Example of KPIs are as follows :

Unit of Frequency of
Item Description Type of Measure
Measurement Measurement
A. ENGINEERING
Monthly
Index = Mhrs actual/
Engineering Performance
1 (Mhrs earned +
Productivity Quality Project Close-Out
approved variation)
Index = # of design
deliverables planned
per schedule / Monthly
Performance and
2 Timely Delivery
# of deliverable Product Quality Project Close-Out
actual approved &
issued

% = # of dwgs Monthly
Control of Design issued revised AFC / Performance and
3
Change Total # of AFC Product Quality Project Close-Out
Drawings
B. PROCUREMENT
Monthly
Index =
Procurement Budget Performance
1 ActualCost /
Efficiency Quality Project Close-Out
Forecast Budget
Monthly
Actual Goods
Material Delivery Performance
2 Received / Vendor
Efficiency Quality Project Close-Out
Promised Date
C. PMT
a. No. of NCRs
issued by Company

b. No. of Companys
formal complaints Monthly
Product &
via MOM or
1 Customer Satisfaction Performance
memos/No. of Project Close-Out
Quality
Companys
Compliments

a)

2 Timely Issue of Project No. of Issued Project Performance Monthly


Documents Documents within a Quality
month / Planned no.
of Project
Documents for
Issuance within a
month
D. QUALITY ASSURANCE
No. of Audits Monthly
Performed within a
Audit Schedule Performance
3 month / No. of Accumulated
Efficiency Quality
Audits Planned Annually
within a month
Monthly
No. of closed CAR /
Product &
Corrective Action No. of raised CAR
4 Performance Accumulated
Request (CAR) per criticality rating
Quality Annually
per audit
Monthly
OS&D Close-out No. of Closed-Out Product &
5 (Delivery Non- OS&D / No. of Performance Accumulated
Conformance) Issued OS&D Quality Annually

Monthly
No. of NCR Closed- Product &
Non-Conformance
6 Out / No. of Issued Performance Accumulated
Reports Close-Out
NCR Quality Annually

E. OPERATIONS
MWB Days Actual / Performance
7 Productivity Project Close-out
MWB Days Earned Quality
Down Time
Performance
8 Barge Downtime Recorded per DPR / Project Close-out
Quality
Total Time
Joints Repaired / Performance &
9 Repair Rate Project Close-out
Joints Inspected Product Quality