AWARDED SOLAR PROJECTS as of June 30, 2016

POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Commercial Stage (FIT System).
Currimao Solar Power Mirae Asia Energy
LUZON I Ilocos Norte Currimao Compliant with all work and financial 20.00
Project Corporation
obligations.
Motion for reconsideration and DOC (FIT
Pasuquin East Solar Power Energy Logics Philippines, System) is under evaluation. For issuance of
Pasuquin, Burgos 50.00
Project Inc. reminder letter due to non compliance with
RESHERR.
Under Commercial Stage (FIT System).
Burgos Solar Power Project Energy Development
Burgos Compliant with all work and financial 4.10
Phase I Corporation
obligations.
Burgos Solar Power Project Energy Development Under Commercial Stage (FIT System -
2.66
Phase 2 Corporation Additional Investment).
For issuance of Termination Letter due to non-
Ilocos Norte Phase I Solar
Paoay Del Sol Energy Primera, Inc. compliance with Milestone Approach and 40.00
Power Project
RESHERR.
For issuance of Termination Letter due to non-
Ilocos Norte Phase II Solar
Del Sol Energy Primera, Inc. compliance with Milestone Approach and 40.00
Power Project
RESHERR.
For issuance of Termination Letter due to non-
Paoay II Solar Power Project Del Sol Energy Segunda, Inc. compliance with Milestone Approach and 40.00
RESHERR.
For issuance of Termination Letter due to non-
Paoay III Solar Power Project Del Sol Energy Tercera, Inc. compliance with Milestone Approach and 40.00
RESHERR.
Laoag, Bacarra,
Solar Philippines Commercial Request for reduction of contract area is on
San Nicolas & Laoag Solar Power Project 45.00
Rooftop Projects, Inc. process.
Paoay
Under Development Stage (FIT System). For
issuance of show-cause letter due to delayed
Sarrat Sarrat Solar Power Project Bosung Solartec, Inc. 1.00
implementation of 5-Year Work Plan and non-
compliance with RESHERR.
No submission of reports regarding
Bulacan 1 Solar Power Cleantech Global compliance to its Milestone Approach. For
Bulacan San Ildefonso 15.00
Project Renewables, Inc. issuance of reminder letter due non
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Request for assignment/transfer to San
Bulacan 2 Solar Power Cleantech Global Ildefonso Renewable Energy Corp. is under
LUZON I Bulacan San Ildefonso 40.00
Project Renewables, Inc. evaluation. For issuance of reminder letter
due non compliance with RESHERR.
For issuance of Termination Letter due to non-
AVGarcia Power Systems posting of Performance Bond and non-
Pangasinan Manaoag Pugaro Solar Power Project 2.00
Corp. compliance with Milestone Approach and
RESHERR.
No submission of reports regarding
Pangasinan I Solar Power Cleantech Global compliance to its Milestone Approach. For
Dasol 50.00
Project Renewables, Inc. issuance of reminder letter due to non
compliance with RESHERR .
No submission of reports regarding
Pangasinan II Solar Power Cleantech Global compliance to its Milestone Approach. For
50.00
Project Renewables, Inc. issuance of reminder letter due to non
compliance with RESHERR .
Compliance with Milestone Approach is on
Labrador Labrador Solar Power Project IJG1 Philippines Inc. 5.00
going.
Compliance with Milestone Approach is on
Ilocos Sur Santa Santa Solar Power Project Satrap Power Corporation 20.00
going.
For issuance of Termination Letter due to
GreEnergy Power Systems expiration of the SESC and non compliance
II Cagayan Aparri Aparri Solar Power Project 105.00
Philippines, Inc. with the Performance Bond, DOC, and
RESHERR.
Natures Renewable Energy
Lal-lo and Lal-lo Hybrid Solar Power Compliance with Milestone Approach is on
Dev't. (NAREDCO) 100.00
Gattaran Project going.
Corporation
Compliant with Milestone Approach. For
Living Projects 4 People
Isabela Ilagan Isabela Solar Power Project issuance of reminder letter due to non- 100.00
Philippines Inc.
compliance with RESHERR.
