S10 Pgina 1

Presupuesto
Presupuesto 0102033 VIVIENDA UNIFAMILIAR
Subpresupuesto 001 VIVIENDA UNIFAMILIAR
Cliente Sr. Lauro leonidas Yaez Fernandez & Sra.Karolay Brigith Lescano Duran Costo al 29/06/2016
Lugar TACNA - TACNA - TACNA

Item Descripcin Und. Metrado Precio S/. Mano de Obra Material Equipo Subcontrato Parcial S/.

01 OBRAS PRELIMINARES 184.41 79.20 49.29 314.40


01.01 TRABAJOS PRELIMINARES 184.41 79.20 49.29 314.40
01.01.01 LIMPIEZA DEL TERRENO MANUAL m2 80.00 1.93 149.50 4.49 154.40
01.01.02 TRAZO Y REPLANTEO INICAL m2 80.00 2.00 34.91 79.20 44.80 160.00
02 ESTRUCTURA 16,680.47 48,219.98 3,149.47 68,043.92
02.01 MOVIMIENTO DE TIERRAS 2,124.22 21.61 586.94 2,733.58
02.01.01 EXCAVACION DE ZANJAS PARA CIMENTACIONES m3 54.16 23.40 1,230.28 36.92 1,267.34
02.01.02 RELLENO CON MATERIAL PROPIO COMPACTADO m3 32.39 18.56 322.83 3.24 275.23 601.16
02.01.03 NIVELACION Y COMPACTACION DE TERRENO m2 73.49 3.03 109.87 18.37 93.70 222.67
02.01.04 ACARREO DE MATERIAL EXCEDENTE m3 28.30 16.70 449.99 22.50 472.61
02.01.05 ELIMINACION DE MATERIAL EXCEDENTE m3 28.30 6.00 11.25 158.59 169.80
02.02 CONCRETO SIMPLE 1,187.51 3,969.57 246.55 5,403.40
02.02.01 SOLADO DE E=8", C:H-1:12 m2 33.23 30.84 267.82 692.01 65.01 1,024.81
02.02.02 FALSO PISO 1:8 - C:H E = 4" m2 73.49 24.97 462.32 1,270.86 102.06 1,835.05
02.02.03 CIMIENTOS CORRIDOS 1:10 C:H + 30% P.G. C.T.V. m3 13.70 185.66 457.37 2,006.70 79.48 2,543.54
02.03 CONCRETO ARMADO 13,368.74 44,228.80 2,315.98 59,906.94
02.03.01 SOBRECIMIENTO ARMADO 837.85 1,753.58 74.27 2,665.72
02.03.01.01 SOBRECIMIENTO REFORZADO: CONCRETO f'c=175 kg/cm2 C.T.V. m3 3.66 339.74 159.10 1,030.85 53.57 1,243.45
02.03.01.02 SOBRECIMIENTO REFORZADO: ENCOFRADO Y DESENCOFRADO m2 48.85 26.65 661.46 620.40 19.84 1,301.85
02.03.01.03 SOBRECIMIENTO ARMADO: ACERO CORRUGADO FY= 4200 kg/cm2 kg 29.66 4.06 17.29 102.33 0.86 120.42
02.03.02 ZAPATAS 303.06 2,904.22 86.90 3,293.13
02.03.02.01 ZAPATAS: CONCRETO f'c=210 kg/cm2 C.T.V m3 8.07 319.45 210.47 2,296.61 70.87 2,577.96
02.03.02.02 ZAPATAS: ACERO CORRUGADO FY= 4200 kg/cm2 kg 188.70 3.79 92.59 607.61 16.03 715.17
02.03.03 VIGA DE CIMENTACION 1,109.78 3,760.96 111.02 4,979.14
02.03.03.01 VIGAS DE CIMENTACION: CONCRETO f'c=210 kg/cm2 C.T.V. m3 5.22 319.45 136.14 1,485.54 45.84 1,667.53
02.03.03.02 VIGAS DE CIMENTACION : ENCOFRADO Y DESENCOFRADO NORMAL m2 41.76 32.87 722.62 628.07 21.69 1,372.65
02.03.03.03 VIGAS DE CIMENTACION: ACERO CORRUGADO FY= 4200 kg/cm2 kg 511.60 3.79 251.02 1,647.35 43.49 1,938.96
02.03.04 COLUMNAS 2,773.08 9,456.33 237.35 12,464.13
02.03.04.01 COLUMNAS: CONCRETO f'c=210 kg/cm2 m3 10.09 288.26 414.80 2,346.78 146.97 2,908.54
