EXAMEN N03

INGRESO DE RECURSOS A PROJECT


HOJA DE PRESUPUESTO
Item Descripcin Und.
01.00.00 ESTRUCTURAS
01.01.00 MOVIMIENTO DE TIERRAS
01.01.01 LIMPIEZA DE TERRENO MANUAL m2
01.01.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 mTERRENO NORMAL m3
01.02.00 CONCRETO ARMADO
01.02.01 COLUMNAS
01.02.01.01 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg
01.02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2
01.02.01.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3
01.02.02 VIGAS
01.02.02.01 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS kg
01.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2
01.02.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3
OJECT
O
Metrado Precio (S/.) Parcial (S/.)
12,043.76
668.33
72.00 1.40 100.88 0.067 4.80384 0.05 378.00
32.40 17.51 567.45 0.834 27.0216 1.05
11,375.43 0.034688
5,743.54
378.00 3.03 1,144.75
72.00 39.13 2,817.04 0.3000 72.00
5.40 329.95 1,781.75 0.3000
5,631.89 0.3500
551.25 3.03 1,669.43 4.2400
42.45 42.14 1,788.92 0.77
7.88 276.00 2,173.53

0.9000 5.40
0.5000
0.2000
9.2000
8.0000
6.0000
15.3333

0.05 551.25
1.05
0.034688

0.21 42.45
0.24
5.03
0.51573333

0.68 7.88
0.55
0.2
9.2
1.35216
18.9
396.9
13.112064

21.6
21.6
25.2
305.28
55.6992

4.86
2.7
1.08
49.68
43.2
32.4
82.8

27.5625
578.8125
19.12176

8.9145
10.188
213.5235
21.89288

5.355
4.33125
1.575
72.45
10.64826 14.19
Partida 01.01.01 LIMPIEZA DE TERRENO MANUAL

Rendimiento kg/DIA 50.0000 EQ. 50.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010004 OFICIAL hh

Materiales
Equipos
0301010006 HERRAMIENTAS MANUALES %mo

Partida 01.01.02 EXCAVACION PARA CIMIENTOS HASTA H=1.10 M.

Rendimiento kg/DIA 4.0000 EQ. 4.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010004 OFICIAL hh

Materiales
Equipos
0301010006 HERRAMIENTAS MANUALES %mo

Partida 01.02.01.01 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS

Rendimiento kg/DIA 250.0000 EQ. 250.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010004 OFICIAL hh

Materiales
02040100010002 ALAMBRE NEGRO RECOCIDO N 16 kg
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg

Equipos
0301010006 HERRAMIENTAS MANUALES %mo
Partida 01.02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS

Rendimiento m2/DIA 10.0000 EQ. 10.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010005 PEON hh

Materiales
02040100010001 ALAMBRE NEGRO RECOCIDO N 8 kg
02041200010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg
02041200010007 CLAVOS PARA MADERA CON CABEZA DE 4" kg
0231010001 MADERA TORNILLO p2

Equipos
0301010006 HERRAMIENTAS MANUALES %mo

Partida 01.02.01.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2

Rendimiento m3/DIA 12.0000 EQ. 12.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010004 OFICIAL hh
0101010005 PEON hh
01010100060002 OPERADOR DE EQUIPO LIVIANO hh

Materiales
02070100010002 PIEDRA CHANCADA 1/2" m3
02070200010002 ARENA GRUESA m3
0207070001 AGUA PUESTA EN OBRA m3
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol

Equipos
03012100030001 WINCHE ELECTRICO 3.6 HP DE DOS BALDES hm
03012900010002 VIBRADOR DE CONCRETO 4 HP 1.25" hm
03012900030001 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm
Partida 01.02.02.01 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS

Rendimiento kg/DIA 250.0000 EQ. 250.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010004 OFICIAL hh

Materiales
02040100010002 ALAMBRE NEGRO RECOCIDO N 16 kg
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg

