PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :

BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126


COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR JAMB, TRACK, & GLASS PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

5 WOOD DOOR PANEL DMCI

CEILING

6 CEILING FRAME TSI

7 CEILING BOARD Living Room / TSI

8 CEILING PAINT Foyer/ TPI

FLOORING Dining Area

9 HOMOGENOUSE FLOOR TILES On-Going DMCI

10 FLOOR TILE GROUT OBSTRUCTED DMCI

11 BALCONY RAILING OBSTRUCTED

12 BALCONY FLOOR TILES OBSTRUCTED

13 BALCONY FLOOR TILES GROUT OBSTRUCTED

14 WATER PROOFING OBSTRUCTED

WALLS, FLOORING, & CEILING

UNDER CONSTRUCTION OBSTRUCTED KITCHEN

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

25 WOOD DOOR PAINT TPI

26 DOOR PANEL DMCI

27 DOOR ACCESSORIES / HARDWARES OSM

28 WALL PAINT TPI

CEILING

30 CEILING PAINT MAID'S ROOM TPI

CEILING BOARD TSI

CEILING FRAME TSI

FLOORING

31 FLOOR TILES On-Going DMCI

32 FLOOR TILE GROUT DMCI

WATER PROOFING

WALL

34 PVC DOOR PANEL MAID'S T&B DMCI

35 DOOR ACCESSORIES / HARDWARES MAID'S T&B DMCI

36 WALL PAINT MAID'S T&B TPI

37 WALL TILE GROUT MAID'S T&B DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

38 CEILING FRAME TSI

39 CEILING BOARD TSI

40 CEILING PAINT MAID'S T&B TPI

FLOORING

41 FLOOR GROUT DMCI

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

WALL

42 WOOD DOOR PAINT TPI

43 DOOR PANEL DMCI


44 DOOR FRAME & GLASS
45 WINDOW FRAME & GLASS Concurred by:
46 DOOR ACCESSORIES / HARDWARES OSM
47 WALL PAINT TPI M.BALLESTER/R.NOMA
CEILING MASTER BDRM. Project In-Charge / Project Manager
48 CEILING BOARD Installed TSI
49 CEILING PAINT On-Going TPI
FLOORING D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
50 LAMINATED WOOD FLOOR EVERGREN

51 BASEBOARD ROYAL JD

FLOORING

52 WATER PROOFING ROMTECH

53 TILES BALCONY DMCI

54 RAILING GREAT DURA

WALL

55 WOOD DOOR PAINT TPI

56 DOOR PANEL DMCI

57 DOOR ACCESSORIES / HARDWARES MASTER BDRM. OSM

58 WALL TILE On-Going T&B DMCI

59 WALL TILE GROUT DMCI

60 MIRROR

61 TOWEL BAR OSM

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

62 TOWEL RING OSM

63 SOAP HOLDER OSM

64 TISSUE HOLDER OSM


CEILING
65 CEILING FRAME Concurred by:
66 CEILING BOARD MASTER BDRM. TSI
67 CEILING PAINT T&B TPI M.BALLESTER/R.NOMA
FLOORING Project In-Charge / Project Manager
68 FLOOR TILES DMCI
69 FLOOR TILE GROUT DMCI
70 STONE ZOCALLO D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
71 GLASS PARTITION EAGI

WALL

WOOD DOOR PAINT TPI

72 DOOR PANEL DMCI

73 DOOR ACCESSORIES / HARDWARES JUNIOR OSM

74 WALL PAINT On-Going MASTER BDRM. TPI

75 WINDOW FRAME & GLASS

CEILING

76 CEILING BOARD Installed TSI

77 CEILING PAINT On-Going TPI

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

FLOORING

78 LAMINATED WOOD FLOOR JUNIOR EVERGREEN

79 BASEBOARD MASTER BDRM. ROYAL JD


FLOORING
80 WATERPROOFING Obstructed ACCU LEDGE ROMTECH Concurred by:
81 RAILING Obstructed ACCU LEDGE GOLDEN KNIGHT
WALL M.BALLESTER/R.NOMA
82 WOOD DOOR PAINT TPI Project In-Charge / Project Manager
83 DOOR PANEL DMCI
84 DOOR ACCESSORIES / HARDWARES OSM
85 WALL TILE On-Going DMCI D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
86 WALL TILE GROUT DMCI