02.03.04.02 COLUMNAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 137.00 19.27 1,365.40 1,233.00 40.98 2,639.99
02.03.04.03 COLUMNAS: ACERO CORRUGADO FY= 4200 kg/cm2 kg 1,703.35 4.06 992.88 5,876.55 49.40 6,915.60
02.03.05 PLACAS 464.78 1,308.65 40.64 1,813.69
02.03.05.01 PLACAS: CONCRETO f'c=210 kg/cm2 m3 1.83 288.26 75.23 425.63 26.66 527.52
02.03.05.02 PLACAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 21.96 21.84 273.76 197.64 8.22 479.61
02.03.05.03 PLACAS: ACERO CORRUGADO FY= 4200 kg/cm2 kg 198.66 4.06 115.79 685.38 5.76 806.56
02.03.06 VIGAS 4,056.11 11,909.62 900.73 16,861.34
02.03.06.01 VIGAS: CONCRETO f'c=210 kg/cm2 m3 13.76 297.12 697.71 3,200.37 190.29 4,088.37
02.03.06.02 VIGAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 175.77 24.95 2,154.20 1,581.93 650.53 4,385.46
02.03.06.03 VIGAS: ACERO CORRUGADO FY= 4200 kg/cm2 kg 2,065.89 4.06 1,204.20 7,127.32 59.91 8,387.51
02.03.07 LOSAS ALIGERADAS 3,202.67 11,528.67 714.55 15,451.71
02.03.07.01 LOSA ALIGERADA: CONCRETO f'c=210 kg/cm2 m3 13.77 288.53 605.14 3,202.69 165.04 3,973.06
02.03.07.02 LOSA ALIGERADA: ENCOFRADO Y DESENCOFRADO NORMAL m2 137.67 24.95 1,687.25 1,239.03 509.51 3,434.87
02.03.07.03 LOSA ALIGERADA: ACERO CORRUGADO FY= 4200 kg/cm2 kg 1,104.26 4.06 643.67 3,809.69 32.02 4,483.30
02.03.07.04 LOSA ALIGERADA: LADRILLO DE TECHO DE 30 x 30 x 15 cm und 1,156.00 3.08 266.61 3,277.26 7.98 3,560.48
02.03.08 ESCALERAS 621.41 1,606.77 150.52 2,378.08
02.03.08.01 ESCALERAS: CONCRETO f'c=210 kg/cm2 m3 2.35 297.12 119.16 546.58 32.49 698.23
02.03.08.02 ESCALERAS: ENCOFRADO Y DESENCOFRADO NORMAL m2 30.10 24.95 368.89 270.90 111.40 751.00
02.03.08.03 ESCALERAS: ACERO CORRUGADO FY= 4200 kg/cm2 kg 228.78 4.06 133.36 789.29 6.63 928.85
03 ARQUITECTURA 29,110.48 93,744.88 1,426.73 124,302.48
03.01 MUROS Y TABIQUES DE ALBAILERIA 5,420.73 21,034.05 286.83 26,737.64
03.01.01 MUROS DE LADRILLOS KK DE ARCILLA DE SOGA CON MEZCLA 1:4 x 1.5 CM m2 372.65 71.75 5,420.73 21,034.05 286.83 26,737.64
03.02 REVOQUES Y ENLUCIDOS 11,542.30 5,047.99 346.30 16,942.48
03.02.01 TARRAJEO PRIMARIO O RAYADO m2 67.18 17.07 781.24 341.67 23.44 1,146.76
03.02.02 TARRAJEO EN MURO INTERIORES Y EXTERIORES m2 572.07 17.07 6,652.70 2,909.54 199.60 9,765.23
03.02.03 TARRAJEO SUPERFICIE DE COLUMNAS Y VIGAS m2 353.28 17.07 4,108.36 1,796.78 123.26 6,030.49
03.03 CIELO RASOS 1,600.99 881.50 231.61 2,714.85
03.03.01 TARRAJEO DE CIELORASO m2 137.67 19.72 1,600.99 881.50 231.61 2,714.85
03.04 PISOS Y PAVIMENTOS 4,537.20 12,076.96 285.38 16,899.68
03.04.01 PISO DE PORCELANATO 60 X 60 CM m2 43.95 98.15 655.07 3,639.14 19.65 4,313.69
03.04.02 PISO CERAMICO 40 X 40 m2 82.87 67.49 1,314.96 4,238.48 39.43 5,592.90