No submission of reports regarding
compliance to its Milestone Approach. For
Cordon Cordon Solar Power Project Greenergy Solutions Inc. 50.00
issuance of reminder letter due non-
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
No submission of reports regarding
Sta. Maria Solar Power compliance to its Milestone Approach. For
LUZON II Isabela Sta. Maria Greenergy Solutions Inc. 125.00
Project issuance of reminder letter due to non
compliance with RESHERR .
East Coast FAS Renewable
Compliance with Milestone Approach is on
Energy and Industrial 30.00
going.
Corporation
Ramon & Compliance with Milestone Approach is on
Ramon Solar Power Project AAESUN Corporation 5.00
Santiago going.
Ilagan City Solar Power Compliance with Milestone Approach is on
Ilagan City Greenergy Solutions Inc. 100.00
Project going.
Under Commercial Stage (FIT System). For
Pampanga Solar Power
III Pampanga Mexico RASLAG Corp. issuance of reminder letter due to non- 10.00
Project
compliance with RESHERR.
Pampanga Solar Power Under Commercial Stage (FIT System -
RASLAG Corp. 13.14
Project Phase II Additional Investment).
DOC (FIT System) is under evaluation. For
Porac (formerly applied as Solar Power Utilities
Porac issuance of reminder letter due to non 50.00
Guagua) Solar Power Project Generator Corporation
compliance with RESHERR.
Under Commercial Stage (FIT System). For
Enfinity Philippines
Mabalacat Clark Solar Power Project issuance of reminder letter due to non- 22.33
Renewable Resources Inc.
compliance with RESHERR.
Under Commercial Stage (FIT System). For
YH Green Energy
Bataan Hermosa Hermosa Solar Power Project issuance of reminder letter due to non 14.51
Incorporated
compliance with RESHERR.
No submission of reports regarding
compliance to its Milestone Approach. For
Solana Solar Alpha Inc. 20.00
issuance of reminder letter due non-
compliance with RESHERR.
SPARC Solar Powered Agri- Under Development Stage (FIT System). On-
Morong Morong Solar Power Project Rural Communities going commissioning. Subject for on-site 5.02
Corporation validation of its Successful Commissioning.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Development Stage (FIT System). On-
going construction/commissioning. Subject for
Next Generation Power
LUZON III Bataan Mariveles Bataan Solar Power Project on-site validation of its Successful 18.00
Technology Corp.
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
For issuance of Termination letter due to non
nv vogt Philippines Solar
Bataan I Solar Power Project compliance with Milestone Approach and 55.00
Energy Four, Inc.
RESHERR.
For issuance of Termination Letter due to
Orani Bataan Solar Power Project BWST, Inc. delayed implementation of its Work Program 150.00
and non-compliance with RESHERR.

SPARC Solar Powered Agri- Under Development Stage (FIT System). On-
San Rafael Solar Power
Bulacan San Rafael Rural Communities going commissioning. Subject for on-site 3.82
Project
Corporation validation of its Successful Commissioning.
Bulacan Solar Energy Corp.
Under Commercial Stage (FIT System). For
Bulacan 3 Solar Power
San Ildefonso (formerly Cleantech Global
issuance of reminder letter due to non 15.00
Project
Renewables, Inc.) compliance with RESHERR.
SPARC Solar Powered Agri-
Under Commercial Stage (FIT System). For
Zambales Palauig Palauig Solar Power Project Rural Communities issuance of reminder letter due to non 5.02
Corporation compliance with RESHERR.
DOC (FIT System) is under evaluation. For
Solar Power Utilities
Salaza Solar Power Project issuance of reminder letter due to non 50.00
Generator Corporation
compliance with RESHERR.
Bato (formerly applied as DOC (FIT System) is under evaluation. For
Solar Power Utilities
Bulawen) Solar Power issuance of reminder letter due to non 40.00
Generator Corporation
Project compliance with RESHERR.
