Professional Documents
Culture Documents
PARTICLE BOARD
:LAT JACK, APPROX.
TOP PL
I M DIAMETER
*CONCRETE /
NX, 76 MM DIAMETER,
CORE DRILL HOLE
APPROX. 6 FLATJACK / HYDRAULIC
DIAMETERS D E E P ~ LEAD WIRE
SCREWS FOR SET
UP AND REMOVAL
PREPARED DIAMETER
1.5 TO 2 TIMES MPa HYDRAULIC PUMP
FLATJACK DIAMETEI
(b) Instruments for measuring deformations should If blasting is required for initial test surface prep-
include a reliable multiple position borehole exten- aration, care should be exercised to produce surfaces
someter (MPBX) for each instrumentation hole, and which are relatively free from blast damage. Detailed
a tunnel diameter gauge. All instruments should be of site preparation procedures can be found in [2].
sufficient accuracyand sensitivity to be compatible with (b) An instrumentation hole should be core drilled
anticipated deformations. Experimental errors in excess into each prepared test surface. Care must be exercised
of 0.01 mm can invalidate test results when the modulus to insure that the two holes are coaxial with each other
of the rock mass exceeds 3.5 x 104 MPa. A discussion and with the restraint column assembly.
of the ramifications of experimental error can be found (c) Examination of the core and the instrumentation
in [1]. hole itself will assist in locating anchor points for the
5. (a) The loading apparatus should be capable of MPBX's. The anchors should be located so that they
applying simultaneous uniform pressures to two areas are not placed on joints, and so they bracket zones
on opposite sides of the tunnel, each approximately 1 m of structural or lithologic change. The deepest anchor
in diameter. As shown in Fig. 1, the equipment used should be located approximately 6 flat jack diameters
to apply the desired loads to the prepared and instru- below the rock surface in order to provide a fixed point
mented rock may consist of calibrated flat jacks and to which the movements of all other anchors can be
restraint columns having the capability of sustaining referenced. In general, the remaining anchors should
the maximum desired uniform pressure with a suitable be concentrated in the zone of maximum stress between
factor of safety. The hydraulic pump system with the rock surface and a point approximately 3 jack dia-
necessary fittings, valves, gages, and hoses should have meters back from the surface. Figure 2 illustrates some
sufficient pressure capability and volume to apply and recommended locations. It is desirable for the sensor
maintain desired pressures to within 3?/0 of a selected head and all anchors to be attached to the side walls
value throughout the duration of the test. of the instrumentation hole. This precludes the neces-
sity of monitoring the movement of the test setup com-
ponents, since all measurements will be referenced in
PROCEDURE the rock.
6. Site preparation
(a) The area selected for testing should be carefully 7. Equipment installation
prepared. All loose rock material should be removed (a) The complete installation of a proposed type of
by using chipping hammers and drills. In order to restraining and load applying setup together with
reduce the restraining influence of adjoining rock, an deformation measuring instrumentation is shown sche-
area with a diameter 1 to 2 times that of the test matically in Fig. 1. A properly located wooden platform
pad should be prepared. The two test areas should be (not shown in Fig. I) allows for alignment of all test
concentric with and in planes oriented perpen- components. The space between the flat jack assembly
dicular to the axis of the restraint column assembly. and rock should be filled with small aggregate concrete.
.1 ROCK SURFACE
~--~v~llllllr~7~
OD~
~ SENSORH E ~ ~'~
,=.,
F,
OPEN JOINTS" ~ ~
r~ 3D~
I
iii.! .....
I I
6D--
NO STRUCTURAL JOINTS LITHOLOGY ;OUGE SCALE
OR LITHOLOGIC CHANGE SEAM
FEATURES D=Jack Diameter
NOTE: NOT TO SCALE
Fig. 2. Typical anchor locations.
