IAPP-SA-017 Attachment 4.

1 - PAYMENT SCHEDULE Ic Anadolu Combined Cycle Power Plant Project

Remineralized Water Tank Potable/Service Water Tank


MILESTONE Demineralized Water Tank 1 Demineralized Water Tank 2 Fuel Oil Tank
MILESTONE TITLE Supporting Document Percentage of Payment Amount Milestone LD
NO
Sub-Contract Price (USD) Applicable
750M3 750M3 3000M3 500M3 300M3
Percentage Milestone Date Percentage Milestone Date Percentage Milestone Date Percentage Milestone Date Percentage Milestone Date

According to Attachment According to Attachment According to Attachment According to Attachment


1 Material on Site ready for Erection Quality Documentation 4.00% 4.00% 2.00% 1.00% According to Attachment 5.1 1.00% 12.00% 0.00% YES
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


2 Welding of Floor Plates Completed Quality Documentation 3.00% 3.00% 3.00% 1.00% According to Attachment 5.1 1.00% 11.00% 0.00%
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


3 Welding of Shell Plates Completed Quality Documentation 4.00% 4.00% 3.00% 1.00% According to Attachment 5.1 1.00% 13.00%
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


4 Welding of Roof Plates Completed Quality Documentation 4.00% 4.00% 4.00% 2.00% According to Attachment 5.1 2.00% 16.00% 0.00% YES
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


5 All Erection & Welding Works Completed Quality Documentation 5.00% 5.00% 4.00% 2.00% According to Attachment 5.1 2.00% 18.00% 0.00%
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


6 Hydrotest Successfully Completed Quality Documentation 7.00% 7.00% 6.00% 2.00% According to Attachment 5.1 2.00% 24.00% 0.00% YES
5.1 5.1 5.1 5.1

According to Attachment According to Attachment According to Attachment According to Attachment


7 Surface Preparation, Painting Completed Quality Documentation - - 4.00% 1.00% According to Attachment 5.1 1.00% 6.00% 0.00% YES
5.1 5.1 5.1 5.1

TOTAL 27.00% 27.00% 26.00% 10.00% 10.00% 100.00%

Subcontract Price:

Page 1 of 1