Under Development Stage (FIT System). For
Solar Power Utilities issuance of show-cause letter due to delayed
Botolan Botolan Solar Power Project 39.27
Generator Corporation implementation of 5-Year Work Plan and non-
compliance with RESHERR.
Under Commercial Stage (FIT System). For
Cabanatuan Solar Power First Cabanatuan Renewable
Nueva Ecija Cabanatuan City issuance of reminder letter due to non 10.26
Project Ventures, Inc.
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Development Stage (FIT System). On-
going construction. For issuance of show-
LUZON III Bataan Morong -Hermosa Sta. Rita Solar Power Project Jobin-Sqm Inc. cause letter due to delayed implementation of 100.44
5-Year WP and non-compliance with
RESHERR.
Under Development Stage (FIT System). For
Concepcion Solar Power Enfinity Philippines issuance of show-cause letter due to delayed
Tarlac Concepcion 50.55
Project Renewable Resources Inc. implementation of 5-Year Work Plan and non-
compliance with RESHERR.
For issuance of Termination letter due to non
nv vogt Philippines Solar
Tarlac City Tarlac Solar Power Project compliance with Milestone Approach and 55.00
Energy Three, Inc.
RESHERR.
Under Commercial Stage (FIT System). For
PetroSolar Corporation issuance of reminder letter due to non 50.07
compliance with RESHERR.
Under Development Stage (FIT System). On-
going construction/commissioning. Subject for
nv vogt Philippines Solar
Armenia Solar Power Project on-site validation of its Successful 8.84
Energy Three, Inc.
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.

Under Development Stage (FIT System). On-


going construction/commissioning. Subject for
nv vogt Philippines Solar
Dalayap Solar Power Project on-site validation of its Successful 7.48
Energy Four, Inc.
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
Tarlac,
Solar Philippines Commercial Request for reduction of contract area is on
Concepcion, La Tarlac Solar Power Project 100.00
Rooftop Projects, Inc. process.
Paz & Victoria
Greenergy Capas Solar Compliance with Milestone Approach is on
Capas Greenergy Solutions Inc. 50.00
Power Project going.
Concepcion,
Tarlac and Capas & Bamban Concepcion Solar Power Solar Philippines Commercial Request for reduction of contract area is on
75.00
Pampanga and Magalang & Project Rooftop Projects, Inc. process.
Mabalacat
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
No submission of reports regarding
San Jose City and compliance to its Milestone Approach. For
LUZON III Nueva Ecija San Jose Solar Power Project SJC SolarPower Corporation 10.00
Lupao issuance of reminder letter due non
compliance with RESHERR.
DOC (FIT System) is under evaluation. For
V-Mars Solar Energy
San Jose & Lupao San Jose Solar Power Project issuance of reminder letter due to non- 10.00
Corporation
compliance with RESHERR.
No submission of reports regarding
Nueva Ecija Solar Power compliance to its Milestone Approach. For
Pantabangan Firmgreen Phils. Inc. 100.00
Project issuance of reminder letter due to non
compliance with RESHERR .
Cabanatuan City Cabanatuan Solar Power Compliance with Milestone Approach is on
Greentech Solar Energy Inc. 6.25
and Laur Project going.
Compliance with Milestone Approach is on
Muoz and Lupao Talugtug Solar Power Project Greenergy Solutions Inc. 125.00
going.
San Leonardo Solar Power OCT Renewable Energy Compliance with Milestone Approach is on
San Leonardo 5.00
Project Corporation going.
No submission of reports regarding
Tarlac City,
compliance to its Milestone Approach. For
Tarlac Concepcion & Tarlac Solar Power Project Firmgreen Phils. Inc. 50.00
issuance of reminder letter due to non
Capas
compliance with RESHERR .
Under Commercial Stage (FIT System). For
Rosario and Cavite Economic Zone Solar Majestics Energy
IV-A Cavite issuance of reminder letter due to non 41.30
General Trias Power Project Corporation
compliance with RESHERR.
