13.1 LM 15.00 196.50
Dhs.8/m)

Marble Perla to Thresholds, 200 T0300mm wide,


30 mm thick, exposed edges pencil rounded: set
3 334.8 LM 72.00 24,105.60
15mm above finished floor level. (PC supply rate
Dhs. 40/m)

TOTAL CARRIED TO COLLECTION Page-03 Dhs. 143,279.70


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

C WALL FINISHING

Sand cement render; 15 mm thick in two coats,


1
finished smooth:

a) To walls - block wall & shear wall 18649.20 m2 24.00 447,580.80

b) To walls of staircases 793.9 m2


24.00 19,053.60

c) To O.T.S. 1015.0 m2 30.00 30,450.00

Supply & fixing of Marble/Granite Tiles, including


2 sand cement backing and pointed with approved
coloured grout:

a) Granite tiles cladding for Main Lobby with 3m high


a) 107.3 m2 372.00 39,915.60
(Rate for supply not more than Dhs. 250/m2)

Wall tiles "Ceramic granite Tiles", laid on and


including cement sand mortar (1:3) and pointing
3
with approved coloured grout: (PC supply rate Dhs.
451m2) By RAK Ceramics or equv.

a) a) Main Corridor walls in all typical floors 664.3 m2 96.00 63,772.80

Coloured glazed ceramic wall tiles; including sand


4 cement backing and pointed with approved 13.1 m2 15.00 196.50
coloured grout:

Office Bathroom ,W.C in G round floor, Kitchens and


a) bathrooms in all typical floors, (Rate for supply not 4125.0 m2 96.00 396,000.00
more 4,125.0 than Dhs. 35/m2).

Garbage room ,Pump room in Ground floor (Rate for


b) 142.0 m2 66.00 9,372.00
supply not more than Dhs. 20/m2).

Watchman Pantry and Bath in Ground Floor (Rate for


c) 52.0 m2 60.00 3,120.00
supply not more than Dhs. 18/m2).

TOTAL CARRIED TO COLLECTION Page-04 Dhs. 1,009,461.30


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

C CEILING FINISHING

1 Sand cement render; 10 mm thick finished smooth:

a) under landings and steps and soffits of staircases. 255.00 m2 30.00 7,650.00

Supply and fix of 60 x 60 cm Gypsum tiles with


3 galvanized steel suspension include emulsion
paint.

For Shops, Watchman room, Office, Shop Store in Ground


a) 315.0 m2 50.00 15,750.00
floor (PC supply & fix y rate Dhs. 501m2)

For Flat Entries and corridors in All typical floors (PC


b) 450.0 m2 50.00 22,500.00
supply & fix y rate Dhs. 1m2)

Supply and fix of 60 x 60 cm powder coated


5 Aluminium tiles with galvanized steel suspension
(PC supply & fix rate Dhs.80/m2)

For Watch man pantry& bath ,Office bath and WC in


a) 910.0 m2 80.00 72,800.00
Ground floor, Kitchens and Bath rooms in all typical floors

b) for Main Corridor between flats in All Typical floors 210.0 m2 80.00 16,800.00

TOTAL CARRIED TO COLLECTION Page-05 Dhs. 135,500.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 10-FINISHING WORKS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Collection

TOTAL FROM PAGE NO. 01 Dhs. 143,724.00

TOTAL FROM PAGE NO. 02 Dhs. 427,045.20

TOTAL FROM PAGE NO. 03 Dhs. 143,279.70

TOTAL FROM PAGE NO. 04 Dhs. 1,009,461.30

TOTAL FROM PAGE NO. 05 Dhs. 135,500.00

BILL NO.10-FINISHING WORK TOTAL CARRIED TO


Page-06 Dhs. 1,859,010.20
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 11-PAINTING

ITEM DECRIPTION QTY UNIT RATE AMOUNT

l-Internal
Supply and apply two coats of
Fenomastic emulsion paint for internal, allowing
for surface preparation, putty, primer and all
related and necessary works.( National)

1 To walls - block wall & shear wall 11535.00 m2 12.00 138,420.00

2 To walls of staircases 800.0 m2


12.00 9,600.00

3 To ceiling, plaster base 2450.0 m2 12.00 29,400.00

4 To landings and soffits of staircases 252.0 m2 12.00 3,024.00

2-External

Prepare and apply Full Epoxy paint as specified:


Colour to be agreed,

To backside of parapet walls and Machine Room at the


1 265.0 m2 30.00 7,950.00
roof
2 OTS walls 1014.98 m2 30.00 30,449.40

3 To Staircases at the Roof 132.60 m2


30.00 3,978.00

4 To External Elevations 1049.88 m2 30.00 31,496.40

BILL NO.11-PAINTING & DECORATION TOTAL CARRIED TO


Page-01 Dhs. 254,317.80
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 12-PAINTING

ITEM DECRIPTION QTY UNIT RATE AMOUNT

1-Interlocking Blocks

Precast concrete interlocking paving blocks for


220mm. x 110mm. laid onto SOmm. compacted,
crushed sand bed over lS0mm. hardcore fill. Joints
Smm wide, filled with fine sand all complete to
Engineer's approval:

1 60mm Thick Allow 1.2 meters wide around the building 126.00 m2 60.00 7,560.00

80mm Thick for external car parking as per the approved


2 675.0 m2 72.00 48,600.00
layout drawing no. A-01 for 39 cars.