03.04.03 PISO DE ADOQUIN DE CONCRETO DE 10x20x4cm m2 63.43 83.14 1,845.16 3,336.36 92.26 5,273.57
03.04.04 CONTRAPISO DE 1" m2 81.61 21.07 722.01 862.98 134.04 1,719.52
03.05 ZOCALOS 1,211.44 8,467.57 36.33 9,714.92
03.05.01 ZOCALO DE PORCELANATO 60 X 60 CM m2 77.14 98.97 1,211.44 6,387.20 36.33 7,634.55
03.05.02 ZOCALO DE MADERA H=0.10M m 198.13 10.50 2,080.37 2,080.37
03.06 CARPINTERIA DE MADERA 26,200.00 26,200.00
03.06.01 PUERTAS 12,600.00 12,600.00
03.06.01.01 PUERTA CONTRAPLACADA DE TRIPLAY C/MARCO DE CEDRO und 8.00 500.00 4,000.00 4,000.00
03.06.01.02 PUERTA DE MADERA LEVADIZA MACIZA DE CEDRO und 1.00 5,000.00 5,000.00 5,000.00
03.06.01.03 PUERTA DE MADERA MACIZA DE CEDRO und 3.00 1,200.00 3,600.00 3,600.00
03.06.02 CLOSET und 3.00 1,200.00 3,600.00 3,600.00
03.06.03 MUEBLES DE COCINA und 1.00 7,000.00 7,000.00 7,000.00
03.06.04 PERGOLAS DE MADERA und 1.00 1,500.00 1,500.00 1,500.00
03.06.05 QUIEBRAVISTAS und 1.00 1,500.00 1,500.00 1,500.00
03.07 CARPINTERIA METALICA 3,500.00 3,500.00
03.07.01 BARANDA DE FIERRO EN ESCALERA glb 1.00 3,500.00 3,500.00 3,500.00
03.08 VIDRIOS, CRISTALES Y SIMILARES 12,935.03 12,935.03
03.08.01 VENTANAS 7,745.43 7,745.43
03.08.01.01 VIDRIO SIST. MODUGLASS INCOLORO 6 MM m2 33.53 231.00 7,745.43 7,745.43
03.08.02 MAMPARAS 5,189.60 5,189.60
03.08.02.01 MAMPARA DE 10MM. SIST. MODUGLASS m2 9.98 520.00 5,189.60 5,189.60
03.09 PINTURAS 4,797.82 3,601.78 240.28 8,657.88
03.09.01 PINTURA LATEX 2 MANOS EN MUROS INTERIORES Y EXTERIORES m2 925.35 8.12 4,157.39 3,131.29 208.20 7,513.84
03.09.02 PINTURA LATEX 2 MANOS EN CIELO RASO m2 137.67 8.31 640.43 470.49 32.08 1,144.04
04 INSTALACIONES SANITARIAS 7,060.38 11,070.31 287.72 18,420.34
04.01 SISTEMA DE AGUA FRIA 2,564.81 2,546.52 69.53 5,181.33
04.01.01 TUBERIA PVC CLASE A-10/AGUA POTABLE DE 1" m 9.00 25.31 50.18 176.04 1.51 227.79
04.01.02 TUBERIA PVC CLASE A-10/AGUA POTABLE DE 1/2" m 97.80 15.77 545.31 979.96 16.37 1,542.31
04.01.03 SALIDA DE AGUA FRIA C/TUBERIA DE PVC SAP DE 1/2" pto 21.00 94.86 1,029.46 931.77 30.88 1,992.06
04.01.04 VALVULA COMPUERTA DE 1/2" und 9.00 62.51 247.56 315.00 562.59
04.01.05 TEE PVC-SAP 1/2" und 13.00 16.27 178.81 27.40 5.36 211.51
04.01.06 CODO PVC SAP 1" x 90 und 4.00 16.77 55.01 10.43 1.65 67.08
04.01.07 CODO PVC SAP 1/2" x 90 und 27.00 17.77 371.36 97.42 11.14 479.79
04.01.08 REDUCCION DE PVC SAP C/R 3/4" A 1/2" C-10 und 3.00 19.44 52.27 4.50 1.57 58.32
04.01.09 REDUCCION DE PVC HIDRO 1" A 1/2" und 2.00 19.94 34.85 4.00 1.05 39.88
04.02 SISTEMA DE AGUA CALIENTE 386.30 550.51 17.94 954.67
04.02.01 TUBERIA PVC HIDRO DE 1/2" m 24.61 23.71 186.63 387.61 9.33 583.50
04.02.02 SALIDA DE AGUA CALIENTE CON TUBERIA PVC HIDRO DE 1/2" pto 3.00 93.57 130.91 143.25 6.55 280.71
