You are on page 1of 17

Master Specification

SECTION 26 08 00

COMMISSIONING OF ELECTRICAL SYSTEMS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Work Included: The work of this Section consists of furnishing all labor,
materials, test equipment, and technical supervision to perform and record
the electrical field tests as specified, and perform and record all electrical
tests as required, including tests on 600 volt wire and cable, low voltage
panelboards, bus ducts, and grounding.

1.02 RELATED SECTIONS

A. Section 01 33 01 Submittals.

1.03 DESCRIPTION

A. This Section also includes requirements for furnishing all labor, materials,
and technical supervision to perform training for equipment and special
systems described herein.

B. This Section specifies that Contractor shall engage the services of a


recognized independent testing company for performing final inspections
and tests as specified.

1. The CM will witness Inspections and tests. Notify the CM a minimum


of 14 working days in advance of testing date.

C. The testing company shall provide all material, test instruments, equipment,
labor, and technical supervision to perform such tests and inspections.

D. It is the intent of these tests to verify that electrical equipment is operational


within industry and manufacturer's tolerances, and is installed in
accordance with these specifications.

E. Perform tests, calibration, adjustment of relays and inspections before


energizing any equipment.

F. Upon completion of the tests and inspections specified, a label shall be


provided in accordance with NETA labeling.

G. Relay settings shall be made using approved relay setting reports, short
circuit and coordination studies.

December 01, 2010 26 08 00-1 Commissioning of Electrical


Systems
Master Specification

1.04 QUALITY ASSURANCE

A. Reference Standards:

1. OSHA Part 1910; Subpart S. 1910.308.


2. American National Standards Institute: ANSI
3. American Society for Testing and Materials: ASTM
4. Association of Edison Illuminating Companies: AEIC
5. Institute of Electrical and Electronics Engineers: IEEE
6. Insulated Cable Engineers Association: ICEA
7. National Electrical Manufacturers Association: NEMA
8. National Electrical Testing Association: NETA

Note: Information and procedures for acceptance testing taken from


Acceptance Testing Specifications for Electrical Power Distribution
Equipment and Systems is copyright by InterNational Electrical
Testing Association, PO Box 687, 231 Red Rocks Vista Drive,
Morrison, Colorado 80465.

9. National Fire Protection Association (NFPA):

a. a. 70, National Electrical Code (NEC).

B. All inspections and tests shall use the following references.

1. Contract Specifications.
2. Drawings.
3. Manufacturer's instruction manuals and approved shop drawings for
applicable equipment.
4. Acceptance Testing Specifications for Electrical Power Distribution
Equipment and Systems by InterNational Electrical Testing
Association (NETA).

C. Qualifications of Testing Company:

1. The testing company shall meet OSHA 29 CFR 1907 criteria for
accreditation of testing laboratories. A testing company with full
membership in NETA constitutes proof of meeting such criteria.
Contractors with employees that are full members of NETA are not
acceptable.
2. Contractor shall submit the testing company's qualifications and the
resumes of the personnel proposed to be assigned to this Project for
the CM's approval before commencement of the work.

1.05 SUBMITTALS

A. In accordance with the requirements of Sections 01 33 01.

December 01, 2010 26 08 00-2 Commissioning of Electrical


Systems
Master Specification

B. Submit the testing company's qualifications and the resumes of the


personnel proposed to be assigned to this Project.

C. Fixed test procedures as recommended by the equipment/system


manufacturer.

D. Submit proposed testing program and test procedures for review and
approval by the CM before beginning any testing. Each procedure shall
include the following as a minimum:

1. Statement of procedure objective and scope.


2. List of equipment required to set up and perform the procedure.
3. List of equipment or services required from areas outside Contractor's
control.
4. List of prerequisite tests that need to be completed before the
procedure can be performed.
5. Description of the required procedure setup, including diagrams
illustrating test equipment connections and identifying test points,
where applicable.
6. Step-by-step instructions for performing the procedure identifying the
points where data is to be recorded and the limits for acceptable data,
in accordance with referenced standards.
7. Provisions for recording pertinent test conditions and environment at
time of test.
8. Instructions for recording data on data sheets and verifying that
procedure steps have been completed.