3 Kerbstone 110.0 m2 90.00 9,900.00

2-External Wall Finishes

Sand cement render; 20 mm thick in two coats,


finished smooth:

To backside of parapet walls and Machine Room at the


1 265.0 m2 33.00 8,745.00
roof

2 To Staircases at the Roof 135.00 m2 33.00 4,455.00

3 To External Elevations 1060.00 m2 33.00 34,980.00

2 Granite Cladding

Supply and fix (DRY FIX) Type Granite Cladding including


all angles, Bolts, glue and accessories For External walls
175.00 m2 540.00 94,500.00
at Ground floor (Rate for supply not more than
350/m2)

Granite tiles cladding for Main Entrance and Out side WC


Entry with 3m high (Rate for supply not more than 63.00 m2 540.00 34,020.00
Dhs. 3S0/m2)

BILL NO.12-EXTERNAL WORKS TOTAL CARRIED TO


Page-01 Dhs. 242,760.00
SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 13-LIFTS

ITEM DECRIPTION QTY UNIT RATE AMOUNT

1-Interlocking Blocks

Supply, installation, Connection, testing and


commissioning of Lifts (2 Nos. - Passenger Lift, Capacity
800Kg 13P ) complete as specified, as shown on the
drawings (Brand - Otis or equv )

A 2 Nos. Passenger lifts specification 2 Item 203,500.00 407,000.00

1 Quantity: 2 Nos. Passenger Elevators

2 Carrying Capacity: 800 kg, 13 Persons

3 No. of Stops: 8

4 Speed: 1.6 meters/sec

5 Individual Shaft: 2000 X 2000 mm

6 Cabin : 1100 x 1550 X 2100 mm

7 Entrance : single @ front side only

Builders works related to Elevators Works 1.00 Item 20,000.00 20,000.00

BILL NO.13-LIFT WORKS TOTAL CARRIED TO SUMMARY Page-01 Dhs. 427,000.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 14-PLUMBING & DRINAGE WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

PLUMBING & DRINAGE WORK


A Rain Water Installation

Supply & Install the following UPVC rain water


disposal system within building complete with roof
drains, elbows, tee, etc.

Make- Cosmoplast or equiv.

1 110m dia Horizontal Roof drains 6.0 No. 60.50 363.00

2 75mm dia Horizontal Roof drains 2.0 No. 49.50 99.00

3 50mm dia Balcony drains 28.0 No. 44.00 1,232.00

4 110mm dia. UPVC pipe 260.0 No. 19.80 5,148.00

5 75mm dia UPVC pipe 20.00 No. 15.40 308.00

B Soil & Waste System

Supply & Install the following UPVC soil, waste and


vent pipes laid exposed in walls, shafts or under
the slab as specified and shown on the drawings
complete with all the accessories, clean outs,
supports, hangers, etc to Engineer's approval.

Brand: Ployfab/Mincom or equiv.

1 4" dia UPVC pipes 1500.00 Mtr. 17.60 26,400.00

2 3" dia UPVC pipes 1130.00 Mtr. 13.20 14,916.00

3 2" dia UPVC pipes 1400.00 Mtr. 11.00 15,400.00

4 Floor Traps 4"x3"x2" 176.00 No. 38.50 6,776.00

5 Floor Trap Cover 6"x4" 176.00 No. 49.50 8,712.00

6 UPVC drainage fittings & accessories 1.00 LS 89,314.50 89,314.50

Underground Drainage Installation


Supply & install the following UPVC underground
C
drainage system as specified and shown on
drawings complete with all fittings & accessories

Make- Polyfab/Mincom or equiv.


1 160 mm dia. UPVC pipe. 600.00 Mtr. 27.50 16,500.00

2 110 mm dia. UPVC pipe. 50.00 Mtr. 22.00 1,100.00

3 82 mm dia. UPVC pipe 60.00 Mtr. 19.80 1,188.00

4.00 No. 181.50 726.00

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 188,182.50


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 14-PLUMBING & DRINAGE WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT


D Cold & Hot Water SuppIy Pipe work
SuppIy & install the following cold & hot water
suppIy pipe work as specified & shown on
drawings, laid under ceiling, over false ceiling, in
shafts, roof, in walls, etc/ complete with fittings,
valves, strainers, unions, joints, water hammer
arrestors, supports, etc.

