You are on page 1of 167

5/11/2014

ADVANCED OPEN PIT MINE


PLANNING AND DESIGN

Presenter
Prof Emmanuel Chanda
The University of Adelaide, Australia

ADVANCED OPEN PIT MINE


PLANNING AND DESIGN
M1-Strategic mine planning
M2-Open pit optimisation
M3-Mine Production scheduling
M4-Optimum Cut-off Grades
M5-Mine Planning Software
M6-Mine-to-Mill Optimisation
M7-Equipment Selection
M8-Financial Technical Modelling
M9-Dewatering and Pumping
Open Pit Mine Planning and Design 2

1
5/11/2014

Objectives

Fundamentals of open pit mine design and


current developments in planning and design
methodology,
Current industry practices to maximise economic
return.
Open pit mine planning and design process in
theory and practice,
Unit Operations Drill-Blast-Load-Haul
Apply this knowledge to plan/evaluate new
open pit projects and/or existing mines.

Open Pit Mine Planning and Design 3

What do you expect to learn from this


Course?

Open Pit Mine Planning and Design 4

2
5/11/2014

Module 1
Strategic Mine Planning
1. What is strategic planning?

2. Mine planning process

3. Mining strategy

4. Feasibility Studies

5. Exercises
Open Pit Mine Planning and Design 5

Overview/scope
Big picture mine planning and design process

Big picture decision-making process

Applies to Greenfields as well operating mines

SP takes place at all levels of the company


Corporate level: vision, mission, feasibility, etc
Business unit level: expansion of production
Mine level: medium/long term production strategy

Analogy: military strategy


Open Pit Mine Planning and Design 6

3
5/11/2014

What is Strategic Mine


Planning?
Strategic mine planning is concerned with those
decisions that largely determine the value of the
mining business whereas tactical mine planning
deals with the tasks required to actually achieve
that value.
Both types of planning are necessary; they can be
looked at separately, even discussed separately,
but they cannot be separated in practice!

Open Pit Mine Planning and Design 7

Types of planning and mine life cycle


Mine Planning

Tactical Mine
Planning

Strategic Mine
Planning

Prospecting Exploration Development Production Closure

Life cycle of an orebody

Open Pit Mine Planning and Design 8

4
5/11/2014

Strategic mine planning focuses on those technical


variables that affect the life of a mine and the value of
the underneath mineral resource
It starts with the discovery of the mineral resource and
finishes when it is exhausted or abandoned.

Go! List variables (factors) considered in SMP

Open Pit Mine Planning and Design 9

Business Strategy

Strategic Decision- Economic


Planning Making Evaluation
Behaviour

Mine Planning

Open Pit Mine Planning and Design 10

5
5/11/2014

Decision-Making Behaviour:
Risk Averse seeks other business goals
Risk Neutral seeks maximise NPV

Open Pit Mine Planning and Design 11

Mine Planning Process Flowchart

Open Pit Mine Planning and Design 12

6
5/11/2014

Mine Planning Process


Four main stages of mine planning process:
Geology of resource
Value of resource
Long-Term planning (Strategic) feasibility
studies
Medium-term/Short-term planning - production

Mine Planning Process*:


Geology + Data Analysis Resource Model Mining Method Selection

Optimisation Mine Design Optimal Schedulling Financial Technical Model

* A dynamic and iterative process *


Open Pit Mine Planning and Design 13

Activity 1:
Work in Groups of 2-4
To plan a new open pit mine in Kerman Province. List all the
data required to perform a feasibility study and where
these data would come from.

Open Pit Mine Planning and Design 14

7
5/11/2014

Technical Aspects:
Once the geological features are understood and the
physical characteristics of the ore body are determined,
the main technical decisions that follow are:
Mining method selection
Processing route
Scale of operation (size)
Mining sequence
Selective cut-offs (e.g. cut-off grade at the mine)

Open Pit Mine Planning and Design 15

All these variables are inextricably interrelated in the


sense that they cannot be determined in isolation from
each other
Moreover, they cannot be determined without taking
into account the market variables and related data from
the geologic, metallurgical, geotechnical, and
environmental models.
.as shown on next slide

Open Pit Mine Planning and Design 16

8
5/11/2014

MARKET

Geological Metallurgical
Model Model

Mining Processing
Method Route
Geotechnical Environmental
Model Model
Scale of Mining
Operation Sequence

Selective
Cut-offs

MINE PLAN
Open Pit Mine Planning and Design 17

Mining Method Selection

The choice of the mining method depends on the


shape, emplacement and properties of the
orebody and host rock; again, beyond technical
considerations, this is an economic decision

In general, there are two main mining methods:


Surface mining (open pit, quarries)
Underground mining (block caving, cut & fill)

Open Pit Mine Planning and Design 18

9
5/11/2014

However, depending on the emplacement of the


orebody and its grade distribution, there are cases
where both methods are feasible e.g. open-pit
followed by underground mining or the other way
around
This is the classic case of sub-vertical deposits such as
kimberlitic pipes containing diamonds and some
porphyry copper deposits

Open Pit Mine Planning and Design 19

Economic considerations

Many decisions concerning the choice of the mining


method are related to the "opportunity cost concept

For example:
In massive, disseminated deposits that are close to
surface, open pit mining is more productive than an
underground

Underground mining usually requires more


development and preparation works

Open Pit Mine Planning and Design 20

10
5/11/2014

Considerations in Mining Method Selection


Finances:
Finance influences method selection:

Length of pre-production development and phases

Thoroughness of the ore body delineation program

Scale of operations bulk mining methods, eg., block


caving

Technology applications - automation

Open Pit Mine Planning and Design 21

Markets

The mining method should be flexible enough to


respond to market changes.

When and how to high grade during peak commodity


prices

Changes to mine development schedule

Focus on production of by-products (eg. cobalt in copper


ore)

Mining companies are price takers. What can be done


about this?
Open Pit Mine Planning and Design 22

11
5/11/2014

Technology and Human Resources


Choice of particular mining method commits operation
to certain type of technology, equipment, human
resources and processes.

Later change in method will be at a cost

Must allow for possibility of introducing new


technology

Necessary skills must be available to operate selected


mining system
Lack of expertise may eliminate a particular mining
method, though technically suitable.

Consider specific training and supervision


Open Pit Mine Planning and Design 23

Processing route

The selection of the processing route depends


essentially on the characteristics of the ore; however,
beyond technical considerations, this is a business
decision

Essentially, there are basically two main routes:


Physical methods (concentration)
Chemical methods (hydrometallurgy)

Open Pit Mine Planning and Design 24

12
5/11/2014

Mineral

Liberation Comminution

Unacceptable

Classification

Acceptable

Separation Concentration

Physical Chemical
Open Pit Mine Planning and Design 25

Factors to consider
Products recovered
Recoveries and achievable grades
Environmental aspects
Market considerations
Capital and operating costs
Cycle times
Mine plan
Cash flow and profitability

In short, technical and financial considerations


Open Pit Mine Planning and Design 26

13
5/11/2014

Metallurgical tests

Lab testing for initial investigation


Core samples and samples from outcrops
(chip samples)
Pilot tests to confirm lab tests and design
Core samples and some bulk samples from
underground workings
Industrial tests to feasibility
Bulk samples from underground workings
and additional core samples

Open Pit Mine Planning and Design 27

Scale of the operation


The scale of the operation refers to production
capacity, which in turn is related to the physical size of
the installations at the mine and plants
This is directly related to the capital investment
required to produce the final output deemed to put in
the market
The larger the scale, the higher the investment and
production

Case Study: Olympic Dam Expansion Project


in South Australia

Open Pit Mine Planning and Design 28

14
5/11/2014

From the point of view of a mining project, the


scale of the operation is the dominant factor
for establishing the mine life and business
value
There is a compromise between the NPV of a
project and its size the optimum size exits,
because a very large operation may shorten
the mine life too much, making the marginal
investment unworthy

Open Pit Mine Planning and Design 29

Size-profitability-risk relationship
Scenario 500 kt/d
NPV Scenario 300 kt/d
(MUS$) Scenario 150 kt/d

Scenario 72 kt/d
3000
Risk

2700

2000

1000

Scale of operation
Open Pit Mine Planning and Design 30

15
5/11/2014

Mining Sequence and Final Limits


It refers to the path or trajectory employed to exploit
a mine from an initial situation until reaching the
final limits or exhausting the ore reserves

Usually, these two variables are treated separately


but because of their co-dependency they should be
handled together

Open Pit Mine Planning and Design 31

The mining sequence is usually defined in


terms of sequential cuts or "sectors in
which a final mining envelope is split to guide
the mining extraction

These sectors can be phases, cut-backs or


push-backs as they are usually called in open-
pit mining; or blocks, panels, rooms or stopes
as these are commonly referred to in
underground mining

Open Pit Mine Planning and Design 32

16
5/11/2014

It is worth noting that the partition of a final


mining envelope into cuts or sectors is done
because the time value of money

In effect, the purpose is to postpone


expenditures and bring forward revenue as
much as possible from production sales

Open Pit Mine Planning and Design 33

The scheduling saw graph

To illustrate how the time value of money


affects the economics of mining it is useful to
introduce the saw graph tool
It assumes that mining activities always
require some preparation works
(development) prior to ore extraction:
Stripping in open pit mining (t, m3)
Developments in underground (m3,
m2, m, t)

Open Pit Mine Planning and Design 34

17
5/11/2014

The scheduling Saw Graph

Minimum Ore
Exposure
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Time

Open Pit Mine Planning and Design 35

Integral optimisation of the final pit


Exploitation phases
500 t (ore)

100 t (waste) 3

6 Revenue 2.2 $/t


Cost -1.0 $/t
Open Pit Mine Planning and Design 36

18
5/11/2014

Partial and cumulative tonnage

Partial tonnage Cumulative tonnage


Phase
Ore Waste O/W Ratio Ore Waste O/W Ratio
1 500 100 0.2 500 100 0.2
2 500 300 0.6 1,000 400 0.4
3 500 500 1.0 1,500 900 0.6
4 500 700 1.4 2,000 1,600 0.8
5 500 900 1.8 2,500 2,500 1.0
6 500 1,100 2.2 3,000 3,600 1.2
7 500 1,300 2.6 3,500 4,900 1.4

Breakeven point Phase 6

Open Pit Mine Planning and Design 37

When neither the time value of money nor other


operational factors such as mine and plant
capacities are taken into account, the optimal final
limit is reached at Phase 6

The implicit assumption is that ore is exposed


simultaneously with waste and that ore revenue
occurs at the same time as waste cost

Open Pit Mine Planning and Design 38

19
5/11/2014

When accepting that ore and waste extraction have to


consider certain physical restrictions in their
programming (phase size and available equipment), then
the time value of money becomes a relevant issue
The programming can be done using the saw graph
early described

Open Pit Mine Planning and Design 39

Case 1: Open pit plan with 6 phases


Plant 500 t/y
Mine 1,300 t/y
500 1 2 3 4 5 6

1 yr-1 yr-2 yr-3 yr-4 yr-5 yr-6 Time


2
500 3

4 Waste removal
1,000 5
6
Open Pit Mine Planning and Design 40

20
5/11/2014

Economic evaluation: Phase 6

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
- 300 Time

- 1,000 - 800
-225 -546 +706

Present value(t=0, r=10%) = - 65

Open Pit Mine Planning and Design 41

Economic evaluation: Phase 5

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
Time
- 400
- 500
- 1,000
-331 -376 +776

Present value(t=0, r=10%) = + 70

Open Pit Mine Planning and Design 42

21
5/11/2014

Case 2: Open pit plan with 5 Phases


Plant 500 t/y
Mine 1,300 t/y
500 1 2 3 4 5

1 yr-1 yr-2 yr-3 yr-4 yr-5 Time


2
500 3
4

1,000 5

Open Pit Mine Planning and Design 43

Economic evaluation: Phase 5

+1,250
1,000

0
yr-1 yr-2 yr-3 yr-4 yr-5 yr-6
- 100
Time

- 1,000 - 800
-83 -601 +776

Present value (t=0, r=10%) = + 92

Open Pit Mine Planning and Design 44

22
5/11/2014

Economic evaluation

Net Present Value @ r = 10 % ($)


Phase Case 1 (6 Phases) Case 2 (5 Phases)
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 250 2,504 275 2,529
5 70 2,574 92 2,621
6 -65 2,509 - -

Open Pit Mine Planning and Design 45

Summary of results

6
Discounted final
limit (Phase 5)
Breakeven final
limit (Phase 6)

Open Pit Mine Planning and Design 46

23
5/11/2014

Considering an underground
alternative

Open Pit Mine Planning and Design 47

2 open pit phases, 4 underground lifts

2
NPV(1)
3
$ 800
4
5
6

(1) Net present value at the beginning of year 1


Open Pit Mine Planning and Design 48

24
5/11/2014

3 open pit phases, 3 underground lifts.

