You are on page 1of 6

The Zone Classis WBS Layout 21-May-17 13:51

Activity ID Activity Name Original Duration Start Finish Predecesso

The Zone 185 10-Apr-17 11-Nov-17


Mobilization 40 10-Apr-17 25-May-17
Shop Drawings 60 10-Apr-17 18-Jun-17
Procurement 0
Site & Structural Works 185 10-Apr-17 11-Nov-17
Excavation 28 10-Apr-17 11-May-17
Building A1 7 10-Apr-17 17-Apr-17
EXC1000 Excavation up to Foundation Level 7 10-Apr-17 17-Apr-17
Building A2 7 16-Apr-17 23-Apr-17
W.F.tank 10 19-Apr-17 30-Apr-17
Building B1 12 16-Apr-17 29-Apr-17
Building B1` 6 16-Apr-17 22-Apr-17
Building B2 18 10-Apr-17 30-Apr-17
Building B2` 18 10-Apr-17 30-Apr-17
Building C1 17 10-Apr-17 29-Apr-17
Building C1` 17 10-Apr-17 29-Apr-17
Building C2 16 10-Apr-17 27-Apr-17
Building C2` 16 10-Apr-17 27-Apr-17
Building D1 16 10-Apr-17 27-Apr-17
Building D1` 16 10-Apr-17 27-Apr-17
Building D2 14 10-Apr-17 25-Apr-17
Building D2` 14 10-Apr-17 25-Apr-17
Building E 22 10-Apr-17 04-May-17
Parking 1 28 10-Apr-17 11-May-17
Parking 2 28 10-Apr-17 11-May-17
Concrete 185 10-Apr-17 11-Nov-17
Building A1 134 18-Apr-17 20-Sep-17
PC Footing 4 18-Apr-17 22-Apr-17
CON0999 Shuttering PC Footing 1 18-Apr-17 18-Apr-17 EXC1000
CON1000 Anti Termite & Vapour Barrier 1 19-Apr-17 19-Apr-17 CON0999
CON1010 Plain Concrete 1 20-Apr-17 20-Apr-17 CON1000
CON1560 De Shuttering 1 22-Apr-17 22-Apr-17 CON1010
RC Footing 7 23-Apr-17 30-Apr-17
CON1020 Foundation Shuttering 2 23-Apr-17 24-Apr-17 CON1560
CON1030 Foundation Steel Fixing 3 25-Apr-17 27-Apr-17 CON1020

Page 1 of 6 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 21-May-17 13:51
Activity ID Activity Name Original Duration Start Finish Predecesso