With 04 April 2016 letter giving 30 days
G.A. Philkor Multi Energy deadline to submit additional DOC
Naic Sabang Solar Power Project 50.00
Corp. documents. For issuance of reminder letter
due to non compliance with RESHERR.
Under Development Stage (FIT System). For
Noveleta, Rosario, Enfinity Philippines issuance of show-cause letter due to delayed
Cavite Solar Power Project 3.00
Gen. Trias, Tanza Renewable Resources Inc. implementation of 5-Year Work Plan and non-
compliance with RESHERR.
For issuance of Termination Letter due to non-
Dasmarias Solar Power Solar Philippines Commercial posting of Performance Bond and non-
Dasmarias 0.80
Project Rooftop Projects, Inc. compliance with Milestone Approach and
RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Development Stage (FIT System).
Issued show-cause letter due to delayed
Macabud Solar Power ATN Philippines Solar Energy
LUZON IV-A Rizal Rodriguez implementation of 5-Year Work Plan, non- 30.00
Project Group, Inc.
posting of Performance Bond, and non-
compliancce with RESHERR.
Motion for reconsideration is not acceptable.
Canlubang Solar Power Transnational Renewable
Laguna Calamba For issuance of Termination Letter with 0.206
Project Energy Corporation
finality.
Under Development Stage (PSA with Central
Central Mall Bian Solar Solar Philippines Commercial Mall Binan). For issuance of show-cause letter
Binan 0.70047
Power Project Rooftop Projects, Inc. due to non-posting of Performance Bond and
non-compliance with RESHERR.
For issuance of Termination Letter due to non-
Solar Philippines Commercial posting of Performance Bond and non-
Cabuyao Cabuyao Solar Power Project 16.00
Rooftop Projects, Inc. compliance with Milestone Approach and
RESHERR.
For issuance of Termination letter due to non
Solar Power Utilities
Luisiana Luisiana Solar Power Project compliance with Milestone Approach and 30.00
Generator Corporation
RESHERR.
Under Development Stage (FIT System). On-
going construction/commissioning. Subject for
CW Home Depot Solar Power CW Marketing &
Sta. Rosa on-site validation of its Successful 1.68
Project Development Corporation
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
For issuance of Termination Letter due non-
FPIP Batangas Solar Power posting of Performance Bond, non-compliance
Batangas Sto. Tomas First Gen Visayas Energy Inc.
Project with Milestone Approach, and non-
compliance with RESHERR.
For issuance of Termination letter due to non
Candelaria Solar Power Solar Power Utilities
Quezon Candelaria compliance with Milestone Approach and 50.00
Project Generator Corporation
RESHERR.
Pulo Ilayan Solar Power Sun Premier Pagbilao Compliance with Milestone Approach is on
Pagbilao 15.00
Project Philippine Corporation going.
Sun Premier Pagbilao Compliance with Milestone Approach is on
Ikirin Solar Power Project 10.00
Philippine Corporation going.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Commercial Stage (FIT System).
Calatagan Solar Power Solar Philippines Calatagan
LUZON IV-A Batangas Calatagan Compliant with all work and financial 63.30
Project Corporation
obligations.
Under Commercial Stage (FIT System). For
Lian Lian Solar Power Project Absolut Distillers, Inc. issuance of reminder letter due to non 2.04
compliance with RESHERR.
Compliant with Milestone Approach. For
Balayan Batangas Solar Power Project EarthEnergy Corp. issuance of reminder letter due to non- 30.00
compliance with RESHERR.
No submission of reports regarding
Roxas Green Energy compliance to its Milestone Approach. For
Nasugbu and Tuy Nasugbu Solar Power Project 30.00
Corporation issuance of reminder letter due non
compliance with RESHERR.
No submission of reports regarding
compliance to its Milestone Approach. For
Rosario Rosario Solar Power Project EEI Power Corporation 10.00
issuance of reminder letter due to non
compliance with RESHERR .
Solar Philippines Commercial Request for reduction of contract area is on
Rizal Taytay Taytay Solar Power Project 1.50
Rooftop Projects, Inc. process.