3
NPV(1)
4 $ 450
5
$ 200
6
$ 50

(1) Net present value at the beginning of year 1


Open Pit Mine Planning and Design 49

NPV of underground lifts


+800

500 +450

+200
+50
0
3 6 4 6 5 6 6 Lifts

NPV Lift 3 (t=0, r=10%) = + 350


NPV Lift 4 (t=0, r=10%) = + 250
NPV Lift 5 (t=0, r=10%) = + 150
NPV Lift 6 (t=0, r=10%) = + 50

Open Pit Mine Planning and Design 50

25
5/11/2014

Economic evaluation
(Open Pit vs Underground)

Net Presente Value @ r = 10 % ($)


Phase Case 3 (OP/UG) Case 4 (Optimum)
Partial Cum Partial Cum
1 1,036 1,036 1,036 1,036
2 733 1,769 733 1,769
3 485 2,254 485 2,254
4 275 2,529 275 2,529
5 92 2,621 150 2,679
6 50 2,671 50 2,729

Open Pit Mine Planning and Design 51

Optimum configuration

5
6

Open Pit Mine Planning and Design 52

26
5/11/2014

Summary of evaluations

Net Present Value @ r = 10 % ($)


Phase
Case 1 Case 2 Case 3 Case 4

1 1,036 1,036 1,036 1,036


2 1,769 1,769 1,769 1,769
3 2,254 2,254 2,254 2,254
4 2,504 2,529 2,529 2,529
5 2,574 2,621 2,621 2,679
6 2,509 - 2,671 2,729

Open Pit Mine Planning and Design 53

NPV and Shareholder Value

Firm's Information Case 1 Case 2 Case 3 Case 4

Net present value ($) 2,509 2,621 2,671 2,729


Firm 's net debt ($) 1,000 1,000 1,000 1,000
Firm 's m arket value ($) 1,509 1,621 1,671 1,729
N Shares 1,500 1,500 1,500 1,500
Share value ($/Sh) 1.01 1.08 1.11 1.15

Open Pit Mine Planning and Design 54

27
5/11/2014

Role Of Feasibility Studies


Why Feasibility Study

Scoping Study

Preliminary Study

Bankable Feasibility Study

Risks

Open Pit Mine Planning and Design 55

Origin of the FS
The Feasibility Study is a development of mine
valuation reports. These had remained almost
invariable from 1900 to 1960s.
More complex and larger mining operations in
1960s and 1970s required sophisticated studies
and reporting. The FS was developed which:
Brings together all aspects of an operation into
one study
Looks at the inter-relationships and tries to solve
any problems
Aims to determine technical and economic
viability of a project

Open Pit Mine Planning and Design 56

28
5/11/2014

Feasibility Studies
Demonstrate that the project is economically
viable to the satisfaction of the Board, the
shareholders and all other stakeholders.
The FS enable the financing of:
Preliminary earthworks
Engineering construction
Infrastructure

Open Pit Mine Planning and Design 57

Feasibility Studies
Provide a detailed analysis of all the
factors affecting a projects viability.
Enable determination of a go or no
go decision
Have become an aid in obtaining
financial backing

Open Pit Mine Planning and Design 58

29
5/11/2014

Phases
Scoping Study
Pre-Feasibility Study
Final Feasibility Study

Open Pit Mine Planning and Design 59

Scoping Study
The Scoping Study is a preliminary investigation into a
project between a back of envelope and a pre-feasibility
study, or an assessment of necessary size, grade of a
target to explore.
It may also be called a Concept(ual) Study.

The study is normally undertaken with limited technical


and other data being available.

There is high reliance on experience and knowledge of


similar projects and it normally involves a basic level of
literature search.

Open Pit Mine Planning and Design 60

30
5/11/2014

Aim of A Scoping Study


Provide a document for decision-making.
Identify key factors that will influence the
overall outcome of the project.
Identify and briefly assess possible options,
identify risks
Give an indication of the potential financial
worth of the project

Open Pit Mine Planning and Design 61


MCA Project Management in Mine Planning and Design

Outcomes of Scoping Study


The outcomes will depend on the situation of the
particular project and reasons for the study. The
outcomes of a scoping study mayl include:
Information for decisions regarding the future of
the project.
Identification of key factors and probably risk
areas, requiring further early investigation.
Highlighting project activities or aspects which
have the greatest influence (sensitivity) on the
project value or return.
Highlighting project parameters that require
more accurate measurement or definition.
A proposed plan to advance, or close, the project
with schedules and estimated costs.
Open Pit Mine Planning and Design 63

31
5/11/2014

Scoping Study- Case Study


A scoping study for the Flying Fox T1 deposit as a stand-alone
underground mine with offsite ore treatment was prepared by
mining consultants Golder Associates Pty Ltd.

Main outcomes of the T1 scoping study were as follows:


Mineable Resources at 196,000t @ 5.4% Ni*
Contained nickel in concentrate 10,587 Ni tonnes
Gross Revenue (after royalties) A$101 million
Operating costs (mining, site, transport, treatment) A$201/tonne
ore (A$1.70/lb Ni produced)
Capital costs - Establishment A$6.0 million
- Mine development A$12.8 million
Undiscounted Net cash flow (before tax and D&A) A$37.2
million

* Note : Mineable Resources do not constitute a JORC compliant


resource or reserve category.
Open Pit Mine Planning and
Design
64

Preliminary Feasibility Study


Decisions: Abandon project, change or continue?
Planning: Focus continued investigations on project-
critical areas.
Justify detailed site investigation and resource
definition.
Determine the optimum project scope.
Identify risks opportunities and potential show
stoppers/fatal flaws.
Economic justification: Justify a full feasibility study.
Help sell the project.
Obtain private finance.
Development: Support permitting and stakeholder
liaison

Open Pit Mine Planning and Design 65


MCA Project Management in Mine Planning and Design

32
5/11/2014

Pre Feasibility looking at


alternate scenarios
Andean Golds Cerro Negro project in Argentina
Open pit optimization for the Vein Zone was completed using Whittle 4x software
and recovered gold block grades. A US$800/oz gold price was used as the base
case and the remaining inputs are as shown below:

Waste Ore Recovered


Pit Optimization Parameters Pit
Revenue
Factor
Tonnes Tonnes
Recovered
Au (g/t)
Ounces
Strip Ratio
(W:O)
('000) ('000) ('000)
Bench Angle 85o 1 0.30 9,763.1 2,083.3 5.30 355.0 4.69
5 0.38 11,922.4 2,580.3 4.84 401.3 4.62
Berm Width 9 metres every 20 metres 10
15
0.48
0.58
14,631.9
15,704.0
3,111.4
3,580.2
4.43
4.06
443.6
467.2
4.70
4.39
20 0.68 16,357.2 3,941.0 3.81 482.6 4.15
Pit Slope 52o overall slope with ramps 25 0.78 16,697.4 4,143.1 3.68 489.8 4.03
28 0.84 16,765.5 4,247.6 3.61 493.0 3.95

Mining Cost $1.50 per tonne mined 29


30
0.86
0.88
25,403.2
25,370.3
4,547.3
4,581.3
3.56
3.54
520.4
521.2
5.59
5.54
36 1.00 25,725.8 4,750.5 3.45 526.2 5.42
Processing Cost $14.00 per tonne ore 40 1.14 26,977.6 5,016.1 3.31 534.3 5.38
45 1.28 27,120.3 5,110.1 3.26 536.3 5.31

General & Administrative Cost $3.00 50


55
1.42
1.60
27,163.4
29,865.5
5,199.4
5,363.9
3.22
3.15
537.9
543.6
5.22
5.57
60 1.72 29,983.6 5,422.6 3.12 544.6 5.53
per tonne ore 67 2.00 30,555.8 5,536.6 3.07 546.5 5.52

66
Open Pit Mine Planning and
Design

Pre Feasibility scheduling


production
Open pit schedule
Oxide
Mix "Ore" Totals Waste
"Ore" Oxide "Ore" Mix "Ore" Totals Strip
Period (000's (000's (000's
(000's (g/t Au) (g/t Au) (g/t Au) Ratio
Tonnes) Tonnes) Tonnes)
Tonnes)
Pre-production 2.4 2.58 2,290.7
Year 1 644.1 3.05 28.2 4.00 672.3 3.09 3,615.3 5.38
Year 2 670.6 3.71 4.7 2.18 675.3 3.7 5,063.0 7.50
Year 3 643.1 4.62 31.7 3.65 674.9 4.58 2,022.2 3.00
Year 4 758.0 4.39 89.3 3.45 847.3 4.29 7,476.7 8.82
Year 5 1,186.7 2.55 163.3 2.76 1,350.0 2.58 7,619.7 5.64
Year 6 279.6 4.39 130.4 2.52 410.0 3.8 2,287.7 5.58
Totals 4182.1 3.59 447.7 2.96 4,629.8 3.53 30,375.3 6.56

Open pit and underground schedule


Vein Zone Eureka Cerro Negro Total
Period
Portable Ore Portable Ore Portable Ore
g/t Au g/t Au g/t Ag g/t Au g/t Ag
000's Tonnes 000's Tonnes 000's Tonnes
Year 1 672.3 3.09 677.7 11.54 242.81 1,350.0 7.33 121.89
Year 2 675.3 3.70 674.7 14.07 258.86 1,350.0 8.88 129.37
Year 3 674.9 4.58 675.1 12.97 203.05 1,350.0 8.77 101.55
Year 4 847.3 4.29 502.7 6.69 120.41 1,350.0 5.18 44.84
Year 5 1,350.0 2.58 1,350.0 2.58 0.00
Year 6 410.0 3.80 410.0 3.80 0.00
Totals 4,629.8 3.53 2,530.2 11.63 212.16 7,160.0 6.39 74.97

67
Open Pit Mine Planning and
Design

33
5/11/2014

Pre Feasibility things will change


over time
Brisas Gold Mine Venezuela
Key Economic Parameters and Results 2008 2006
Mill Through-Put Range (tonnes per day) 75,000 - 68,000 70,000
Metallugy Recovery
Plant Recovery - Gold 83% 83%
Plant Recovery - Copper 87% 87%
Net Payable Metal - Gold 82% 81%
Net Payable Metal - Copper 83% 83%
Life of Mine Production (payable metals)
Gold (million ounces) 8.35 8.41
Copper (million ounces) 1,156 1,113
Average Annual Production
Gold (ounces) 457,000 456,000
Copper (ounces) 63 60
Mine Life (years) 18.25 18.5

Initial Capital Cost ($million) 2008 2006


$ $
Mine 59.0 76.6
Mill 314.7 241.5
Infrastructure 67.8 65.8
Tailings management facility 38.3 23.8
Owner's Costs 63.4 55.6
Pre-Stripping 16.7 18.3
Indirect Costs (includes EPCM and Camp) 127.6 97.0
Contingency 43.8 59.4
Total Initial Capital $731.3 $638.0
69
Open Pit Mine Planning and
Design

Pre Feasibility things


will change over time
Base Case Economics 2008 2006
$ $
Metal Prices
Gold per ounce $600 $470
Copper per pound $2.25 $1.80
Cash Operating Cost Per Ore Tonne
Mining and Dewatering $2.68 $2.08
Processing 3.00 2.59
General and Administrative 0.43 0.42
Transport and Freight 0.43 0.34
Smelting and Refining 1.08 1.02
Total cash operating cost per tonne $7.62 $6.45
Cash per Ounce of Gold
Cash Operating Costs $120 $126
Exploitation Tax 22 16
Capital Cost (initial, sustaining and sunk) 135 111
Total Costs (including sunk costs) $277 $253
Total Cost (excluding sunk costs) $268 $245
Pre-Tax
Internal Rate of Return 20.5% 15.4%
Net Present Value (NPV)
@ 0% discount (billions) $2.77 $1.91
@ 5% discount (billions) $1.29 $0.78
70
Open Pit Mine Planning and
Design

34
5/11/2014

(Final) Feasibility Study (FFS)


The Feasibility Study Report is a decision-making
document based on verified facts and minimum
assumptions (criteria). The report may be used for
several purposes:
Assemble a comprehensive framework of facts.
Present a detailed project description.
Forecast profitability.
Facilitate partners and/or sources of finance.
Basis for detailed engineering.