Equipos
0301010006 HERRAMIENTAS MANUALES %mo

Partida 01.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS

Rendimiento m2/DIA 9.0000 EQ. 9.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010005 PEON hh

Materiales
02040100010001 ALAMBRE NEGRO RECOCIDO N 8 kg
02041200010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg
0231010001 MADERA TORNILLO p2

Equipos
0301010006 HERRAMIENTAS MANUALES %mo

Partida 01.02.02.03 CONCRETO EN VIGAS f'c=210 kg/cm2

Rendimiento m3/DIA 20.0000 EQ. 20.0000

Cdigo Descripcin Recurso Unidad


Mano de Obra
0101010002 CAPATAZ hh
0101010003 OPERARIO hh
0101010004 OFICIAL hh
0101010005 PEON hh

Materiales
02070100010002 PIEDRA CHANCADA 1/2" m3
02070200010002 ARENA GRUESA m3
0207070001 AGUA PUESTA EN OBRA m3
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol

Equipos
0301010006 HERRAMIENTAS MANUALES %mo
03012100030001 WINCHE ELECTRICO 3.6 HP DE DOS BALDES hm
03012900010002 VIBRADOR DE CONCRETO 4 HP 1.25" hm
03012900030001 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm
1.40

Cuadrilla Cantidad Precio S/. Parcial S/.

0.1000 0.0160 13.40 0.21


1.0000 0.1600 7.00 1.12
1.33

5.0000 1.33 0.067


0.07

A H=1.10 M.

17.51

Cuadrilla Cantidad Precio S/. Parcial S/.

0.1000 0.2000 13.40 2.68


1.0000 2.0000 7.00 14.00
16.68

5.0000 16.68 0.834


0.83

COLUMNAS

3.03

Cuadrilla Cantidad Precio S/. Parcial S/.

0.2000 0.0064 13.40 0.09


1.0000 0.0320 12.00 0.38
1.0000 0.0320 7.00 0.22
0.69

0.0500 4.00 0.20


1.0500 2.00 2.10
C 2.30

5.0000 0.69 0.035


0.03
RMAL EN COLUMNAS

39.13

Cuadrilla Cantidad Precio S/. Parcial S/.

0.1000 0.0800 13.40 1.07


1.0000 0.8000 12.00 9.60
1.0000 0.8000 6.00 4.80
15.47

0.3000 4.00 1.20


0.3000 4.00 1.20
0.3500 4.00 1.40
4.2400 4.50 19.08
22.88

5.0000 15.47 0.77


0.77

329.95

Cuadrilla Cantidad Precio S/. Parcial S/.

0.2000 0.1333 13.40 1.79


2.0000 1.3333 12.00 16.00
2.0000 1.3333 7.00 9.33
8.0000 5.3333 6.00 32.00
3.0000 2.0000 12.00 24.00
83.12

0.9000 31.00 27.90


0.5000 26.00 13.00
0.2000 9.00 1.80
9.2000 19.00 174.80
217.50

1.0000 0.6667 12.00 8.00


1.0000 0.6667 9.00 6.00
1.0000 0.6667 23.00 15.33
29.33
3.03

Cuadrilla Cantidad Precio S/. Parcial S/.

0.2000 0.0064 13.40 0.09


1.0000 0.0320 12.00 0.38
1.0000 0.0320 7.00 0.22
0.69

0.0500 4.00 0.20


1.0500 2.00 2.10
2.30

5.0000 0.69 0.035


0.03

RMAL EN VIGAS

42.14

Cuadrilla Cantidad Precio S/. Parcial S/.

0.1000 0.0889 13.40 1.19


1.0000 0.8889 12.00 10.67
1.0000 0.8889 6.00 5.33
17.19

0.2100 4.00 0.84


0.2400 4.00 0.96
5.0300 4.50 22.64
24.44

3.0000 17.19 0.52


0.52

276.00

Cuadrilla Cantidad Precio S/. Parcial S/.

