DIAGRAMA GANTT DE LA OBRA "MEJORAMIENTO DEL SERVICIO DE INSFRAESTRUCTURA VIAL URBANA PISTAS Y VEREDAS EN CALLE AREQUIPA, DISTRITO DE CORRALES -

TUMBES - TUMBES"
Id Texto1 Nombre de tarea Duracin Comienzo Fin 17 jul '16 31 jul '16 14 ago '16 28 ago '16 11 sep '16 25 sep '16
S X D J L V M S X D J L V M S X D J L V
1 MEJORAMIENTO DEL SERVICIO DE ALCANTARILLADO DE LA CALLE AREQUIPA DEL DISTRITO 60 das lun 01/08/16 jue 29/09/16
2 DEINICIO
CORRALES - TUMBES - TUMBES
DEL PROYECTO 60 das lun 01/08/16 jue 29/09/16
3 1 OBRAS PROVISIONALES 2 das lun 01/08/16 mar 02/08/16

4 1.01 SUMINISTRO Y COLOCACIN DE CARTEL DE OBRA (3.60X2.40M) 1 da lun 01/08/16 lun 01/08/16
5 1.02 CASETA DE GUARDIANIA Y/O ALMACEN 1 da mar 02/08/16 mar 02/08/16
6 01.01 TRABAJOS PRELIMINARES 5 das lun 01/08/16 vie 05/08/16