Open Pit Mine Planning and Design 71


MCA Project Management in Mine Planning and Design

Requirements of a FS to be
bankable

A FS must be;
Credible
Definitive
Relevant
Independent

Open Pit Mine Planning and Design 72

35
5/11/2014

Final Feasibility high level issues


Geology and ore reserves - size, shape and depth of the ore, the grade of the
ore and distribution, how homogeneous, any major faults or intrusions and
hydrological reports.
Mining method and schedule surface, open cut, underground, annual
production rate vs life of mine, phasing of development, envisaged ROM
grade, capital equipment and manning levels required. (High production rate,
high capital expenditure, shorter mine life what is the optimum?)
Infrastructure requirements - including ancillary buildings, roads, drainage,
tailings disposal, general arrangement drawings of infrastructure layout.
Metallurgy/concentrator/washery design recovery factor, concentrate grade,
product quality.
Recommendations for the process plant including:
Flow diagram
Material and water balances
Equipment list (major items) together with budget quotations
General arrangement plan and elections of process plant to scale
1:100
Electrical system (line diagram)

73
Open Pit Mine Planning and
Design

- high level issues continued


Infrastructure, water, power, accommodation and environmental issues
source, capital and operating cost, disposal of tailings.
Permits right to mine and discharge waste and make good.
Construction schedule timing, how long to first production the quicker the
better.
Logistics - of supply materials, equipment and manpower to site including an
investigation of transport modes.
Identification of strategic decisions required - early ordering of long delivery
items, early starts to opening of negotiations for right-of-way dispensation etc.
Preliminary programme -for carrying-out the Project.
Construction cost minimum expenditure to get the project operating, which
varies depending on type and size of mine. All costs to include transport and
commissioning costs, fees and all management costs except for Client's own
costs.
Markets and marketing transport to market (FOB or CIF), price for product
quality sold, secondary processing costs, adequate demand for product.
Financial analysis put all of the above together to determine if the project is
financially viable.

74
Open Pit Mine Planning and
Design

36
5/11/2014

Things can go wrong


Mt Todd gold mine
Combination of many errors in forecasting can
be fatal for any project.
Project owner is Pegasus Gold Inc and wrote off
US$353.5 million in November 1997 after
closing down the project.
This write down of shareholders funds was of
balance sheet items amounting to US$122.6
million of acquisition costs, US$49.4 million of
deferred preproduction and development
expenses and US$181.3 million for property and
equipment.

Rudenno, 2008
Open Pit Mine Planning and Design
75

Case Study Mt Told Gold


Project
Commodity price overoptimism resulted in a
forecast gold price of US$385 per ounce,
including a hedging premium above
expected spot prices.
Spot prices while the project was operating
were about US$315 per ounce and the
hedging premium was small.

MCA - Risk Assessment in Mine Planning and Design

Open Pit Mine Planning and Design


76

37
5/11/2014

Case Study Mt Told Gold


Project
Forecast Actual Change

Reserves grade 1.07g/tAu 0.96g/tAu -10%


Metallurgical recovery of gold 84% 74% -12%
Throughput per year 8 Mt 6.7 Mt - 16%
Crushing costs $1.36/t $2.49/t +83%
Contract mining $1.00/t $1.15/t +15%
Power costs $0.058/kwh $0.075/kwh +29%
Cyanide usage 0.68kg/t 0.86kg/t +26%
Total cash costs $11.86/t $13.58/t +15%
Cash costs per ounce gold US$287/oz US$415/oz +45%
produced
Gold price US$385 US$315 -18%
Exchange rate, A$1.00=US$ 0.7 0.74 +6%

Open
MCA Pit MineinPlanning
- Risk Assessment and
Mine Planning Design
and Design
77

NATURE & PURPOSE OF


FEASIBILITY STUDIES IN MINING
Your Audience
Type Scoping Preliminary Feasibility

Audience Internal Technical Mixed Professional External

Exploration Business Executives Boards


Development
Joint venture Financiers
Executive
Extracts to stake Investors
holders
Consultants
Their Interests Critical factors Optimum project scope Profitability
Potential Profitability Costs
Cost of next stage Schedule
Risks, etc

Open Pit Mine Planning and Design 78 of 10

38
5/11/2014

Cost Accuracy
Scoping Preliminary Feasibility Project Control
Study Feasibility Study Estimate

Class 1 Class 2 Class 3 Class IV


(+/- 30% - 50%) (+/- 25%) (+/- 10% - 15%) (+/- 5% - 10%)

Order of
magnitude Equipment factor Definitive;
Forced detail estimate
Capacity factor estimate Fall out detail estimate
estimate

Open Pit Mine Planning and Design 79 of 10

Mining is a Business, but risky

Open Pit Mine Planning and Design 80

39
5/11/2014

MINING PROJECT RISKS


ECONOMIC / FINANCIAL
RISKS

TECHNICAL RISKS
OH&S RISKS

POLITICAL
RISKS

Participants discuss these elements of


Risk in Mining Projects.
81
Open Pit Mine Planning and Design

Conclusion
Strategic planning (SP) involves developing a range
of options, carrying out some form of evaluation,
assessing criteria and decision-making.

Open Pit Mine Planning and Design 82

40
5/11/2014

Activity 2:
Individual learning
Refer to worksheet 1
Development of a mining strategy: open pit and/or
underground?

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 83

Module 2
OPEN PIT OPTIMIZATION
What you will learn:

Block Values and Cost calculation

Pit Optimisation techniques

Pit Optimisation Software

Open Pit Mine Planning and Design 84

41
5/11/2014

Block Grade to Block Value

Dollar Value = Revenue - Costs

0.3%Cu -$1.13/t

Some factors to consider:


Location of the block relative to the surface effect on
cost
Processing costs my depend on rock type

Dollar Value = Revenues - Costs

Revenues can be calculated from:


Ore tonnages
Grades
Recoveries
Product price
Costs can be calculated from:
Mining cost
Milling cost
Overheads

Open Pit Mine Planning and Design 86

42
5/11/2014

A Formula for a Block Value used in Whittle


VALUE
= (METAL*RECOVERY*PRICE - ORE*COSTP) - ROCK*COSTM

Calculate the value of ore block X:

200 grams of metal X


100 tonnes of rock/ore
Metallurgical recovery = 97%
Selling price of metal $10.00 per gram
Cost of processing $12.00
Cost of mining $5.00
BV = [200x0.97x10 100x12 100x5] = $240

Calculating Costs

Must calculate values for:

Mining Cost per Tonne Mined


Processing Cost per Tonne Processed
Rehabilitation Cost per Tonne of Waste
Selling Cost per Unit of Product

Some Time Costs must be included

Open Pit Mine Planning and Design 88

43
5/11/2014

Include
Any cost which is directly proportional to the tonnes
or units of product:
Fuel oil
Wages
Spare parts
Explosives
etc

Include with the appropriate activity

Open Pit Mine Planning and Design 89

Include
Time costs which would stop if mining
stopped:
Site administration
Site infrastructure maintenance
Interest on working capital loan
Fall in resale value of equipment
Capital replacement
Truck purchase (long project)

Open Pit Mine Planning and Design 90

44
5/11/2014

What to do with Time Costs


When mill limited
Divide annual time cost by annual mill throughput
and add the result to the processing cost
When mining limited
Divide annual time cost by annual mining capacity
and add the result to the mining cost
N.B. Even add the mill time costs!
When selling limited ...

Open Pit Mine Planning and Design 91

Dont Include
Time costs which continue whether
you continue mining or not

Up-front/sunk costs

Open Pit Mine Planning and Design 92

45
5/11/2014

Activity 3:
Individual learning
Refer to worksheet 2
Block Values and Cost Calculation

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 93

Open Pit Optimisation


Resource Model

Resource
Mine survey
Classification

Resource estimate Dilution &


Measured ore losses
Indicated
Inferred

Diluted Resource Process


Parameters

Beneficiation Economic Operating


factors Parameters Costs

position in mine
Ore Reserve Model

planning flow Open pit optimisation Revenue, cost and

sheet
and design slope parameters

Potential Ore Mining production Overburden


Reserve schedule & sub-grade

Reserve Ore Reserve estimate Beneficiation


Classification Proved and Probable product

Open Pit Mine Planning and Design 94

46
5/11/2014

Activity 4 :
Individual learning
Refer to worksheet 3
Pit Optimisation Task 1

Complete the task and discuss the calculations with the


person(s) sitting next to you!

Open Pit Mine Planning and Design 95

Definition of the Optimal Outline


Any feasible outline has a Dollar Value. In this context
feasible means that it obeys safe slope requirements

The optimal outline is defined as the one with the highest


dollar value (Profit = Revenue Costs)

Nothing can be added to an optimal outline which will


increase the value without breaking the slope constraints.

Nothing can be removed from an optimal outline which


will increase the value without breaking the slope
constraints.

96 Open Pit Mine Planning and Design

47
5/11/2014

Pit Optimisation Techniques


Moving/Floating/Dynamic Cone Algorithm

Lerchs-Grossmann 2-D Dynamic Programming


Algorithm

LG 3-D Graph Theory Algorithm.

Network Analysis Algorithm

Linear Programming (integer programming)

etc

Open Pit Mine Planning and Design 97

Floating Cone Method


Position an inverted cone, with the required slopes,
on each block with a positive value

If the total value of all blocks in the cone is positive,


mine those blocks

Repeat these steps until no cone has a positive


value

There are two problems

Open Pit Mine Planning and Design 98

48
5/11/2014

Floating Cone Method

Courtesy: Kores Corpration


Open Pit Mine Planning and Design 99

Floating Cone- Mining too little

-30
-80 -80

+100 +100

Open Pit Mine Planning and Design 100

49
5/11/2014

Floating Cone- Mining too much

Open Pit Mine Planning and Design 101

Lerchs-Grossman Algorithm
Works with block values

Works with block mining precedence

Guarantees to find the three-dimensional


outline with the highest possible value

Open Pit Mine Planning and Design 102

50
5/11/2014

Lerchs-Grossman Algorithm
Works with block values

Works with block mining precedence

Guarantees to find the three-dimensional


outline with the highest possible value

Open Pit Mine Planning and Design 103

Lerchs-Grossman Algorithm

Open Pit Mine Planning and Design 104

51
5/11/2014

LG 3d block and graph representation


Orthogonal set of blocks 2 basic geometries to represent open
pit
Arrows point to the blocks that first need to be removed to
access the underlying block (at the base)

Open Pit Mine Planning and Design 105

Final Pit Design composite plan

Open Pit Mine Planning and Design 106

52
5/11/2014

Activity 5 :
Individual learning
Refer to worksheet 3
Pit Optimisation Task 2

Follow the example calculation of the LG pit optimisation


algorithm

Open Pit Mine Planning and Design 107

Precautions with the OP algorithms


1) Ascribing costs to blocks
The algorithms to determine the final pit
limit assume that an economic value can be
assigned to each block

However, many of the costs are time costs;


it means that assigning them to blocks
requires an assumption about what is the
unitary operation that restricts production
(to express these costs in terms of that
activity)
Open Pit Mine Planning and Design 108

53
5/11/2014

2) Assumption of a breakeven grade


To calculate the net value of a block one has
to assume a breakeven cut-off grade

A common assumption is to classify as ore


those blocks with a positive value and waste
those blocks with a negative value. If the
mine is the limiting operation, this misses the
opportunity to create value.

Open Pit Mine Planning and Design 109

3) Time value of money


There are costs that can not be estimated
without a mining plan. This is the case of waste
material, which has to be placed in a dump and
the cost will depend on the time that this
happens because of the haul distance

This can be solved by iterations!

Open Pit Mine Planning and Design 110

54
5/11/2014

4) Blending requirements
There are cases where blocks should be
blended with others to be classified as
ore. But that again requires a mining plan in
advance.

This can also be solved by iterations!

Open Pit Mine Planning and Design 111

Major General Mine Design Systems


Fully functional packages (with build-in CAD systems):
VULCAN
DATAMINE/CAE
SURPAC/GEMCOM
MineSight
Minex/Gemcom - WHITTLE
Micromine

CAD overlaying packages:


AutoCAD
SurvCADD/Carlson
LKAB System

Open Pit Mine Planning and Design 112

55
5/11/2014

Data Import

Import
+
3D Borehole
Processing

Open Pit Mine Planning and Design 113

Geological Interpretation

Open Pit Mine Planning and Design 114

56
5/11/2014

Block Model + Grade Assessment

Block Model with Grade

Open Pit Mine Planning and Design 115

Economical Model - Grade


>>> $Value
Au >>> Value
[g/t] $$$

Open Pit Mine Planning and Design 116

57
5/11/2014

Optimisation/Design
Major optimisation programs based on Lerchs-
Grossman algorithm:

Whittle FX Optimiser (stand alone)

MineMax Planner (stand alone)

Pit Optimizer (Vulcan 3D)

NPV Scheduler (Datamine)

Pit Optimiser (Surpac)


Open Pit Mine Planning and Design 117

Whittle FX
Strategic Mine Planning Software

Import Block Model Pit by Pit Graph

Constrains:
Economical
Geometrical No access constrains
Operational No haul road/ramp
Open Pit Mine Planning and Design 118

58
5/11/2014

Optimal Pit

Open Pit Mine Planning and Design 119

Mine Design

Open Pit Mine Planning and Design 120

59
5/11/2014

Mine Design

Geomechanics/Geotechnical
Access constraints
Equipment selection
Ventilation network (underground)
Rehabilitation
Environmental constraints

Open Pit Mine Planning and Design 121

Final Optimal Pit

Open Pit Mine Planning and Design 122

60
5/11/2014

Final Optimal Pit & Pushbacks

Open Pit Mine Planning and Design 123

Reporting & Evaluation

Open Pit Mine Planning and Design 124

61
5/11/2014

Scheduling

Open Pit Mine Planning and Design 125

The Pushbacks Generation

Open Pit Mine Planning and Design 126

62
5/11/2014

Optimizing Production
Schedules

Open Pit Mine Planning and Design 127 of 26

Optimizing Production Schedules

+ =

Open Pit Mine Planning and Design 128

63
5/11/2014

Activity 6 :
Individual learning
Review the following technical paper:

Chanda, E.K., Spencer, E. (1999). Maximising Resource


Utilisation in Open Pit Design, in Proc. 28th International
Symposium on Computer Applications in the Minerals
Industry, 20-22 October, Colorado School of Mines, pp359-366,
(SME-AIME, Littleton).

