Professional Documents
Culture Documents
Abstract
The effectiveness of four commercially available corrosion inhibitors for use in cement-based materials was assessed in mortar exposed to
chloride solution. Although, in a parallel study of steel in synthetic pore solutions, the inhibitors were observed to be ineffective in increasing
the chloride threshold value of reinforcing steel exposed to chlorides, in the present study all inhibitors were found to delay the onset of
corrosion, but to differing degrees. Moreover, in agreement with the parallel study, the inhibitors were found to have little detectable effect on
the corrosion rate of the embedded steel once active corrosion had been initiated. This study confirmed that calcium nitrite inhibitors delay
the onset of corrosion but raises questions regarding the mechanism of inhibition. D 2001 Elsevier Science Ltd. All rights reserved.
0008-8846/01/$ see front matter D 2001 Elsevier Science Ltd. All rights reserved.
PII: S 0 0 0 8 - 8 8 4 6 ( 0 1 ) 0 0 4 7 0 - 7
714 S.M. Trepanier et al. / Cement and Concrete Research 31 (2001) 713718
AC impedance tests were also carried out to determine Fig. 2(a) and (b) show the time-to-corrosion for samples
the corrosion rates. The theory and merits of this corrosion having W/C ratios of 0.5 and 0.7, respectively. The left side
measuring technique have been discussed in numerous of each bar corresponds to the last measurement taken
papers [6 10]. In addition to providing information on before active corrosion began in any of the four samples
the kinetics of the electrochemical system (i.e. corrosion in a given batch. The right side corresponds to the first
rate), this nondestructive test can also show which mechan- measurement taken after all samples in a given batch were
ism is involved in the process (i.e. passivation, activation, actively corroding. In other words, it can be said that all four
or diffusion control). For this investigation, the AC impe- samples in a particular batch started to corrode in the time
dance tests consisted of applying a 10-mV sinusoidal range indicated by the bar. Because of the interval between
potential signal to the working electrode, and measuring corrosion measurements, the left end of the bar only
the current response. The AC signal was stepped logarith- indicates that no samples were corroding at that specific
mically over the frequency range 100 kHz down to 10 mHz time, not necessarily that corrosion began at that time.
(or less). Since this test required about 40 min, and testing Similarly, the right side of the bar shows that all four
to lower frequencies exponentially increases the time samples were corroding at that time, not necessarily that
required for each measurement, it was impractical to use the last sample started to corrode at that particular time.
a final testing frequency inferior to 10 mHz for all the All four corrosion inhibitors delayed the onset of corro-
samples. This technique allows the determination of the sion but to varying degrees, depending on the W/C and the
polarisation resistance (Rp) value which is used to compute inhibitor dosage. The only inhibitor to provide a substantial
corrosion rates. delay in corrosion initiation time, however, was CN(1). At
both W/C ratios, the degree of effectiveness of CN(1)
increases with increasing dosage. This result is consistent
3. Results and discussion with earlier work [2,3] stating that corrosion can only be
inhibited if the nitrite to chloride ratio is high enough. In
3.1. Time-to-corrosion fact, one sample at the higher CN(1) dosage (30 l/m3) and at
W/C = 0.5 still was not corroding after 640 days of exposure
The time-to-corrosion is the time required for chlorides to chlorides. The severity of the chloride environment in this
to penetrate the concrete cover in sufficient quantities to test meant that a high concentration of nitrites (to maintain a
initiate corrosion and was determined with the combination sufficient NO2 /Cl ) was necessary to inhibit corrosion.
of half-cell potential and AC impedance tests. All specimens The other inhibitors delayed corrosion to a lesser degree.
having a half-cell potential more negative than 275 mV Only the low dosages of ORG(2) and CN(2) successfully
SCE which were tested using AC impedance gave a delayed corrosion at the lower W/C, while they did not have
response indicative of active corrosion. No specimens giv- any appreciable effect on corrosion initiation time at their
ing passive responses in the AC impedance tests were found higher dosages.
to have very negative half-cell potentials, as would be the As expected, the onset of corrosion occurred earlier in
case if the specimens lacked oxygen. Since the more rapid the samples at W/C = 0.7. Aside from CN(1), only CN(2), at
half-cell potential tests were performed more frequently than the recommended dosage, substantially delayed corrosion.