Green Atom Renewable Compliance with Milestone Approach is on
Pililla Tanay Solar Power Project 12.00
Energy Corporation going.
Request for exemption on Milestone
Approach and deferred DOC due to its
Sabang Renewable Energy
IV-B Palawan Puerto Princesa Palawan Solar Power Project peculiarity as QTP is under evaluation. For
Corp.
issuance of reminder letter due to non
compliance with RESHERR.
For issuance of Termination Letter due to non-
Phil. Solar Farm-Palawan, posting of Performance Bond and non-
10.00
Inc. compliance with Milestone Approach and
RESHERR.
With 12 May 2016 letter giving 30 days
deadline to submit additional DOC
SolarPacific Energy
El Nido Island El Nido Solar Power Project documents. Request for SESC Assignment is 3.00
Corporation
under evaluation. For issuance of reminder
Letter due to non-compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Commercial Stage (FIT System).
Request for assignment of SESC dated 20 June
SM North Solar Power Solar Philippines Commercial 2016 to Solar Philippines North EDSA
LUZON NCR Metro Manila Quezon City 1.50
Project Rooftop Projects, Inc. Corporation is under evaluation. For issuance
of reminder letter due to non compliance with
RESHERR.
For issuance of Termination Letter due to non-
Quezon City 1 Solar Power Solar Philippines Commercial payment of Signature Bonus, non-posting of
Metro Manila Quezon City 1.20
Project Rooftop Projects, Inc. Performance Bond, and non-compliance with
Milestone Approach and RESHERR.
With 29 June 2016 letter requesting
additional DOC documents. For issuance of
Pasay City Solar Power Solar Philippines Commercial
Pasay City reminder letter due to non-compliance with 3.20
Project Rooftop Projects, Inc.
RESHERR and non posting of Performance
Bond.
Under Commercial Stage (FIT System). For
Valenzuela Solar Power
Valenzuela City Valenzuela Solar Energy Inc. issuance of reminder letter due to non 8.50
Project
compliance with RESHERR.
DOC (FIT System) is under evaluation. For
Paranaque City Solaire Solar Power Project SOLNRG, Inc. issuance of reminder letter due to non- 1.00
compliance with RESHERR.
For issuance of Termination Letter due to non-
V Camarines Sur Pili Pili Solar Power Project Emerging Power Inc. compliance with Milestone Approach and 12.00
RESHERR.
No submission of reports regarding
Calabanga Solar Power Calabanga Renewable compliance to its Milestone Approach. For
Calabanga 50.00
Project Energy (CARE), Inc. issuance of reminder letter due non
compliance with RESHERR.
Del Gallego Solar Power Sun Premier Sud Philippine Compliance with Milestone Approach is on
Del Gallego
Project Corporation going.
Compliant with Milestone Approach. For
Catanduanes Solar Power Local Government Unit of
Catanduanes Caramoran issuance of reminder letter due to non 1.00
Project Caramoran
compliance with RESHERR.
LUZON Sum 2,609.95 283.73
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Helios Solar Energy Corp. Under Commercial Stage (FIT System).
Negros
VISAYAS VI Cadiz City Cadiz Solar Power Project (formerly Phil-Power Solar Compliant with all work and financial 132.50
Occidental
Energy Corp.) obligations.
San Carlos Solar Power Under Commercial Stage (FIT System). For
San Carlos City Project Phase I-A and I-B San Carlos Solar Energy Inc. issuance of reminder letter due to non 22.00
(SACASOL I-A&I-B) compliance with RESHERR.
San Carlos Solar Power Under Commercial Stage (FIT System). For
Project Phase I-C and I-D San Carlos Solar Energy Inc. issuance of reminder letter due to non 23.00
(SACASOL I-C&I-D) compliance with RESHERR.
Amended DOC to merge SACASOL II-A and II-
La Carlota Solar Power Negros Island Solar Power B. For issuance of reminder letter to settle all
La Carlota City 18.00
Project (SACASOL II-A) Inc. its Financial obligations (i.e. Training
Assistance and Development Assistance).

