DIRECT MANPOWER ALLOCATION REPORT - ALPINE TOWER

61 Date:- Monday, July 10, 2017

ELECTRICAL
Sl.No ELECTRICAL Level Location Supervisor Electrician Helper Welder OTHER Sub-Total Remarks
Tower-1 16th,17th Flr DB installation work 1 1 2
16th flr chockup work All Appartments 1 1 2
3
1 24th flr chockup work All Appartments 1 1 2
M/s Prabhat Power
36 th Flr All Appartments - RCC Box Fixing&conduiting 1 1 2

TOWER-2 18th flr Chock up clearing 1 1 2


19th floor Wall conduiting work 2 1 3
1
2 21th flr Wall conduiting work 1 1 2
M/s Asean Power
38th service floor Slab conduiting work 1 1 2
7th & 8th flr Flooring work 1 1 2
TOTAL ELECTRICAL MANPOWER 23
PLUMBING
Sl.No Plumbing Level Location Supervisor Plumber Helper Welder Fitter OTHER Sub-Total Remarks
Tower-1 0
13th Flr Toiltes all Appts 1 1 2
1 16th Flr Toiltes all Appts 1 1 1 2
M/S Sterling & Wilson
1th to 13th Flr Pumbing Shafts 1 & 4 2 2 4
Slab Sleeve Fixing On Slab 1 1 2

TOWER-2 10th Flr Toiltes all Appts 1 1 2


13th Flr Toiltes all Appts 1 1 2
2 16th Flr Toilets all Appts 1 1 1 2
M/S Sterling & Wilson
16th Flr Toilets all Appts 1 2 3
7th to 10th Flr Toilets all Appts 1 1 2
TOTAL PLUMBING MANPOWER 21
FIRE FIGHTING
Sl.No Fire Fighting Level Location Supervisor Fitter Welder Helper Sub-Total Remarks
TOWER-1 0
1 17th Flr All Appartments 1 1 1 2 4
M/S Sterling & Wilson
18th Flr All Appartments 1 1 2 4
TOWER-2 0
2 12th Flr All Appartments 1 1 1 2 4
M/S Sterling & Wilson
13th Flr All Appartments 1 1 3 5
Total Fire Fighting Manpower 17