Document number Sent Date Received Received BPs comments Our Reply

Date Code
AF-WS00ZZ-MT-PRO- 11/08/17 26/08/17 Code 3 1. Specify revision no. of 1. AD-CDZZZZ-MT-SPE-
0003 this specification AD- 1008-000_D02
Consumable Storage and CDZZZZ-MT-SPE-1008-000
Handling Procedure

2. Details of how the welding


consumables are issued 3. WELDING CONSUMABLE
to the welder and this ISSUE
information is recorded. All consumables shall be
This is particularly
important for cellulosic issued by the store man and
electrodes which require recorded on a Consumable
maintenance of coating
conditions for operability Issue Sheet (Appendix D).
These issue sheets are
periodically reviewed by the
4. Details of how long
Welding Inspector and are
welding consumables can
be issued to the welder, held in the relevant welding
how will the welder store
stores. The welder shall
the consumable (quiver,
original packaging etc.), determine from the relevant
how will the issuing time
WPS which consumable is
period be specified and
controlled, what controls required, confirmed if
are in place for the return
necessary by the foremen
of welding consumables at
the end of the shift.
or Welding Inspector.
The required quantity of
electrodes will be kept in
special boxes (no heating will
be applied) by welders with the
label contains date, welder
name and his signature and
they will be used during the
working shift. Welding foreman
and QC inspector is
responsible to check the data
of electrode issuance.
Remaining electrodes will be
returned in the original tin
cans to the stores at the end
of the working shift.
Alternatively, returned
electrodes may be used for
training purposes. Welding
foreman has responsibility to
control all not used electrodes
are returned to the store

Document number Sent Date Received Date Received Code BPs comments Our Reply
AF-WS00ZZ-MT- 12/8/17 26/08/17 Code 3 1. The hot pass 1. Hot pass shall be run
PRO-0004 shall be immediately after
completed completion of root pass
AF-WS00ZZ-MT- immediately Lowering-off shall
PRO-0005 following the root not be take place
pass and lowering before completion
AF-WS00ZZ-MT- off shall not take of Hot pass
PRO-0006 place until the hot
pass is completed 2. For welds on
(pWPS) steep slope the
weld shall be
completed with 4
2. For welds on passes before
steep slopes the lowering off.
weld shall be
completed with 4
passes before
lowering off - see
AF-WS00ZZ-CM-
DVR-0001-K01
Document number Sent Date Received Date Received Code BP comment Azfen Comment
AF-WS00ZZ-MT-PLN- 09/08/17 25/08/17 CODE 3 1. The statement 1. REMOVED
0001-000 that the test rings
EXECUTION PLAN will be supplied
FOR WPQT AND with backing rings
WQT and run off tabs is
not clear. Why are
backing rings being
considered?
2. BP-WS00ZZ-MT-
2. Add specification SPE-0001-000_D01
number here.
3. All welders
3. Do the welders involved in
have experience in qualification
the use of cellulosic welding shall have
electrodes? an experience in
pipeline welding
and they have
experience in the
use of cellulosic
4. Induction heating electrode.
is mandatory for
pipe dia >20" and 4. According to AF-
pre-heat >80 deg C WS00ZZ-CM-DVR-
0005-000 using Gas
flame is permitted
for 21 inch pipe.
For 36 inch pipe
diameter separate
DVR needs to be
raised.

5. Charpy impact
test positions are 5. Charpy Impact
missing test positions added
to the list.