PRESUPUESTO ESTIMADO

CLIENTE :

OC:
PROYECTO : IMPLEMENTACION DE INFRAESTRUCTURA
SUB PROYECTO : AREA ALMACENES - LACTARIO - MECANICA
UBICACIN : CUSCO

FECHA :

Item Descripcin Unidad Metrado C.Unitario C.Parcial Sub Totales

1.00.00 OBRASPROVICIONALES TOTALES 10,544.64


1.00.01 TRANSPORTEDEMATERIALESAOBRA GLB 1.00 1,000.00 1,000.00
1.00.02 salud ocupacional glb 1.00 1,500.00 1,500.00
1.00.03 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 72.00 5.00 360.00
1.00.04 NIVELACION DEL TERRENO m2 72.00 11.00 792.00
1.00.05 COMPACTACION DEL TERRENO m2 72.00 24.00 1,728.00
1.00.06 DEMOLICION DE MUROS y techos EXISTENTES CON MAQU m2 72.00 32.00 2,304.00
1.00.07 habilitacion de acceso a estacionamiento glb 1.00 800.00 800.00
1.00.08 Acarreo de desmonte y restos de obra m3 38.88 25.00 972.00
1.00.09 ELIMINACINDEMATERIALEXCEDENTE m3 38.88 28.00 1,088.64

2.00.00 Trabajos en concreto armado 12,035.00


2.00.01 Concreto armado kfc 175kgr/cm2 m3 19.50 420.00 8,190.00
2.00.02 Fierro fc kgr 400.00 6.20 2,480.00
2.00.03 Encofrado y desencofrado ml 30.00 45.50 1,365.00

4.00.00 Trabajos revoques y acabados 1,200.00


3.00.01 Resane de paredes m2 80.00 15.00 1,200.00

5.00.00 Trabajos de cobertura 5,200.00


6.00.01 Mejoramiento de cobertura existente m2 80.00 65.00 5,200.00

6.00.00 Instalaciones elctricas 3,926.00


10.00.01 Salida de tomacorrientes pto 10.00 52.00 520.00
10.00.02 Salida centro de luz interiores pto 8.00 27.00 216.00
10.00.03 Salida de interuptor pto 6.00 51.00 306.00
10.00.05 Placa tomacorriente und 10.00 10.00 100.00
10.00.06 Placa interutpr und 6.00 10.00 60.00
10.00.07 Luminarias und 8.00 28.00 224.00
10.00.10 cableado electrico glb 1.00 1,000.00 1,000.00
10.00.09 Tablero general glb 1.00 1,500.00 1,500.00

7.00.00 Trabajos de carpinteria 500.00


11.00.07 MANTENIMIENTO DE PUERTAS EXISTENTES und 5.00 100.00 500.00

8.00.00 Trabajos de carpinteria METALICA 2,000.00


8.00.01 PORTON DE INGRESO GLB 1.00 2,000.00 2,000.00

9.00.00 Trabajos de pintura 9,000.00


9.00.01 Pintura en interiores y exteriores m2 600.00 15.00 9,000.00

Costo Directo 44,405.64


Utilidad -
Gastos Generales -
Sub total 44,405.64
Igv 18% 7,993.02
Costo Total 52,398.66
PRESUPUESTO ESTIMAD

CLIENTE :

OC:
PROYECTO : IMPLEMENTACION DE INFRAESTRUCTURA
SUB PROYECTO : OFICINAS ADMINISTRATIVAS
UBICACIN : CUSCO

Item Descripcin Unidad

1.00.00 Trabajos preliminares


1.00.01 Movilizacin y desmovilizacin de persona y material glb
1.00.02 Salud ocupacional - bienestar glb
1.00.03 Trazo y replanteo m2
1.00.04 Desmontaje de instalaciones existentes glb
1.00.05 Picado de piso ceramico m2
1.00.06 Acarreo de desmonte y restos de obra m3
1.00.07 Eliminacin de desmonte y restos de obra m3