1) What is unique about the the approach used by the


authors?
Open Pit Mine Planning and Design 129

waste dump planning

What you will learn:

Principles of dump design and


Dump optimisation

Open Pit Mine Planning and Design 130

64
5/11/2014

Why waste dump planning?

A strip ratio of 10:1, say, implies that for every unit of


ore mined, 10 times of waste rock is mined.
The waste rock ends up being stored in a waste
dump
Traditionally little attention has been paid to dump
design and planning, the focus being on planning of
ore extraction
It has been recognised that dump design and
planning is an integral part of pit design.

Open Pit Mine Planning and Design 131

Rock flow in an open pit mine

Yu (2014)
Open Pit Mine Planning and Design 132

65
5/11/2014

Waste Dump Design


Two main approaches:

1) Top-down dumps waste rock is dumped


over an advancing face (angle of repose)
approx 38o from horizontal. After
dumping is complete . The dump is
reshaped to its intended configuration,
usually using bulldozers.

Open Pit Mine Planning and Design 133 of 10

Waste Dump Design

2) Bottom-up storage waste rock


is dumped in series of piles ,
and then spread to form a
relatively thin layer. Also known
as paddock dumping.

Open Pit Mine Planning and Design 134 of 10

66
5/11/2014

Waste Dump Design

Hybrid dumping whereby top


down used is used to produce
relatively thick layers (10 or 15 m,
say), which are then overlain by
subsequent equally thick layers.
This approach is safer and
requires leas reshaping.

Open Pit Mine Planning and Design 135 of 10

Waste Dump Design

Dump progression with shortest haul first strategy

Open Pit Mine Planning and Design 136 of 10

67
5/11/2014

Waste Dump Design

Dump design considering NAF PAF material (Yu 2013)

Open Pit Mine Planning and Design 137 of 10

Waste Dump
Optimisation- how?
MINEMAX Software
Simultaneous pit and waste dump design
Dump modelled as blocks

WHITTLE Software
Dump optimisation as mirror image of open pit
optimisation

XPAC Advanced Destination Scheduler) Software


Module schedules rock placement

Open Pit Mine Planning and Design 138 of 10

68
5/11/2014

Waste Dump Optimisation-


Recent Developments

Integrated modelling of dumping system (Yu 2013)

Open Pit Mine Planning and Design 139 of 10

Module 3
PRODUCTION SCHEDULING
What you will learn:

Principles of production scheduling

Scheduling Software

Open Pit Mine Planning and Design 140

69
5/11/2014

Mine Scheduling (definition)


A mining schedule, which tell us when things
occur, can be constructed by applying
production constraints to the mining
sequence
Basis for preparing and controlling the
mines development and production
A schedule determines the cash flow ($$$)
associated with mining.

Open Pit Mine Planning and Design 141

Typical Timeline

Year
-2 -1 +1 +2

Pre-production
(Development Production
Construction)

Open Pit Mine Planning and Design 142

70
5/11/2014

Inputs
The scope of the work to be done from Mining
Layout Designs
Rates at which this work is normally prepared,
from Key Performance Indicators (KPI)
Labour working hours and rosters from
Strategic Planning module
Plant capacities, from the Strategic Planning
modules
Production schedules, Ore reserves, tonnes and
grades, recoveries and dilutions

Open Pit Mine Planning and Design 143

Types of Mining Schedule


Production schedules
Long Term or Life of Mine (10+ years)
Medium Term (5 years approx.)
Short Term (3 months 2 years)
Extremely Short Term (down to a shift, or for specific jobs)
Exploration drilling schedules
Development schedules
Production drilling schedules
Equipment schedules
Labour schedules
Filling schedules
Consumable schedules
Special project schedules
Open Pit Mine Planning and Design 144

71
5/11/2014

Scheduling Packages
XPAC
iGannt
MS Project
MS Excel
Whittle 4D
In-house

Open Pit Mine Planning and Design 145

XPAC
Developed by Runge Software
Business focussed mine scheduling application
Specifically developed for forecasting, reserve
database and mine scheduling management of all
types of mineral deposits and mining methods
Easy-to-use tools for the adaptation, analysis and
scheduling of mineral resources
Designed for surface/underground coal mining
Has limitations in underground mining or in pits with
complex geometries

Open Pit Mine Planning and Design 146

72
5/11/2014

iGantt
Developed by MineMax

Tool for open-pit and underground production


scheduling

Integrates Gantt chart, 3D visualization and


spreadsheet views of a production schedule

Used for scheduling a single operation or multiple


operations across an enterprise

Open Pit Mine Planning and Design 147

Open Pit Mine Planning and Design 148

73
5/11/2014

Open Pit Mine Planning and Design 149

Open Pit Mine Planning and Design 150

74
5/11/2014

Financial Technical Model


Plant design
Infrastructure (road, power, water, village, etc.)
Equipment selection
Capitals
Operating costs
Royalty
Tax
Revenue

NCF NPV, IRR, PB, etc.

Open Pit Mine Planning and Design 151

Activity 8 :
Individual learning
Refer to worksheet 4
Production Scheduling

Calculate the monthly production figures for a small gold


mine

Open Pit Mine Planning and Design 152

75
5/11/2014

Module 4
Cut-off grade optimization
1. Background
2. The model
3. Example 1: an hypothetical case
4. Example 2: a copper open pit mine
& mill
5. Conclusions
6. References

Open Pit Mine Planning and Design 153

1. Background

This model was developed in the early


1960s by Ken Lane, a mathematician who
made his professional career in the Rio
Tinto Group

At the time, the model was used in various


mines of Rio Tinto including Palabora
mine in South Africa, and Bougainville
mine in PNG.
Open Pit Mine Planning and Design 154

76
5/11/2014

2. The model
Final product

Concentrates Qr
Ore

Qc
R
C
Cut-off gx
Slag
Qm Tailings

Waste

M
Open Pit Mine Planning and Design 155

Variables used in Lanes Model

M = Mine capacity per period (t of material)


C= Plant capacity per period (t of ore)
R= Refinery capacity per period (t of product)
Qm = Quantity of run-of-mine material (t of material)
Qc = Quantity of ore (t of ore)
Qr = Quantity of final product (t of product) = Qcgy
T= Time to mine, process or refine Qm
P= Profit

Open Pit Mine Planning and Design 156

77
5/11/2014

Models variables (cont)

d= annual discount rate


m= mining costs ($/t of material)
c= concentrating costs ($/t of ore)
r= refining and marketing costs ($/t of product)
f= fixed costs, per period ($/period)
s= selling price ($/t of final product)
y= overall metallurgical recovery

Open Pit Mine Planning and Design 157

The profit equation for Qm

P s - r Qr c Qc m Qm f T (1)

As Q r Q c g y

P s - r g y c Qc m Qm f T (1a)

Open Pit Mine Planning and Design 158

78
5/11/2014

Profit from Qm and Present Value


f

Qm
Qc

V
W
gx Grade

V = Present value at the beginning of period T


W= Remaining present value after mining Qm

Open Pit Mine Planning and Design 159

P P2 P3 P4 Pn

0 Time
W

PW
V (2)
(1 d)T
Open Pit Mine Planning and Design 160

79
5/11/2014

If time T is small:

(1 + d)T 1 + dT (3)

Replacing in (2):
PW
V (4)
(1 d T)
Re-arranging:

V(1 + dT) = P + W (5)

Open Pit Mine Planning and Design 161

Re-arranging:

v = V - W = P - dVT (6)

Where v is the contribution that the


fraction Qm of the ore deposit makes to
the present value of the business

As such, v is the variable to maximise


when choosing the optimum cut-off
grade
Open Pit Mine Planning and Design 162

80
5/11/2014

Replacing (1) in (6):


v s r Qr c Qc m Qm f d V T (7)

But the optimum present value V on the


right side of equation (7) is unknown
until the cut-off grade policy is optimised

This chicken and egg problem is solved


by iterations, using an arbitrary value of
V in the first iteration and stoping when V
converges
Open Pit Mine Planning and Design 163

Economic cut-off grades

v s r Qr c Qc m Qm f d V T (7)
In equation (7), time T depends on the
stage that limits the pace at which ore is
mined

That is, the quantities Qm, Qc or Qr and


their respective capacities M, C, or R

This leads to three economic cut-off


grades:
Open Pit Mine Planning and Design 164

81
5/11/2014

a) When the mine imposes a limit (M)

Qm
In this case, T
M

Replacing this in expression (7):

m f d V
v m s r Qr c Q c Qm
M

Max vm v m
0
g

Open Pit Mine Planning and Design 165

As Qm is given, g only affects Qc and Qr

Then g must be chosen to make (s-r)Qr - cQc


as large as possible

s - r Qc g y c Qc
Therefore:
c
gm
s r y
Open Pit Mine Planning and Design 166

82
5/11/2014

b) When the plant imposes a limit (M)

Qc
In this case, T
C

Replacing this in expression (7):

f d V
v c s r Qr c Q c m Qm
C

Max vc v c
0
g

Open Pit Mine Planning and Design 167

In the same way, as Qm is given, g must be


chosen to maximise:

s - r Qc g y c f d V Qc
C

Therefore:
c
f d V
gc C
s r y

Open Pit Mine Planning and Design 168

83
5/11/2014

c) When the refinery imposes a limit (R)

Qr
In this case, T
R

Replacing this in expression (7):


v r s r
f d V Q c Q m Q
R r c m

Max vr v r
0
g

Open Pit Mine Planning and Design 169

In the same way, as Qm is given, g


must be chosen to maximise:

s r
f d V Q g y c Q
R c c

Therefore:
c
gr

s r
f d V y

R

Open Pit Mine Planning and Design 170

84
5/11/2014

Balancing cut-off grades


The operation is sometimes limited by two or
eventually three stages simultaneously

Then, three balancing cut-off grades can be


introduced into the analysis

gmc: Mine-Plant
gmr: Mine-Refinery
grc : Refinery-Plant

Open Pit Mine Planning and Design 171

Mine-mill example
f
Qm

gm gmc gc Grade

gmc fully utilises mine and mill capacities;


that is, maximum stripping ratio at the mine
and throughput at the mill

Open Pit Mine Planning and Design 172

85
5/11/2014

Mine capacity: 650,000 t/d


Mill capacity: 150,000 t/d
gm: 0.25 %Cu
gc: 0.65 %Cu
Possible throughputs:
Cut-off Mine Mill Grade
% Cu t/d t/d % Cu

0.25 450,000 150,000 0.9


0.50 650,000 150,000 1.2
0.65 650,000 120,000 1.3

0.5 %Cu is a balancing cut-off

Open Pit Mine Planning and Design 173

In summary, Lanes model considers six


cut-off grades:
three economic cut-off grades, and
three balancing cut-off grades
The former depend on economic factors
and capacities whereas the latter are
determined by the grade distribution that
can vary widely throughout irregular ore
bodies
None of these considers mining costs!
Open Pit Mine Planning and Design 174

86
5/11/2014

Optimum cut-off grades

The overall optimum is one of the six cut-


off grades already defined:
1) gm
2) gc
3) gr
4) gmc
5) gmr
6) grc

To assess which one is the optimum it is


best to consider each pair of stages in
turn
Open Pit Mine Planning and Design 175

To see which one is the optimum it is best


to plot the value functions considering
each pair of stages in turn

Mine-Concentrator

m f d V
v m s r Qr c Q c Qm
M

f d V
v c s r Qr c Q c m Qm
C

Open Pit Mine Planning and Design 176

87
5/11/2014

Gmc = gmc
vm vc

gm gmc gc g

Gmc = gm
vm vc

gmc gm gc g

Open Pit Mine Planning and Design 177

Gmc = gc

vm vc

gm gc gmc g

In a similar way, by considering the other


pair of stages, it is possible to obtain Gmr
and Grc

Open Pit Mine Planning and Design 178

88
5/11/2014

The overall optimum cut-off grade is:

G = Middle value (Gmc,Gmr,Grc)

vr

vm vc

gm grc gmr gmc gc gr g

Open Pit Mine Planning and Design 179

3. Example 1: an hypothetical case


Mine capacity (M) = 100
Plant capacity (C) = 50
Refinery capacity (R) = 40
Mining costs (m) =1
Concentrating costs (c)= 2
Refining costs (r) =5
Fixed costs (f) = 300
Selling price (s) = 25
Overall recovery (y) = 100 %
Annual discount rate (d)= 15 %

Open Pit Mine Planning and Design 180

89
5/11/2014

Grade-tonne relationship
f(t)

Grade
Quantity
interval
0.0 0.1 100
0.1 0.2 100
0.2 0.3 100 100

. .
.
0.9 1.0 100
1000

0 0.5 1.0 g

Open Pit Mine Planning and Design 181

Balancing cut-off grades


Tonnage Ratios
Cut-off
Mine Mill Grade Ref. M/C M/R C/R
0.0 1000 1000 0.50 500 1.00 2.00 2.00
0.1 1000 900 0.55 495 1.11 2.02 1.82
0.2 1000 800 0.60 480 1.25 2.08 1.66
0.3 1000 700 0.65 455 1.43 2.20 1.54
0.4 1000 600 0.70 420 1.67 2.38 1.43
0.5 1000 500 0.75 375 2.00 2.67 1.33
0.6 1000 400 0.80 320 2.50 3.13 1.25
0.7 1000 300 0.85 255 3.33 3.92 1.18
0.8 1000 200 0.90 180 5.00 5.56 1.11
0.9 1000 100 0.95 95 10.00 10.53 1.05

M/C = 100/50 = 2.00 gmc = 0.50


Balancing
M/R = 100/40 = 2.50 gmr = 0.45 cut-off grades
C/R = 50/40 = 1.25 grc = 0.60

Open Pit Mine Planning and Design 182

90
5/11/2014

Economic cut-off grades


c
gm 0.10
s r y

c
f d V For V = 0
gc C 0.40
s r y
c
gr 0.16

s r
f d V
y

R

Open Pit Mine Planning and Design 183

Optimum cut-off grades

Gmc = Mid (0.10, 0.40, 0.50) = 0.40

Gmr = Mid (0.10, 0.16, 0.45) = 0.16

Grc = Mid (0.16, 0.40, 0.60) = 0.40

G = Mid (0.16, 0.40, 0.40) = 0.40

Open Pit Mine Planning and Design 184

91
5/11/2014

Intermediate mine plan


Year Cut-off Mine Mill Ref. Profit
1 0.4 83.3 50 35 216.7
2 0.4 83.3 50 35 216.7
. . . . . .
. . . . . .
. . . . . .
12 0.4 83.3 50 35 216.7

P = (25 - 5)35 250 183.3 3001

P = 216.7
PV@12y and 15% = 1174

Open Pit Mine Planning and Design 185

Second iteration
c
gm 0.10
s r y

c
f
d V For V = 1174
gc C 0.58
s r y
c
gr 0.25

s r
f d V
y

R

Open Pit Mine Planning and Design 186

92
5/11/2014

Optimum cut-off grades

Gmc = Mid (0.10, 0.50, 0.58) = 0.50

Gmr = Mid (0.10, 0.25, 0.45) = 0.25

Grc = Mid (0.25, 0.58, 0.60) = 0.58

G = Mid (0.25, 0.50, 0.58) = 0.50

Open Pit Mine Planning and Design 187

A new mine plan...

With the new cut-off grade of 0.5, a new


mine plan can be developed but this time
changing the present value from year to year
If annual profits are discounted to time 0 and
added up, it gives another estimate of V
If the difference of the initial and final value
of V exceeds a defined tolerance threshold,
the whole process is repeated

Open Pit Mine Planning and Design 188

93
5/11/2014

Annual profit for the first year...

For a 0.5 cut-off grade, the annual profit and


present value is as follow:

P = (25 - 5)37.5 250 1100 3001


P = 250
PV@ 10y and 15% = 1255

Open Pit Mine Planning and Design 189

Optimum mine plan and cut-off grades policy


Year Cut-off Mine Mill Ref. Profit PV
1 0.50 100 50 37.5 250 1255
2 0.50 100 50 37.5 250 1194*
3 0.50 100 50 37.5 250 1123
4 0.50 100 50 37.5 250 1041
5 0.50 100 50 37.5 250 947
6 0.50 100 50 37.5 250 840
7 0.50 100 50 37.5 250 716
8 0.49 97 50 37.1 245 573
9 0.46 93 50 36.5 238 414
10 0.41 89 50 35.9 229 238
11 0.41 21 13 8.8 55 45

1000 513 380.8 2517

PV @ 11y and 15%= 1256


* W = V(1+d) - P
W = 1255 1.15 250 = 1194
Open Pit Mine Planning and Design 190

94
5/11/2014

4. Example 2: a copper open pit mine & mill


Relevant data:
Mine capacity (M) = 18.9 Mt/a
Plant capacity (C) = 7.2 Mt/a
Mining costs (m) = 0.85 $/t material
Milling costs (c) = 3.7 $/t ore
Fixed costs (f) = 3.5 M$/a
Copper price (s) = 2205 $/t Cu ($1.0 /lb)
TC/RC & selling cost (r) = 705 $/t Cu ($0.32 /lb)
Overall recovery (y) = 85 %
Annual discount rate (d) = 10 %

Open Pit Mine Planning and Design 191

A set of four pushbacks

Open Pit Mine Planning and Design 192

95
5/11/2014

Input to the model: four scheduled, nested pits


(periods) from a preliminary mine plan

PP 1
1
3

1
3
2 4

Open Pit Mine Planning and Design 193

Grade-tonnage relationship for the four pits


Cut-off Period 1 Period 2 Period 3 Period 4
% Cu Mt % Cu Mt % Cu Mt % Cu Mt % Cu
0.0 20.3 1.05 36.5 0.79 56.3 0.57 80.1 0.59
0.2 18.7 1.13 30.1 0.92 40.8 0.76 60.4 0.77
0.4 15.3 1.32 24.4 1.08 28.5 0.97 50.2 0.87
0.6 12.9 1.47 19.7 1.22 21.7 1.11 38.3 0.98
0.8 11.0 1.61 13.7 1.45 15.1 1.30 22.7 1.18
1.0 8.6 1.80 10.2 1.64 10.0 1.49 14.6 1.35
1.2 7.1 1.95 7.6 1.83 6.9 1.67 9.0 1.49
1.4 5.9 2.08 5.6 2.02 4.4 1.88 5.0 1.65
1.6 4.4 2.27 4.0 2.24 2.7 2.11 2.9 1.75

Open Pit Mine Planning and Design 194

96
5/11/2014

Output for a Base case


Cut-off Mine Mill Ratio Profit PV
Year Period 1
(% Cu) (Mt) (Mt) (% Cu) (W/O) (M$) (M$)

1 1 0.85 14.2 7.2 1.67 0.97 110.3 475.5


2 1 0.78 6.1 3.4 1.59 0.82 49.6 412.8
2 2 0.78 9.8 3.8 1.43 1.56 44.8 412.8
3 2 0.72 16.8 7.2 1.37 1.34 81.3 359.6
4 2 0.67 9.9 4.7 1.31 1.13 50.4 314.2
4 3 0.61 6.7 2.5 1.12 1.62 19.4 314.2
5 3 0.61 18.9 7.2 1.12 1.62 56.3 275.8
6 3 0.60 18.6 7.2 1.11 1.58 55.8 247.0
7 3 0.56 12.1 4.9 1.08 1.45 36.5 215.9
7 4 0.56 4.5 2.3 0.96 0.98 14.9 215.9
8 4 0.53 13.6 7.2 0.94 0.89 44.5 186.1
9 4 0.50 13.1 7.2 0.92 0.82 43.3 160.3
10 4 0.47 12.6 7.2 0.91 0.75 42.4 132.9
11 4 0.44 12.1 7.2 0.89 0.68 41.4 103.9
12 4 0.41 11.6 7.2 0.87 0.61 40.2 72.9
13 4 0.37 11.2 7.2 0.86 0.55 38.9 39.9
14 4 0.33 1.5 1.0 0.84 0.50 5.1 5.0

193.2 94.6 1.11 1.04 PV = 475.5


Open Pit Mine Planning and Design 195

Output for an expanded case (Mill from 7.2 to 9.0 Mt/a)


Cut-off Mine Mill Ratio Profit PV
Year Period 1
(% Cu) (Mt) (Mt) (% Cu) (W/O) (M$) (M$)

1 1 0.78 16.3 9.0 1.59 0.81 131.8 521.2


2 1 0.71 4.0 2.3 1.53 0.71 33.1 441.6
2 2 0.67 14.0 6.7 1.30 1.10 71.3 441.6
3 2 0.65 18.5 9.0 1.29 1.05 95.4 381.3
4 2 0.60 4.1 2.2 1.22 0.86 22.1 324.0
4 3 0.45 14.2 6.8 1.00 1.10 46.6 324.0
5 3 0.45 18.9 9.0 1.00 1.10 62.0 287.7
6 3 0.45 18.9 9.0 1.00 1.10 62.0 254.4
7 3 0.45 4.2 2.0 1.00 1.10 13.7 217.9
7 4 0.51 12.9 7.0 0.93 0.84 43.2 217.9
8 4 0.48 15.9 9.0 0.91 0.76 54.1 182.8
9 4 0.45 15.2 9.0 0.89 0.69 52.9 146.9
10 4 0.42 14.6 9.0 0.88 0.62 51.5 108.8
11 4 0.38 14.1 9.0 0.86 0.56 50.0 68.1
12 4 0.34 7.4 4.9 0.84 0.51 26.4 25.0

193.2 103.9 1.06 0.86 PV = 521.2

Open Pit Mine Planning and Design 196

97
5/11/2014

Conclusion for this case


The Base Case produces a declining cut-off
grade policy starting at 0.85 %Cu and yielding
a PV of $ 475.5 million
The Expanded Case lowers the initial cut-off
from 0.85 to 0.78 %Cu and increases the PV
by $46 million from $475.5 to $521.2 million
If the expansion capital investment is less than
$46 million, then it is worth going ahead

Open Pit Mine Planning and Design 197

5. Concluding remarks
Lanes cut-off grade model is a first attempt to
define economically what material is ore in a
life-of-mine (LOM) plan
It requires a holistic view of mining in that the
optimisation needs a preliminary LOM plan.
That is, a final pit limit, pushbacks design and
scheduling based on a breakeven cut-off - the
mine or plant cut-off grade, for instance

Open Pit Mine Planning and Design 198

98
5/11/2014

Activity 8 :
Individual learning
Refer to worksheet 5
Cutoff Grade Optimisation

Follow the calculations to the problems

Open Pit Mine Planning and Design 199

Lanes model considers various variables as


fixed input capacities, and downstream cut-
offs such as metallurgical recovery at the mill
Most recent developments have expanded the
model to include some of these variables and
handle them simultaneously
When the problem becomes too complex, it is
solved using other mathematical tools, integer
linear programming being one of them

Open Pit Mine Planning and Design 200

99
5/11/2014

6. References
Kenneth F. Lane - The economic definition of ore, Mining
Journal Books, London 1988
Kenneth F. Lane - Choosing the optimum cut-off grade,
Colorado School of Mines Quarterly. Vol. 59-4, 1964, pp. 811-
829
Blackwell, M. Some aspects of the evaluation and planning of
the Bougainville copper project, Decision-Making in the
Mineral Industry, CIM Special Vol 12, 1971 pp. 261-269

Open Pit Mine Planning and Design 201

Module 5
Mine Planning Software

Software Packages
Categories
Capabilities
Providers

Open Pit Mine Planning and Design


202

100
5/11/2014

Common Software Packages

Open Pit Mine Planning and Design


203

Categories of Mining Software

Open Pit Mine Planning and Design


204

101
5/11/2014

Mapping Software

Open Pit Mine Planning and Design


205

Geological & Data managent

Source: (Sable, 2013)


Open Pit Mine Planning and Design
206

102
5/11/2014

Geological Modelling/
Resource Estimation

Drill hole display (Source: Geovia, SUPARC)

Open Pit Mine Planning and Design


207

Geological Modelling/
Resource Estimation

Ore body model(Source: CAE, STUDIO 3)

Open Pit Mine Planning and Design


208

103
5/11/2014

Mine Design

Pit Design (Source: Maptek, VULCAN)

Open Pit Mine Planning and Design


209

Planning and Scheduling

Pit Design (Source: Geovia, MineSched)

Open Pit Mine Planning and Design


210

104
5/11/2014

Financial Evaluation

Financial Analysis Software


(RungePincockMinarco)

Open Pit Mine Planning and Design


211

Optimisation/Risk Analysis

Pit Optimisation (Geovia, WHITTLE)

Open Pit Mine Planning and Design


212

105
5/11/2014

Monitoring & Control

Truck Dispatching (Modular Mining System; (DISPATCH)


Open Pit Mine Planning and Design
213

Simulators

Coal Mining Simulator (Immersive Technologies)


Open Pit Mine Planning and Design
214

106
5/11/2014

Virtual Reality

ViMine VR Software 3D Ore body model


Open Pit Mine Planning and Design
215

Summary

Advances in Computer technology has


made it possible to model complex mining
environments
Most widely software is for Mine Design &
Planning
Further developments in simulation and
risk modelling
Mining software harmonisation by
suppliers

Open Pit Mine Planning and Design


216

107
5/11/2014

Module 6
mine to mill optimisation
Concept embraced and practiced by mining
companies
The philosophy is base on:
Characterise
Track
Measure
Model
Potential to save mining companies thousands of
Dollars

Open Pit Mine Planning and Design


217

Mine production system processes

Drilling
Blasting
Loading
Hauling
Milling (Crushing, grinding)

Examine total system with regard to cost,


productivity, product quality, optimisation...