04.02.03 TEE PVC HIDRO DE 1/2" und 1.00 17.38 13.75 3.22 0.41 17.38
04.02.04 CODO PVC HIDRO 1/2" x 90 und 4.00 18.27 55.01 16.43 1.65 73.08
04.03 SISTEMA DE DESAGUE 4,109.27 7,973.28 200.25 12,284.34
04.03.01 TRABAJOS PRELIMINARES 47.06 61.11 35.99 145.04
04.03.01.01 TRAZO Y REPLANTEO m2 61.72 2.35 47.06 61.11 35.99 145.04
04.03.02 MOVIMIENTO DE TIERRAS 668.68 61.72 73.25 803.67
04.03.02.01 EXCAVACION DE ZANJA PARA RED DE DESAGUE m3 8.64 27.30 228.98 6.87 235.87
04.03.02.02 REFINE Y NIVELACION ZANJA m 61.72 3.32 203.11 2.03 204.91
04.03.02.03 COLOCACION DE CAMA Y SOBRECAMA PARA RED DE DESAGUE m 61.72 2.80 107.65 61.72 3.24 172.82
04.03.02.04 RELLENO COMPACTADO C/EQUIPO MAT./PROPIO m3 3.70 14.99 32.29 23.17 55.46
04.03.02.05 ACARREO DE MATERIAL EXCEDENTE m3 5.93 16.70 94.29 4.71 99.03
04.03.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 5.93 6.00 2.36 33.23 35.58
04.03.03 RED DE DESAGUE 2,713.01 1,472.33 82.63 4,268.60
04.03.03.01 SALIDA DE PVC SAL PARA DESAGUE 4" pto 14.00 65.28 610.90 284.55 18.33 913.92
04.03.03.02 SALIDA DE PVC SAL PARA DESAGUE 2" pto 15.00 40.79 436.34 162.38 13.09 611.85
04.03.03.03 CAJA DE REGISTRO 0.40 x 0.50 mts. C/TAPA und 1.00 99.98 61.89 35.00 3.09 99.98
04.03.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC SAL 2" m 13.60 18.84 184.75 65.82 5.54 256.22
04.03.03.05 SUMINISTRO E INSTALACION DE TUBERIA PVC SAL 4" m 48.12 22.54 653.70 410.94 19.62 1,084.62
04.03.03.06 SUMINISTRO E INSTALACION YEE PVC SAL 4" x 4" und 4.00 16.24 41.82 21.90 1.25 64.96
04.03.03.07 SUMINISTRO E INSTALACION YEE PVC SAL 4" x 2" und 6.00 19.24 62.72 50.85 1.88 115.44
04.03.03.08 SUMINISTRO E INSTALACION YEE PVC SAL 2" x 2" und 4.00 15.14 41.82 17.52 1.25 60.56
04.03.03.09 SUMINISTRO E INSTALACION CODO PVC SAL 4" x 45 pza 5.00 13.87 52.27 15.51 1.57 69.35
04.03.03.10 SUMINISTRO E INSTALACION CODO PVC SAL 2" x 45 pza 1.00 12.35 8.71 3.38 0.26 12.35
04.03.03.11 SUMIDEROS DE 2" pza 10.00 56.44 348.86 205.00 10.47 564.40
04.03.03.12 REGISTRO ROSCADO DE BRONCE 4" und 4.00 37.94 69.69 80.00 2.09 151.76
04.03.03.13 SALIDA DE PVC SAL PARA VENTILACION 2" pto 3.00 66.79 87.27 110.48 2.62 200.37
04.03.03.14 REJILLA DE VENTILACION DE BRONCE 2" und 3.00 20.94 52.27 9.00 1.57 62.82
04.03.04 APARATOS Y ACCESORIOS SANITARIOS 575.98 2,478.12 5.24 3,059.35
04.03.04.01 INODORO TANQUE BAJO pza 4.00 253.89 174.54 841.00 1,015.56
04.03.04.02 LAVATORIO DE LOSA pza 4.00 144.89 174.54 405.00 579.56
04.03.04.03 LAVATORIO DE ACERO INOXIDABLE pza 4.00 200.00 800.00 800.00
04.03.04.04 DUCHA CROMADA und 3.00 92.69 52.36 225.72 278.07
04.03.04.05 LLAVE CROMADA DE 1/2" P/LAVAMANOS und 4.00 45.77 87.27 93.20 2.62 183.08
04.03.04.06 LLAVE CROMADA DE 1/2" P/LAVADERO DE ACERO INOXIDABLE und 4.00 50.77 87.27 113.20 2.62 203.08