CON1040 Foundation Concrete Pouring 1 29-Apr-17 29-Apr-17 CON1030


CON1050 Foundation De Shuttering 1 30-Apr-17 30-Apr-17 CON1040
Neck Column 7 01-May-17 08-May-17
CON1060 Neck Steel Fixing 3 01-May-17 03-May-17 CON1050
CON1070 Neck Shuttering 2 04-May-17 06-May-17 CON1060
CON1080 Neck Concrete Pouring 1 07-May-17 07-May-17 CON1070
CON1090 Neck De Shuttering 1 08-May-17 08-May-17 CON1080
Damp Proofing 2 09-May-17 10-May-17
CON1100 Foundation Damp Proofing 1 09-May-17 09-May-17 CON1090
CON1110 Neck Column Damp Proofing 1 10-May-17 10-May-17 CON1100
Back Filling 4 14-May-17 17-May-17
CON1120 Foundation Backfilling 4 14-May-17 17-May-17 ELE10790
Ground Beam 11 18-May-17 30-May-17
CON1121 Plain Concrete Shuttering & Vapour Barrier 1 18-May-17 18-May-17 CON1120
CON1122 Pouring Plain Concrete 1 20-May-17 20-May-17 CON1121
CON1123 De Shuttering Plain Concrete 1 21-May-17 21-May-17 CON1122
CON1130 Ground Beam Shuttering 3 22-May-17 24-May-17 CON1123
CON1140 Ground Beam Steel Fixing 3 25-May-17 28-May-17 CON1130
CON1150 Ground Beam Concrete Pouring 1 29-May-17 29-May-17 CON1140
CON1160 Ground Beam De Shuttering 1 30-May-17 30-May-17 CON1150
GB Damp Proofing 1 31-May-17 31-May-17
CON1170 Ground Beam Damp Proofing 1 31-May-17 31-May-17 CON1160
GB Back Filling 3 01-Jun-17 04-Jun-17
CON1180 Ground Beam Backfilling 3 01-Jun-17 04-Jun-17 CON1170
Slab on Grade 4 05-Jun-17 08-Jun-17
CON1185 Anti Termite & Vapour Barrier 1 05-Jun-17 05-Jun-17 CON1180
CON1190 SOG Steel Fixing 1 06-Jun-17 06-Jun-17 CON1185
CON1200 SOG Concrete Pouring 1 08-Jun-17 08-Jun-17 MECH120
Ground Column 9 10-Jun-17 19-Jun-17
CON1210 Ground Column Steel Fixing 4 10-Jun-17 13-Jun-17 CON1200
CON1220 Ground Column Shuttering 3 14-Jun-17 17-Jun-17 CON1210
CON1230 Ground Column Concrete Pouring 1 18-Jun-17 18-Jun-17 CON1220
CON1240 Ground Column De Shuttering 1 19-Jun-17 19-Jun-17 CON1230

Page 2 of 6 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 21-May-17 13:51
Activity ID Activity Name Original Duration Start Finish Predecesso

First Slab 27 20-Jun-17 20-Jul-17


CON1250 First Slab Shuttering 8 20-Jun-17 28-Jun-17 CON1240
CON1260 First Slab Steel Fixing 4 29-Jun-17 03-Jul-17 CON1250
CON1270 First Slab Concrete Pouring 1 09-Jul-17 09-Jul-17 MECH400
CON1275 Curing 7 10-Jul-17 17-Jul-17 CON1270
CON1280 First Slab De Shuttering 3 18-Jul-17 20-Jul-17 CON1275
First Column 9 22-Jul-17 31-Jul-17
CON1290 First Column Steel Fixing 4 22-Jul-17 25-Jul-17 CON1280
CON1300 First Column Shuttering 3 26-Jul-17 29-Jul-17 CON1290
CON1310 First Column Concrete Pouring 1 30-Jul-17 30-Jul-17 CON1300
CON1320 First Column De Shuttering 1 31-Jul-17 31-Jul-17 CON1310
Roof Slab 24 01-Aug-17 28-Aug-17
CON1330 Roof Slab Shuttering 6 01-Aug-17 07-Aug-17 CON1320
CON1340 Roof Slab Steel Fixing 3 08-Aug-17 10-Aug-17 CON1330
CON1350 Roof Slab Concrete Pouring 1 16-Aug-17 16-Aug-17 MECH401
CON1355 Curing 7 17-Aug-17 24-Aug-17 CON1350
CON1360 Roof Slab De Shuttering 3 26-Aug-17 28-Aug-17 CON1355
Roof Column and P
Parapet 7 29-Aug-17 05-Sep-17
Concrete 4 29-Aug-17 02-Sep-17
Block 3 03-Sep-17 05-Sep-17
Upper Roof Slab 6 06-Sep-17 12-Sep-17
CON1420 Upper Roof Slab Shuttering 2 06-Sep-17 07-Sep-17 CON1410
CON1430 Upper Roof Slab Steel Fixing 2 09-Sep-17 10-Sep-17 CON1420
CON1440 Upper Roof Slab Concrete Pouring 1 11-Sep-17 11-Sep-17 CON1430
CON1450 Upper Roof Slab De Shuttering 1 12-Sep-17 12-Sep-17 CON1440
Block Work Ground Floor 7 13-Sep-17 20-Sep-17
CON1480 Block Work For Ground Floor 7 13-Sep-17 20-Sep-17 CON1450
Block Work First Floor
Flo 5 14-Sep-17 19-Sep-17
CON1470 Block Work First Floor 5 14-Sep-17 19-Sep-17 CON1480
Block Work Roof Floor
Fl 1 16-Sep-17 16-Sep-17
CON1460 Block Works For Roof Floor 1 16-Sep-17 16-Sep-17 CON1470
Building A2 134 18-Apr-17 20-Sep-17
Building B1 168 30-Apr-17 11-Nov-17
Water Tank 37 01-May-17 12-Jun-17