Open Pit Mine Planning and Design 218

108
5/11/2014

Loading: increased fragmentation => higher rate of


shovel productivity, hence lower costs per BCM.
Hauling: Truck production per hour will increase with
greater fragmentation due to faster shovel loading rates.
Reduced cycle time.
Crushing: Lower crushing costs result from increased
fragmentation as more material pass through as under
size.
Drilling and blasting costs are harder to relate to
fragmentation).

Open Pit Mine Planning and Design 219

Optimum Fragmentation Curves

Unit costs as a function of the degree of


fragmentation
Systems optimisation:

Overall Cost Curve

Degree of fragmentation

Open Pit Mine Planning and Design 220

109
5/11/2014

Exploration Drilling
Intact rock data
Crushing/grinding
Mineralogy data
Energy data Ore body modeling and
Bond's Work Index Fracture frequency data pit design
Settings

Hauling Blasthole Drilling


Payload data Bore diameter

Process
Voids ratio* Hole deviation monitor
LCM Geophysical data

Optimization
TKPM rating
Real time drilling data
Autonomy

Blast design,
Routing data

Excavation/Loading
Load-Haul
Digability* S01U264007
Blast Design
Dig rate* 120

100 Pattern layout


Percentage Passing (%)

Dipper design 80

60
S01U264007
35.2Mtpa ROM Target
VOID
Power consumption 40

20 Powder factor
Swing analysis 0
1 10
Size (mm)
100 1000

Explosive
Autonomy

Muckpile properties
Blast Modelling
Size distribution*
Displacement model
Voids ratio*
Fly rock
LCM
Heave mechanics
Visualization
Density

Optimum Fragmentation
Examine individual components and the whole system
Goal: achieving a prescribed level of fragmentation at
minimum cost
In-situ ore with particle size considered to be very large
and reducing to size in the order microns (eg -80 mesh).
Measuring Fragmentation, how?
Diggability (BCM/HR)

Size distribution of muckpile (WIPFrag Software),


Split-Desktop software
Photographs are taken from muck pile, digging
face, moving truck, etc.
Open Pit Mine Planning and Design 222

110
5/11/2014

Drilling and Blasting SubSystem

Fragmentation evaluation
Measurement of parameters- correlate with
fragmentation
Photographs are taken from muck pile, digging face,
moving truck, etc.
Crusher monitoring - energy, feed, product size,
throuputghput
Shovel monitoring- load, wait, down time, swing, power

Open Pit Mine Planning and Design 223

Case Study

Open Pit Mine Planning and Design 224

111
5/11/2014

Case Study
Modeling Muck Pile Fragment Size to Optimize
Excavator Productivity in Open Pit Mining

Prominent Hill Copper Mine, South Australia

Open Pit Mine Planning and Design 225

Prominent Hill

Open Pit Mine Planning and Design 226

112
5/11/2014

Prominent Hill

Muckpile Image Analysis using SPLIT DESKTOP:

The split desktop system uses digital image


analysis technology to convert an image
captured from a digital camera to a distribution
of defined areas within the photograph.

The software was developed from a system of


manual image analysis where a photographic
image was manually delineated and the diameter
of each particle measured

Open Pit Mine Planning and Design 227

Prominent Hill

Camera

Photo of muckpile

Photo collection and scale placement on flitch face.

Open Pit Mine Planning and Design 228

113
5/11/2014

Prominent Hill

Blast master 10040RL


Open Pit Mine Planning and Design 229

Prominent Hill

Open Pit Mine Planning and Design 230

114
5/11/2014

Prominent Hill

Open Pit Mine Planning and Design 231

Prominent Hill

Our modelling of the excavator production rates


has suggested that P80 of 800 mm would be the
optimal size to maximise excavator productivity
at 6300 t/hr.

However due to mine machinery and crusher


constraints we believe a revised figure of 600
mm would be more appropriate

Open Pit Mine Planning and Design 232

115
5/11/2014

Module 7
Equipment Selection
Simulation modelling using GPSS/H Case Study

Cost Estimation (Capital & Operating)

Open Pit Mine Planning and Design


233

Simulation and Animation of an


Australian Surface Mine
Study Background
Methodology
Results
Discussion
Conclusion
Recommendations

Open Pit Mine Planning and Design 234

116
5/11/2014

Wilcherry Hill Iron Ore Mine


The Wilcherry Hill project is
located 30 km north of the
township of Kimba in South
Australia.
The Wilcherry Hill project
comprises of four tenements
and covers an area of 976
square kilometres.
The tenements are EL4162-
Wilcherry Hill, EL4286-Valley
Dam, EL4421- Peterlumbo,
EL3981-Eurilla Dam.

Open Pit Mine Planning and Design 235

Project Development
Development at Wilcherry Hill is proposed in three
phases; stage 1, 2 and 3.

Stage 1 will be the focus of this project

Comprises mining, crushing and export of Direct


Shipping Ore (DSO)

Ore sourced from the upper parts of the mining pits.

Open Pit Mine Planning and Design 236

117
5/11/2014

Methodology
Aim
Simulation and animation model using the Stage
1 layout of the mine
Determine the optimum number of shovels and
trucks required for this mining scenario
Provide the company with a model they can use
for many what if? scenarios.

Open Pit Mine Planning and Design 237

Programming in GPSS/H
Approximately 1,200 lines of computer code were
used to model this mining scenario

Over 60,000 command lines were used to generate


this animation

Open Pit Mine Planning and Design 238

118
5/11/2014

Methodology
GPSS/H Simulation Main Commands

Open Pit Mine Planning and Design 239

Methodology
Variables, User Information and Generate
Variables:
REAL &X,&Y,&Z,&A,&B,&C,&D,&E,&F,&G,&H,&I

User Information:
PUTSTRING (' ')
PUTSTRING ('HOW MANY TRUCKS?')
PUTSTRING (' ')
INTEGER &TRUCKS
GETLIST &TRUCKS

Generate:
GENERATE 3,,0,&TRUCKS,,12PH,12PL

Open Pit Mine Planning and Design 240

119
5/11/2014

Methodology

Animation

Open Pit Mine Planning and Design 241

Methodology
Mine Layout (Draw, Class and Paths)

Open Pit Mine Planning and Design 242

120
5/11/2014

Methodology

Run

Open Pit Mine Planning and Design 243

Methodology

Animation

Open Pit Mine Planning and Design 244

121
5/11/2014

Methodology
Animation

Open Pit Mine Planning and Design 245

Results

Assumptions

HD 785
EMPTY: 72 t
LOADED: 164 t
LOADED SF: 147.6 t
ORE WEIGHT: 75.6 t
STRUCK BODY CAPACITY: 40 m3
ORE SPECIFIC GRAVITY: 4
FULL STRUCK LOAD ORE WEIGHT: 160 t
HOURS PER SHIFT: 8

Open Pit Mine Planning and Design 246

122
5/11/2014

Results

Ore Results

TRUCKS: 3 4 5 6 7
ORE DUMPS PER SHIFT: 9 13 17 20 23 DUMPS
STOCKPILE DEPOSITION PER SHIFT: 1440 2080 2720 3200 3680 T
STOCKPILE WITHDRAWAL RATE: 180 260 340 400 460 T/HR
COMPARISON (IRONCLAD): 291 T/HR

Open Pit Mine Planning and Design 247

Results

Ore Results

Open Pit Mine Planning and Design 248

123
5/11/2014

Results

Waste Results

TRUCKS: 3 4 5 6 7
WASTE DUMPS PER SHIFT: 68 87 104 123 142 DUMPS
DUMP DEPOSITION PER SHIFT: 5140.8 6577.2 7862.4 9298.8 10735.2 T
DUMP RATE: 642.6 822.15 982.8 1162.35 1341.9 T/HR
COMPARISON (IRONCLAD): 885 T/HR

Open Pit Mine Planning and Design 249

Results

Waste Results

Open Pit Mine Planning and Design 250

124
5/11/2014

Conclusion

GPSS/H Simulation and Animation


Number of shovels: one shovel
Number of trucks: five trucks and possibly an
extra standby truck

TALPAC simulations
Number of shovels: one shovel
Number of trucks: six trucks
Open Pit Mine Planning and Design 251

Acknowledgements
Postgraduate Students:
Sophie Mellor
Jian Liu

Open Pit Mine Planning and Design 252

125
5/11/2014

Cost Estimation

Capital Costs

Operating Costs

Capital cost estimation: general


considerations
Indicative capital cost estimates
Based on empirical data from other
projects
Estimates are within +/- 30% accuracy
Suitable for scoping or pre-feasibility
studies
Often use rules-of-thumb to estimate
costs

Open Pit Mine Planning and


254 of 10
Design

126
5/11/2014

Capital cost estimation: general


considerations:
Indicative capital cost estimates (cont.)
The sixth-tenths rule (Mular, 1978):
Cost 1 / Cost 2 = (Capacity 1 / Capacity 2)0.6
Capacity 2 and Cost 2 relate to a known similar
operation in a similar environment
Capacity 1 relates to the operation being
studied
Cost 1 is then estimated
Annualised cost per tonne rule:
Annualised cost per tonne of a known operation
= {Total capital cost} {tonnes per year}
Use this factor directly to estimate capex for
another, similar operation.
Open Pit Mine Planning and Design 255

Capital cost estimation: general


considerations
Cost indices
Most cost estimations are based on historical
data available to the estimator.
These data date and cost indices can be used to
update them:
Cost now = {cost then}{cost index now/cost index
then}
Indices available from Cost Guides

Open Pit Mine Planning and Design 256

127
5/11/2014

Capital cost estimation: general


considerations
Working capital
This is the capital component of operating
costs needed to support the operation
prior to substantial revenue inflows.
Often underestimated and can result in
project failure.
Sometimes a factor (such as 10% of fixed
capital cost) is applied. However a more
detailed analysis is usually good practice.

Open Pit Mine Planning and


257 of 10
Design

Capital cost estimation: general


considerations
Options for capital equipment
Contract mining
capital not available;
short duration;
specialist skills required; and/or
specialist equipment required.
Hired equipment
machine only and hirer responsible for fuel,
oil, servicing and operation (dry hire); or
full hire (all inclusive), usually hourly rate
with standby rate.

Open Pit Mine


258
Planning
of 10 and Design

128
5/11/2014

Capital cost estimation: general


considerations
Ownership cost
Fixed cost per hour irrespective of whether
the machine is working or not
It is a function of:
purchase price
cost of any extras
freight charges
tyre costs
resale value
depreciation period

Open Pit Mine Planning and Design 259

Capital cost estimation: general


considerations
Ownership cost (cont.)
Straight-line depreciation formula:
D = (P - R) / (N.H) where D is depreciation per
hour, P is purchase price, R is residual value, N is
useful life in years, H is hours of service per year.
Interest component of the cost:
I = P(r + i)(N + 1) / 200 N.H where I is interest cost
per hour, r is interest rate on capital (%), i is
insurance rate (%).
Total hourly ownership charge in $/hour, C = D + I

Open Pit Mine Planning and Design 260

129
5/11/2014

Capital cost estimation: general


considerations
Ownership cost example:
Assume:
Cost $400,000;
Life 10,000 hours over seven years;
residual value 35% of capital cost; and
interest and insurance is 12% per year.
D = (400,000 - 140,000) / 10,000 = $26.00/hour
I = (400,000 x 12 x 8) / (200 x 10,000) =
$19.20/hour
C = 26 + 19.20 = $45.20/hour

Open Pit Mine Planning and Design 261

Capital cost estimation: general considerations


Equipment replacement
Equipment becomes uneconomic when actual owning and
operating cost exceeds that of a new unit
Overhaul or replace?
Cost of overhaul?
Time to overhaul and requirement for temporary
replacement?
How long will economic life be extended?
Other work required during the extension of life?
Rate charged to mining operation to cover cost compared
with cost of new equipment and economics of mine?
Will overhauled equipment have acceptable availability?