87 MIRROR JUNIOR

88 TOWEL BAR MASTER T&B OSM

89 TOWEL RING OSM

90 SOAP HOLDER OSM

91 TISSUE HOLDER OSM

CEILING

92 CEILING FRAME TSI

93 CEILING BOARD TSI

94 CEILING PAINT TPI

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

FLOORING

95 FLOOR TILES JUNIOR DMCI

96 FLOOR GROUT MASTER T&B DMCI


97 STONE ZOCALLO
98 GLASS PARTITION EAGI Concurred by:
WALL
99 WOOD DOOR PAINT TPI M.BALLESTER/R.NOMA
100 DOOR PANEL DMCI Project In-Charge / Project Manager
101 DOOR ACCESSORIES / HARDWARES OSM
102 WALL PAINT On-Going TPI
103 WINDOW FRAME & GLASS Obstructed EAGI D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING BEDROOM 3

104 CEILING BOARD TSI

105 CEILING PAINT TPI

FLOORING

106 LAMINATED WOOD FLOOR EVERGREEN

107 BASEBOARD ROYAL JD

FLOORING

108 WATERPROOFING Obstructed BALCONY ROMTECH

109 TILES Obstructed BALCONY DMCI

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

110 RAILING Obstructed BALCONY GREAT DURA

WALL

111 WOOD DOOR PAINT TPI


112 DOOR PANEL DMCI
113 WALL TILES On-Going DMCI Concurred by:
114 WALL TILE GROUT DMCI
115 MIRROR M.BALLESTER/R.NOMA
116 TOWEL BAR OSM Project In-Charge / Project Manager
117 TOWEL RING COMMON OSM
118 SOAP HOLDER T&B OSM
119 TISSUE HOLDER OSM D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10A BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

120 CEILING FRAME

121 CEILING BOARD TSI

122 CEILING PAINT TPI

FLOORING

123 FLOOR TILES DMCI

124 FLOOR TILE GROUT DMCI

125 STONE ZOCALLO

126 GLASS PARTITION OSM

Prepared by: Checked by:

P.PATLIN/JC BAES B.GOMEZ

CQC Engineer CQC HEAD

OP-C-072-0

Concurred by:

M.BALLESTER/R.NOMA
Project In-Charge / Project Manager

D.M Consunji, Inc.


PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

SLIDING DOOR FRAME & GLASS EAGI

CEILING

5 CEILING BOARD On-Going Living Room / TSI

6 CEILING PAINT Foyer/ TPI

FLOORING Dining Area

7 FLOOR TILE GROUT DMCI

8 BASEBOARD ROYAL JD

9 BALCONY RAILING BALCONY GREATDURA

10 BALCONY FLOOR TILES BALCONY DMCI

11 BALCONY FLOOR TILE GROUT BALCONY DMCI

WATERPROOFING BALCONY ROMTECH

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

12 DOOR JAMB, TRACK, & GLASS PANEL EAGI

13 WALL PAINT On-Going TPI

14 KITCHEN ACCESSORIES / FIXTURES OSM

15 CERAMIC COUNTER WALL TILE DMCI

CEILING

16 TILE GROUT KITCHEN DMCI

17 CEILING BOARD On-Going TSI

18 CEILING PAINT TPI

FLOORING

19 CERAMIC FLOOR TILES On-Going DMCI

20 FLOOR GROUT DMCI

21 BASEBOARD ROYAL JD

WALL

22 WOOD DOOR PAINT TPI

23 DOOR PANEL MAID'S ROOM DMCI

24 DOOR ACCESSORIES / HARDWARES MAID'S ROOM OSM

25 WALL PAINT MAID'S ROOM TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

26 CEILING PAINT MAID'S ROOM TPI

FLOORING

27 FLOOR TILES On-Going MAID'S ROOM DMCI

28 FLOOR TILE GROUT MAID'S ROOM DMCI

WALL

29 PVC DOOR JAMB DMCI

30 PVC DOOR PANEL DMCI

31 DOOR ACCESSORIES / HARDWARES DMCI

32 WALL PAINT On-Going TPI

33 WALL TILES DMCI

34 WALL TILE GROUT MAID'S T&B DMCI

CEILING

35 CEILING FRAME

36 CEILING BOARD TSI

37 CEILING PAINT TPI

FLOORING

38 FLOOR TILES On-Going DMCI

39 FLOOR TILE GROUT DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

41 SEALANT XEEL

42 WOOD DOOR PAINT TPI

43 DOOR PANEL DMCI

44 DOOR ACCESSORIES / HARDWARES OSM

45 WALL PAINT On-Going TPI

46 WINDOW FRAME & GLASS

47 DOOR FRAME & GLASS

CEILING MASTER BDRM.