Page 3 of 6 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 21-May-17 13:51
Activity ID Activity Name Original Duration Start Finish Predecesso

Building B1` 162 10-Apr-17 15-Oct-17


Building B2 0
Building B2` 0
Building C1 5 10-Apr-17 15-Apr-17
Building C1` 5 10-Apr-17 15-Apr-17
Building C2 5 10-Apr-17 15-Apr-17
Building C2` 5 10-Apr-17 15-Apr-17
Building D1 5 10-Apr-17 15-Apr-17
Building D1` 5 10-Apr-17 15-Apr-17
Building D2 5 10-Apr-17 15-Apr-17
Building D2` 5 10-Apr-17 15-Apr-17
Building E 5 10-Apr-17 15-Apr-17
Parking 1 0
Parking 2 0
Mechanical Works 149 10-Apr-17 30-Sep-17
Building A1 99 07-Jun-17 30-Sep-17
Ground Floor 99 07-Jun-17 30-Sep-17
MECH1200 Plumbings 4 07-Jun-17 11-Jun-17 CON1190
MECH1205 Drainage System 1 07-Jun-17 07-Jun-17 MECH120
MECH1210 Water Supply System 3 21-Sep-17 24-Sep-17 CON1480
MECH1230 Fire Fighting 5 25-Sep-17 30-Sep-17 MECH121
First Floor 75 04-Jul-17 28-Sep-17
MECH4000 Plumbings 4 04-Jul-17 08-Jul-17 CON1260
MECH4005 Drainage System 1 04-Jul-17 04-Jul-17 MECH400
MECH4020 Water Supply System 3 20-Sep-17 23-Sep-17 CON1470
MECH4060 Fire Fighting 5 24-Sep-17 28-Sep-17 MECH402
Roof Floor 39 12-Aug-17 25-Sep-17
MECH4010 Plumbings 4 12-Aug-17 15-Aug-17 CON1340
MECH4015 Drainage System 1 12-Aug-17 12-Aug-17 MECH401
MECH4030 Water Supply System 3 17-Sep-17 19-Sep-17 CON1460
MECH4070 Fire Fighting 5 20-Sep-17 25-Sep-17 MECH403
Building A2 9 10-Apr-17 19-Apr-17
W.F.tank 15 10-Apr-17 26-Apr-17
Building B1 67 10-Apr-17 26-Jun-17
Building B1` 9 10-Apr-17 19-Apr-17

Page 4 of 6 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 21-May-17 13:51
Activity ID Activity Name Original Duration Start Finish Predecesso