Brand- RAK Therm or equiv

1 96mm diameter 60.0 Mts. 44.00 2,640.00

2 5mm diameter 60.0 Mts. 33.00 1,980.00

3 40mm diameter 580.0 Mts. 22.00 12,760.00

4 32mm diameter 780.0 Mts. 13.20 10,296.00

5 25mm diameter 750.00 Mts. 8.80 6,600.00

6 25mm diameter - Stabi 750.00 Mts. 13.20 9,900.00

7 PPR fitting & accessories 1.00 LS 26,517.70 26,517.70

Supply & Install the PEX pipes laid in the walls


E
complete with all the fittings & accessories

Make- RAK Therm or equiv.

1 1/2" PEX pipe 3200.00 Mtr. 6.60 21,120.00

2 Fittings & Accessories 1.00 LS 16,035.80 16,035.80

F Valves
SuppIy & install the following gate valves of given
sizes
Brand- Pegler or Equiv.

1 4" brass gate valve 1.00 No.

2 2" brass gate valve 30.00 No.

3 1" brass gate valve 100.00 No. 15,490.20 15,490.20

25mm PPR gate valve 150.00 No.

2" NRV 4.00 No.

1" NRV 44.00 No.

Water Eguipment's
Water heaters as per the following capacities as
G
shown on the drawing & specified complete with
all accessories

Make- Ariston or equiv.

1 80 lit. capacity 84.00 No. 539.00 45,276.00

2 50 Itr. Capacity 31.0 No. 440.00 13,640.00

TOTAL CARRIED TO COLLECTION Page-02 Dhs. 182,255.70


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 14-PLUMBING & DRINAGE WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

H Water Tanks
Supply, installation, testing & commissioning of
the following water tanks
Brand: Solico or equiv.
GRP insulated roof water tank 7mx6mx3m (33750
1 1 No. 137,052.30 137,052.30
USGal)
I Water Pumps

Supply, installation & testing of the following


water pumps

Brand: Biral(Grundfos) or equiv.


Water Transfer pump (1 duty+ 1 stand by) 2.761/s @
1 1 Set 18,304.00 18,304.00
36m head.
Water Booster pump(l duty+ 1 stand by)80 GPM @ 35m
2 1 Set 12,578.50 12,578.50
head.
J Sanitary wares
Receive & install the following sanitary wares
along with their fixtures
1 Shower Tray 80x80cm 28 No. 82.50 2,310.00

2 WC 118 No. 82.50 9,735.00

3 WB Pedestal Type 118 No. 77.00 9,086.00

4 Bidet 56 No. 82.50 4,620.00

5 Bath Tub 56 No. 93.50 5,236.00

Supply and fixing of Manhole Cover HV Grade B


K 9 No. 1,320.00 11,880.00
60X60cm

Civil and Builder's Works related to Plumbing


L 1.00 Item 30,000.00 30,000.00
works

TOTAL CARRIED TO COLLECTION Page-03 Dhs. 240,801.80


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 14-PLUMBING & DRINAGE WORK

ITEM DECRIPTION QTY UNIT RATE AMOUNT

Collection

Total of Page No. 1 Dhs. 188,182.50

Total of Page No. 1 Dhs. 182,255.70

Total of Page No. 1 Dhs. 240,801.80

BILL NO. 14 - PLUMBING & DRINAGE TOTAL


Page-04 Dhs. 611,240.00
CARRIED TO SUMMARY
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

A WIRING DEVICES:
Supply & installation of the following wiring
devices, complete with PVC conduits, wiring,
accessories etc .. As shown in drawings
1 Normal Light Points 878 No. 88.55 77,746.90

2 Chandelier Light Points 196 No. 126.55 24,803.80

3 Pent Light Points 2 No. 253.00 506.00

4 Signage Light Points 9 No. 151.80 1,366.20

5 Ceiling Fan Point 1 No. 88.55 88.55

6 13 A SSO Points 433 No. 126.50 54,774.50

7 13 A DSO Points 10 No. 139.15 1,391.50

8 15 A SSO Points 193 No. 139.15 26,855.95

9 Bell Points 56 No. 88.55 4,958.80

10 Water heater Points 115 No. 189.75 21,821.25

11 Exhaust Fan Points 115 No. 88.55 10,183.25

12 Exhaust Fan Points (lnline Duct) 28 No. 88.55 2,479.40

B WIRING ACCESSORIES:

1 13A SSO 433 No. 56.93 24,650.69

2 13A DSO 10 No. 69.58 695.80

3 15A SSO 193 No. 69.58 13,428.94

4 Bell 56 No. 202.40 11,334.40

5 Push Button Switch for Bell 56 No. 63.25 3,542.00

6 Water heater outlet 115 No. 63.25 7,273.75

7 20A DP Switch W/H 115 No. 120.18 13,820.70

8 Exhaust Fan Outlet 115 No. 56.93 6,546.95

9 Exhaust Fan Outlet( Inline Duct) 28 No. 88.55 2,479.40

10 Ceiling Fan 1 No. 328.90 328.90

11 1 Gang 1 Way 79 No. 31.63 2,498.77

12 2 Gang 1 Way 88 No. 44.28 3,896.64

13 3 Gang 1 Way 227 No. 69.58 15,794.66

14 1 Gang 2 Way 6 No. 37.95 227.70

15 Intermediate Switch 14 No. 126.50 1,771.00

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 335,266.40


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

A DISTRIBUTION BOARDS:

Supply & installation of the main, sub-main & final


distribution boards:

1 MDB 1 No. 101,598.48 101,598.48

2 466 KVR CAPACITOR BANK 1 No. 64,704.75 64,704.75

3 SMDB-T 7 No. 8,766.45 61,365.15

4 SMDB-S 1 No. 6,723.48 6,723.48

5 SMDB-SH 1 No. 6,261.75 6,261.75

6 DBSH-l 1 No. 2,055.63 2,055.63

7 DBSH-2 1 No. 2,036.65 2,036.65

8 DBSH-3 1 No. 2,055.63 2,055.63

9 DBSH-4 1 No. 2,036.65 2,036.65

10 DBSH-5 1 No. 2,036.65 2,036.65

11 DBSH-6 1 No. 2,055.63 2,055.63

12 DB-Sl 1 No. 1,789.98 1,789.98

13 DB-S2 1 No. 1,789.98 1,789.98

14 DB-S3 1 No. 1,220.73 1,220.73

15 DB-LIFT 1 No. 2,270.68 2,270.68

16 DB-G 1 No. 3,295.33 3,295.33

17 DB-P 1 No. 1,353.55 1,353.55

18 DB-l&4&5&8 28 No. 3,896.20 109,093.60

19 DB-2&3&6&7 28 No. 2,251.70 63,047.60

D CABLING

Supply & installation of the cables & feeders


between the main DB's and final DB's, complete
with cable trays, conduits, supports, etc ..

1 lCX630mm2 XLPE/SWA/PVC /CU 60 m 423.78 25,426.80

2 4CX150mm2 XLPE/SWA/PVC /CU 280 m 425.04 119,011.20

3 4CX95mm2 XLPE/SWA/PVC /CU 15 m 271.98 4,079.70

4 4CX35mm2 XLPE/SWA/PVC /CU 15 m 111.32 1,669.80

5 4CX25mm2 XLPE/SWA/PVC /CU 22 m 82.23 1,809.06

6 4CX16mm2 XLPE/SWA/PVC /CU 1304 m 54.40 70,937.60

7 lCX300mm2 PVC/ECC/CU 15 m 211.26 3,168.90

8 lCX70mm2 PVC/ECC/CU 280 m 48.07 13,459.60

TOTAL CARRIED TO COLLECTION Page-01 Dhs. 676,354.56


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

9 lCX35mm2 PVC/ECC/CU 15.0 m 25.30 379.50

10 lCX16mm2 PVC/ECC/CU 1341 m 12.65 16,963.65

11 3CX16mm2 XLPE/SWA/PVC /CU 96 m 49.34 4,736.64

12 2" PVC Conduits 1200 m 26.57 31,884.00

13 4" PVC Conduits 25 m 37.95 948.75

14 100CM H.D.G.I Cable tray 55 m 189.75 10,436.25

15 10CM H.D.G.I Cable tray 15 m 35.42 531.30

TELEPHONE SYSTEM

Supply and installation of the following Telephone


& Data System:

1 MONU CABINET 1 No. 4,269.38 4,269.38

2 ONT CABINET (600X600X500) 64 No. 942.43 60,315.52

3 ONTCABINET 8 No. 759.00 6,072.00

4 Data Junction Box 8 No. 379.50 3,036.00

5 Data Point with Cat-6 Cable 296 No. 253.00 74,888.00

6 Data Outlet RJ - 45 PVC 296 No. 113.85 33,699.60

7 Testing and Commissioning 1 L.S. 11,385.00 11,385.00

8 12 Core SM Fiber Optic 800 m 18.98 15,184.00

9 2 Core SM Fiber Optic 4250 m 15.18 64,515.00

10 24 Port CAT6a Patch Panels 64 No. 379.50 24,288.00

11 1U 4-Hoop Cable Management Bar Metal-Black 15 No. 44.28 664.20

12 Fiber Optic FTIH micro ODF,Sc Simplex 51 No. 31.63 1,613.13

13 24 Port Fiber Optic Panels 15 No. 430.10 6,451.50

14 2*32 Splitters, 1 NO in 1U Modual 2 No. 1,707.75 3,415.50

15 Pigtail SC/UPC 9/125,9/125, lm,Sm ,D=O,9mm,LSOH 300 No. 31.63 9,489.00

16 4" UPVC Conduits For Telephone 120 m 37.95 4,554.00

17 2" PVC Conduits For Telephone 1152 m 26.57 30,608.64

18 30CM H.D.G.I Cable tray 40 m 53.13 2,125.20

19 20CM H.D.G.I Cable tray 56 m 44.28 2,479.68

20 Telephone Earth System 1 L.S. 4,427.50 4,427.50

TOTAL CARRIED TO COLLECTION Page-03 Dhs. 429,360.94


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRAH
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY UNIT RATE AMOUNT

F INTERCOM SYSTEM:

Supply and installation of the Intercom system as


per drawings

1 Intercom Outlet Point 56 No. 253.00 14,168.00

2 Intercom Junction Box 8 No. 379.50 3,036.00

3 Intercom System Complete 1 L.S. 40,986.00 40,986.00

4 30CM H.D.G.I Cable tray 40 m 53.13 2,125.20

G EARTHING SYSTEM:

1 Supply and installation of earthing system. 1 L.S. 10,752.50 10,752.50

H SMATV SYSTEM:

Supply and installation of the TV system as per drawings -

1 Satellite Dish Point 3 No. 632.50 1,897.50

2 TV Point with Cable 140 No. 253.00 35,420.00

3 TV Main Distribution Box 7 No. 379.50 2,656.50

4 TV Outlet PVC Type 140 No. 113.85 15,939.00

5 TV System Complete 1 L.S. 31,308.75 31,308.75

6 1.5"PVC Conduits 910 No. 26.57 24,178.70

7 30CM H.D.G.I Cable tray 40 m 53.13 2,125.20

I GARBAGE CHUTTE SYSTEM:

1 Electrical and fire alarm works for garbage chute system 1 L.S. 10,120.00 10,120.00

J FIRE ALRAM SYSTEM: -


Supply and installation of the Fire alarm system as
-
per drawings
1 FACP (Addressable) (2-LOOPS) 1 No. 18,975.00 18,975.00

2 Fire alarm points with Fire Rated cable 329 No. 215.05 70,751.45

3 Exit & Emergency Light with Fire Rated cable 13 No. 215.05 2,795.65

4 Addressable Smoke detector 33 No. 474.38 15,654.54

5 Addressable Optical Smoke detector 10 No. 474.38 4,743.80

6 Addressable Heat detector 61 No. 506.00 30,866.00

7 Fire Alarm Pull station 15 No. 442.75 6,641.25

8 Fire Alarm Bell 8 No. 506.00 4,048.00

9 Fire Alarm Bell-Weather Proof 4 No. 759.00 3,036.00

10 Monitor Modual 17 No. 2,024.00 34,408.00

11 Control Modual 2 No. 2,024.00 4,048.00

12 Emergency Light 198 No. 499.68 98,936.64

13 Exit Light (Wall mounted) 10 No. 499.68 4,996.80

14 Exit Light (Hanging Type) 3 No. 822.25 2,466.75

TOTAL CARRIED TO COLLECTION Page-04 Dhs. 497,081.23


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJ
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY

K ISOLATORS:

Supply & installation of the power isolators with


cables:

1 25A SPN ISOLATOR W/P 1

2 32A TPN ISOLATOR W/P 2

3 40A SPN ISOLATOR W/P 61

4 40A TPN ISOLATOR W/P 36

5 100A TPN ISOLATOR W/P 1

L LIGHT FITTING

Installation of the light fittings as per the


following:
1 60 X 60 FL. LIGHT FIXTURE (4X20W) 429

2 TUBE LIGHT FIXTURE (lx40W) 48

3 CHANDALIER LIGHT FIXTURE 196

4 CEILING LIGHT FIXTURE 91

5 MIRROR LIGHT FIXTURE 115

6 BRACKET LIGHT FIXTURE 195

7 PENT LIGHT 2

M Supply and fix flat musical Bill 56

Supply and fixing of Manhole cover for etisalat


N 3
manhole
Supply and fixing of JRC12 Joint Box etisalat
O 1
standard

P Builders works related to Electrical Works 1


TOTAL CARRIED TO COLLECTION Page-05
L FLOOR -AL OWAID -FUJAIRAH
LARM SYSTEM
UNIT RATE AMOUNT

No. 1,012.00 1,012.00

No. 1,087.90 2,175.80

No. 1,062.60 64,818.60

No. 1,157.48 41,669.28

No. 1,644.50 1,644.50

No. 25.30 10,853.70

No. 25.30 1,214.40

No. 189.75 37,191.00

No. 25.30 2,302.30

No. 25.30 2,909.50

No. 25.30 4,933.50

No. 1,265.00 2,530.00

No. 132.00 7,392.00

No. 1,100.00 3,300.00

No. 13,200.00 13,200.00

Item 100,000.00 100,000.00

-
Page-05 Dhs. 297,146.58
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJ
BILL NO. 15-ELECTRICAL & FIRE ALARM SYSTEM

