Pkg-077-01

1. No of packages made after termination for completion of Balance work :-


(i) Pkg-077-01A: Turn Key TS.( Balance Work For External Water System For SMS-III)
(ii) Pkg-077-01A1: Non Turnkey TS for Balance Civil works of Essential facilities under External
Water System for SMS-III (WTP-1, Common pump house, ECR for SST PH).
(iii) Package-077-01A2: Non Turn Key Civil work for WTP-2.
(iv) Package-077-01D: Non turnkey TS for EOHT (Structural ).
(v) Placement of order of items (to be supplied as free issue items to contractors) on existing
vendors (of earlier contractor) by BSP
(vi) Package-077-01E: Turn-Key TS: Cooling Towers; as an option in case of any advantage in
excluding the Cooling Towers from Turn Key TS for balance works Pkg-077-01A. Dropped;
Not Required
(vii) Package-077-01F: Non turnkey TS for Structural work of Pipe cum Cable gallery.

2. Status of Package
(i) Package-077-01A: Tender discussions completed. Status on 09.09.16. TAR likely by
15.09.16.
(ii) Package-0077-01A1 (NTK): Work awarded to M/s A Mohan on 25.04.2016 (SC-STB)
(iii) Package-077-01A2(NTK): Work awarded to M/s HSCL (LTB) on 24.06.16
(iv) Package-077-01D (NTK): Work awarded to M/s Sanmathi (SC-STB) on 02.06.2016
(v) Placement of order on existing vendors (of earlier contractor) by BSP completed 11(12-1)
(vi) Package-077-01E (TK): TS Issued on 05.07.16. Dropped; Not Required.
(vii) Package-077-01F (NTK): Draft TS issued on 11.08.16; TS issued on 22.08.16

Pkg-078

1. No of packages after termination for completion of balance work including design & engineering :-
(i) Pkg-078A: Turn Key TS for Balance Work ( DWTP- complete , Erection of Plant and
Equipment for DWPH , MWPH , Intake well PH and ECR, etc).
(ii) Pkg-078B1: Non Turnkey TS for Balance out door piping work.
(iii) Pkg-078B2: Non Turnkey TS for Civil work for Balance outdoor Piping and cable gallery.
(iv) Pkg-078B3: Non Turnkey TS for Structural work for Balance outdoor Piping and cable
gallery
(v) Package-078C: Non Turn Key Civil work for IWPH,DWPH,MWPH & ECRs
(vi) Package-078D: Erection for Balance Mechanical Equipment
(vii) Package-078E: Erection for Balance Electrical Equipment
(viii) Package-078F: Non Turnkey TS for Balance outdoor piping work of SMS-III & BRM area
~1500m route length @
(ix) Placement of order of items (to be supplied as free issue items to contractors) on existing
vendors (of earlier contractor) by BSP-6.

2.0 Status of packages :-


(i) Pkg-078A (Turn Key TS); NIT uploaded on 29.07.2016, PBC on 05.08.16 & LDS;
19/26.08.16. Offer from 4 bidders; Techno-Commercial discussion at Ranchi from
19 to 27.09.16.
(ii) Pkg-078B-1 ( NTK) ; TS for balance Piping Work STB; Work awarded to M/s I A Dhas on
24.06.16
(iii) Pkg-078B-2 (NTK): TS for Civil Work for balance piping and cable gallery- STB; Work
awarded to M/s I A Dhas on 25.06.16.
(iv) Pkg-078B-3 (NTK): TS for Structural Work for balance piping and cable gallery- STB; Work
awarded M/s BCCI on 25.06.16.
(v) Package-078C (Non Turn Key): Civil work for IWPH, DWPH, MWPH & ECRs: Work awarded
to M/s Five Star, Bhilai on 03.08.16.
(vi) Package-078D: Erection for Balance Mechanical Equipment; issued on 08.07.16. Estimated
Cost & eligibility issued on 16.07.2016. 04 Offer recd on 24/25.08.16; Work Awarded to
M/s M A Ansari on 10.09.2016.
(vii) Package-078E: Erection for Balance Electrical Equipment; Issued on 07.07.16 Estimated
Cost & eligibility issued on 18.07.2016. 05 Offer recd on 26.08.16; TAR issued on
09.09.2016.
(viii) Package-078F: Non Turnkey TS for Balance outdoor piping work;
(ix) Placement of order is in progress.

Note :- the highlighted package MECON has evaluated the offer and issued TAR.

Pkg-077-02

1. No of Packages after termination for completion of Balance work:-


(i) Packag-077-02A (Turn-key): Balance work
(ii) Package-077-02B-1( NTK): Civil work for WTP-5
(iii) Package-077-02B-2 ( NTK): Erection for Balance Mechanical Equipment
(iv) Package-077-02B-3 (NTK): Civil and Structural for WTP-1, 2,3,4,6 &7 including Pipe cum
cable gallery and tunnel.
(v) Package-077-02B-4 (NTK): Erection of Balance Electrical
(vi) Package-077-02C-1(NTK): Civil work for RCC Overhead Water Tanks (2 no) for URM &
BRM
(vii) Placement of order of items (to be supplied as free issue items to contractors) on existing
vendors (of earlier contractor) by BSP-17
2. Status of Packages;
(i) Packag-077-02A: Final issued on 03.08.16.NIT issued on 22.08.16 PBD on 29.08.16; LDS
13.09.16
(ii) Package-077-02-B1 (NTK):Work awarded to M/s Sudhansu Brothers (STB) on 24.06.16
(iii) Package-077-02B-2(NTK):05 Offer recd on13.08.16; TAR issued on 27.08.16. Work
Awarded to M/s Gimex India Project & Engg Pvt. Ltd on
08.09.2016.
(iv) Package-077-02B-3 (NTK): Work awarded to M/s HSCL on 12.08.16.
(v) Package-077-02B-4: Work awarded to M/s Sambhu Singh Engineers Pvt Ltd on 20.07.16.
(vi) Package-077-02C-1: Civil work for RCC Overhead Water Tanks (2 no) for URM & BRM;
Final TS issued on 27.07.16
(vii) Placement of order is in progress.

Note :- the highlighted package MECON has evaluated the offer and issued TAR