48 CEILING BOARD TSI

49 CEILING PAINT On-Going TPI

FLOORING

50 LAMINATED WOOD FLOOR EVERGREN

51 BASEBOARD ROYAL JD

WALL

52 WOOD DOOR PAINT TPI

53 DOOR PANEL DMCI

54 DOOR ACCESSORIES / HARDWARES MASTER BDRM. OSM

55 WALL TILE On-Going T&B DMCI

56 WALL TILE GROUT DMCI

57 MIRROR

58 TOWEL BAR OSM

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
59 TOWEL RING OSM

60 SOAP HOLDER OSM

61 TISSUE HOLDER OSM

CEILING

62 CEILING FRAME

63 CEILING BOARD MASTER BDRM. TSI

64 CEILING PAINT T&B TPI

FLOORING

65 FLOOR TILES DMCI

66 FLOOR TILE GROUT DMCI

67 STONE ZOCALLO

68 GLASS PARTITION EAGI

WALL

69 WOOD DOOR PAINT TPI

70 DOOR PANEL DMCI

71 DOOR ACCESSORIES / HARDWARES JUNIOR OSM

72 WALL PAINT On-Going MASTER BDRM. TPI

CEILING

73 CEILING BOARD TSI

74 CEILING PAINT TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
FLOORING

75 LAMINATED WOOD FLOOR JUNIOR EVERGREEN

76 BASEBOARD MASTER BDRM. ROYAL JD

WALL

77 WOOD DOOR PAINT TPI

78 DOOR PANEL DMCI

79 DOOR ACCESSORIES / HARDWARES OSM

80 WALL TILE On-Going DMCI

81 WALL TILE GROUT DMCI

82 MIRROR JUNIOR

83 TOWEL BAR MASTER T&B OSM

84 TOWEL RING OSM

85 SOAP HOLDER OSM

86 TISSUE HOLDER OSM

CEILING

87 CEILING FRAME

88 CEILING BOARD TSI

89 CEILING PAINT TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
FLOORING

90 FLOOR TILES JUNIOR DMCI

91 FLOOR TILE GROUT MASTER T&B DMCI

92 STONE ZOCALLO

93 GLASS PARTITION EAGI

WALL

94 WOOD DOOR PAINT TPI

95 DOOR PANEL DMCI

96 DOOR ACCESSORIES / HARDWARES OSM

97 WALL PAINT On-Going TPI

98 CLADDING FRAME

99 CLADDING BOARD

CEILING BEDROOM 3

100 CEILING PAINT On-Going TPI

FLOORING

101 LAMINATED WOOD FLOOR EVERGREEN

102 BASEBOARD ROYAL JD

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

103 WOOD DOOR PAINT TPI

104 DOOR PANEL DMCI

105 DOOR ACCESSORIES / HARDWARES OSM

106 CLADDING FRAME TSI

107 CLADDING BOARD TSI

108 WALL PAINT On-Going TPI

CEILING BEDROOM 4

109 CEILING PAINT On-Going TPI

FLOORING

110 LAMINATED WOOD FLOOR EVERGREEN

111 BASEBOARD ROYAL JD

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 126
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10B BALANCE : 126
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

112 DOOR JAMB Installed DMCI

113 DOOR PANEL DMCI

114 WALL TILES Installed DMCI

115 WALL TILE GROUT DMCI

116 MIRROR

117 TOWEL BAR OSM

118 TOWEL RING COMMON OSM

119 SOAP HOLDER T&B OSM

120 TISSUE HOLDER OSM

CEILING

121 CEILING BOARD Installed TSI

122 CEILING PAINT TPI

FLOORING

123 FLOOR TILES Installed DMCI

124 FLOOR TILE GROUT DMCI

125 STONE ZOCALLO

126 GLASS PARTITION EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 36
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10C BALANCE : 36
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

5 SLIDING DOOR FRAME & GLASS Living Room / EAGI

6 CERAMIC COUNTER WALL TILE Kitchen/ DMCI

CEILING Dining Area

7 CEILING BOARD On-Going TSI

8 CEILING PAINT TPI

FLOORING

9 HOMOGENOUSE FLOOR TILES On-Going DMCI

10 FLOOR TILE GROUT DMCI

11 BASEBOARD ROYAL JD

12 BALCONY RAILING BALCONY GREATDURA

13 BALCONY FLOOR TILES BALCONY DMCI

14 BALCONY FLOOR TILE GROUT BALCONY DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 36
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10C BALANCE : 36
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 36
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10C BALANCE : 36
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