In Situ Deformability of Rock 199
The concrete should be allowed to cure sufficiently to (c) While the test is in progress, rock deformations
obtain adequate strength prior to commencement of monitored by the instrumentation should be recorded
the test. The space between the fiat jack and the base continuously or at sufficient intervals to obtain desired
and top plates should have a special partical board data. If a noncontinuous recording system is utilized,
filler (wood chips and resin) or other suitable material a minimum of four readings during the first hour of
fabricated to accommodate the flat jack configuration each load increment or decrement is recommended.
on one side and the base plate on the other side. (d) The maximum test pressure, number of cycles to
the maximum pressure, and number of pressure incre-
8. Testing ments in each cycle will be determined by test con-
(a) After all components of the instrumentation are ditions and desired information. A maximum pressure
installed in the drill holes, they should be checked (elec- of 1.2-1.5 times that imposed by the structure is usually
tronically or mechanically). After the loading and re- considered adequate. At least five pressure increments,
straining components are installed, another check each followed by a period of zero pressure, should be
should be made of the instrumentation. A final check used for each cycle. A typical one-cycle loading
of all mechanical, hydraulic, and electronic components sequence is shown in Fig. 3.
should be made after the concrete pads are placed and (e) The duration of each pressure increment will be
again before the first load increment is applied. determined by the creep characteristics of the rock
(b) Tests should be conducted continually on a 24-hr mass. Until the behavior of the rock mass is well under-
a day basis utilizing load ranges and increments com- stood, at least 48 hr should be allowed for each pressure
patible with the particular design considerations under increment followed by 24 hr at zero pressure. Obser-
investigation. vations during the first pressure increments can be used
8.3
6.9 r
//
n
5.5
a,,
05
t/)
tO
//
h-
a.
t.9
Z 4.1
ILl
m
2.11
1.4
0
0 O.IOZ o. 203 o.ao5 0.406
DEFORMATION, MM
Fig. 3. Rock Surface deformation as a function of bearing pressure.
200 International Society for R o c k M e c h a n i c s
,, 1 3 S , ,
o ,~ ~10
N~I~33V7dSIO 311SV73N]
=. Q
~D
0
#.
=E
C)
rm ._~
g.
r~
E
o3
o v
g~
'5
ill
g. 0
"" E
0
p
,q.
0
J
O
IO
k
g_
0
IE >-
.2"
\
to O
od
d d
ININ ~30V..-I~nS J.V NOII~'IAI~O.-13C] >I30U
In Situ Deformability of Rock 201
to modify time requirements for successive increments. cycles are utilized to compute deformation moduli
Jack pressure should be maintained within 3% of the according to appropriate formulae. Because of their
target value for the duration of each increment. The simplicity, expressions based on the theory of elasticity
time frame for a typical test is shown in Fig. 4. I-3] are normally used to approximate actual field con-
ditions.
(c) For a uniformly distributed pressure on a circular
CALCULATIONS area, the displacement at any point beneath the center
9. (a) Data gathered during the test may be plotted to of the area may be expressed:
provide a display of Deformation vs Time, Pressure,
or Depth. These plots aid in the analysis of the creep, 2q(1 -/~2) 1-(a2 + z2) 1/2 _ z]
w=- E
rebound, and permanent set characteristics of the rock
mass. Example plots are shown in Figs 3, 4, and 5. qz(1 + #)[z(a 2 + z2)_1/2 _ 1] (1)
(b) Deformation measurements for the various load E
0.3 I
f
0.6
f
0.9
1.2
1.5
1.8
o3
rr
tU 2.1
I-"-
hi
=E
2.4
Z
LU 2.7
/
0
1"
5.0
/
.J
ANCHOR DEPTHS
3.4
SENSOR HEAD 0.0 M
ANCHOR ONE 0.5 M
o 3.7 ANCHOR TWO I. I M
I ANCHOR THREE 1.8 M
4.0 ANCHOR FOUR 2.4 M
123 ANCHOR FIVE 3.2 M
ANCHOR SIX 4.3 M
4.3
ANCHOR SEVEN 6. I M
O-DEPTHS WHERE
4.6 ROCK DEFORMATION
WAS MEASURED
WHEN LOADS WERE
4.9 APPLI ED AT SURFACE
(0- DEPTH )
5.2
5.5
561I/DEEPEST
I
EXTENSOMETER ANCHOR
6jdr I ~ I
Fig. 5. Uniaxial displacement vs depth referenced to deepest anchor at 6.9 M P a bearing pressure.