Under Development Stage (FIT System). On-


going construction/commissioning. Subject for
Negros Island Solar Power
Islasol Solar Power Project on-site validation of its Successful 32.00
Inc.
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
Energy Development Request for voluntary surrender of SESC is
Bago Bago Solar Power Project
Corporation under evaluation.
Under Development Stage (FIT System). On-
going construction/commissioning. Subject for
Manapla and Manapla Solar Power Project Negros Island Solar Power
on-site validation of its Successful 48.00
Cadiz (SACASOL III) Inc.
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
Under Commercial Stage (FIT System). For
Bais City Solar Power Project
Bais City Monte Solar Energy Inc. issuance of reminder letter due to non 18.00
(SACASOL IV)
compliance with RESHERR.
Compliant with Milestone Approach. For
Energy Development
Murcia Murcia Solar Power Project issuance of reminder letter due to non
Corporation
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Development Stage (FIT System). For
VictoriaSolar Energy Corp.
Negros issuance of show-cause letter due to delayed
VISAYAS VI Victorias City Victorias Solar Power Project (formerly SunAsia Energy 60.00
Occidental implementation of 5-Year Work Plan and non-
Inc.)
compliance with RESHERR.
Amended DOC to merge SACASOL II-A and II-
La Carlota Solar Power Negros Island Solar Power B. For issuance of reminder letter to settle all
La Carlota City 14.00
Project (SACASOL II-B) Inc. its Financial obligations (i.e. Training
Assistance and Development Assistance).
La Carlota Solar Power Request for suspension of obligation is under
Megawatt Clean Energy, Inc.
Project evaluation.

Under Development Stage(FIT System).


Approved Assignment to Silay Solar Power,Inc.
Silay Solar Power, Inc.
On-going construction/commissioning.
Silay City Silay Solar Power Project (formerly Megawatt Clean 25.01
Subject for on-site validation of its Successful
Energy, Inc.)
Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.

Under Development Stage (FIT System). On-


going construction/commissioning. Subject for
SACASUN Solar Power
San Carlos City San Carlos Sun Power Inc. on-site validation of its Successful 58.98
Project
Commissioning. Compliant with all work and
financial obligations.
DOC (FIT System) is under evaluation. For
Bacolod City Solar Power
Bacolod City Negros PH Solar Inc. issuance of reminder letter due to non- 200.00
Project II
compliance with RESHERR.
No submission of reports regarding
Amatera Renewable Energy compliance to its Milestone Approach. For
Bacolod Solar Power Project 50.00
Corporation issuance of reminder letter due non-
compliance with RESHERR.
No submission of reports regarding
Bacolod City and compliance with its Milestone Approach. For
Murcia Solar Power Project PH Solar Advance Corp. 120.00
Murcia issuance of reminder letter due non-
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Compliant with Milestone Approach. For
Negros Oxy Solar Manapla
VISAYAS VI Manapla Manapla Solar Power Project issuance of reminder letter due non- 5.00
Occidental Corporation
compliance with RESHERR.
Under Development Stage (FIT System). On-
Iloilo Miag-ao Miag-ao Solar Power Project Cosmo Solar Energy, Inc. going commissioning. Subject for on-site 5.67
validation of its Successful Commissioning.
Under Development Stage (FIT System). For
Solexar Energy International, issuance of show-cause letter due to delayed
Iloilo Tigbauan Tigbauan Solar Power Project 34.30
Inc. implementation of 5-Year Work Plan and non-
compliance with RESHERR.
For issuance of Termination letter due to non-
Roxas City Solar Power Solar Philippines Commercial compliance with Milestone Approach,
Capiz Roxas City 0.70
Project Rooftop Projects, Inc. RESHERR and non posting of Performance
Bond.
DOC (FIT System) is under evaluation. For
Daanbantayan Solar Power Ceko Solar Farm Systems
VII Cebu DaanBantayan issuance of reminder due to non compliance 25.00
Project Corporation
with RESHERR.