AC impedance tests, the time-to-corrosion of some samples The only inhibitor whose dosage had the same effect on the
was based partially or solely on half-cell potential results, time-to-corrosion at both W/C ratios was CN(1) with the
following the ASTM C876 guidelines. onset of corrosion being increasingly delayed as the dosage
Fig. 2. (a) Time to initiate corrosion for samples with W/C 0.50. (b) Time to initiate corrosion for samples with W/C 0.70.
716 S.M. Trepanier et al. / Cement and Concrete Research 31 (2001) 713718
was increased. The time-to-corrosion of the ORG(1) sam- are not clear but this discrepancy is an indication of the
ples seemed to be independent of the dosage at the lower W/ degree of scatter typically observed in corrosion rate mea-
C, but its effectiveness increased with dosage at the higher surements. Once corrosion begins, the changes in corrosion
W/C. This may be explained by the fact that ORG(1) is rate are very varied. At a W/C ratio of 0.5, there is a general
believed to be a pore blocker and the lower dose is sufficient decrease in corrosion rate relative to the control samples,
to block most of the pores in the low W/C mortar, whereas a whereas at a W/C ratio of 0.7 the reverse trend was
higher dosage is required to fill the more numerous and/or observed. However, this discrepancy may be due to the
larger pores of the higher W/C mortar. unexpectedly high corrosion rate of the control samples with
W/C of 0.5.
3.2. Corrosion rate It has been hypothesised that an insufficient dosage of a
calcium nitrite (anodic) inhibitor can accelerate corrosion by
Corrosion rates were calculated using Rp values obtained increasing the cathode to anode ratio [11 13]. This hypoth-
from AC impedance tests. Rp values for each test were esis is not supported by the current results: the corrosion
determined using equivalent circuit modelling for test rates measured in samples containing either calcium nitrite
frequencies ranging from 100 kHz down to 10 mHz. inhibitor were found to be independent of the inhibitor
Results from the final round of AC impedance tests were dosage, and to be of similar magnitude or less than those
compared to establish the impact of corrosion inhibitors on of the control samples. These results indicate that this type
the corrosion rate of samples which have been actively of inhibitor does not accelerate corrosion when the chloride
corroding for an extended period of time. The final corro- to nitrite corrosion threshold is exceeded.
sion rate measurements were taken after approximately 550
days of ponding. The rates were calculated assuming that 3.3. Electrical resistance of mortar
the corrosion took place over the entire exposed steel area
of 62.7 cm2. However, a subsequent visual inspection of Increasing the electrical resistance (or resistivity) of
split samples revealed that the corrosion was usually con- concrete is one of several ways for a chemical admixture
fined to an area slightly greater than 1 cm2 and never to reduce the corrosion rate. The value of the mortar's
exceeded 4 cm2. Therefore, the actual local corrosion rates resistance is related to the solution resistance value yielded
are 15 to 100 times higher than those shown in Fig. 3. The by AC impedance tests. Assuming that the resistance of the
calculation of corrosion rates is subject to other uncertain- saline solution in the test cell is negligible, the solution
ties, including the determination of Rp from curve-fitting of resistance (Rs) can be considered to be the electrical resis-
the raw AC impedance test data and the value of the Tafel tance of the mortar surrounding the steel of the lollipop
constant used. Nevertheless, the results allowed a compara- sample, and can, therefore, be used as a measure of corro-
tive evaluation of the inhibitors' influence on these nominal sion resistance.
corrosion rates. The solution resistance values obtained from the final
Nominal corrosion rates for the specimens having W/C round of AC impedance tests, for both W/C ratios, are
ratios of 0.5 and 0.7 are illustrated in Fig. 3(a) and (b), illustrated in Fig. 4(a) and (b). For a given inhibitor and
respectively. The corrosion rate for specimens having a W/C dosage, the Rs value was usually lower at the 0.7 W/C than
of 0.5 was usually lower than that of their counterparts with at 0.5 W/C, as expected. With the exception of ORG(2), the
a W/C of 0.7. However, the opposite was true for the control inhibitors had no effect or caused small increases in elec-
samples and the corrosion rates of the ORG(1) specimens trical resistance. The decrease in resistance caused by
were very similar at both W/C ratios. The reasons for this ORG(2) could be detrimental to the durability of concrete.