3.00.00 Trabajos revoques y acabados


3.00.01 resane de paredes m2

4.00.00 Pisos y pavimentos


3.00.01 Piso enchape en porcelanato rustico m2
3.00.02 zocalo ceramico ml

6.00.00 Trabajos de cobertura


6.00.01 Sellado de cobertura en mal estado m2
6.00.03 Canaleta pluvial + soportes ml
6.00.04 Bajante pluvial de 4'' und

7.00.00 Trabajos en drywall


7.00.01 Cielo Razo suspendido m2
7.00.02 Tabiqueria de drywall m2
7.00.03 Refuerzo de techo glb

8.00.00 Instalaciones elctricas


8.00.01 Salida de tomacorrientes pto
8.00.02 Salida centro de luz interiores pto
8.00.04 Salida de interruptor pto
8.00.05 Salida de data cat 5 pto
8.00.06 Placa tomacorriente und
8.00.07 Placa interruptor und
8.00.08 Luminarias fluorecente con rejilla und
8.00.09 Placa de data und
8.00.11 cableado elctrico glb
8.00.12 Tablero general glb
8.00.14 pozo a tierra glb

9.00.00 Instalaciones sanitarias


9.00.04 COLOCACION DE LAVATORIOS und
9.00.05 LLAVES DE LAVATORIOS und
9.00.06 INODOROS EN SS.HH und
9.00.07 URINARIO und
9.00.08 FLUXOMETRO PARA URINARIO VAINSA und
9.00.09 SUMIDEROS DE BRONCE DE 2'' und
9.00.10 PAPELERA, TOALLERO, DISPENSADOR DE JABON und
9.00.11 suministro e instalacion de cubiculo und

9.00.00 Trabajos de carpintera


9.00.01 Modulo de oficina und
9.00.02 Modulo de oficina en L und
9.00.03 escritorio de gerencia und
9.00.04 Mesa de reuniones und
9.00.05 Cafetin und
9.00.06 credesa und
9.00.07 archivadores und

10.00.00 Trabajos de pintura


10.00.01 pintura de paredes m2

11.00.00 Trabajos de vidrio


11.00.01 ventanas m2
11.00.02 puerta ingreso und
11.00.03 puerta GG encapsulada und
11.00.04 puerta reuniones encapsulada und
11.00.05 puerta reuniones und
11.00.04 puertas corrediza und

12.00.00 Trabajos de contingencia


12.00.01 Habilitacion de oficinas containers und

13.00.00 Trabajos de ventilacion


13.00.01 ventilacion de ambientes glb
SUPUESTO ESTIMADO

Metrado C.Unitario C.Parcial Sub Totales

6,080.60
1.00 1,000.00 1,000.00
1.00 1,500.00 1,500.00
102.00 5.00 510.00
1.00 1,000.00 1,000.00
102.00 15.00 1,530.00
10.20 25.00 255.00
10.20 28.00 285.60

3,312.00
220.80 15.00 3,312.00

7,526.00
102.00 58.00 5,916.00
64.40 25.00 1,610.00

3,059.60
112.20 18.00 2,019.60
18.00 50.00 900.00
4.00 35.00 140.00

11,972.00
112.20 60.00 6,732.00
54.00 60.00 3,240.00
1.00 2,000.00 2,000.00

7,485.00
25.00 52.00 1,300.00
15.00 27.00 405.00
5.00 51.00 255.00
13.00 35.00 455.00
25.00 10.00 250.00
5.00 10.00 50.00
15.00 38.00 570.00
25.00 20.00 500.00
1.00 1,200.00 1,200.00
1.00 1,500.00 1,500.00
1.00 1,000.00 1,000.00

2,235.00
2.00 280.00 560.00
2.00 80.00 160.00
2.00 320.00 640.00
1.00 180.00 180.00
1.00 80.00 80.00
1.00 35.00 35.00
1.00 80.00 80.00
2.00 250.00 500.00

12,150.00
10.00 220.00 2,200.00
3.00 300.00 900.00
1.00 450.00 450.00
2.00 500.00 1,000.00
1.00 2,500.00 2,500.00
3.00 1,200.00 3,600.00
6.00 250.00 1,500.00

3,312.00
220.80 15.00 3,312.00

3,759.20
16.20 16.00 259.20
1.00 1,000.00 1,000.00
1.00 500.00 500.00
1.00 550.00 550.00
2.00 500.00 1,000.00
1.00 450.00 450.00

6,000.00
3.00 2,000.00 6,000.00

550.00
1.00 550.00 550.00

Costo Directo 67,441.40


Utilidad -
Gastos Generales - USD
Sub total 67,441.40 20,437
Igv 18% 12,139.45
Costo Total 79,580.85
PRESUPUESTO ESTIMADO

CLIENTE :