15 WOOD DOOR PAINT TPI

16 DOOR PANEL DMCI

17 DOOR ACCESSORIES / HARDWARES OSM

18 WALL PAINT On-Going TPI

CEILING BEDROOM

19 CEILING PAINT On-Going TPI

FLOORING

20 LAMINATED WOOD FLOOR EVERGREN

21 BASEBOARD ROYAL JD

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 36
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10C BALANCE : 36
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

22 WOOD DOOR PAINT TPI

23 DOOR PANEL DMCI

24 DOOR ACCESSORIES / HARDWARES OSM

25 WALL TILE DMCI

26 WALL TILE GROUT DMCI

27 MIRROR

28 TOWEL BAR OSM

29 TOWEL RING OSM

30 SOAP HOLDER MASTER BDRM. OSM

31 TISSUE HOLDER T&B OSM

CEILING

30 CEILING FRAME TSI

31 CEILING BOARD TSI

32 CEILING PAINT TPI

FLOORING

33 FLOOR TILES DMCI

34 FLOOR TILE GROUT DMCI

35 STONE ZOCALLO EAGI

36 GLASS PARTITION EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

5 SEALANT XEEL

6 SLIDING DOOR FRAME & GLASS EAGI

CEILING

7 CEILING BOARD Living Room / TSI

8 CEILING PAINT Foyer/ TPI

FLOORING Dining Area

9 FLOOR TILE GROUT DMCI

10 BASEBOARD ROYAL JD

11 BALCONY RAILING BALCONY GREATDURA

12 BALCONY FLOOR TILES BALCONY DMCI

13 BALCONY FLOOR TILE GROUT BALCONY DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

14 WALL PAINT On-Going TPI

15 KITCHEN ACCESSORIES / FIXTURES OSM

16 CERAMIC COUNTER WALL TILE DMCI

17 TILE GROUT KITCHEN DMCI

CEILING

18 CEILING BOARD TSI

19 CEILING PAINT TPI

FLOORING

20 CERAMIC FLOOR TILES On-Going DMCI

21 FLOOR GROUT DMCI

22 BASEBOARD ROYAL JD

WALL

23 WOOD DOOR PAINT MAID'S ROOM TPI

24 DOOR PANEL MAID'S ROOM DMCI

25 DOOR ACCESSORIES / HARDWARES MAID'S ROOM OSM

26 WALL PAINT On-Going MAID'S ROOM TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

27 CEILING PAINT On-Going MAID'S ROOM TPI

FLOORING

28 TILE SKIRTING MAID'S ROOM DMCI

29 FLOOR TILE GROUT MAID'S ROOM DMCI

WALL

30 PVC DOOR JAMB DMCI

31 PVC DOOR PANEL DMCI

32 DOOR ACCESSORIES / HARDWARES DMCI

33 WALL PAINT TPI

35 WALL TILE GROUT MAID'S T&B DMCI

CEILING

36 CEILING BOARD On-Going TSI

37 CEILING PAINT TPI

FLOORING

38 FLOOR GROUT DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

40 WOOD DOOR PAINT TPI

41 DOOR PANEL DMCI

42 DOOR ACCESSORIES / HARDWARES OSM

43 WALL PAINT TPI

CEILING MASTER BDRM.