Open Pit Mine Planning and


262 of 10
Design

130
5/11/2014

Infrastructure capital (cont.)


Access and site works
location and logistics
access and service roads ($65,000 to $230,000/km
depending on purpose)
port facilities
airstrips ($700,000 to $4.5 million)
site works (highly variable; $65,000 to
$400,000/ha).
drainage
fencing and security

Open Pit Mine


263
Planning
of 10 and Design

Infrastructure capital (cont.)


Industrial facilities
workshops and servicing facilities
warehouses
materials handling
mobile equipment
Utilities
power generation, transmission, distribution
water supply (source, quantities, storage,
distribution)
fuel storage and distribution
sewerage and solid waste disposal
Open Pit Mine Planning and Design 264

131
5/11/2014

Infrastructure capital (cont.)


Communications
external
internal
Port and marine facilities
Waste disposal systems
overburden dumps
water management
tailings handling and storage
solid wastes

Open Pit Mine Planning and Design 265

Infrastructure capital (cont.)


Administration facilities
administration building
laboratories
training facilities
change rooms
crib/lunch rooms
safety and medical facilities
fire station
core storage
security

Open Pit Mine Planning and


266 of 10
Design

132
5/11/2014

Infrastructure capital (cont.)


Transportation
road transport
rail transport
slurry pipeline
overland conveyors
sea or river transport
cableways (aerial ropeways)

Open Pit Mine Planning and Design 267

Infrastructure capital (cont.)


Townships
housing
roads
services
recreation facilities
shopping facilities
medical facilities
educational facilities
service industries
Construction facilities

Open Pit Mine Planning and Design 268

133
5/11/2014

Estimating of Operation Costs


Before any economic analysis or decision-making can be
undertaken the operating and capital costs of equipment
must be estimated.
Equipment operating costs vary between mine sites and
there is no cost which can be applied universally.
Equipment costs are generally derived from mine
statistics, from suppliers or estimated from first
principles.
The standard presentation of costs is Dollars per
Operating Hour or Dollars per Tonne
Make sure to cross-check your estimated costs with
currently prevailing mine sites.

Open Pit Mine Planning and Design 269

Major Mine Equipment Operating Costs

Open Pit Mine Planning and Design 270

134
5/11/2014

Open Pit Mine Planning and Design 271

Cost Calculation Steps Some equipment needs to be


replaced. Equipments have
lifetime as 5, 10, 20 yrs.
Ownership Costs consists
ore and Capital and Owning depreciation and average annual
investment cost.
Daily Production waste Costs for the
Rate equipment AAI=(n+1)Capital Cost / 2n

AAI should include tax, interest,


Shovels, insurance. So AAIC with a
Mine buildings
trucks, percent
and costs
drills,
excavators
associated with Other capital AAIC=P x AAI
the mine
Select Equipment etc.
development expenditures
Ownership Cost = Depreciation +
period AAIC

Direct operating
# of Milling Costs costs, total
machines operating costs,
Production Rate for (ownership and direct operating
required
each equipment capital costs) costs +
maintenance -
Ore and Waste

Mining Costs

# of production &
support employees Productivity
(tonnes/manshift)
salaries
Total Mining Cost = Total
Operating Cost + ownership Cost
Other Costs Materials,
supplies, power
and labour costs Total Mining Cost
($/hr or $/m or
$/tonnes)
Ore and waste
Operating Costs separation will be
Open Pit Mine
madePlanning and Design 272

135
5/11/2014

Module 8
Financial Technical Modelling

What is Financial Technical Modeling?


Revenue Assumptions
Project Financing
Evaluation Guidelines
The Frame Work of Evaluation
Project Cost of Capital
Conclusions

Open Pit Mine Planning and Design


273

WHAT IS A FINANCIAL TECHNICAL MODEL


(FTM)?
Financial/technical models of mining projects are
spreadsheets in which the technical processes of
ore and waste mining, ore processing and
production of salable product are incorporated as
quantities mined, processed and sold and, in turn,
as generating the revenues earned and costs
incurred in such processes.
The revenues earned depend on forecasts of
product prices, generally supplied by sources
external to the mining operation.
The costs are determined by technical analysis of
the project by project staff.

Open Pit Mine Planning and Design 274

136
5/11/2014

Other financial inputs, such as interest rates,


debt raisings and repayments and
depreciation schedules will normally be
supplied by head office corporate staff.

Forecasts of future inflation rates and


exchange rates may well be supplied by
external sources.

Example 1 of Financial Technical Model

Open Pit Mine Planning and Design 275

REVENUE ASSUMPTIONS - 1
World market prices dominant but hard to
predict
World economic conditions are volatile
Uneven outlook throughout the world
Supply and demand dominates - excess
supply is usual but not now (China!)
Potential for major economic disruptions,
e.g. oil price shocks, Soviet collapse, GFC,
war, China effect, etc.

Open Pit Mine Planning and Design 276

137
5/11/2014

PROJECT FINANCE

Money lent for developing a project


Secured against assets and cash flow
of project
Repayable from earnings of project
Limited recourse (sometimes no
recourse) to other assets of project
owners

Open Pit Mine Planning and Design 277

SOURCES OF FINANCE
EQUITY:
New Issues (shares, options, hybrids, units)
Asset sales
Retained earnings
Term loans
Securities (bills, bonds, notes, debentures)
Commodity loans-Leases
Project finance

DEBT: security, recourse to borrowing

Open Pit Mine Planning and Design 278

138
5/11/2014

ADVANTAGES OF EQUITY FINANCING


It's less risky than a loan because you don't have to pay
it back, and it's a good option if you can't afford to take
on debt.
You tap into the investor's network, which may add
more credibility to your business.
Investors take a long-term view, and most don't expect
a return on their investment immediately.
You won't have to channel profits into loan repayment.
You'll have more cash on hand for expanding the
business.
There's no requirement to pay back the investment if
the business fails.

Open Pit Mine Planning and Design 279

DISADVANTAGES OF EQUITY FINANCING


It may require returns that could be more than the rate
you would pay for a bank loan.
The investor will require some ownership of your
company and a percentage of the profits. You may not
want to give up this kind of control.
You will have to consult with investors before making
big (or even routine) decisions -- and you may disagree
with your investors.
In the case of irreconcilable disagreements with
investors, you may need to cash in your portion of the
business and allow the investors to run the company
without you.
It takes time and effort to find the right investor for your
company.
Open Pit Mine Planning and Design 280

139
5/11/2014

ADVANTAGES OF DEBT FINANCING

The bank or lending institution has no say in the way


you run your company and does not have any
ownership in your business.
The business relationship ends once the money is paid
back.
The interest on the loan is tax deductible.
Loans can be short term or long term.
Principal and interest are known figures you can plan in
a budget (provided that you don't take a variable rate
loan).

Open Pit Mine Planning and Design 281

DISADVANTAGES OF DEBT FINANCING


Money must paid back within a fixed amount of
time.
If you rely too much on debt and have cash flow
problems, you will have trouble paying the loan
back.
If you carry too much debt you will be seen as
"high risk" by potential investors which will limit
your ability to raise capital by equity financing in
the future.
Debt financing can leave the business vulnerable
during hard times when sales take a dip.
Debt can make it difficult for a business to grow
because of the high cost of repaying the loan.
Assets of the business can be held as collateral to
the lender.
Open Pit Mine Planning and Design 282

140
5/11/2014

EQUITY/DEBT FINANCING MIX

Most businesses opt for a blend of both equity and


debt financing to meet their needs when expanding
a business.

The two forms of financing together can work well


to reduce the downsides of each.

The right ratio will vary according to your type of


business, cash flow, profits and the amount of
money you need to expand your business (50:50;
30:70, etc)

Open Pit Mine Planning and Design 283

EVALUATION GUIDELINES
Made at a point in time
Sunk costs (dont worry!)
Constant $ or current $
For comparing alternatives, make sure
techniques used permit fair comparisons
Computer financial models (spreadsheet
modeling)
Investment decision versus sale/purchase
evaluation

Open Pit Mine Planning and Design 284

141
5/11/2014

FRAMEWORK OF EVALUATION
A construction of cash flows - in and out
Express every aspect in terms of cash
Express uncertainty in ranges of values,
creating multiple models of the one project
Cash flows not accounting profits
Evaluate on a stand alone basis
Ignore side issues unless the side issue is the
purpose of the project

Open Pit Mine Planning and Design 285

MAJOR ITEMS IN FTM

CASH ($):
Cash is the lifeblood of the enterprise
Cash flows are actual $ spent or received
Non-cash items (e.g. depreciation) are important as
far as they affect cash flows
Project cash flows for a period are inflows minus
outflows - may be +ve or -ve
Periods are usually years; may be quarters or
months, depending on the size of the project

Open Pit Mine Planning and Design 286

142
5/11/2014

INFLOWS AND OUTFLOWS*

Inflows: sales revenue; may include other


minor items
Outflows: Initial capital expenditure, working
capital, maintaining capital, operating costs,
taxes, royalties, rehabilitation costs, etc
Royalties: ?Treat as reductions in revenue
Off site costs, such as realisation costs, ?
Treat as reductions in revenue

Open Pit Mine Planning and Design * Very important! 287

WORKING CAPITAL
Component of initial Cap. ex. - to fund op.
costs until sales revenues arrive - in theory
recovered at end of mine life
Required throughout project life but generally
supplied by sales revenues
Itemised on a period by period basis in
detailed financial models
Avoid double counting in financial model but
must be counted in initial funding
requirement

Open Pit Mine Planning and Design 288

143
5/11/2014

CURRENCY
Local currency (A$ for Australian projects in Australia)
Because costs in local currency
Convert revenues to local currency
Forecast exchange rates can dominate the evaluation
Foreign projects in host country currency - limited
conversion to A$ needed
In cases of foreign country hyperinflation, use a stable
currency, e.g. US$, if sales revenues in US$

Open Pit Mine Planning and Design 289

EXCHANGE RATES
$ EXCHANGE RATE IS QUITE VOLATILE
Moves with commodity prices but affected by other
influences as well.
Forex turnover in all currencies in Australian market
represents 4.3% of global turnover, 7th largest forex
market in the world.
A$/US$ pair ~45% of total turnover. Euro/US$ pair ~14%.
A$/JPY only 1%
Aust. forex market grew with world market. Also, helped
by carry trade and hedge fund activity, plus growing funds
under management in Australia seeking to invest
overseas. Bulk of trades with overseas FIs
Aust. banks hedge ~ 100% of forex deals.

Open Pit Mine Planning and Design 290

144
5/11/2014

CONSTANT VS CURRENT $
$ change in value over time
Constant $ - generally average value of $ of the day
at time of evaluation, preserved throughout project
life.
Current $ - $ of the day for each period in the future
- requires calculation of the change in value from
period to period, i.e. usually inflation rates
Costs affected by local inflation, revenues by world
inflation, up to a point. Mineral commodity
revenues controlled by supply and demand most of
the time.

Open Pit Mine Planning and Design 291

MORE CONSTANT VS CURRENT $


Constant $ evaluation easier
Present day costs known but not future revenues
Current $ evaluation both costs and revenues based
on forecasts of future events
But current $ are the real world - constant $ is
artificial simplification
Constant $ evaluations can be misleading by ignoring
inflation but can be very effective in choosing
between alternatives
Constant $ cost of funds different from current $ cost
of funds

Open Pit Mine Planning and Design 292

145
5/11/2014

INTEREST RATES
A function of the time value of money
On debt, represent low risk return
Therefore, risky investments offer higher
return
Diversified equity investments offer about
6% above the risk free rate
Government bonds represent risk free rate
Interest rates and discount rates closely
linked

Open Pit Mine Planning and Design 293

PROJECT COST OF CAPITAL


Invested funds are recovered from future
returns with interest
What rate of interest is appropriate for using
funds in this project?
Must be above the risk free rate but how much
above?
Individual resource projects generally have a
slightly higher cost of capital than the
company as a whole
Function of project risk, diminishing reserves
and need for exploration
The appropriate cost of capital should be the
discount rate for project evaluation purposes.

Open Pit Mine Planning and Design 294

146
5/11/2014

COMPANY COST OF CAPITAL


Co funds - equity plus debt
Cost of equity - empirical measures
Cost of debt - average after tax interest rate on debt
- factual
Cost of funds = weighted average cost of equity and
debt
Current $ cost of capital - includes allowance for
inflation -can be converted to constant $

Open Pit Mine Planning and Design 295

CURRENT $ TO CONSTANT $

1 + CONSTANT $ COST OF CAPITAL


= (1+ CURRENT $ COST OF CAP)/(1+ INFLATION
RATE)

Open Pit Mine Planning and Design 296

147
5/11/2014

MORE ON COST OF CAPITAL


Cost of equity capital applies for 100% equity
funding
Debt lowers the cost of capital but increases
risk
What is the minimum acceptable return on
equity?
Historically, 8% real on all equities - therefore,
higher in current $ terms
Should it be higher for risky mining
investments?