ITEM DECRIPTION QTY

COLLECTION

Total of Page No.1

Total of Page No.2

Total of Page No.3

Total of Page No.4

Total of Page No.5


BILL NO. 15 - ELECTRICAL & FIRE ALARM TOTAL
Page-06
CARRIED TO SUMMARY
L FLOOR -AL OWAID -FUJAIRAH
LARM SYSTEM
UNIT RATE AMOUNT

Dhs. 335,266.40

Dhs. 676,354.56

Dhs. 429,360.94

Dhs. 497,081.23

Dhs. 297,146.58
Page-06 Dhs. 2,235,209.71
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJ
BILL NO. 16-AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM

ITEM DECRIPTION QTY

HEATING VENTILATION AIR CONDITIONING (HVAC)

AC units complete as per capacity scheduled and


A
relevant specifications

Brand: Trane

1 Ducted Split Units 1.5 TR(R22) 2

2 Ducted Split Units 2 TR(R22) 28

3 Ducted Split Units 2.5 TR(R22) 1

4 Ducted Split Units 3 TR(R22) 28

5 Ducted Split Units 3.75 TR(R22) 31

6 Ducted Split Units 5 TR(R22) 3

7 1.5 TR Wall Mounted Split A/C units(R22) 1

8 2 TR Wall Mounted Split A/C units(R22) 1

SuppIp, installation, fabrication, testing &


commissioning of Copper Pipes(SuppIy & return)
B 1
for the AlC units along with all the accessories &
insulation.

Brand: Maksal/Trox or equiv

SuppIy, Install, testing & commissioning of Wall


C
Mounted Air Exhaust Fans for Bathroom Area

Brand: Metrico or equiv

1 Wall Mounted Exhaust Fan 300 CFM 115

2 Inline Ducted Exhaust Fan 300 CFM 28

SuppIy, install, testing & commissioning of


D 1
Electrical Cabling for the A/C units

SuppIy, installation & testing of AC drainage pipes


E complete with fittings & accessories 1
Brand: Cosmoplast or equiv.
SuppIy, installation & fabrication of GI ducting for
the AC units & exhaust air system complete with
F 1
all the accessories & insulation
Brand: PAL or equiv.

TOTAL CARRIED TO COLLECTION Page-01


L FLOOR -AL OWAID -FUJAIRAH
AL VENTILATION SYSTEM
UNIT RATE AMOUNT

nr. 5,731.00 11,462.00

nr. 6,785.90 190,005.20

nr. 6,936.60 6,936.60

nr. 7,992.60 223,792.80

nr. 9,802.10 303,865.10

nr. 12,818.30 38,454.90

nr. 3,468.30 3,468.30

nr. 4,072.20 4,072.20

L.S. 150,683.50 150,683.50

nr. 286.00 32,890.00

nr. 316.80 8,870.40

LS 14,326.40 14,326.40

LS 6,785.90 6,785.90
LS 206,541.50 206,541.50

Page-01 Dhs. 1,202,154.80


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJ
BILL NO. 16-AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM

ITEM DECRIPTION QTY

SuppIy & installation of the following Air outlets &


G inlets
Brand: Tecnostream, Tecnalco or eguiv.

1 Supply air difuser 300x300mm 20

2 Return air difuser 300x300mm 20

3 Exhaust air difuser 300x300mm 28

4 Disc Valve 6" 28

5 Supply air grills 750x150mm 280

6 Return air grills 750x150mm 280

B Builders works related to AC Works. 1

TOTAL CARRIED TO COLLECTION Page-02


L FLOOR -AL OWAID -FUJAIRAH
AL VENTILATION SYSTEM
UNIT RATE AMOUNT

nr.

nr.

nr.
106,845.20 106,845.20
nr.

nr.

nr.

L.S. 65,000.00 65,000.00

Page-02 Dhs. 171,845.20


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJ
BILL NO. 16-AIR CONDITIONING & MECHANICAL VENTILATION SYSTEM

ITEM DECRIPTION QTY

COLLECTION

1 Total of Pages No.1

2 Total of Pages No.2

BILL NO. 16 -A/C & VENTILATION TOTAL


Page-03
CARRIED TO SUMMARY
L FLOOR -AL OWAID -FUJAIRAH
AL VENTILATION SYSTEM
UNIT RATE AMOUNT

Dhs. 1,202,154.80

Dhs. 171,845.20

Page-03 Dhs. 1,374,000.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FU
BILL NO. 17-FIRE FIGHTING & SPRINKLER SYSTEM

