Malikai Project

Piping Construction
Standard
Project Malikai EPC TLP Project

Document Title Piping Construction Standard

Shell Document Number MLK-011-300-MP-3375-001

TMJV Document Number 5886-300-STC-1390-001

Document Revision A

Version Code Not Applicable

Document Status Issued for IDC

Shell Document type B

Originator / Author Mohd Redwan

Security Classification Restricted

ECCN EAR 99

Issue Date 15-Dec-2012

Revision History is shown next page

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 1 of 7


REVISION HISTORY

Rev # Date of Issue Description Originator Reviewer Approver


Mohd
A 15-Dec-2012 Issued for IDC Sergio Palon CW Fong
Redwan

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 2 of 7


TABLE OF CONTENTS

1.0 INTRODUCTION 6

2.0 SCOPE 6
3.0 GENERAL NOTES 7

15.0 PIPING CONSTRUCTION STANDARD 35

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 3 of 7


1.0 INTRODUCTION

Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell
Petroleum Company is the designated operator. A floating Dry Tree Unit (DTU) will be
installed over Malikai field utilising a Tension Leg Platform (TLP) design that suits the
Malikai environment.
The Malikai Dry Tree Unit (DTU) is to be located about 110 km off the shore of Sabah
(East Malaysia) in the South China Sea. Water depth at the location is about 500 m (1500 ft).
The Malikai DTU design will accommodate 24 slots with initial 17 well developments (11
producers and 6 water injectors) and additional well slots to allow for future well
developments.
The Malikai DTU is designed to produce a nameplate capacity of 60,000 bbls of liquid
(Oil + Water) per day and 50 MMSCFD of associated gas. The untreated crude oil will be
sent to Kebabangan platform (KBB) for processing via 50 km 10 pipeline and
eventually exported to Sabah Oil & Gas Terminal (SOGT). The associated gas will be
compressed and mainly used for gas lift and fuel gas system with the excess gas exported to
KBB via 8 pipeline. The gas pipeline will be designed to enable reverse flow in later field
life when additional gas is required for start-up and/or fuel gas make up.
The Malikai TLP will be designed as a fully manned platform, complete with living
quarters and a control room.

2.0 SCOPE
This document covers all Piping Constructions Standards to be used for TLP MALIKAI.

This document does not supersede the requirements of the Project Specifications as defined in
the Contract. For the avoidance of doubt in the case of conflict between this document and
the requirements of the Project Specifications, then the Project Specifications shall govern.

3.0 GENERAL NOTES

2.1 All materials of construction shall be in accordance with Specification for Piping
Material Class documents no. MLK-300-MP-7730-0001.

2.2 The Standards shall be read in conjunction with the following DEPs :

DEP 31.38.01.10 - Piping Classes Basis of Design

DEP 31.38.01.11 - Piping - General Requirements

DEP 31.38.01.15 - Piping Classes - Exploration & Production

2.3 Flow and pressure instrument to be tapped at the lower quadrant of liquid lines and top
quadrant for gas / vapor lines.

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 4 of 7


4.0 PIPING CONSTRUCTION STANDARD

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 5 of 7


ITEM NO.
STC DESCRIPTION Standard Rev Date Rev Date
1340
A 15/12/12
TYPICAL ARRANGEMENT FOR FLOW
001
ORIFICE AND FLOWMETER.

TYPICAL ARRANGEMENT FOR A 15/12/12


002 PRESSURE INSTRUMENT SUPPLY
LIMIT.
TYPICAL ARRANGEMENT FOR A 15/12/12
003 TEMPERATURE INSTRUMENT
SUPPLY LIMIT.
A 15/12/12
TYPICAL ARRANGEMENT FOR
004
SAMPLE CONNECTION.

A 15/12/12
TYPICAL ARRANGEMENT FOR LEVEL
GAUGE, LEVEL TRANSMITTER
(LG/LT),
005
DP CELL, MAGNETIC TYPE, RADAR
TYPE, CORROSION PROBE.

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 6 of 7


ITEM NO.
STC DESCRIPTION Standard Rev Date Rev Date
1370
A 15/12/12
PROCESS VENT ON PIPING TYPICAL
001
ARRANGEMENTS

A 15/12/12
PROCESS DRAIN ON PIPING
002
TYPICAL ARRANGEMENTS

A 15/12/12
HYDROTEST VENT ON PIPING
003
TYPICAL ARRANGEMENTS

A 15/12/12
HYDROTEST DRAIN ON PIPING
004
TYPICAL ARRANGEMENTS

MLK-011-300-MP-3375-001/ 5886-300-STC-1390-001 Rev A Page 7 of 7