Check for the need of Note No. 2, if possible refer any standard in justification to statement
Size of Buried rail to be checked
Check for the Size of 16 mm diameter bolt
Length of 100 mm diameter cable guard riser
Remove Earth Connection of Cross Track with Earth Mat
Size of 1.1 kV XLPE UG Cable to be Verified / Calculated
Details of Cable Connection to Buried Rail
Separate view of Trench Cross section needs to be shown while passing the cable through Hume
pipes
Cable termination kit and connection to bus bar details? RI No if available
Details of flat connection to rail
Interface with CTP contractor
All cable entries /pipes to be sealed a suitable note to be included (Standard may be referred)
Notes on discharge of water collected in trench to be included
Arrangement of carrying cables vertically from trench to Equipment/Junction Box
Check the position of power and control cables in trench drawing
Aluminum cable used for 230 V AC? Check contract agreement
Return cable and 25 kV power cable positioning