0.2000 0.0800 13.40 1.07


2.0000 0.8000 12.00 9.60
2.0000 0.8000 7.00 5.60
12.0000 4.8000 6.00 28.80
45.07

0.6800 31.00 21.08


0.5500 26.00 14.30
0.2000 9.00 1.80
9.2000 19.00 174.80
211.98

3.0000 45.07 1.35


1.0000 0.4000 12.00 4.80
1.0000 0.4000 9.00 3.60
1.0000 0.4000 23.00 9.20
18.95
Precios y cantidades de recursos requeridos por tipo

Cdigo Recurso Unidad Cantidad Precio

MANO DE OBRA

0101010002 CAPATAZ hh 255.5328 13


0101010003 OPERARIO hh 1,374.0392 12
0101010004 OFICIAL hh 1,564.0357 7
0101010005 PEON hh 2,848.2833 6
01010100060 OPERADOR DE EQUIPO LIVIANO hh 141.5684 12
01010300000 PERSONAL DE TOPOGRAFIA da 61.0000 60

MATERIALES

0201030001 GASOLINA gal 13.7450 12


0201040001 PETROLEO D-2 gal 50.3100 8
02040100010 ALAMBRE NEGRO RECOCIDO N 8 kg 129.0079 4
02040100010 ALAMBRE NEGRO RECOCIDO N 16 kg 494.4600 4
0204030001 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 17,645.4720 2
02041200010 CLAVOS PARA MADERA CON CABEZA DE 3" kg 81.4200 4
02041200010 CLAVOS PARA MADERA CON CABEZA DE 4" kg 67.3200 4
02070100010 PIEDRA CHANCADA 1/2" m3 104.8150 31
0207010005 PIEDRA MEDIANA m3 10.8619 32
0207010006 PIEDRA GRANDE DE 8" m3 33.0000 32
02070200010 ARENA GRUESA m3 53.9500 26
0207030001 HORMIGON m3 123.1417 18
0207070001 AGUA PUESTA EN OBRA m3 38.4790 9
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 1,597.0800 19
02160100040 LADRILLO PARA TECHO 8H DE 15X30X30 cm und 5,888.3000 0
02190800010 ESCANTILLON DE CONCRETO 0.05x0.05x0.40 m und 249.6000 1
0231010001 MADERA TORNILLO p2 4,098.9111 4
0231190001 MADERA PINO p2 8.7000 5
0276030004 SEPARADORES PLASTICOS (3 cm.) EN FIERRO DE mll 0.2496 5
VIGAS
EQUIPOS

03010000120 EQUIPO TOGRAFICO da 61.0000 17


03010600020 REGLA DE MADERA PINO 2" X 6" X 10' und 1.4500 5
030114000100TALADRO CINCELADOR TE 504 hm 28.3335 100
03012100030 WINCHE ELECTRICO 3.6 HP DE DOS BALDES hm 527.3141 12
03012200040 CAMION VOLQUETE DE 10 m3 hm 22.4000 87
03012900010 VIBRADOR DE CONCRETO 4 HP 1.25" hm 44.8689 9
03012900030 MEZCLADORA DE CONCRETO 11 P3 (23 HP) hm 100.3309 23
0301340001 ANDAMIO METALICO da 1.4994 8
03013500010 CONTENEDOR DE INODOROS Y LAVATORIOS da 90.0000 20
03013500010 CONTENEDOR DE ALMACENES da 90.0000 20
03013500010 CONTENEDOR DE OFICINAS da 90.0000 20

Total
s por tipo

Precio S/. Parcial S/.

