You are on page 1of 4

SAUDI ARAMCO ID/PID FORM REV 7 - 010109 Rev 8 COS 30-June-14

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Paint Application of Liquid Coating Systems (Industrial Facilities) SATIP-H-100-01 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Coating Procedure SAIC-H-2023 RH RH

Coating Personnel Qualification &


Certification Card
SAIC-H-2010
1.2 a) Blaster RH RH
b) Paint applicator
c) Crew supervisor

2.0 MATERIAL RECEIVING

Verification and Visual Inspection of


2.1 SAIC-H-2024 SAIC-H-2024 H W
Paints and abrasives
Storage and Handling of Paints and
2.2 SAIC-H-2025 SAIC-H-2025 H W
Abrasives

2.3 Equipment Inspection SAIC-H-2026 SAIC-H-2026 H H Use SATR-H-2006

3.0 APPLICATION

Inspection of Surface Preparation & Prior


3.1 to Application of liquid coating systems SAIC-H-2027 SAIC-H-2027 H W Use SATR-H-2006
(New Installations)

In-Process Inspection of Primer Coat OR


3.2 SAIC-H-2028 SAIC-H-2028 H W Use SATR-H-2006
First Coat Application

Inspection of Primer Coat prior to top


3.3 SAIC-H-2029 SAIC-H-2029 H W Use SATR-H-2006
coating

In-Process Inspection of Intermediate


3.4 SAIC-H-2030 SAIC-H-2030 H S Use SATR-H-2006
and/or Top Coat Application

Inspection of Top Coat Application


3.5 SAIC-H-2031 SAIC-H-2031 H W Use SATR-H-2006
(Dry/Cured Coating)

Inspection of Repair/Touch-up of
3.6 SAIC-H-2032 SAIC-H-2032 H W Use SATR-H-2006
Coatings

Page 1 of 4
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Paint Application of Liquid Coating Systems (Industrial Facilities) SATIP-H-100-01 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Safety Color coding and Stenciling of


3.7 SAIC-H-2033 SAIC-H-2033 W W
Identification on Equipment/piping

4.0 PRE-COMMISSIONING

Final Coating Inspection/ Punchlisting


4.1 SAIC-H-2034 SAIC-H-2034 H W Use SATR-A-2011
(Contractor)
Mechanical Completion Punch listing
4.2 SA-6133 H
(Saudi Aramco)

GENERAL NOTES

1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
2
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
3
attendance.
4 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 4
DISCIPLINE:

MECHANICAL
CONTRACTOR/SUBCONTRACTOR

REMARKS

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Page 3 of 4
DISCIPLINE:

MECHANICAL
CONTRACTOR/SUBCONTRACTOR

REMARKS

Use SATR-A-2011

GENERAL NOTES

Construction Organization
in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization

in advance. Inspection or test shall not be carried out without the QA/QC organization representative in

en the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
Review of Documents
Review and Approval of Documents
100% Contractor Inspection

Page 4 of 4

You might also like