E. Test Report (Draft and Final)

1. The draft and final test reports, shall include, but not be limited to, the
following:

a. Summary of Project.
b. Description of equipment tested.
c. Description of test.
d. List of test equipment used in calibration and calibration date.
e. Test results, including plots/graphs and actual
readings/measurements taken including corrected values.
f. Conclusions and recommendations.
g. Appendix, including appropriate test forms.
h. All test reports shall be signed by the CM's authorized witness
present at the test.

2. The final test report shall be bound and its contents certified.
3. Furnish ten copies of the completed final test report to the CM no later
than 15 days after completion of the inspection and testing.

December 01, 2010 26 08 00-3 Commissioning of Electrical


Systems
Master Specification

F. Instruments: Submit list of instruments and certification indicating that


instruments that will be used for testing have been calibrated and their
accuracy certified within a previous period of not more than one month. List
types of instruments to be used, manufacturer, model, serial number, latest
date of calibration, and calibration organization.

1.06 DIVISION OF RESPONSIBILITY

A. Contractor shall perform routine insulation resistance, continuity and


rotation tests for distribution and utilization equipment before tests
performed by the testing company specified.

B. Contractor shall provide all power supplies and facilities for testing, at no
additional cost to the Agency.

C. Contractor shall notify the testing company when equipment becomes


available for acceptance tests. Work shall be coordinated to expedite
project scheduling.

D. Contractor shall supply a complete set of electrical plans, specifications and


pertinent change orders to the testing company before commencement of
testing.

E. The testing company shall notify the CM a minimum of two weeks before
commencement of testing.

F. The testing company shall be responsible for implementing final settings


and adjustments on protective devices.

G. System material or workmanship that is found to be defective based on


acceptance tests shall be reported to the CM. Contractor, without additional
cost shall make corrections to the CM.

H. The testing company shall maintain a written record of tests and upon
completion of the work, assemble and certify a final test report. A draft final
test report shall be submitted to the CM for review and comment before the
final report is submitted.

1.07 TEST INSTRUMENT SERVICE AND CALIBRATION

A. Calibration Program and Accuracy:

1. The testing company shall have a calibration program that maintains


applicable test instrumentation within rated accuracy in accordance
with manufacturers recommendations and standard industry practice.
2. The accuracy shall be traceable to the National Bureau of Standards
(NBS) in an unbroken chain.

December 01, 2010 26 08 00-4 Commissioning of Electrical


Systems
Master Specification

3. Instruments shall be calibrated in accordance with the following


frequency schedule:

a. Field instruments: 6 months, maximum.


b. Laboratory instruments: 12 months.
c. Leased specialty equipment: 12 months (where accuracy is
guaranteed by the lessor)

4. Dated calibration labels shall be visible on test equipment.

B. Safety and Precautions:

1. Safety practices shall include, but are not limited to, the following
requirements.

a. OSHA
b. Accident Prevention Manual for Industrial Operations, Seventh
Edition, National Safety Council, Chapter 4.
c. Applicable State and local safety operating procedures.

2. Acceptance tests shall be performed with apparatus de-energized,


unless otherwise specified.
3. The testing company shall have a designated safety representative
who shall be present on the Project and supervise operations with
respect to safety.
4. Circuits operating in excess of 600-volts between conductors shall
have conductors shorted to ground by a hot-line grounded device UL
approved for the purpose.
5. In all cases, work shall not proceed until the safety representative has
determined that it is safe to do so.
6. The testing company shall have available sufficient protective barriers
and warning signs. The testing company shall place the protective
barriers and warning signs in close proximity to the area where testing
is being performed.

1.08 DEFINITION OF TESTS

A. Preliminary Inspection and Tests: Visual inspections of electrical


equipment, wire checks of factory wiring and any other preliminary work
required to prevent delays during performance of electrical acceptance
tests. Contractor or testing agency shall verify connections shown on the
One-Line Diagram.