13.40 3,424.14
12.00 16,488.47
7.00 10,948.25
6.00 17,089.70
12.00 1,698.82
60.00 3,660.00

53,309.38

GRUPO DE COMBUSTIBLE
12.00 164.94 GRUPO DE ACERO
8.00 402.48 GRUPO DE AGREGADOS
4.00 516.03 MADERA
4.00 1,977.84 CEMENTO
2.00 35,290.94 LADRILLO
4.00 325.68
4.00 269.28 FECHA DE TERMINO 30 DE AGOSTO DEL 2016
31.00 3,249.27
32.00 347.58
32.00 1,056.00
26.00 1,402.70
18.00 2,216.55
9.00 346.31
19.00 30,344.52
0.67 3,945.16
1.50 374.40
4.50 18,445.10
5.00 43.50
5.00 1.25

100,719.53
17.00 1,037.00
5.00 7.25
100.00 2,833.35
12.00 6,327.77
87.00 1,948.80
9.00 403.82
23.00 2,307.61
8.00 12.00
20.00 1,800.00
20.00 1,800.00
20.00 1,800.00

20,277.60

Total S/. 174,306.51


AGOSTO DEL 2016
CRONOGRAMA VALORIZA
PROYECTO CONSTRUCCIN DE CERC

Item Descripcin Und. Metrado


01.00.00 ESTRUCTURAS
01.01.00 MOVIMIENTO DE TIERRAS
01.01.01 LIMPIEZA DE TERRENO MANUAL m2 72.00
01.01.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 mTERRENO NORMAL m3 32.40
01.02.00 CONCRETO ARMADO
01.02.01 COLUMNAS
01.02.01.01 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 378.00
01.02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 72.00
01.02.01.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 5.40
01.02.02 VIGAS
01.02.02.01 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS kg 551.25
01.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 42.45
01.02.02.03 CONCRETO EN VIGAS f'c=210 kg/cm2 m3 7.88
COSTO DIRECTO
GASTOS GENERALES 10%
UTILIDADES 7%
SUBTOTAL
IGV 18%
TOTAL
AMA VALORIZADO
CIN DE CERCO PERIMTRICO
MES DE AGOSTO
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 TOTAL
S/. 141.51 S/. 402.82 S/. 3,040.41 S/. 2,249.72 S/. 3,805.49 S/. 2,403.80 S/. 12,043.75
S/. 141.51 S/. 402.82 S/. 124.00 S/. 668.33
S/. 100.88 S/. 100.88
S/. 40.63 S/. 402.82 S/. 124.00 S/. 567.45
S/. 2,916.41 S/. 2,249.72 S/. 3,805.49 S/. 2,403.80 S/. 11,375.42
S/. 1,246.13 S/. 2,249.72 S/. 2,247.34 S/. 5,743.19
S/. 1,144.40 S/. 1,144.40
S/. 101.73 S/. 2,249.72 S/. 465.59 S/. 2,817.04
S/. 1,781.75 S/. 1,781.75
S/. 1,670.28 S/. 1,558.15 S/. 2,403.80 S/. 5,632.23
S/. 1,670.28 S/. 1,670.28
S/. 1,558.15 S/. 231.26 S/. 1,789.41
S/. 2,172.54 S/. 2,172.54
S/. 141.51 S/. 402.82 S/. 3,040.41 S/. 2,249.72 S/. 3,805.49 S/. 2,403.80 S/. 12,043.75
S/. 14.15 S/. 40.28 S/. 304.04 S/. 224.97 S/. 380.55 S/. 240.38 S/. 1,204.38
S/. 9.91 S/. 28.20 S/. 212.83 S/. 157.48 S/. 266.38 S/. 168.27 S/. 843.06
S/. 165.57 S/. 471.30 S/. 3,557.28 S/. 2,632.17 S/. 4,452.42 S/. 2,812.45 S/. 14,091.19
S/. 31.46 S/. 89.55 S/. 675.88 S/. 500.11 S/. 845.96 S/. 534.36 S/. 2,677.33
S/. 197.02 S/. 560.85 S/. 4,233.16 S/. 3,132.29 S/. 5,298.38 S/. 3,346.81 S/. 16,768.51
vamos a diagrama de gantt y a uso de tareas

con clic derecho podemos cambiar lo que queremos que nos muestre
y nos muestra como desagregado el costo de nuestras actividades, nos muestra el costo de las partidas por dia
podemos acomodarlo segn lo que requiramos
s partidas por dia