202 International Society for Rock Mechanics
(d) When loads are applied with a circular flat jack 1. Benson R. P., Murphy D. K. & McCreath D. R. Modulus testing
of rock at the churchill falls underground powerhouse, Labrador,
with a hole in the center, the effect of the unloaded from determination of the in situ modulus of deformation of rock,
area in the center must be subtracted. Using the American Society for Testing and Materials STP477, (1969).
notation: 2. Misterek D. L., Slebir E. J. & Montgomery J. S. Bureau of recla-
mation procedures for conducting uniaxial jacking tests, paper
a 2 : outer radius of flat jack presented at American Society for Testing and Materials Annual
al = inner radius of flat jack or radius of hole Meeting, June 24-29, 1973, Philadelphia, Pennsylvania.
3. Timoshenko S. & Goodier J. N. Theory of Elasticity. McGraw-
_ 2q(1 - 2) Hill, New York (1951).
Wz /2 [(a 2 + z2)l/E(a2 + z2) 1/2]
E
100 TONNE
PROVINGRING
[I SUBSIOIARYLOADING
FRAME
HYDRAULIC
JACK
MAIN LOADINGFRAME ti SETTLEMENT
MEASUREMENT REFERENCE SEAM
~ LOCKINGKEYS
\
\ "a-~ A A A
0
,I
'I 0
REFERENCE ,-<
COLUMN --I
"2 -
]]__ '~
gi
1 E~----- . . . .
LOADING
COLUMN
CONCRETE BLOCKS o
'3
LINEOF5 t~
PILES
CEI
LOADINGPLATE
15ram OF PLASTER
Jack
Dial -I To reference
beam
Measuring
column support
Measuring
Loading column
ht liner
~ P l a s t e r of Paris
......"
;ement mortar
Fig. 2. Details of plate-test equipment.
12. Testing 13. The equipment is removed from the test hole and
(a) With the seating load applied (paragraph lid), further tests may be carried out on deeper horizons
load and displacement should be observed and by re-drilling in the same hole (paragraphs 11 and 12).
recorded over a period not less than 48 hours to estab-
lish datum values and to assess variations due to
ambient conditions. 6 CALCULATIONS
(b) Loads and load increments to be applied during
14. (a) Graphs are plotted of incremental settlement
the test should be selected to cover a range 0.3-1.5 qo,
(or uplift in the case of unloading) against the logarithm
where qo is the stress intensity produced by the pro- of time (Fig. 3).
posed structure, v
(b) Bearing pressure versus settlement curves are
(c) Load is increased in not less than five approxi-
plotted for each test (Figs 4 and 5).
mately equal increments to a maximum of approxi-
(c) Deformation modulae may be determined from
mately 1/3 the maximum for the test. At each increment
tangents to the pressure-settlement curve. In Fig. 6
the load is held constant (___3~) and displacement
three such moduli are defined where
recorded as a function of time until it stabilizes. 7 The
procedure is continued for decreasing load increments Ei is the initial tangent modulus
until the seating load is again reached. E e is the elastic modulus obtained from a re-
(d) The procedure 12(c) is repeated for maximum loading cycle
cycle loads of approximately 2/3 and 3/3 the maximum and
for the test. Ey is a "yield" modulus.
206 International Society for Rock Mechanics
'" 451 k P a
~ 71~ k P a
i
e-
I I I
10 100 1000
Time (minutes)
Fig. 3. Typical relationships between incremental displacement and time for various load-intensities.