B. Electrical Startup Tests: Those inspections and tests required to show that
the workmanship, methods, inspections, and materials used in erection and
installation of the electrical equipment conforms to accepted engineering
practices, IEEE Standards, the National Electrical Code, manufacturers

December 01, 2010 26 08 00-5 Commissioning of Electrical


Systems
Master Specification

instructions, and Electrical Work of this Contract, and to determine that the
equipment involved may be energized for operational tests.

C. Operating Tests: Those tests performed on all electrical equipment installed


as part of the Electrical Work of the Contract and under other sections of
the Specifications, to show that the electrical equipment will perform the
functions for which it was designed.

1.09 AUTHORIZED WITNESSES

A. Perform all acceptance, startup and operating tests in the presence of the
CM or designated authorized witness.

B. Notify vendors and manufacturers of electrical equipment of the time of tests


and extend reasonable cooperation to them or their representatives to
permit them to witness tests should they so request.

1.10 DATA TO BE RECORDED

A. Maintain reproducible test data sheets showing results of tests described in


the accepted test procedures. Provide reproducible data sheets, listing
acceptable or specified test limits and values actually measured. Retain
one copy of test data sheets at the site. Furnish four copies to the CM.

B. Provide data sheets showing test set-up, equipment used, names of


persons performing test, names of witnesses, date, location, and serial
number of equipment under test. Test data sheets will be reviewed by the
CM and accepted as submitted, or additional tests may be required. If
additional tests are required because initial test results do not comply with
Specifications, document the re-testing and submit as before at no
additional cost to BSDA.

1.11 ENVIRONMENT

A. Do not perform megger or high potential tests during times of high relative
humidity.

B. Do not perform tests on outdoor equipment during inclement weather. Do


not perform tests on direct burial ground conductors or on ground rods
within a 48-hour period following rainfall.

C. During cable tests, station a man at each point where cable has exposed
connections.

D. Schedule sequence of tests so that equipment can be energized


immediately after completion of the applicable tests and approval of test
reports. Notify the CM of time of test at least 48 hours before testing.

December 01, 2010 26 08 00-6 Commissioning of Electrical


Systems
Master Specification

1.12 GUARANTEE

A. Tests shall not alter Contractor's guarantee of the equipment. Replace and
retest work and materials found to be in non-compliance with the Contract
Documents at no additional cost to the Agency.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

3.01 GENERAL TESTING REQUIREMENTS

A. Perform preliminary inspections and tests immediately before performing


startup tests.

B. Do not perform more than one high potential test on any conductor unless
specifically authorized by the CM.

C. Megger Tests

1. Megger readings specified are the minimum readings desired at an


ambient temperature of 60-degrees Fahrenheit and at a relative
humidity of less than 60-percent. When megger readings are taken at
other than 60-degrees Fahrenheit, convert readings to equivalent
values at 60-degrees Fahrenheit.
2. When megger readings fall below the specified minimum values at 60-
degrees Fahrenheit, devise some means of applying heat for drying
out the equipment subject to the approval of the CM. If drying is to be
done by applying an electric potential to a piece of equipment, do not
exceed the continuous voltage or current ratings of the equipment
being dried, directly or by induction.

D. Continuity Tests: Perform continuity tests with a dc type device using a bell,
buzzer, or multi-meter. Do not use telephones for continuity tests; use
telephones only for communication.

E. Restore all connections and equipment to operating conditions after testing


has been completed.

December 01, 2010 26 08 00-7 Commissioning of Electrical


Systems
Master Specification

3.02 TESTS ON WIRE AND CABLES RATED 600 VOLT AND BELOW

A. General: Give each 480-volt power feeder and branch circuit cable a
continuity test and a megger test. Verify phase identification our each
power feeder and branch circuit. Verify identification of all lighting circuits
and branch circuits on panel directories and make operational checks on all
lighting circuits and branch circuits to prove that the circuits perform all
functions for which they are designed. Check all power feeder and
subfeeder cable connections for workmanship and conformance with
standard practice by visual inspection.