44 CEILING PAINT TPI

FLOORING

45 LAMINATED WOOD FLOOR EVERGREN

46 BASEBOARD ROYAL JD

WALL

47 WOOD DOOR PAINT TPI

48 DOOR PANEL DMCI

49 DOOR ACCESSORIES / HARDWARES MASTER BDRM. OSM

50 WALL TILE On-Going T&B DMCI

51 WALL TILE GROUT DMCI

52 MIRROR

53 TOWEL BAR OSM

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
54 TOWEL RING OSM

55 SOAP HOLDER OSM

56 TISSUE HOLDER OSM

CEILING

57 CEILING FRAME TSI

58 CEILING BOARD MASTER BDRM. TSI

59 CEILING PAINT T&B TPI

FLOORING

60 FLOOR TILES DMCI

61 FLOOR GROUT DMCI

62 STONE ZOCALLO

63 GLASS PARTITION EAGI

WALL

64 WOOD DOOR PAINT TPI

65 DOOR PANEL DMCI

66 DOOR ACCESSORIES / HARDWARES BEDROOM OSM

67 WALL PAINT On-Going TPI

68 WALL CLADDING FRAME TSI

69 WALL CLADDING BOARD TSI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

70 CEILING PAINT BEDROOM TPI

FLOORING

71 LAMINATED WOOD FLOOR EVERGREEN

72 BASEBOARD ROYAL JD

WALL

73 WOOD DOOR PAINT TPI

74 DOOR PANEL DMCI

75 WALL TILE GROUT COMMON DMCI

76 MIRROR T&B

77 TOWEL BAR OSM

78 TOWEL RING OSM

79 SOAP HOLDER OSM

80 TISSUE HOLDER OSM

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 87
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10D BALANCE : 87
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

81 CEILING FRAME TSI

82 CEILING BOARD TSI

83 CEILING PAINT TPI

FLOORING COMMON

84 FLOOR TILES T&B DMCI

85 FLOOR GROUT DMCI

86 STONE ZOCALLO

87 GLASS PARTITION EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

5 SLIDING DOOR FRAME & GLASS EAGI

CEILING

6 CEILING BOARD Living Room / TSI

7 CEILING PAINT On-Going Foyer/ TPI

FLOORING Dining Area

8 FLOOR TILE GROUT DMCI

9 WOOD SKIRTING / BASEBOARD DMCI

10 BALCONY RAILING BALCONY GREATDURA

11 BALCONY FLOOR TILES BALCONY DMCI

12 BALCONY FLOOR TILE GROUT BALCONY DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

13 DOOR JAMB, TRACK, & GLASS PANEL EAGI

14 WALL PAINT On-Going TPI

15 KITCHEN ACCESSORIES / FIXTURES OSM

CEILING

16 CERAMIC COUNTER WALL TILE DMCI

17 TILE GROUT KITCHEN DMCI

18 CEILING FRAME TSI

19 CEILING BOARD TSI

20 CEILING PAINT TPI

FLOORING

21 FLOOR GROUT DMCI

22 BASEBOARD ROYAL JD

WALL

23 WOOD DOOR PAINT MAID'S ROOM TPI

24 DOOR PANEL MAID'S ROOM DMCI

25 DOOR ACCESSORIES / HARDWARES MAID'S ROOM OSM

26 WALL PAINT On-Going MAID'S ROOM TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

27 CEILING PAINT On-Going MAID'S ROOM TPI

FLOORING

28 FLOOR TILES MAID'S ROOM DMCI

29 FLOOR TILE GROUT MAID'S ROOM DMCI

30 WATERPROOFING On-Going MAID'S ROOM ROMTECH

31 TOPPING MAID'S ROOM DMCI

WALL

32 PVC DOOR JAMB DMCI

33 PVC DOOR PANEL DMCI

34 DOOR ACCESSORIES / HARDWARES DMCI

35 WALL PAINT TPI

36 WALL TILE GROUT MAID'S T&B DMCI

CEILING

37 CEILING FRAME TSI

38 CEILING BOARD TSI

39 CEILING PAINT TPI

FLOORING

40 FLOOR TILES DMCI

41 FLOOR GROUT DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

42 WOOD DOOR PAINT TPI

43 DOOR PANEL DMCI

44 DOOR ACCESSORIES / HARDWARES OSM

45 WALL PAINT On-Going TPI

46 DOOR FRAME & GLASS EAGI

47 WINDOW FRAME & GLASS EAGI

CEILING MASTER BDRM.