ITEM DECRIPTION QTY

FIRE FIGHTING SYSTEM


A
As per our Design and Civil Defense Reguirements

1 6" X 4 way Breaching Inlet Valve -Nafco or Equiv

2 Cabinet for breaching inlet valve 5.5- Nafco or Equiv.

2.5" Landing Valve with P.R.V -Nafco, Shield, Jintian or


3
Equiv. -LPCB, Kitemark or UL

Hose Reel 1" X 100 Ft wlo cabinet Nafco, Jintian or


4
Equiv. -LPCB, Kitemark or UL

Fire Hose 2.5" X 100 Ft wlo cabinet with nozzle- Nafco,


5
Jintian or Equiv. -LPCB, Kitemark or UL

6 6" Non return valve - Nafco, Rapidrop or equiv.

7 1" P.R.V - Nafco, Rapidrop or equiv.


10 Lbs C02 Fire Extinguisher -Nafco, Jintian or Equiv. -
8 1
LPCB, Kitemark or UL
5 Lbs C02 Fire Extinguisher -Nafco, Jintian or Equiv. -LPCB
9
Kitemark or UL

10 Lbs Dry Powder Extinguisher -Nafco, Jintian or Equiv. -


10
LPCB, Kitemark or UL

Auto. 10 Lbs Dry Powder Extinguisher -Nafco, Jintian or


11
Equiv.

NON UL Combined Fire Pump set 1 ( Electric + Diesel +


12
Jockey) as hydraulic calculations

B SPRINKLER SYSTEM
Sprinkler Head Pendent Upright Type Chrome-( Shield,
Rapidrop)
Escutcheon Plate Chrome plated- double -( Shield,
Rapidrop)
Gate Valve OS & Y ( Shield, Rapidrop)

Zone control Valve ( Shield, Rapidrop)


Wet Alarm Gong Valve Assembly ( Shield, Rapidrop)

C Builders works related to Fire Fighting Works. 1

BILL NO. 17 -FIRE FIGHTING SYSTEM TOTAL


Page-01
CARRIED TO SUMMARY
L FLOOR -AL OWAID -FUJAIRAH
NKLER SYSTEM
UNIT RATE AMOUNT

Item 489,500.00 489,500.00


Item 25,000.00 25,000.00

Page-01 Dhs. 514,500.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FU
BILL NO. 18-PROVISIONAL SUM

ITEM DECRIPTION QTY

PROVISIONAL SUMS

A Decoration False Ceiling for Entrance


False Ceiling for entrance floor Provisional Sum
1
Items=30,000.00 Dhs.
Add for Attendance & profits. 1

Add for Builder's Work. 1

B Recegtion Counter

Supply and fix MDF counter with marble top Provisional


1
Sum Item= 5,000.00 Dhs.

Add for Attendance & profits. 1

Add for Builder's Work. 1

C Electrical Works (Light Fitting)

Supply only of light fitting, including all internal & external


1
light fitting. Provisional Sum Items= 125,000 Dhs.

Add for Attendance & profits. 1

Add for Civil & Builder's Work. 1

D Central Antenna & Dish Works


Supply and fix of central dish. Provisional Sum Items=
1
28,000.00 Dhs.

Add for Attendance & profits. 1

Add for Builder's Work. 1

E Directory Board.

Supply and fix of central dish. Provisional Sum Items=


1
28,000.00 Dhs.
Add for Attendance & profits. 1

Add for Builder's Work. 1

TO Collection Page-01
L FLOOR -AL OWAID -FUJAIRAH
SUM
UNIT RATE AMOUNT

P.S. 30,000.00 30,000.00

Item 3,000.00

Item 1,500.00

P.S. 5,000.00 5,000.00

Item 500.00

Item 250.00

P.S. 125,000.00 125,000.00

Item 12,500.00

Item 6,250.00

P.S. 28,000.00 28,000.00

Item 2,800.00

Item 1,400.00

P.S. 3,000.00 3,000.00


Item 300.00

Item 150.00

Page-01 Dhs. 219,650.00


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJA
BILL NO. 18-PROVISIONAL SUM

ITEM DECRIPTION QTY

Supply & fixing of top and bottom Aluminium


kitchen cabinet and pantry cabinet including sink,
F 290
mixers and marble work top (Supply and
installation P.S= 800/m .)

Add for Civil and Builder's Work. 1

Add for Builder's Work. 1

G Signage Board

Aluminium sign age on metal and wooden doors(all


Service & Flats doors ,Provisional Sum Items 1
=10,000.00 Dhs.

Add for Attendance & profits. 1

Add for Builder's Work. 1

D Garbage Chute

Supply and installation of complete Garbage Chute, Local


1
fabrication (1 No.) .Provisional Sum Items=55,000.0 Dhs.