7 01.01.01 TRAZO Y REPLANTEO INICIAL DEL PROYECTO, PARA LNEAS-REDES 1 da lun 01/08/16 lun 01/08/16 01/08
8 01.01.02 CERCO DE MALLA HDP DE 1 M ALTURA PARA LMITE DE SEGURIDAD DE OBRA 1 da lun 01/08/16 lun 01/08/16 01/08
9 01.01.03 CONO FIBRA VIDRIO FOSFORESCENTE P/DESVO DE TRNSITO S/D (PROV. DURANTE OBRA) 1 da lun 01/08/16 lun 01/08/16
10 01.01.04 TRANQUERA T/BARANDA 2.4 X 1.2M PROV.P/SEALIZACION - PROTECCION 1 da lun 01/08/16 lun 01/08/16
11 01.01.05 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA S/D (PROV. DURANTE OBRA) 2 das mar 02/08/16 mi 03/08/16
12 01.02 MOVIMIENTO DE TIERRAS 5 das lun 01/08/16 vie 05/08/16
13 01.02.01 EXCAVACION DE ZANJAS 17 das lun 01/08/16 mi 17/08/16
14 01.02.01.01 EXCAVACIONES-CORTES EN TERRENO SATURADO CON CARGADOR RETROEXCAVADORA 5 das lun 01/08/16 vie 05/08/16
15 01.02.01.02 EXCAV. ZANJA(MQ)P/COL.PRINCIPAL C/ENT.METLICO T-SATURADO DN 200-250 DE 1,21 M A 5 das vie 05/08/16 mar 09/08/16
1,50 M PROF.
16 01.02.01.03 EXCAV. ZANJA(MQ)P/COL.PRINCIPAL C/ENT.METLICO T-SATURADO DN 200-250 DE 1,51 M A 5 das mar 09/08/16 sb 13/08/16
2,00 M PROF.
17 01.02.01.04 EXCAV. ZANJA(MQ)P/COL.PRINCIPAL C/ENT.METLICO T-SATURADO DN 200-250 DE 2,51 M A 5 das sb 13/08/16 mi 17/08/16
3,00 M PROF.
18 01.02.01.05 EXCAV. ZANJA(MQ)P/COL.PRINCIPAL C/ENT.METLICO T-SATURADO DN 200-250 DE 3,51 M A 7 das lun 01/08/16 dom 07/08/16
4,00 M PROF.
19 01.02.01.06 EXCAV. ZANJA(MQ)P/COL.PRINCIPAL C/ENT.METLICO T-SATURADO DN 315-760 DE 4,51 M A 7 das lun 01/08/16 dom 07/08/16
5,00 M PROF.
20 01.02.02 REFINE Y CONFORMACIN DE ZANJAS 5 das mi 17/08/16 dom 21/08/16
21 01.02.02.01 REFINE Y NIVEL DE ZANJA T-SATURADO P/TUB. DN 200 - 250 PARA TODA PROF. 5 das mi 17/08/16 dom 21/08/16
22 01.02.03 DRENAJE DE AGUAS SERVIDAS 30 das sb 20/08/16 dom 18/09/16
23 01.02.03.01 DRENAJE DE ZANJAS C/BOMBEO P/TUBERA DN 200-250MM TODA PROF. 30 das sb 20/08/16 dom 18/09/16
24 01.02.04 ENTIBADO DE ZANJAS 7 das sb 20/08/16 vie 26/08/16
25 01.02.04.01 ENTIBADO DE ZANJA DE 1.21 HASTA 1.50 M 3 das sb 20/08/16 lun 22/08/16
26 01.02.04.02 ENTIBADO DE ZANJA DE 1.51 HASTA 2.00 M 3 das lun 22/08/16 mi 24/08/16
27 01.02.04.03 ENTIBADO DE ZANJA DE 2.51 HASTA 3.00 M 3 das lun 22/08/16 mi 24/08/16
28 01.02.04.04 ENTIBADO DE ZANJA DE 3.51 HASTA 4.00 M 3 das sb 20/08/16 lun 22/08/16
29 01.02.04.05 ENTIBADO DE ZANJA DE 4.51 HASTA 5.00 M 3 das sb 20/08/16 lun 22/08/16
30 01.02.05 CAMA DE APOYO Y PROTECCION PARA TUBERIAS 24 das mar 23/08/16 jue 15/09/16
31 01.02.05.01 RELLENO CON MATERIAL DE PRSTAMO OVER (INCLUYE PROVISIN) A MAQUINA. E=0.30 7 das mar 23/08/16 lun 29/08/16
32 01.02.05.02 CAMA DE GRAVA MANUAL E=0.15 P/COL.PRINCIPAL DN 200-250MM 5 das lun 29/08/16 vie 02/09/16
33 01.02.05.03 CAMA DE ARENA MANUAL E=0.30 SCT P/TUBERA DN 200-250MM 5 das vie 02/09/16 mar 06/09/16
34 01.02.06 RELLENO, APISONADO Y COMPACTACION ZANJAS 6 das mar 23/08/16 dom 28/08/16
35 01.02.06.01 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN 200-250 DE 1,21M A 1,50M PROF. 5 das dom 11/09/16 jue 15/09/16
36 01.02.06.02 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN 200-250 DE 1,51M A 2,00M PROF. 5 das mar 06/09/16 sb 10/09/16
37 01.02.06.03 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN 200-250 DE 2,51M A 3,00M PROF. 4 das vie 09/09/16 lun 12/09/16
38 01.02.06.04 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN 200-250 DE 3,51M A 4,00M PROF. 5 das dom 11/09/16 jue 15/09/16
39 01.02.06.05 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN 315-750 DE 4,51M A 5,00M PROF. 5 das mar 23/08/16 sb 27/08/16
40 01.02.07 ACARREO Y ELIMINACION MATERIAL EXCEDENTE 7 das jue 15/09/16 jue 22/09/16
41 01.02.07.01 ELIMINACIN DE DESMONTE EN TERRENO NORMAL R=5 KM CON MAQUINARIA 2 das vie 16/09/16 sb 17/09/16
42 01.03 SUMINISTRO E INSTALACION DE TUBERIA 7 das vie 16/09/16 jue 22/09/16
43 01.03.01 TUBERA PVC-U SC NTP ISO 21138 SN 8 DN 200MM INCL. ANILLO + 2% DESPERDICIOS 5 das sb 17/09/16 mi 21/09/16
44 01.03.02 TUBERA PVC-U SC NTP ISO 21138 SN 4 DN 200MM INCL. ANILLO + 2% DESPERDICIOS 5 das vie 16/09/16 mar 20/09/16
45 01.03.03 INSTALACIN DE TUBERA DE PVC P/DESAGE DN 200MM 4 das vie 16/09/16 lun 19/09/16
46 01.04 PRUEBA HIDRAULICA 1 da jue 15/09/16 jue 15/09/16 15/09
47 01.04.01 PRUEBA HIDRAULICA DE DESAGUE 2 das vie 16/09/16 sb 17/09/16
48 01.05 CAMARAS DE INSPECCION (BUZONES) 12 das vie 16/09/16 mar 27/09/16
49 01.05.01 BUZN TIPO I DI=1.2M. HASTA 1,50 M PROF.(ENCOF.EXTER.E INTER) 5 das vie 16/09/16 mar 20/09/16
50 01.05.02 BUZN TIPO II DI=1.5M. HASTA 2,50 M PROF.(ENCOF.EXTER.E INTER) 5 das vie 16/09/16 mar 20/09/16
51 01.05.03 BUZN TIPO II DI=1.5M. HASTA 3,50 M PROF.(ENCOF.EXTER.E INTER) 5 das vie 16/09/16 mar 20/09/16
52 01.05.04 BUZN TIPO II DI=1.5M. HASTA 4,50 M PROF.(ENCOF.EXTER.E INTER) 5 das vie 16/09/16 mar 20/09/16
53 01.06 CONEXIONES DOMICILIARIAS DE DESAGUE 7 das vie 16/09/16 jue 22/09/16
54 01.06.01 CONEXIONES DOMICILIARIAS PARA DESAGE DN 200X160MM 7 das mi 21/09/16 mar 27/09/16
55 01.06.02 EXCAVACIONES-CORTES EN TERRENO SATURADO MANUAL 7 das vie 16/09/16 jue 22/09/16
56 01.06.03 REFINE Y NIVEL DE ZANJA T-SATURADO P/TUB. DN 200X160MM PARA TODA PROF. 2 das vie 16/09/16 sb 17/09/16
57 01.06.04 CAMA DE ARENA MANUAL E=0.30 SCT P/TUBERA DN 200X160MM 2 das vie 16/09/16 sb 17/09/16
58 01.06.05 RELLENO COMP.ZANJA P/COL. PRINCIPAL T-SATURADO DN DN 200X160MM DE 1,00M A 3,00M 3 das sb 17/09/16 lun 19/09/16
PROF.
59 01.06.06 ELIMINACIN DE DESMONTE EN TERRENO NORMAL R=5 KM CON MAQUINARIA 2 das vie 16/09/16 sb 17/09/16