48 CEILING PAINT On-Going TPI

FLOORING

49 LAMINATED WOOD FLOOR EVERGREN

50 BASEBOARD ROYAL JD

WALL

51 WOOD DOOR PAINT TPI

52 DOOR PANEL DMCI

53 DOOR ACCESSORIES / HARDWARES MASTER BDRM. OSM

54 WALL TILE T&B DMCI

55 WALL TILE GROUT DMCI

56 MIRROR

57 TOWEL BAR OSM

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
58 TOWEL RING OSM

59 SOAP HOLDER OSM

60 TISSUE HOLDER OSM

CEILING

61 CEILING FRAME TSI

62 CEILING BOARD MASTER BDRM. TSI

63 CEILING PAINT T&B TPI

FLOORING

64 FLOOR TILES DMCI

65 FLOOR GROUT DMCI

66 STONE ZOCALLO

67 GLASS PARTITION EAGI

WALL

68 WOOD DOOR PAINT TPI

69 DOOR PANEL DMCI

70 DOOR ACCESSORIES / HARDWARES BEDROOM 3 OSM

71 WALL PAINT On-Going TPI

CEILING

72 CEILING BOARD TSI

73 CEILING PAINT TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
FLOORING

74 LAMINATED WOOD FLOOR BEDROOM 3 EVERGREEN

75 BASEBOARD BEDROOM 3 ROYAL JD

WALL

76 WOOD DOOR PAINT TPI

77 DOOR PANEL DMCI

78 DOOR ACCESSORIES / HARDWARES OSM

79 WALL PAINT On-Going TPI

CEILING BEDROOM 4

80 CEILING PAINT On-Going TPI

FLOORING

81 LAMINATED WOOD FLOOR EVERGREEN

82 BASEBOARD ROYAL JD

83 RAILING ACCU LEDGE GCC

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 101
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10E BALANCE : 101
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

84 WOOD DOOR PAINT TPI

85 DOOR PANEL DMCI

86 WALL TILES DMCI

87 WALL TILE GROUT DMCI

88 MIRROR

89 TOWEL BAR OSM

90 TOWEL RING COMMON OSM

91 SOAP HOLDER T&B OSM

92 TISSUE HOLDER OSM

CEILING

93 CEILING FRAME TSI

94 CEILING BOARD TSI

95 CEILING PAINT TPI

FLOORING

96 FLOOR TILES DMCI

97 FLOOR GROUT DMCI

98 STONE ZOCALLO

99 GLASS PARTITION EAGI

100 BALCONY RAILING BALCONY GREAT DURA

101 BALCONY TILES BALCONY DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going TPI

CEILING

5 CEILING BOARD Living Room / TSI

6 CEILING PAINT Foyer/ TPI

FLOORING Dining Area

8 FLOOR TILE GROUT DMCI

9 BASEBOARD ROYAL JD

10 SLIDING DOOR FRAME & GLASS EAGI

11 BALCONY RAILING BALCONY GREATDURA

12 BALCONY FLOOR TILES BALCONY DMCI

13 BALCONY FLOOR TILE GROUT BALCONY DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

14 WALL PAINT On-Going TPI

15 KITCHEN ACCESSORIES / FIXTURES OSM

CEILING

16 CERAMIC COUNTER WALL TILE DMCI

17 TILE GROUT KITCHEN DMCI

18 CEILING BOARD TSI

19 CEILING PAINT TPI

FLOORING

21 FLOOR GROUT DMCI

22 BASEBOARD ROYAL JD

WALL

23 WOOD DOOR PAINT MAID'S ROOM TPI

24 DOOR PANEL MAID'S ROOM DMCI

25 DOOR ACCESSORIES / HARDWARES MAID'S ROOM OSM

26 WALL PAINT On-Going MAID'S ROOM TPI

27 TILE SKIRTING MAID'S ROOM DMCI

28 WINDOW GLASS MAID'S ROOM EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

27 CEILING PAINT On-Going MAID'S ROOM TPI

FLOORING

29 FLOOR TILE GROUT MAID'S ROOM DMCI

WALL

30 PVC DOOR JAMB DMCI

31 PVC DOOR PANEL DMCI

32 DOOR ACCESSORIES / HARDWARES DMCI

33 WALL PAINT TPI

35 WALL TILE GROUT MAID'S T&B DMCI

CEILING

36 CEILING FRAME TSI

37 CEILING BOARD TSI

38 CEILING PAINT TPI

FLOORING

39 FLOOR GROUT DMCI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

40 WOOD DOOR PAINT TPI

41 DOOR PANEL DMCI

42 DOOR ACCESSORIES / HARDWARES OSM

43 WALL PAINT On-Going TPI

44 SEALANT XEEL

45 CLADDING FRAME

46 CLADDING BOARD

CEILING MASTER BDRM.

