Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 15-Jun-2017 Thursday No. of Day Report No. DPR- 645

Proj Start Date 2014 Contract Period 1 Year Calendar Day AM PM Fine
Weather
Estimate Completion Date 14-Nov-2017 Remain Period 153 Calendar Day 6~8 8~10 10 ~12 12~2 2~4 4~6 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store Driver Surveyer Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 3 1 1 3 2 1 27 16 23 55
Steel Roofing D&W Ceiling Water
Trades Scaffolder Painter Aluminium Total
Erector worker Installer worker Proofing
Today 4 133

Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Excavator 60 Ton Crane Car Crane
Dozer 50 Ton Crane Folk Lift
1.5 Ton Roller 25 Ton Crane Rummer 1
Boom Lift Generator Truck
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
32mm DF Bar (12M) nos 195 2' Angle Ruler nos 2 Hand Brick (Broken) nos 50
25mm DF Bar (12M) nos 183 nos 2 Sand (river) suds 2.26
20mm DF Bar (12M) nos 206 Hand Brick (Un-broken)) nos 4950

FO-OP-01 REV-00 Page: 1/3


Daily Report

Project Name: Myanmar Aquarium Project

Project Code: 4YG - 04700 Report Date : 15-Jun-2017 Thursday No. of Day Report No.
Test Item Remarks
Sampl
e
LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT Conducted
HSE Tip for being in the rainy season
723124 0 0 0 0 0 By Safety Officer

Works Carried out Details


Trades Of Work Location Remark
I Block(A) F&B Building
1 Demolition the Brick Wall at 1st Floor In Progress

II Block(B) Aquarium Building


1 Formwork installation & Rebar Fixing work For 2nd Floor Beam. (GL:B9 to B13') In Progress
2 Formwork installation For Roof Beam (37.85m Level) In Progress
3 Rebar FIxing For Main Fish Tank (1st floor to 2nd Floor) In Progress
4 Formwork installation For Lift B-2/ B-3/ B-4 In Progress
5 Rebar Production For Stair B-4 In Progress
6 Formworkinstallation For Stair B-4 In Progress

III External Work


1 Brick Work For Retaining Wall (Near Block B) In Progress

III Other Work


1 Cleaning Work at Septic Tank
2 Cleaning the Grass & Bushes around the Site.
Special Event
Visitors Site
Purpose
on Site Instruction
Project Manager Project Engineer Prepare By: Site Engineer

FO-OP-01 REV-00 Page: 2/3


Daily Report

Project Name: Myanmar Aquarium Project


Name Name Sai Thing Nun Name Lin Naing Soe
Project Code: 4YG - 04700 Report Date : 15-Jun-2017 Thursday No. of Day Report No.
Signature Signature Signature

Rebar fixing & Formwork installation at 2nd Floor Beam&Slab Formwork installation For 37.85m Level Roof Beam Excavation For Retaining Wall

Cleaning Work the Grass And Bushes aound on site