Under Development Stage (FIT System). On-
First Toledo Solar Energy going construction/commissioning. Subject for
Toledo Solar Power Project
Toledo Corp. (formerly SunAsia on-site validation of its Successful 60.00
Phase 1
Energy Inc.) Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
Energy Development For issuance of reminder letter due to non-
Bogo Bogo Solar Power Project
Corporation compliance with RESHERR.
Sun Premier Bogo Philippine Compliance with Milestone Approach is on
Bogo III Solar Power Project
Corporation going.
Sun Premier Bogo Philippine Compliance with Milestone Approach is on
Bogo V Solar Power Project 16.70
Corporation going.
No submission of reports regarding
Menlo Renewable Energy compliance to its Milestone Approach. For
Naga Naga Solar Power Project 60.00
Corp. issuance of reminder letter due non-
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
No submission of reports regarding
Negros compliance to its Milestone Approach. For
VISAYAS VII Mabinay Mabinay Solar Power Project Lohas & Soul Lighting Inc. 90.00
Oriental issuance of reminder letter due non-
compliance with RESHERR.
Request for reconsideration of its compliance
under milestone approach is denied. For
VIII Leyte Ormoc Leyte Solar Power Project II Phil. Solar Farm-Leyte, Inc. 30.00
issuance of Termination Letter due to non-
compliance with Milestone Approach.
Under Commercial Stage (FIT System).
Ormoc Solar Power Project Phil. Solar Farm-Leyte, Inc. Compliant with all work and financial 30.00
obligations.
Under Development Stage (FIT System). On-
going construction/commissioning. Subject for
Tacloban, Santa Sulu Electric Power and Light
Palo Solar Power Project on-site validation of its Successful 49.81
Fe and Palo (Phils.), Inc.
Commissioning. Compliant with all work and
financial obligations.
Under Development Stage (FIT System). For
issuance of show-cause letter due to delayed
Biliran Biliran Biliran Solar Power Project E & P Green Energy, Inc. 25.00
implementation of 5-Year Work Plan and non-
compliance with RESHERR.
VISAYAS Sum 1,028.17 225.50
DOC (PSA) is under evaluation. For issuance of
Zamboanga del La Libertad and Zamboanga del Norte Solar Astronergy Development
MINDANAO IX reminder letter due to non compliance with 5.00
Norte Dapitan Power Project Dipolog Inc.
RESHERR.
Under Commercial Stage (PSA with CEPALCO -
ERC approved PHP 8.75 per kWh). DOC and
Misamis Kirahon Solar Energy partial assignment to Kirahon Two Energy
X Villanueva Kirahon Solar Power Project 12.50
Oriental Corporation Corp. are under evaluation. For issuance of
reminder letter due to non compliance with
RESHERR.
Under Commercial Stage (FIT System). For
Bukidnon Kibawe Kibawe Solar Power Project Asian Greenenergy Corp. issuance of reminder letter due to non 10.49
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
DOC (PSA) is under evaluation. For issuance of
Bukidnon Solar Power
MINDANAO X Bukidnon Sumilao SunAsia Energy Inc. remider letter due to non compliance with 2.00
Project
RESHERR.
Liberty Solar Energy
DOC (PSA) is under evaluation. For issuance of
Misamis Laguindingan Solar Power Corporation (formerly
Laguindingan reminder letter due to non compliance with 20.00
Oriental Project Cagayan Electric Power &
RESHERR.
Light Company, Inc.)
Compliant with Milestone Approach. DOC is
The Ark Green Dynamic
Claveria Claveria Solar Power Project under evaluation. For issuance of reminder 60.00
Resources Corp.
letter due to non compliance with RESHERR.
For issuance of Termination Letter due to non-
Misamis Oriental Solar Astronergy Development
Balingasag compliance with Milestone Approach and
Power Project Mindanao, Inc.
RESHERR.
Tagoloan &
Cagayan de Oro
Solar Philippines Commercial Request for reduction of contract area is on
City and Libona, Tagoloan Solar Power Project 45.00
Rooftop Projects, Inc. process.