Building B2 67 10-Apr-17 26-Jun-17


Building B2` 9 10-Apr-17 19-Apr-17
Building C1 67 10-Apr-17 26-Jun-17
Building C1` 9 10-Apr-17 19-Apr-17
Building C2 67 10-Apr-17 26-Jun-17
Building C2` 9 10-Apr-17 19-Apr-17
Building D1 67 10-Apr-17 26-Jun-17
Building D1` 9 10-Apr-17 19-Apr-17
Building D2 67 10-Apr-17 26-Jun-17
Building D2` 9 10-Apr-17 19-Apr-17
Building E 67 10-Apr-17 26-Jun-17
Electrical Works 110 10-Apr-17 15-Aug-17
Building A1 110 10-Apr-17 15-Aug-17
Ground Floor 29 10-Apr-17 13-May-17
Grounding Protection
Protectio System & Lightning 2 11-May-17 13-May-17
ELE10750 Sleeves 2 11-May-17 13-May-17 CON1110
ELE10760 Boxes 2 11-May-17 13-May-17 ELE10750
ELE10770 Pipes 2 11-May-17 13-May-17 ELE10750
ELE10780 Cable Tray 2 11-May-17 13-May-17 ELE10750
ELE10790 Wiring of cables 2 11-May-17 13-May-17 ELE10750
Power Circuit 4 10-Apr-17 13-Apr-17
ELE10800 Sleeves 2 10-Apr-17 11-Apr-17
ELE10810 Boxes 2 10-Apr-17 11-Apr-17 ELE10800
ELE10820 Pipes 2 10-Apr-17 11-Apr-17 ELE10800
ELE10830 Cable Tray 2 10-Apr-17 11-Apr-17 ELE10800
ELE10840 Wiring of cables 2 12-Apr-17 13-Apr-17 ELE10800
Lighting System 2 10-Apr-17 11-Apr-17
ELE10850 Sleeves 2 10-Apr-17 11-Apr-17
ELE10860 Boxes 2 10-Apr-17 11-Apr-17 ELE10850
ELE10870 Pipes 2 10-Apr-17 11-Apr-17 ELE10850
ELE10880 Cable Tray 2 10-Apr-17 11-Apr-17 ELE10850
ELE10890 Wiring of cables 2 10-Apr-17 11-Apr-17 ELE10850
Low Current System 2 10-Apr-17 11-Apr-17
ELE10900 Sleeves 2 10-Apr-17 11-Apr-17

Page 5 of 6 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 21-May-17 13:51
Activity ID Activity Name Original Duration Start Finish Predecesso

ELE10910 Boxes 2 10-Apr-17 11-Apr-17 ELE10900


ELE10920 Pipes 2 10-Apr-17 11-Apr-17 ELE10900
ELE10930 Cable Tray 2 10-Apr-17 11-Apr-17 ELE10900
ELE10940 Wiring of cables 2 10-Apr-17 11-Apr-17 ELE10900
Fire Alarm System 2 10-Apr-17 11-Apr-17
ELE10950 Sleeves 2 10-Apr-17 11-Apr-17
ELE10960 Boxes 2 10-Apr-17 11-Apr-17 ELE10950
ELE10970 Pipes 2 10-Apr-17 11-Apr-17 ELE10950
ELE10980 Cable Tray 2 10-Apr-17 11-Apr-17 ELE10950
ELE10990 Wiring of cables 2 10-Apr-17 11-Apr-17 ELE10950
CCTV System 2 10-Apr-17 11-Apr-17
ELE11000 Sleeves 2 10-Apr-17 11-Apr-17
ELE11010 Boxes 2 10-Apr-17 11-Apr-17 ELE11000
ELE11020 Pipes 2 10-Apr-17 11-Apr-17 ELE11000
ELE11030 Cable Tray 2 10-Apr-17 11-Apr-17 ELE11000
ELE11040 Wiring of cables 2 10-Apr-17 11-Apr-17 ELE11000
First Floor 4 04-Jul-17 08-Jul-17
Roof Floor 110 10-Apr-17 15-Aug-17
Building A2 4 10-Apr-17 13-Apr-17
Building B1 4 10-Apr-17 13-Apr-17
Building B1` 4 10-Apr-17 13-Apr-17
Building B2 4 10-Apr-17 13-Apr-17
Building B2` 4 10-Apr-17 13-Apr-17
Building C1 4 10-Apr-17 13-Apr-17
Building C1` 4 10-Apr-17 13-Apr-17
Building C2 4 10-Apr-17 13-Apr-17
Building C2` 4 10-Apr-17 13-Apr-17
Building D1 4 10-Apr-17 13-Apr-17
Building D1` 4 10-Apr-17 13-Apr-17
Building D2 4 10-Apr-17 13-Apr-17
Building D2` 4 10-Apr-17 13-Apr-17
Building E 4 10-Apr-17 13-Apr-17
SCECO 0
PROJECT HAND OVERING 0

Page 6 of 6 TASK filter: All Activities


Oracle Corporation