Work Method Statement

Section 1

Maintenance Activity: Location of Work: Supervisor on Site: Ukar


Defect Rectification Dry Cooler Area 5TH Floor Area Supervisors Contact Number While on Site: 0857 1110 4322
Separate Method Statement/Risk Assessment Submitted: Method Statement Approved by Engineering/Facility Manager:
If Yes, please indicate document Name: If it has not then the works request can not be processed

Will any of the following tasks be performed under this Works Request (relevant forms to be attached);

Hot Works : Y Live Electrical Conditions: N Work at Roof Area: N Under floor Works : Y Confined Spaces : Y
Section 2

METHOD RISKS IDENTIFIED RISK CONTROLS AREAS AFFECTED


Date: 6 May 2017

1. 09.0009.15 (Duration 15 minute) No risk Dry Cooler Roof 5TH Area


Preparation material

2. 09.15-09.30 (Duration 15 minute) Flood in Dry Cooler Roof 5TH Area Drain the water slowly Dry Cooler Roof 5TH Area
Turn off CRAH unit

3. 09.30-09.45 (Duration 15 minute) No risk Dry Cooler Roof 5TH Area


Turn off pump unit

4. 09.45-10.00 (Duration 15 minute) No risk Dry Cooler Roof 5TH Area


Open drain gate valve Dry Cooler SVR.
Drain and verify the water in pipe is off
No risk Dry Cooler Roof 5TH Area
5. 10.00-11.00 (Duration 1 hour)
Remove the broken thermometer stick
and then install the new thermometer
stick. There is five thermometer stick
replacemens. Install one by one

6. 11.00-11.15 (Duration 15 minute) No risk Dry Cooler Roof 5TH Area


Turn on pump unit

7. 11.15-11.30 (Duration 15 minute) No risk Dry Cooler Roof 5TH Area


Turn on Crah unit

8. 11.30-12.00 (Duration 30 minute) No risk Dry Cooler Roof 5TH Area


Cleaning work area

9. 12.00 Finish

End of Work.

Total duration work: 3 Hours


NOTES ON COMPLETION OF THIS DOCUMENT (if required, additional method statement forms should be attached):
(i) METHOD - The job or task is to be broken down into individual steps to provide a clear statement of how the job is to be done, including any tools and equipment
and any hot works/riser or void access, etc. Generic method statements will not be accepted. Method statements MUST apply to the job in hand.
(ii) RISKS IDENTIFIED - Detail any potential risks to property, personnel, business operations.
(iii) RISK CONTROLS - Detail all measures to be taken to eliminate or mitigate risks identified.
(iv) AREAS AFFECTED - Areas possibly affected by the identified risks.

You might also like