04.03.05 VARIOS 104.54 3,900.00 3.14 4,007.68
04.03.05.01 CONEXION A RED DE DESAGUE EXISTENTE glb 1.00 400.00 400.00 400.00
04.03.05.02 CONEXION NUEVA DE AGUA glb 1.00 607.68 104.54 500.00 3.14 607.68
04.03.05.03 PRUEBA HIDRAULICA PARA AGUA FRIA glb 1.00 500.00 500.00 500.00
04.03.05.04 SUMINISTRO E INSTALACION DE TANQUE ELEVADO INC./ACCESORIOS glb 1.00 2,000.00 2,000.00 2,000.00
04.03.05.05 SUMINISTRO E INSTALACION DE BOMBA DE AGUA INC./ACCESORIOS glb 1.00 500.00 500.00 500.00
05 INSTALACIONES ELECTRICAS 10,944.90 9,796.27 344.81 21,094.90
05.01 RED DE ENERGIA ELECTRICA 319.37 560.00 15.96 895.33
05.01.01 TABLERO GENERAL TG und 1.00 289.53 94.79 190.00 4.74 289.53
05.01.02 TABLERO DE DISTRIBUCION TD -01 und 1.00 317.90 112.29 200.00 5.61 317.90
05.01.03 TABLERO DE DISTRIBUCION TD -02 und 1.00 287.90 112.29 170.00 5.61 287.90
05.02 INSTALACIONES ELECTRICAS 8,894.23 4,144.11 271.63 13,318.34
05.02.01 TUBERIA PVC SEL (ELECTRICA) D= 1" m 59.13 5.36 199.25 110.87 6.00 316.94
05.02.02 TUBERIA PVC SEL (ELECTRICA) D= 3/4" m 276.31 5.19 931.11 469.73 28.02 1,434.05
05.02.03 SUMINISTRO E INSTALACION CONDUCTOR 1x2.5MM2 TW m 388.37 10.13 3,361.05 469.93 100.90 3,934.19
05.02.04 SUMINISTRO E INSTALACION CONDUCTOR 1x 4MM2 TW m 176.32 10.13 1,525.91 213.35 45.81 1,786.12
05.02.05 SUMINISTRO E INSTALACION CONDUCTOR 6MM2 THW m 48.90 6.34 170.70 134.48 5.12 310.03
05.02.06 SUMINISTRO E INSTALACION CONDUCTOR 10MM2 THW m 7.00 7.99 24.44 30.80 0.73 55.93
05.02.07 SALIDA PARA CENTRO DE LUZ EN TECHO pto 74.00 22.02 1,291.63 299.70 38.74 1,629.48
05.02.08 SALIDA PARA CENTRO DE LUZ EN LA PARED pto 17.00 22.02 296.73 68.85 8.90 374.34
05.02.09 SALIDA PARA TOMACORRIENTE pto 32.00 38.91 418.18 814.40 12.55 1,245.12
05.02.10 SALIDA PARA INTERRUPTOR SIMPLE pto 20.00 44.11 261.36 613.00 7.84 882.20
05.02.11 SALIDA PARA INTERRUPTOR DOBLE pto 10.00 53.44 183.83 345.00 5.52 534.40
05.02.12 POZO DE TIERRA und 1.00 815.54 230.04 574.00 11.50 815.54
05.03 ARTEFACTOS DE ILUMINACION 1,467.80 3,541.50 44.05 5,053.90
05.03.01 ARTEFACTO FLUORESCENTE 2 x 40 W und 13.00 48.69 238.98 386.75 7.17 632.97
05.03.02 SPOT LIGHT und 61.00 63.69 1,121.37 2,729.75 33.65 3,885.09
05.03.03 BRAQUET REFLECTOR 32W und 17.00 31.52 107.45 425.00 3.23 535.84
05.04 TELECOMUNICACIONES 263.50 1,550.66 13.17 1,827.33
05.04.01 SALIDA PARA INTERCOMUNICADOR pto 3.00 82.31 65.45 178.20 3.27 246.93
05.04.02 SALIDA PARA TELEFONO INTERNO pto 2.00 280.58 66.02 491.84 3.30 561.16
05.04.03 SALIDA PARA TELEVISION pto 4.00 254.81 132.03 880.62 6.60 1,019.24
Costo Directo 232,176.04

SON : DOSCIENTOS TRENTIDOS MIL CIENTO SETENTISEIS Y 04/100 NUEVOS SOLES

Fecha : 29/06/2016 12:17:53 PM