1. Visual and mechanical inspection

a. Cables shall be inspected for physical damage and proper


connection in accordance with single line diagram.
b. Cable connections shall be torque tested to manufacturer's
recommended values.

B. Connections: Isolate power cable to be megger tested by opening switches


or breakers at each end of cable before testing where such disconnecting
means exists. Where cables are direct connected without a disconnecting
means, do not disconnect cables: Test as connected.

C. Megger Tests

1. Use a 1,000-volt megger for each megger test. Insulation resistance


tests shall be performed at 1,000-volts dc for 30 seconds.
2. Apply megger tests between each conductor and ground with the other
two conductors in the conduit or cable grounded to the same ground.
Test each conductor in the same manner.
3. Minimum acceptable readings: For disconnected cables, 100-
megohm.
4. When insulation resistance is to be determined with all switchboards,
panelboards, fuse holders, switches, and overcurrent devices in place,
the insulation resistance when tested at 500-volts dc shall be no less
than Table 3.4.1.

D. Acceptance: Cable must pass all inspections and tests.

E. Records: Include the following information in test report on each power and
branch circuit cable rated below 600-volts:

1. Complete cable identification and description of isolation means.


2. Megger readings, including converted values.
3. Approximate average cable temperature.

December 01, 2010 26 08 00-8 Commissioning of Electrical


Systems
Master Specification

Table 3.4.1
Minimum Insulation Resistance
Conductor or Circuit Size Minimum Resistance
No. 14 & No. 12 AWG 1,000,000-ohms
25-ampere circuits & above 250,000-ohms

3.03 TESTS ON CONTROL WIRING

A. General: Give each single conductor and multi-conductor control wire or


cable a continuity tests and an insulation strength test. Verify identification
of conductors.

B. Connections: Disconnect and fan out conductors to be tested.

C. Insulation Strength Tests

1. Subject each control wire to a 500-volt, 60-Hertz test.


2. Apply test between each conductor in a wire group and ground with all
other conductors in the wire group grounded to the same ground. Use
a test set having an accurate means of insuring 500-volt test voltage
and provide a series resistance to limit fault when a ground is found.
Hold test voltage only long enough to read instruments. Test each
conductor in the same manner.
3. Instead of the above insulation strength test, megger each control wire
as specified for 480-volt power conductors.

D. Acceptance: Wires must pass all tests.

E. Records: Include the following information in test report on each wire group.

1. Wire and group identification.


2. Type of test, insulation strength or megger.
3. When megger testing is selected, include information as specified for
480-volt power cables.

3.04 TESTS ON TRANSFORMERS RATED 600 VOLTS AND BELOW

A. General: Check continuity and correctness of connections of windings and


give each winding a megger test.

1. Visual and mechanical inspection

a. Inspect for physical damage.


b. Compare equipment nameplate information with latest single line
diagram and report discrepancies to the CM.
c. Verify proper auxiliary device operation for components including,
but not limited to, fans, indicators, and tap changer.

December 01, 2010 26 08 00-9 Commissioning of Electrical


Systems
Master Specification

d. Check tightness of accessible bolted electrical joints in


accordance with Table 3.7.1. Check hardware, bushings, and
vibration mats.
e. Perform specific inspections and mechanical tests in accordance
with the manufacturer's instructions.

B. Connections: Isolate transformer by opening the line side circuit breaker


and disconnect secondary conductors at panels. Tie conductors together
on each winding.

C. Megger Tests

1. Use a 1,000-volt megger for megger tests on 480-volt windings and a


500-volt megger for megger tests on lesser voltage windings.
Appropriate guard circuit shall be used under bushings.
2. Apply a megger test between each transformer winding tied together
and ground. Ground all windings not included in the test to the same
ground. Winding resistance tests shall be made for each winding at
nominal tap position. Perform a megger test of the secondary
windings.
3. Minimum acceptable readings: 480-volt winding to ground, 45-
megohms: lesser voltage winding to ground, 30-megohms.
4. Hold all megger tests for at least one minute or until the reading
maintains a constant value for 15 seconds.