Tarea Resumen Hito inactivo solo duracin solo el comienzo Hito externo Divisin crtica
Proyecto: CRONOGRAMA COR Divisin Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha lmite Progreso

Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas crticas Progreso manual

Pgina 1
DIAGRAMA GANTT DE LA OBRA "MEJORAMIENTO DEL SERVICIO DE INSFRAESTRUCTURA VIAL URBANA PISTAS Y VEREDAS EN CALLE AREQUIPA, DISTRITO DE CORRALES -
TUMBES - TUMBES"
Id Texto1 Nombre de tarea Duracin Comienzo Fin 17 jul '16 31 jul '16 14 ago '16 28 ago '16 11 sep '16 25 sep '16
S X D J L V M S X D J L V M S X D J L V
60 01.07 DADOS DE CONCRETO 2 das lun 01/08/16 mar 02/08/16
61 01.07.01 CONCRETO F'C 175 KG/CM2 PARA ANCLAJES Y/O DADOS (CEMENTO MS) 2 das lun 01/08/16 mar 02/08/16
62 01.07.01 MITIGACION DE IMPACTO AMBIENTAL 3 das lun 26/09/16 jue 29/09/16
63 FIN DEL PROYECTO 0 das lun 26/09/16 lun 26/09/16 26/09

Tarea Resumen Hito inactivo solo duracin solo el comienzo Hito externo Divisin crtica
Proyecto: CRONOGRAMA COR Divisin Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha lmite Progreso

Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas crticas Progreso manual

Pgina 2