Manolo Fortich &
Malitbog
No submission of reports regarding
compliance with its Milestone Approach. For
Jasaan Jasaan Solar Power Project Lohas & Soul Lighting Inc. 60.00
issuance of reminder letter due non-
compliance with RESHERR.
Expired SESC. For issuance of reminder letter
to settle all its Financial Obligations (i.e.
XI Davao del Sur Sta. Cruz Darong Solar Power Project PhilNewEnergy, Inc. 35.00
Training Assistance and Development
Assistance).
For issuance of Termination letter due to non-
Davao Oriental Solar Power Sun Option for Livelihood
Davao Oriental Mati City compliance with Milestone Approach and 60.00
Project Alternative Resources Inc.
RESHERR
Under Development Stage (FIT System). On-
Enfinity Philippines going construction/commissioning. Subject for
Davao del Sur Digos City Digos Solar Power Project Renewable Resources on-site validation of its Successful 28.59
Fourth, Inc. Commissioning. For issuance of reminder
letter due to non compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
Under Commercial Stage (FIT System ). For
nv vogt Philippines Solar
MINDANAO XII South Cotabato Surallah Centrala Solar Power Project issuance of reminder letter due to non- 6.23
Energy One, Inc.
compliance with RESHERR.
DOC (PSA) is under evaluation. With 19
February 2016 letter requesting additional
General Santos South Cotabato Solar Power Astronergy Development
document for SESC Assignment. For issuance 20.00
City Project GenSan Inc.
of reminder letter due to non- compliance
with RESHERR.
Under Development Stage (FIT System). For
GenSan Solar Power Project issuance of show-cause letter due to delayed
Del Sol Energy CGS, Inc. 48.00
Phase I implementation of 5-Year Work Plan and non-
compliance with RESHERR.
Under Development Stage (FIT System). For
GenSan Solar Power Project issuance of show-cause letter due to delayed
Del Sol Energy CGS, Inc. 48.00
Phase II implementation of 5-Year Work Plan and non-
compliance with RESHERR.
SolarPacific Energy Request for suspension of its obligation or
Sarangani Alabel Alabel Solar Power Project 15.00
Corporation moratorium is under evaluation.
North President Roxas President Roxas Solar Power Energy Development Request for voluntary surrender of SESC is
Cotabato and Magpet Project Corporation under evaluation.
Kilada-Matalam Solar Power Energy Development Request for voluntary surrender of SESC is
Matalam
Project Corporation under evaluation.
With 15 February 2016 letter requesting
El Elyon Power Plant Phils. additional DOC documents. For issuance of
Sarangani Alabel Alabel Solar Power Project 160.00
Inc. reminder letter due to non-compliance with
RESHERR.
Natures Renewable Energy
Maasim Hybrid Solar Power Compliance with Milestone Approach is on
Maasim Dev't. (NAREDCO) 100.00
Project going.
Corporation
For issuance of Termination Letter due to non-
Agusan del Butuan City 1 Solar Power Enfinity Philippines
XIII Butuan City compliance with Milestone Approach and 10.00
Norte Project Renewable Resources Inc.
RESHERR.
No submission of reports regarding
San Francisco Solar Power compliance to its Milestone Approach. For
Agusan del Sur San Francisco GPower Inc. 10.00
Project issuance of reminder letter due non-
compliance with RESHERR.
AWARDED SOLAR PROJECTS as of June 30, 2016
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
For issuance of Termination Letter due to
expiration of SESC, non-posting of
Tagoloan II, Performance Bond, non-compliance with
Local Government Unit of
MINDANAO ARMM Lanao del Sur Saguiaran & ICOM Solar Power Project RESHERR, delayed implementation of 2-Year 35.00
the Islamic City of Marawi
Marawi City Work Program, and non-submission of
documentary requirements for its DOC (FIT
System).
MINDANAO Sum 761.59 29.22
Grand Total 4,399.71 538.45