D. Electrical tests

1. A dielectric absorption test shall be made winding to winding and


winding to ground for ten minutes. The polarization index shall be
computed.
2. A turn ratio test shall be performed between windings for all tap
positions. The final tap setting shall be determined and set by the
testing company upon completion of the ratio testing acceptable
values.
3. AC over-potential test shall be made on all high and low voltage
winding to ground.
4. Individual exciting current tests shall be performed on each phase in
accordance with established procedure.
5. Perform special test and adjustments in accordance with the
manufacturer's instructions for tap changer, fan and controls, and
alarm functions.
6. Perform a double power factor excitation test with a 10-kV tester.
7. Perform a core ground test.
8. Test temperature control panel and verify alarm stages and interlock
for shutdown.

E. Test values
December 01, 2010 26 08 00-10 Commissioning of Electrical
Systems
Master Specification

1. Insulation resistance and absorption test voltage shall be in


accordance with Table 3.13.1. Results shall be temperature corrected.
2. The absorption test polarization index shall be above 2.0 unless an
extremely high value is obtained at the end of 1 minute, that when
doubled will not yield a meaningful value with the available test
equipment.
3. AC high potential test voltage shall not exceed 75-percent of factory
test voltage or Table 3.13.3 for a one-minute duration. Evaluation shall
be on go, no-go, basis; NEMA ST-20.
4. Power factor test values more than 3-percent shall be investigated.
5. Winding resistance test results shall compare within 1-percent of
adjacent windings.
6. Turns ratio test results shall not deviate more than 0.50 percent from
calculated ratio

F. Acceptance: Transformers must pass all inspections and tests.

G. Records: Make complete and accurate records of each test. Include the
following in each test report:

1. Complete identification of transformer.


2. Megger readings, including converted values and ambient
temperature at time of test.

Table 3.13.1 - Insulation Resistance Test Voltage


Voltage Rating (Volts) Test Voltage (Volts)
150 - 600 1,000
601 5,000 2,500
5,001 15,000 5,000

Values of insulation resistance (IR) less than manufacturer's minimum or kV plus 1 in


megohms shall be investigated. Over-potential tests shall not proceed until IR levels
are raised to specified minimum.

3. Over-potential test voltages shall be applied in accordance with ANSI


C37.20c, Table 3.13.2.

Table 3.13.2 - Overpotential Test Voltages


Test Voltage kV
Rated kV
AC DC
5 14.3 20.2
15 27.0 37.5
25 45.0 Consult manufacturer
35 60.0 Consult manufacturer

December 01, 2010 26 08 00-11 Commissioning of Electrical


Systems
Master Specification

Test results are evaluated on a go, no-go basis by slowly raising the test voltage to the
required value and applying the final test voltage for 1 minute.

Table 3.13.3 - Applied Potential Test Voltages


Nameplate Winding Voltage Test Potential, kV
Rating, Volts
0 250 2.5
251 1,200 4
1,201 2,500 10
2,501 5,000 12
5,001 8,660 19
8,661 15,000 31

3.05 TESTS ON CIRCUIT BREAKERS, LOW VOLTAGE (MOLDED CASE)

A. Visual and mechanical inspection

1. Circuit breakers shall be checked for proper mounting, conductor size,


and feeder designation.
2. Operate circuit breakers to insure smooth operation.
3. Inspect case for cracks and other defects.
4. Check tightness of connection with torque wrench in accordance with
manufacturer's instructions.

B. Electrical tests

1. Contact resistance shall be measured.


2. Time-current characteristic tests shall be performed by passing 300
percent rated current through each pole separately. Trip time shall be
determined.
3. Instantaneous pickup current shall be determined by run-up or pulse
method. Clearing times shall be within 4-cycles or less.
4. Insulation resistance shall be determined pole to pole, across pole and
pole to ground. Test voltage shall be 1,000-volts DC.