(d) The modulus is calculated from the formula in their derivation. Variations with depth in the ground
should also be shown graphically as 'deformability pro-
E = dq ~ D ( 1 - v 2) I~ files' superimposed on the geotechnical log of the test
hole.
where
q is the applied pressure
p is the settlement NOTES
D is the plate diameter 1. The test hole should preferably be of sufficient
v is Poissons's ratio (between 0.1 ar/d 0.3 for diameter to allow manual inspection, and preparation
most rocks) of the bearing surface. Where the hole is insufficiently
lc is a depth correction factor given in Fig. 7.
(e) A time-dependent parameter R (known as the
creep ratio) is determined for each load increment. The /
parameter R is defined as the incremental settlement
per cycle of log time divided by the total overall settle- ;
t
ment due to the applied pressure. The relationship tt
between R and applied pressure may be presented t
t
REPORTING OF RESULTS
0.
I /
/
t! /
I it
15. The report should include the following I i
!
(a) Diagrams and detailed descriptions of the test t
J /
groundwater regime. , / /"
(c) Detailed geotechnical logs and descriptions of /.
,, z
versus time for each load increment, and graphs of load /
/
Load intensity (k Pa )
0 200 400 600 800 I000 1200
I ~o
.1
i~=0.49
g
~ ~ _ =, 0.25 case la)
s,--O.O
E
E
i
t_ I
v
..4
Q g o.71- I 1
E I
0 O
O 0
E 0
o-5 W %
o E
o. i~:0.5
._.R
C36 ~o.52 ~ '""I ""l ,,,,.4f._"1. . . . i-case (bl
5 tO 15 20
- Z/D
o _,.IDI.,- ~ I
Fig. 5. Fig. 7. (a) Uniform circular load at base of unlined shaft. (b) Uniform
circular load within semi-infinite solid (case treated by Fox, 1948).
I &
150(
I~l o T4.1
0 + ; iT4.2
n ~l x x T4.3
Q
+ T2.1
E ,- I 0 0 ( + X~ A A T2.3
0 t
_o .m
o. m
X ~0 A
=..
C3 5o + I
"10
g
I I I I !
.J 0 ~0 20 30 40 50 6b
R(per cent)
that readings should continue until the rate of displace- to within 5% over a period of at least 24 hr, together
ment is less than 2~o of the incremental displacement with all necessary hoses, connectors and fluid.
per hour may be used. This criterion may be modified (b) Flat jacks, when used for load application
to suit the purpose of the test. The final increment in (Fig. la), should be designed to load the maximum of
any one cycle should be held for as long as practical the full circumference of the lining, with sufficient sep-
if the displacement is still increasing. aration to allow displacement measurements, and
should have a bursting pressure and travel consistent
with the anticipated loads and displacements.
(c) Water pressure, when used for load application
(Fig. l b) requires water seals to contain the pressurized
PART 3. S U G G E S T E D
water between the concrete lining and the reaction
M E T H O D FOR frame. Special water seals are also required to allow
the passage of extensometer rods through the lining
M E A S U R I N G ROCK MASS
and reaction frame; pressurized water should not be
DEFORMABILITY U S I N G allowed to escape into the rock since this will greatly
affect the test results.
A RADIAL JACKING TEST
5. Load measuring equipment comprising one or more
hydraulic pressure gauges or transducers s, of suitable
SCOPE range and capable of measuring the applied pressure
1. (a) This test measures the deformability of a rock with an accuracy better than _+2~o.
mass by subjecting a test chamber of circular cross sec- 6. (a) Displacement measuring equipment to monitor
rock movements radial to the tunnel with a precision
tion to uniformly distributed radial loading; the conse-
better than 0.01 ram. Single or multiple position exten-
quent rock displacements are measured, from which
someters conforming with the ISRM "Suggested
Elastic or Deformation modulae may be calculated. 1.