Open Pit Mine Planning and Design 297

CAPITAL ASSET PRICING MODEL


Developed from long term studies of equity markets
in USA:
R = Rf + B(Rm -Rf)
Where:
R = required rate of return
Rf = risk free interest rate
B =relative risk of particular stock
Rm = average market return

Open Pit Mine Planning and Design 298

148
5/11/2014

MARKET RISK PREMIUM


Rm-Rf = market risk premium
Expected premium, but based on historical data as
proxy
Australian data over 100 years indicates 5% to 6%
arithmetic average - 6% geometric average
US data indicates 5% to 6% geometric average
Volatility of returns means (Rm-Rf) geometric
average is 2% to 10% with 95% confidence. A pretty
big range.

Open Pit Mine Planning and Design 299

WEIGHTED AVERAGE COST OF


CAPITAL
WACC* = (E/A)R +(D/A)Rd(1-tc)
Where;
E = market value of equity
D = debt
A =debt + equity
R = cost of capital, from CAPM
Rd = interest rate on debt
and tc = corporate tax rate
R is after tax, Rd is pre-tax
*used where a mix of DEBT & EQUITY applies

Open Pit Mine Planning and Design 300

149
5/11/2014

PROJECT PERIODS
Equal length periods cover entire life of project
Permits use of standard compound interest
relationships and rules
Periods = years, generally
May be quarters or months for small projects
Project commences with the first period of
investment
Evaluation relates to beginning of first period

Open Pit Mine Planning and Design 301

SUNK COSTS:
Past expenditures have no bearing on the
evaluation,e.g., exploration expenditure.

The evaluation is considering future expenditures


and revenues resulting from a decision yet to be
made.

True of cost of evaluation and confirmatory work


except for tax benefits

Open Pit Mine Planning and Design 302

150
5/11/2014

END OF PERIOD CONVENTION


Expenditures and receipts occur irregularly
through time - but, for purposes of
evaluation, all cash flows are deemed to take
place at the end of the period

Generally conservative

Midpoint of period can be used

Open Pit Mine Planning and Design 303

PAUSE REFLECT!
Revenue assumptions
Sources of finance
Cash
In- Outflow $
Lagged revenue
Sunk Costs
Project periods
WACC
Cost of Capital
Currency, Exchange rates
Constant vs Current $
Working Capital

CAPM
Interest rates
Equity vs Debt Financing
Royalties
End of period convention

Open Pit Mine Planning and Design 304

151
5/11/2014

DEPRECIATION
Depreciation is the means of recovering capital
expenditure
Depreciation deducted from cash flow to
determine taxable income, and thus tax payable
Depreciation then added back to after tax profit
to determine period cash flow
Dividend payments are not part of the project
evaluation.
Positive NPV of cash flows mean capital has
been serviced at the discount rate while
invested, has been recovered and excess return
has been received

Open Pit Mine Planning and Design 305

Capital Expenditure
Expenditure providing for mine operations for
longer than one year

Expenditure for operations within the year are


expensed, not capitalised

Depreciation schedules straight line over life of


asset, life of mine or 10 years; declining balance
depreciation can defer tax but eventually returns to
straight line.

Open Pit Mine Planning and Design 306

152
5/11/2014

Tax payable calculations

Taxable income = sales revenue for year


minus all operating costs, overhead costs,
interest payments and depreciation
Tax rate 30% at present (Australia)
Negative taxable income, no tax paid and no
tax refund except where group taxation
makes immediate use of tax losses possible
Usually, tax losses carried forward to reduce
taxable income in later years

Open Pit Mine Planning and Design 307

Period cash flows


Project cash flows for each year (or shorter period)
made up of:
After tax profit or loss
Plus any depreciation added back
Plus adjustments for any after tax items such as
capital expenditures, loan drawdowns or loan
repayments made or received during the year.

Open Pit Mine Planning and Design 308

153
5/11/2014

ROYALTIES
Charge levied by State or Federal Government in
return for permission to mine

Reflects Crown ownership of minerals

Various forms of royalty: ad valorem, pro rata, profit


share, resource rent taxation in different
jurisdictions

Check what applies to specific project and treat as a


reduction in revenues

Open Pit Mine Planning and Design 309

LAGGED REVENUE
Example: Smelter pays to the company based
on the waiting period to produce the expected
amount of product depending to the shipping
capacity.

For gold it is not much time to produce gold from


ore/concentrate to gold bullion, say1 week, but
base metals may take more time, say 2-3 months
lagged.

Open Pit Mine Planning and Design 310

154
5/11/2014

Module 9
Dewatering and Pump
Selection

Case Study
Pump & Pipe Selection
Pumping Costs

Open Pit Mine Planning and Design


311

Introduction
Proposed mine is in the Mudgee area of NSW
Populated towns nearby in every direction
Long history of coal mining in the Central West
NSW with several active coal mines nearby;
deposits of high-grade coking coal are endemic
The old abandoned open cut mine had 4 identical
pits. Water has filled these pits to an average depth
of 50m
Coking coal prices are expected to rise, thus
prompting a review of the feasibility of
recommissioning and extending the abandoned
mine pits

Open Pit Mine Planning and Design 312

155
5/11/2014

Dogweed Coking Coal Mine

Mudgee

Sydney

Open Pit Mine Planning and Design 313

Objectives

Design a suitable
system to dewater the
pits ahead of the
mining operation
Determine capital
costs and pump
operating costs per
year

Open Pit Mine Planning and Design 314

156
5/11/2014

Methodology
3 methods of water volume estimation:
Volume by Integration
Volume by Parts
Volume by using a modelling program eg
AutoDesk Inventor
Dewatering times, depth of water with time
Calculation of required pump head over water
depth at different velocities/pipe diameters
Pipe system selection and costing

Open Pit Mine Planning and Design 315

Geometry of the Pit

Dimension
70m wide, 75o highwall, 36 lowwall of spoil
80m high, 9m thick, dipping at 6
Depth of water 50m
Infrastructure setting
Top Overburden
In situ density
lowwall
highwall =36
89 m
=75
Waste 2.3t/BCM
Bottom
Overburden

Coal 1.4t/BCM

Open Pit Mine Planning and Design 316

157
5/11/2014

Volume of water estimation

Dimensions of the water in pit

Open Pit Mine Planning and Design 317

Method#1
Estimate volume by parts
The dimension of the water in the pit can be
considered as different parts adding together:
Volume/m3 Formula
Rectangle
Low Wall
Edge 2
High Wall Paramete Formula Value
Edge 2 r
Sides 2 x 70
2 y 1km-2b 973.21
Corners 1 2 2 h 50
3 a 68.82
Corners 2 2 tan 36
3 b 13.40
Open Pit Mine Planning and Design tan 75 318

158
5/11/2014

Method #2
Estimate volume by integration
Looking at the model from top, we can evaluate width X and length Y
in terms of the
incremental height Z:
() ()
=
+ +
2()
=
+
Therefore, the volume is calculated by integrating the area of the cross
section over the height of the model:

= = .
0 0
2 22
That is, = 3
+ 3 + 2 + 2 + +
This confirms the volume by parts. By inputting known variables,
volume of the water in the pit is 5.49x106 m3
Open Pit Mine Planning and Design 319

Method #3
Estimate volume by using Inventor

Open Pit Mine Planning and Design 320

159
5/11/2014

Method #3
Estimate volume by using
Inventor

Open Pit Mine Planning and Design 321

Dewatering time
The disposal flow rate limit is 200 L/s,
therefore the dewatering time can be
calculated:
Volume of Rate of de- Time to Number of Total time
water per watering dewater pits taken for
pit (m3) (m3/s) one pit dewatered dewatering
(days) per year (years)
V Q T=V/(Qx24x N=365/T TT=Nx4
60)
5490065 0.2 317.7 1.15 3.48

Open Pit Mine Planning and Design 322

160
5/11/2014

Depth of Water Over Time


Depth Of Water In Pit Over Time
60.00

50.00

40.00
y = -0.0001837707x2 - 0.0958277546x + 49.5843902089
Depth of Water

R = 0.9996479452
30.00
Depth

20.00

10.00

0.00
0 50 100 150 200 250 300 350
Days Since Dewatering Commenced

Open Pit Mine Planning and Design 323

Calculating Pump Head


Pressure drop: Bernoullis Equation
1 12 2 22
+ 1 + 1 = + 2 + 2 +
2 2
Major head loss:
2
=
2
Minor head loss:
2
=
2

Friction factor: Reynolds number and Moody Chart


Open Pit Mine Planning and Design 324

161
5/11/2014

Pipe System Model

Open Pit Mine Planning and Design 325

Calculation Example

Dept Target Pipe Diameter Pipe Length Reynolds Friction


h Velocity (m) (m) Number Factor
30 2 0.356825 76.25 71364.96 0.022

hZ hV hP hLM hLm V (m/s) L (m) (0 if negligible)


0 30 0 0 0 0 0 0
1 30.5 0.20408 -0.70408 0 0 2
2 30.5 0.20408 61.75476 0 0 2 0
3 30.5 0.20408 61.74711 0 0.007653 2 0
4 30.5 0.20408 60.66451 1.082598 0 2 86.039
5 80 0.20408 10.08396 1.070343 0.010204 2 85.065
6 80 0.20408 0 10.06611 0.017857 2 800

TOTAL PUMP PRESSURE HEAD (m) 62.46

Open Pit Mine Planning and Design 326

162
5/11/2014

Variation of Pump Head with


Depth
Pump Pressure Head wrt Velocity (V)/Pipe Diameter (D)
115

105

95
Required Pump Pressure Head

85

2.829421211 0.3
75
0.439714514 0.761
1.123896216 0.476
65
1.390120911 0.428
y = -x + 109.53
55 1.763489674 0.38
2.228982782 0.338
45 y = -x + 96.312

y = -x + 89.115
35 y = -x + 85.056
y = -x + 82.993
y = -x + 80.325
25
0 10 20 30 40 50 60
Water Depth
Open Pit Mine Planning and Design 327

Pump selection
Must be capable of meeting largest flow rate
Must be capable of pumping largest pressure head
Relatively acceptable costs

ALLIGHT SYKES-HH220I

Open Pit Mine Planning and Design 328

163
5/11/2014

Pump Power Curve


HH220i Power Curve at 200 L/s
400

350

300

250
y = -0.0003x3 + 0.0837x2 - 4.411x + 187.66
kW

200

150

100

50

0
20 40 60 80 100 120 140
Total Head (m)

Open Pit Mine Planning and Design 329

Pump selection
Features:
Diesel, electric or hydraulic drive
Low fuel usage, reduced engine size
Lower maintenance costs

Open Pit Mine Planning and Design 330

164
5/11/2014

Pipe system selection


Pipe type: HDPE
Suited to butt welding
Corrosion, abrasion, weathering and chemical
resistant
Relatively low item cost
Easy installation
Flexible and resilient

Keep in mind:
Velocity must be high enough to prevent too
much settling

Open Pit Mine Planning and Design 331

Electricity Consumed by Pump


kW-Hours Consumed by Pump During Dewatering of a Pit for Different
Pipe Diameters
330

280
kW Required by Pump

230 0.761
0.476
0.428
180 0.38
0.338
0.3
130

80
0 50 100 150 200 250 300 350
Time (Days)

Open Pit Mine Planning and Design 332

165
5/11/2014

System Costs
Change in Costs per System with Increasing Pipe Diameter
700000

600000

500000

400000
Cost ($)

Cap cost of pipes

300000 Op cost of system


Total

200000

100000

0
0.25 0.35 0.45 0.55 0.65 0.75 0.85
Pipe Diameter (m)

Open Pit Mine Planning and Design 333

Optimised System Costs


Optimal pipe diameter = 380mm
Costs from R2, Australian suppliers,

PIPE DIAMETER 380mm

Capital cost of pipe $115697.7 Pipe, transport, installation

Capital cost of pump $81960 Installation costs required

Electricity costs $174935.6 At 10.2 c/kWh

TOTAL $303301.5

Open Pit Mine Planning and Design 334

166
5/11/2014

What Have We
Achieved?
Fundamentals of open pit mine design and
current developments in planning and design
methodology,
Current industry practices to maximise
economic return (technology, operations).
Open pit mine planning and design process in
theory and practice,
Unit Operations Drill-Blast-Load-Haul
Mining Economics
Apply this knowledge to plan/evaluate new open
pit projects and/or existing mines.
Open Pit Mine Planning and Design 335

Bottom Line is..

We mine for profit !!!

Open Pit Mine Planning and Design 336

167

You might also like