C. Test Values

1. Contact resistance shall be compared to adjacent poles and similar


breaker. Deviations of more than 50-percent shall be investigated.
2. Insulation resistance shall not be less than 50 megohms.
3. All trip times shall fall within Table 3.17.1. Circuit breakers exceeding
maximum 300-percent time (Column 5) shall be replaced.
4. Instantaneous pickup current levels shall be within 20-percent of
manufacturer's published values.

December 01, 2010 26 08 00-12 Commissioning of Electrical


Systems
Master Specification

Table 3.17.1 - Values for Overcurrent Trip Test


(at 300% of Rated Continuous Current of Breaker)
Tripping Time, Seconds
Range of Magneti Magneti
Rated c c Maximu
Voltage for Continuou Breakers Breakers m
Volts Current, s Thermal Minimu Maximu Tripping
Protection* Amperes Breakers m m Times
(1) (2) (3) (4) (5) (6)
240 15 - 45 3 --- 50 100
240 50 100 5 --- 70 200
600 15 45 5 5 80 100
600 50 100 5 5 150 200
240 110 225 10 5 200 300
600 110 225 10 --- 200 300
600 250 450 25 --- 250 300
600 500 600 25 10 250 350
600 700 1,200 25 10 450 600
600 1,400 2,500 25 10 600 750

* These values are based on heat tests conducted by circuit breaker


manufacturers on conductors in conduit.

3.06 TESTS ON INSTRUMENT TRANSFORMERS

A. Visual and mechanical inspection

1. Inspect for physical damage and compliance with the Drawings.


2. Check mechanical clearances and proper operations of all
disconnecting and grounding devices associated with potential
transformers.
3. Verify proper operation of grounding or shorting devices.

B. Electrical tests

1. Current transformers (CT) shall have secondary saturation tests done


at a minimum of three points below and one point above knee of
saturation curve.
2. Confirm transformer polarity electrically.
3. Burden tests shall be performed at the secondary leads of the CT to
assure accurate translation of primary current.
4. Verify connection at secondary CT leads by driving a low current
through the leads and checking for this current at applicable devices.
5. Confirm transformer ratio.
6. Measure insulation resistance of transformer secondary and leads with
500 volt Megohm meter.
December 01, 2010 26 08 00-13 Commissioning of Electrical
Systems
Master Specification

7. Measure transformer primary insulation with applicable over-potential


tests.
8. Verify connection of secondary potential transformer (PT) leads by
applying a low voltage to the leads and checking for this voltage at
applicable devices.
9. Check for PT secondary load with secondary voltage and current
measurements. Load shall less than voltage ampere capacity of the
PT.

3.07 TESTS ON METERING AND INSTRUMENTATION

A. Visual and mechanical inspection

1. Examine devices for broken parts, indication of shipping damage and


wire connection tightness.
2. Verify meter connections in accordance with single line meter and
relay diagram.

B. Electrical tests

1. Calibrate all meters at mid scale. Calibration instrument precision shall


be 50-percent or less than the precision of the instrument being tested.
(If the instrument being tested has a precision of plus or minus 10-
percent, the precision of the calibration instrument shall be plus or
minus 5-percent or better.)
2. Calibrate watt-hour meters to 0.50-percent.
3. Verify instrument multipliers.

C. Acceptance: Grounding materials and connections must pass all


inspections and must meet all specified maximum and minimum values.

D. Records: Make complete records of all tests. Include resistance values


obtained, calculations of same, and methods of test and calculation.

3.08 TESTS ON GROUNDING SYSTEMS

A. General: Inspect ground conductors, ground buses, and connections for


conformance with design specifications and for satisfactory workmanship.
Test resistance to earth of each ground rod. Test ground paths for
equipment and structural steel or reinforcing bar grounding.

1. Visual and mechanical inspection: Inspect ground system for


compliance with the Drawings and specifications.