(b) The test loads a large volume of rock so that Methods for Monitoring Rock Displacements" should
be used. Directions of measurement should be chosen
the results may be taken to closely represent the true
with regard to the rock fabi'ic and any direction of
properties of the rock mass, taking into account the
anisotropy.
influence of joints and fissures. The anisotropic defor-
(c) Measurements of movement should be related to
mability of the rock can also be measured.
reference anchors rigidly secured in rock, well away
(c) The results are usually employed in the design
from the influence of the loaded zone. When using mul-
of dam foundations and for the proportioning of pres-
tiple position extensometers the deepest anchor may
sure shaft and tunnel linings.
be used as a reference provided it is situated at least
2 test chamber diameters from the chamber lining.
Alternatively the measurements may be related to a
APPARATUS rigid reference beam passing along the axis of the
chamber and anchored at a distance of not less than
2. Equipment for excavating and lining the test
1 chamber diameter from either end of the chamber
chamber including:
(Fig. 1).
(a) Drilling and blasting materials or mechanical
excavation equipment, z
(b) Concreting materials and equipment for lining the
tunnel, together with strips of weak jointing material PROCEDURE
for segmenting the lining. 3
7, Preparation
3. A reaction frame usually comprising steel rings of
(a) The test chamber location is selected taking into
sufficient strength and rigidity to resist the force
account the rock conditions, particularly the orien-
applied by flat jacks or pressurising fluid. 4 The frame
tation of the rock fabric elements such as joints, bed-
must also act as a waterproof membrane when load
ding and foliation in relation to the orientation of the
is applied by water pressure. When load is applied with
proposed tunnel or opening for which results are
flat jacks the frame must be provided with smooth sur-
required.
faces; hardwood planks are usually inserted between
(b) The test chamber is excavated to the required
the flat jacks and the steel rings.
dimensions. 2,6
4. Loading equipment to apply a uniformly distributed
(c) The geology of the chamber is recorded and speci-
radial pressure to the inner face of the concrete lining,
mens taken for index testing as required.
including:
(d) The chamber is lined with concrete) The reaction
(a) A hydraulic pump capable of applying the
frame and loading equipment are assembled.
required pressure and of holding this pressure constant
(e) The extensometer holes are accurately marked out
and drilled, ensuring no interference between loading
and measuring systems. The extensometers are installed
* Numbers refer to NOTES at the end of the text. and the equipment is checked.
In Situ Deformability of Rock 209
B A
0)
(91
181 (tO)
~----@
Fig. la. Radial jacking test; flat jack loading alternative.
1. Measuring profile. 2. Distance equal to the length of active loading. 3. Control extensometer. 4. Pressure gauge.
5. Reference beam. 6. Handpump. 7. Flat jack. 8. Hardwood lagging. 9. Shotcrete. 10. Excavation diameter. 11. Measuring
diameter. 12. Extensometer drillholes. 13. Dial gauge extensometer. 14. Steel rod. 15. Expansion wedges. 16. Excavation
radius. 18. Inscribed circle. 19. Rockbolt anchor. 20. Steel ring.
Approx 4 m
:';. ~i
-:~:..-,,::~"'"a:.' .. T F,:
. .-... ~: ..~:,.::r..i!-:
*
" ' "" " " "i-'i' ' " " " ' "'
i
i
II
"':.."~
... ...r:""".. ::': :'~: " .~:::..~ ""~ ,.'. ,.. ,. .,..
[i)
""7,
~;5i
14 "
,;j:
~,o
Fig. lb. Radial jacking test equipment; i alternative loading system using water pressure.