Add for Attendance & profits. 1

Add for Builder's Work. 1

I SANITARY FIXTURES

Supply only of Full Set ( Wash basin, water closet and


bidet) for Flats, including all accessories mixers, mirror,
1 56
shattaf, toilet paper & soap tray, bath towels bar and bath
tub (Supply P.S Dhs. 3,500 /Toilet)

2 Supply only of W/C( Wash basin, water closet) for Small 59


Toilets at the Flats, washroom, Office & Out side WC with
all accessories (Supply P.S Dhs. 2,000/Toilet)
3 Supply only Shower tray (Supply P.S Dhs. 300/Toilet) 28

Add for Attendance & profits. 1

Add for Builder's Work. 1

To Collection Page-02
L FLOOR -AL OWAID -FUJAIRAH
SUM
UNIT RATE AMOUNT

LM 880.00 255,200.00

LS 13,780.80 13,780.80

LS 27,561.60 27,561.60

P.S. 10,000.00 10,000.00

Item 1,000.00

Item 500.00

P.S. 55,000.00 55,000.00

Item 5,500.00

Item 2,750.00

P.S. 3,500.00 196,000.00

P.S. 2,000.00 118,000.00


P.S. 300.00 8,400.00

Item 16,120.00

Item 25,792.00

Page-02 Dhs. 735,604.40


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIR
BILL NO. 18-PROVISIONAL SUM

ITEM DECRIPTION QTY

Collection

TOTAL FROM PAGE NO.O1

TOTAL FROM PAGE NO.O2

BILL NO. 18 -PROVISIONAL SUM TOTAL CARRIED TO


Page-03
SUMMARY
LOOR -AL OWAID -FUJAIRAH
M
UNIT RATE AMOUNT

Dhs 219,650.00

Dhs 735,604.40

Page-03 Dhs. 955,254.40


RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRA
ELECTRICAL WORKS LIST OF MATERIALS

ITEM DECRIPTION

1 PVC Conduits & Accessories

2 UPVC

3 PVC Wires & Cables

4 G.I Trays & Trunking

5 G.I Boxes

6 Distribution Panels

7 Earthing System

8 Switches & Sockets

9 Isolators

10 Emergency & Exit Light

11 Fire Alarm System

12 Fire Cables

13 ONT Cabinet

14 Cat-6 Cable

15 Fire Optic Cable


LOOR -AL OWAID -FUJAIRAH
ERIALS
BRAND

Decoduct & Equivalent

Cosmoplast or Equivalent

Oman, NCI, or Equivalent

Novablue or Equivalent

AI Fanar or Equivalent

ABB/Schneider or Equivalent
(Local Assembly)

Furse or Equivalent

MK (PVC) Clipsal (PVC) or


Equivalent

Scame, Gewiss or Equi (PVC


W/P)

Shield (UK) or Equivalent

Sheild UK

Tekab

Rexton or Equivalent

D Link or Equivalent

Begin or Equivalent
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRA
PLUMBING WORKS LIST OF MATERIALS

ITEM DECRIPTION

1 Pex-Pipes and Fittings

2 PP-R Pipes and Fittings

3 Gate, Globe and Check Valves, etc.

4 UPVC Pipes

5 Floor Trap Cover

6 Floor Trap, Rain Water Outlet, Gully Trap

7 Water Tanks

8 Pumps

9 Water Heater

10 AC Drainage pipes
LOOR -AL OWAID -FUJAIRAH
RIALS
BRAND

Raktherm or Equivalent

Raktherm or Equivalent

Pegler or Equivalent

Plyfab/Mincom or equiv

Junaid or equiv

Polyfab/Mincom or equiv

Solico/Pepco or Approved
Eauivalent

KSB, Saer,Lowara or
Equivalent

Ariston, Italy

Cosmoplast or equiv
RESIDANCE & COMMERCIAL BUILDING G+7 TYPICAL FLOOR -AL OWAID -FUJAIRA
HVAC WORKS LIST OF MATERIALS

ITEM DECRIPTION

1 Ducted Split Units

2 Wall Mounted Split Units U.S TR & 2.0TR)

3 Copper Pipes

4 Rubber Insulation for copper pipes

5 GI Ducts

6 Insulation for GI Ducts

7 Grill Difuser & Louvers

8 Volume Control Dampers & Fire Dampers

9 Air Exhaust Fans

10 A/C Drainage piping


LOOR -AL OWAID -FUJAIRAH
ALS
BRAND

Trane, (USA/Thailand)

Trane, (China/China)

Maksal/Trox or Equivalent

Gulf O-Flex or Equiv.


Nisshin/Nippon/Jindalor
equiv.
Apco Flex or equiv

Tecnostream/Tecnalco/ AI
Samah or Equiv.

Tecnalco/AI Samah or Equiv

Vortice / Metrico or Equiv.

Cosmoplast or equiv