OC:
PROYECTO : IMPLEMENTACION DE INFRAESTRUCTURA
SUB PROYECTO : ZONA DE SERVICIO
UBICACIN : CUSCO

Item Descripcin Unidad Metrado C.Unitario C.Parcial Sub Totales

1.00.00 Trabajos preliminares 82,692.97


1.00.01 Movilizacin y desmovilizacin de persona y material glb 1.00 1,000.00 1,000.00
1.00.02 Trazo y replanteo m2 52.37 1,500.00 78,555.00
1.00.03 Desmontaje de instalaciones existentes glb 1.00 1,000.00 1,000.00
1.00.04 Corte y excavacin de concreto para columnas de made und 10.00 50.00 500.00
1.00.05 Picado de falso piso m2 43.82 23.00 1,007.86
1.00.06 retiro de pintura en pared m2 21.12 15.00 316.80
1.00.07 Acarreo de desmonte y restos de obra m3 9.17 25.00 229.31
1.00.08 Eliminacin de desmonte y restos de obra vje 3.00 28.00 84.00

2.00.00 Trabajos en concreto simple -


2.00.01 Concreto armado kfc 201kgr/cm2 m3 3.58 -

3.00.00 Trabajos revoques y acabados 27,879.84


3.00.01 Forjado de pared m2 22.88 420.00 9,609.60
3.00.02 Aplicacin de primer en pares exteriores e interiores m2 22.88 450.00 10,296.00
3.00.03 Solaqueo de paredes exteriores e interiores m2 22.88 50.00 1,144.00
3.00.04 Tarrajeo de paredes exteriores en barro rustico y con p m2 22.88 40.00 915.20
3.00.05 Sellado de tarrajeo de paredes exteriores en barro rusti m2 22.88 38.00 869.44
3.00.06 Enchape de piedra rustica de forma irregular altura ap ml 8.80 65.00 572.00
3.00.07 Sobreciomiento en piedra rustica de forma irregular alt ml 10.80 380.00 4,104.00
3.00.08 Aplicacin de sellador mate en piedra ml 8.80 42.00 369.60

4.00.00 Pisos y pavimentos 2,420.00


3.00.01 Piso cemento semi pulido m2 44.00 55.00 2,420.00

5.00.00 Trabajos carpintera metlica 1,200.00


5.00.01 Puerta metlica decorativa para interiores pasadizo und 1.00 1,200.00 1,200.00

6.00.00 Trabajos de cobertura 12,163.48


6.00.01 Suministro e instalacion de policarbonato m2 52.58 220.00 11,568.48
6.00.03 Canaleta pluvial + soportes ml 10.70 50.00 535.00
6.00.04 Bajante pluvial de 4'' und 2.00 30.00 60.00

7.00.00 Instalaciones elctricas 5,175.00


7.00.01 Salida de tomacorrientes pto 4.00 52.00 208.00
7.00.02 Salida centro de luz interiores pto 8.00 27.00 216.00
7.00.03 Salida centro de luz exteriores pto 5.00 27.00 135.00
7.00.04 Salida de interruptor pto 2.00 51.00 102.00
7.00.05 Salida de data cat 5 pto 4.00 35.00 140.00
7.00.06 Placa tomacorriente hidrobox und 4.00 20.00 80.00
7.00.07 Placa interruptor und 2.00 10.00 20.00
7.00.08 Luminarias und 13.00 38.00 494.00
7.00.09 Placa de data und 4.00 20.00 80.00
7.00.10 cableado elctrico glb 1.00 1,200.00 1,200.00
7.00.11 Tablero general glb 1.00 1,500.00 1,500.00
7.00.12 Troncal elctrica glb 1.00 1,000.00 1,000.00

8.00.00 Trabajos de carpintera 12,715.12


8.00.01 Modulo de informes und 1.00 400.00 400.00
8.00.02 Bancas und 3.00 450.00 1,350.00
8.00.03 Kiosko und 1.00 1,500.00 1,500.00
8.00.04 Estructura de techo viga columna m2 52.58 180.00 9,465.12

9.00.00 Trabajos de pintura 3,295.97


9.00.01 Pintura en celosilla de madera ml 10.80 52.00 561.60
9.00.02 Pintura en estructura vigas y columnas m2 52.58 52.00 2,734.37

Costo Directo 147,542.37


PRESUPUESTO ESTIMADO

CLIENTE :

OC:
PROYECTO : IMPLEMENTACION DE INFRAESTRUCTURA
SUB PROYECTO : ZONA DE SERVICIO
UBICACIN : CUSCO

Item Descripcin Unidad Metrado C.Unitario C.Parcial Sub Totales

Utilidad -
Gastos Generales -
Sub total 147,542.37
Igv 18% 26,557.63
Costo Total 174,100.00