The cycle is completed by unloading in stages taking (b) If flat jacks are used, the applied load values are
readings of pressure and corresponding displacements. first corrected to give an equivalent distributed pressure
(e) The test equipment is then dismantled, or further Pl on the test chamber lining:
tests may be required having grouted the rock. 6
Pl = distributed pressure on the
lining at radius rl
CALCULATIONS
~b p., = manometric pressure in the
9. (a) A solution is given only for the case of a single Pl = 2 . r c . r 1 .P,.- fiat jacks
measuring circle with extensometer anchors immedi-
b = fiat jack width
ately behind the lining. This solution, which also
(see Fig. 5)
assumes linear-elastic behaviour for the rock, is usually
adequate in practice although it is possible to analyse
more complex and realistic test configurations using The equivalent pressure P2 at a "measuring radius" i"2
for example finite element analysis. just beneath the lining is calculated, this radius being
In Situ Deformability of Rock 211
I
(c) Superposition of displacements for two "tic-
ticious" loaded lengths is used to give the equivalent
l? L - displacements A for an "infinitely long test chamber". 9
O Ill lll Illlllllll
A B I q ~ A -- AA1 + AA2 + AA3 = AA1 + 2. An1
(see Fig. 2 to give symbols)
(d) The result of the long duration test (Ad) under
A maximum pressure (max P2) is plotted on the displace-
L "i I ment graph (Fig. 3). Test data for each cycle are pro-
[-. . . . . . -l, ~ ,F---
--i portionally corrected to give the complete long term
pressure-displacement curve. The elastic component
///I- 1 (A,,) and the plastic component (Ap) of the total defor-
mation (A,) are obtained from the deformation at the
final unloading:
A
At=Ap+A,, (see Fig. 3)
~ i IIIIIIIIIIIIlUlIIIII ] (e) The elastic modulus E and the deformation
modulus V are obtained from the pressure-displace-
\ I Y A "/ I / ment graph (Fig. 3) using the following formulae based
on the theory of elasticity"
E-P2"r2 m+ 1
A Ae m
A = AAI A&2+~A3=AAI +2ABI v-P2"rz m+ 1
I_ L! At m
I where P2 is the maximum test pressure and m is an
i estimated value for Poissons Ratio.
i
I (f) Alternatively to (e) above, the moduli of undis-
Fig. 2. Method of superposition to give displacements for equivalent turbed rock may be obtained taking into account the
uniformally distributed loading (elimination of end effects). effect of a fissured and loosened region by using the
following formulae:
outside the zone of irregular stresses beneath the flat =p2.rz(m__++ l lnra~
jacks and the lining and loose rock. E Ae \ m r2/
rl Eb
P2 = - - " Pl = - - " Pm"
r2 2./t. r 2
L Ad I
AA'2AB I~ -I
9p
. ,/
6,0
3,0
. . . . .
-17 I ,
q - A
I00
50
mm
R.M.M.S. 16/3 D
212 International Society for Rock Mechanics
O/o A
I00
f
80
/
P
Prr~x
I/A
//
L btime
/ \
P,
IO
T
\\ J
~6
o.
E5
\ 8
b~
Pi
o. A
=T-
P~ ~o
/
5
i0
~5 r
Pi = Pr + Ps
(o = gap between steel 1.0
and concrete
pro' ~ b = p1.2.~,7r
lq
i ' 5O
1 2 3 4 5 4+5 6 7 4+5+7 8 9
Ad
NR time P2 AA As AA+Aa Ad corr. At Ae Ap
1
2
3a
3b
3c
4
5
6a
6b
6c
7
8
9a
o0
E-P2"r2 m+ 1
Ae m
v-P2"r2 m+ 1
At fir/
214 International Society for Rock Mechanics
4. Either flat jacks or a pressurizing fluid may be 7. Typically the maximum pressure applied in this
used to apply radial pressure to the test chamber; the test is from 5-10 MPa.
two alternatives are illustrated in Fig. la and b. 8. In the case of "creeping" rock it may be necessary
5. Measurements are usually by means of mechanical to stop loading even though the displacements con-
guages. Particular care is required to guarantee the tinue. Not less than 80Y/o of the anticipated long term
reliability of electric transducers and recording equip- displacement should have been reached.
ment when used. 9. This superposition is made necessary by the com-
6. To assess the effectiveness of grouting, two test paratively short length of test chamber in relation to
chambers are usually prepared adjacent to each other. its diameter. Superposition is only strictly valid for elas-
Grouting is carried out after completion of testing in tic deformations but also gives a good approximation
the ungrouted chamber, and the equipment is then if the rock is moderately plastic in its behaviour.
transferred to the grouted chamber.