B. Connections

1. Maintain each ground rod isolated from the associated ground rods for
tests on individual rods for resistance to earth.
December 01, 2010 26 08 00-14 Commissioning of Electrical
Systems
Master Specification

2. Include associated ground rods and interconnecting wiring in test for


resistance to earth.
3. Include ground bus on equipment, room and pullbox connections, and
associated intermediate copper ground conductors in tests on ground
paths for electrical equipment.
4. Include structural steel or reinforcing bar connection, rod connection
and intermediate conductor in tests on ground paths for structural steel
or reinforcing bars.

C. Electrical tests

1. Perform fall of potential test in accordance with IEEE 81, Section 9.04,
on the main grounding electrode or system.
2. Perform the two-point method test in accordance with IEEE 81, to
determine the ground resistance between the main grounding system
and major electrical equipment frames, system neutral, and/or derived
neutral points.

a. Alternate method: Perform ground continuity test between main


ground system and equipment frame, system neutral and/or
derived neutral point. This test shall be made by passing a
minimum of 10 amperes DC current between ground reference
system and the ground point to be tested. Voltage drop shall be
measured and resistance calculated by voltage drop method.

3. Tests on Individual Ground Rods

a. Test each ground rod for resistance to earth by a standard


method. Use a Biddle Ground Tester (AVO International) or the
method of using two auxiliary ground rods as described in IEEE.
The IEEE method requires the use of ac test current. Place
auxiliary test rods sufficiently far away from the rod under test so
that the regions in which their resistance is localized do not
overlap. Calculate ground resistance from the readings taken.
Maximum acceptable resistance to earth: 2-ohms.
b. If the resistance is found to be higher than 2-ohms, drive
additional rods with a minimum separation of 20-feet and connect
in parallel with the rod under test until 2-ohms or less is obtained,
or increase the length of the rod under test until 2-ohms maximum
is obtained.

D. Tests of same, and methods of test and calculation.

3.09 TESTS ON SURGE ARRESTORS

A. Visual and mechanical inspection

1. Inspect for physical damage.


December 01, 2010 26 08 00-15 Commissioning of Electrical
Systems
Master Specification

2. Verify location and nameplate rating with the Drawings and the
specifications.
3. Inspect ground and discharge counter connections for integrity.

B. Electrical tests

1. Perform a 60-Hertz sparkover test.


2. Perform a radio influence voltage (RIV) test.
3. Perform an insulation power factor test.
4. Perform ground continuity test to ground grid system.

C. Test values

1. Sparkover voltage shall:

a. Exceed 1.5 times rating.


b. Not exceed 2.0 times rating.

2. Radio influence voltage (RIV) shall not be detected within voltage


rating of arrestor.
3. Power factor tests shall show similar dielectric loss between similar
arrests.
4. Ground grid connections shall not exceed 0.5-ohms, maximum.

3.10 TESTS ON LIGHTING SYSTEMS STATION AND BUILDINGS

A. Perform operation tests for complete lighting system including switches,


emergency lighting, and receptacles.

3.11 TESTS ON HEATERS, RELAYS, TIMERS, THERMOSTATS & CONTACTORS

A. Perform operational tests on each piece of electrical equipment and verify


equipment ratings.

3.12 SYSTEM FUNCTION TESTS

A. General

1. Each system specified shall be function tested to confirm total system


operation.
2. Upon completion of equipment tests, the system functional tests shall
be performed. System functional tests shall show the proper
interaction of sensing, processing, and action devices to effect the
design end-product or results.
3. Implementation

a. The testing company shall develop a test matrix that includes, but
is not limited to, the following:

December 01, 2010 26 08 00-16 Commissioning of Electrical


Systems
Master Specification

1) Input signal or stimuli. Example: Current transformers;


potential transformers.
2) Decision process. Example: Pilot Wire Relay System
3) Action device. Example: Circuit Breaker - ACB
4) End product or result. Example: Zone Fault Protection

b. All interlocks safety devices and fail-safe functions shall be tested


in addition to design function.
c. The testing company shall propose methods to initiate the
sensing device by physical stimuli and quantitatively monitor the
result or output by measurement.

END OF SECTION 26 08 00

December 01, 2010 26 08 00-17 Commissioning of Electrical


Systems

You might also like