47 CEILING BOARD TSI

48 CEILING PAINT TPI

FLOORING

49 LAMINATED WOOD FLOOR EVERGREN

50 BASEBOARD ROYAL JD

WALL

51 WOOD DOOR PAINT TPI

52 DOOR PANEL DMCI

53 DOOR ACCESSORIES / HARDWARES MASTER BDRM. OSM

54 WALL TILE On-Going T&B DMCI

55 WALL TILE GROUT DMCI

56 MIRROR DMCI

57 TOWEL BAR OSM

58 AWNING FRAME & GLASS EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
59 TOWEL RING OSM

60 SOAP HOLDER OSM

61 TISSUE HOLDER OSM

CEILING

CEILING FRAME TSI

62 CEILING BOARD MASTER BDRM. TSI 23-Feb-17

63 CEILING PAINT T&B TPI 24-Feb-17

FLOORING

64 FLOOR TILES On-Going DMCI

65 FLOOR GROUT DMCI

66 STONE ZOCALLO

67 GLASS PARTITION EAGI

68 RAILING ACCU LEDGE GCC

WALL

69 WOOD DOOR PAINT TPI

70 DOOR PANEL BEDROOM DMCI

71 DOOR ACCESSORIES / HARDWARES OSM

72 WALL PAINT On-Going TPI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

73 BULKHEAD BOARD TSI

74 CEILING PAINT On-Going TPI

FLOORING BEDROOM

75 LAMINATED WOOD FLOOR EVERGREEN

76 BASEBOARD ROYAL JD

WALL

77 WOOD DOOR PAINT TPI

78 DOOR PANEL DMCI 2/26/2017

79 WALL TILES DMCI

80 WALL TILE GROUT COMMON DMCI 2/26/2017

81 MIRROR T&B

82 TOWEL BAR OSM

83 TOWEL RING OSM

84 SOAP HOLDER OSM

85 TISSUE HOLDER OSM

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 92
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10F BALANCE : 92
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
CEILING

86 CEILING FRAME TSI

87 CEILING BOARD TSI

88 CEILING PAINT TPI

FLOORING COMMON

89 FLOOR TILES T&B DMCI

90 FLOOR GROUT DMCI

91 STONE ZOCALLO

92 GLASS PARTITION EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 33
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10G BALANCE : 33
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
ARCHITECTURAL ACTVITIES

WALL

1 WOOD DOOR PAINT TPI

2 DOOR PANEL DMCI

3 DOOR ACCESSORIES / HARDWARES OSM

4 WALL PAINT On-Going BEDROOM/ TPI

CEILING LIVING/

5 CEILING PAINT On-Going DINING TPI

FLOORING

6 FLOOR TILE GROUT DMCI

7 BASEBOARD ROYAL JD

8 RAILING ACCU LEDGE GCC

9 WATERPROOFING ACCU LEDGE ROMTECH

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 33
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10G BALANCE : 33
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

10 WALL PAINT On-Going TPI

11 KITCHEN ACCESSORIES / FIXTURES OSM

CEILING

12 CERAMIC COUNTER WALL TILE DMCI

13 TILE GROUT KITCHEN DMCI

14 CEILING BOARD TSI

15 CEILING PAINT TPI

FLOORING

16 FLOOR GROUT DMCI

17 BASEBOARD ROYAL JD

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.
PRINCEVIEW PARKSUITES RESIDENCES PROJECT SUMMARY :
BINONDO, MANILA TOTAL NO. OF BALANCE OF WORK : 33
COMPLETED AS OF :
SUBJECT : BALANCE OF WORKS AT UNIT-10G BALANCE : 33
AS OF : June 22, 2017 EXPECTED TIME OF COMPLETION (ETC) :

ITEM DESCRIPTION LOCATION ENTITY SCHEDULE CLOSE-OUT


Target Actual PS PIC
WALL

18 WOOD DOOR PAINT TPI

19 DOOR PANEL DMCI

20 DOOR ACCESSORIES / HARDWARES OSM

21 WALL TILE DMCI

22 WALL GROUT DMCI

23 MIRROR

24 TOWEL BAR OSM

25 TOWEL RING OSM

26 SOAP HOLDER T&B OSM

27 TISSUE HOLDER OSM

CEILING

CEILING FRAME TSI

28 CEILING BOARD MASTER BDRM. TSI

29 CEILING PAINT T&B TPI

FLOORING

30 FLOOR TILES DMCI

31 FLOOR GROUT DMCI

32 STONE ZOCALLO

33 GLASS PARTITION EAGI

Prepared by: Checked by: Concurred by:

P.PATLIN/JC BAES B.GOMEZ M.BALLESTER/R.NOMA


CQC Engineer CQC HEAD Project In-Charge / Project Manager

OP-C-072-0
D.M Consunji, Inc.