Fig. 3. (a) Nominal corrosion rates for samples with W/C 0.50. (b) Nominal corrosion rates for samples with W/C 0.70.
S.M. Trepanier et al. / Cement and Concrete Research 31 (2001) 713718 717
Fig. 4. (a) Solution resistance of samples with W/C 0.50. (b) Solution resistance of samples with W/C 0.70.
3.4. Visual inspection CN(1) and 3 l/m3 for CN(2)). The calcium nitrite content of
CN(1) is reported as being 30% by weight while that of
All the samples which half-cell and AC impedance tests CN(2) is listed at 30% to 60%. However, both inhibitors
indicated were corroding were confirmed to be actively were experimentally found to contain similar nitrite con-
corroding by visual examination of the steel immediately centrations although the residue after drying exhibited
after removal from the mortar. Although corrosion was different colours and morphologies [4]. Even if CN(2)
observed at various sections along the exposed length of had twice as much nitrite as CN(1), its recommended
steel bar, most of the corrosion took place just above the dosage would still provide less nitrite than the lowest
water line. This is as anticipated since the concentration of recommended dosage of CN(1) (10 l/m3), not enough to
chlorides is highest at that point, through wicking action, inhibit corrosion at the chloride levels of the lollipop tests.
and the cathodic oxygen requirement is easily met. The It is probable that the recommended dosage of CN(2) needs
most severe corrosion was observed in the ORG(2) samples to be raised to provide a superior level of corrosion
with a 0.7 W/C, and the least amount of corrosion was protection. Any resulting impact on concrete properties
found in the CN(1) samples with 0.5 W/C, thereby agreeing would need to be assessed.
with electrochemical tests. There is a growing number of commercially available
concrete admixtures that are said to have corrosion
inhibiting properties. The results from this test show that
4. Summary and conclusions the incorporation of some of these chemicals (CN(2),
ORG(1), and ORG(2)) in concrete will only provide a
It is evident that the corrosion inhibitors tested in this slight delay in corrosion initiation, which may not justify
investigation delay the onset of corrosion to varying the additional material cost. The use of the CN(1)
degrees, with CN(1) being the most effective and its calcium nitrite inhibitor enhances the level of corrosion
effectiveness increasing with increasing dosage, but they resistance for embedded steel although it does not pre-
all failed to prevent the initiation of corrosion. Once corro- vent corrosion and, as shown in Part II of this study [4],
sion began, there was little variation in nominal corrosion does not have any observable electrochemical benefits on
rates among the samples containing the inhibitors. The steel in synthetic pore solution. The use of calcium
inhibitors caused slight increases in electrical resistance nitrite inhibitors, especially in combination with other
with the exception of ORG(2), which lowered it. The corrosion prevention methods, should effectively prolong
inhibitors performed better at the lower W/C; this is con- the lives of reinforced concrete structures subjected to
sistent with the belief that inhibitors work best in higher salt environments.
quality concrete.
The visual inspection of the split lollipop samples
confirmed the electrochemical test results. The CN(1) Acknowledgments
samples were the least corroded while the most severe
corrosion was found in the ORG(2) samples at the This research program was conducted as partial fulfil-
highest W/C. ment of a Master of Science Degree at Queen's University
There was a considerable difference in the time-to- in Kingston, Ontario, Canada. The authors would like to
corrosion of the samples containing the two calcium nitrite thank the Ministry of Transportation of Ontario (MTO) and
inhibitors. The admixtures vary in appearance [4] and their the National Sciences and Engineering Research Council of
recommended dosages are also different (10 to 30 l/m3 for Canada (NSERC) for their financial support.
718 S.M. Trepanier et al. / Cement and Concrete Research 31 (2001) 713718